    2012-14MIS Project on

    New Customer Registration

    Submitted ByKhalid Mahmood (2012-054)

    ShahzadHameed (2012-057)

    Muhammad Saleh (2012-063

    Usman Hassan (2012-073)

    Muhammad Naeem (2012-07

    AsifIqbal (2009-015)

    SUBMITTED TO

    Prof. ZeshanAhmer

    Institute of Business Administration

    University of the Punjab

  • 8/10/2019 Tugasan Mis

    2/24

    1 | P a g e

    TABLE OF CONTENT

    COMPANY PROFILE..................................................................................................................... 3

    PROBLEM DEFINITION................................................................................................................ 4

    STUDY OF EXISTING SYSTEM .............................................................................................................. 4

    REQUIREMENT ANALYSIS ................................................................................................................... 5

    DATA GATHERING .............................................................................................................................. 5

    SYSTEM PROCESS DOCUMENT SP-SAL-01 ................................................................................................ 5

    New Customer Registration - Domestic ................................................................................................ 5

    1. Overview ........................................................................................................................................... 5

    1.1 Business Process Description ...................................................................................................... 5

    2. Process Activities ............................................................................................................................... 6

    2.1 Activity Summary ........................................................................................................................ 6

    2.2 Activity Narrative ........................................................................................................................ 7

    2.2.1 Receive application form ..................................................................................................... 7

    2.2.2 Issue Acknowledgement Letter............................................................................................ 7

    2.2.3 Select customers for survey ................................................................................................. 8

    2.2.4 Technical Vetting (If Applicable) .......................................................................................... 8

    2.2.5 Note details if application is Non-Feasible........................................................................... 8

    2.2.6 Proposal Letter/ Demand Note is issued ............................................................................. 8

    2.2.7 Bill is issued to the customer ............................................................................................... 8

    2.2.8 Customer pays and produces the proof of payment ........................................................... 8

    2.2.9 Field Activities raised for Distribution .................................................................................. 8

    2.2.10 Ditching is done by Contractor .......................................................................................... 9

    2.2.11 Service Lines are laid by Welding Team ............................................................................. 9

    2.2.12 Meter is installed at customer site .................................................................................... 9

    2.2.13 Gas SA is activated ............................................................................................................. 9

    2.2.14 ToDo for Service Point without Meter Read Cycle ............................................................ 9

    2.2.15 First gas bill is generated.................................................................................................... 9

    3. APPENDICES .................................................................................................................................. 9

    4. Document Information and Revision History ............................................................................. 10

  • 8/10/2019 Tugasan Mis

    3/24

    2 | P a g e

    PROBLEM IN EXISTING SYSTEM ........................................................................................................ 10

    PROPOSAL FOR THE NEW/IMPROVED SYSTEM ................................................................................. 10

    SUGGESTION FOR THE PROBLEM IN EXISTING SYSTEM ...................................................................... 10

    ORGANIZATIONAL CHART ................................................................................................................ 11

    LIST OF ENTITIES OF THE SYSTEM: .................................................................................................... 12

    External Entities: ..................................................................................................................................... 12

    Internal Entities: ...................................................................................................................................... 12

    LIST OF PROCESSES IN THE SYSTEM .................................................................................................. 13

    DATA FLOW DIAGRAMS ................................................................................................................... 13

    Context Level Diagram ............................................................................................................................ 14

    Zero Level Diagram ................................................................................................................................. 15

    Level One Diagram .................................................................................................................................. 16

    Entity Relationship Diagram ................................................................................................................... 17

    ACTIVITY PLANNING AND CONTROL ................................................................................................. 18

    OVERLOADING OF WORKER ............................................................................................................. 20

    GANTT CHART .................................................................................................................................. 21

    PERT DIAGRAM ................................................................................................................................ 22

  • 8/10/2019 Tugasan Mis

    4/24

    3 | P a g e

    COMPANY PROFILE

    Sui Northern Gas Pipelines Limited (SNGPL) was incorporated as a private limited Company in

    1963 and converted into a public limited company in January 1964 under the Companies Act1913, now Companies Ordinance 1984, and is listed on all the three Stock Exchanges of the

    Country.

    The Company took over the existing Sui-Multan System (217 miles of 16 inch and 80 miles of10 inch diameter pipelines) from Pakistan industrial Development Corporation (PIDC) and

    Dhulian-Rawalpindi-Wah system (82 miles of 6 inch diameter pipeline) from Attock Oil

    Company Limited. The Company's commercial operations commenced by selling an average of47 MMCFD gas in two regions viz. Multan and Rawalpindi, serving a total number of 67

    consumers.

    Sui Northern Gas Pipelines Limited (SNGPL) is the largest integrated gas company serving morethan 4.2 million consumers in North Central Pakistan through an extensive network in Punjab,

    Khyber PakhtoonKhwa and Azad Jammu & Kashmir and is certified against ISO 14001:2004& OHSAS 18001:2007 Standards. SNGPLs 11 sites have been registered under the

    "SMART2" Program by Pakistan Environmental Protection Agency (PAK-EPA).. The

    Company has over 49 years of experience in operation and maintenance of high-pressure gas

    transmission and distribution systems. It has also expanded its activities as Engineering,Procurement and Construction (EPC) Contractor to undertake the planning, designing and

    construction of pipelines, both for itself and other organizations.

    SNGPL transmission system extends from Sui in Baluchistan to Peshawar in KhyberPakhtoonKhwa (KPK) comprising over 7,654 KM of Transmission System (Main lines & Loop

    lines). The distribution activities covering 2,494 main towns along with adjoining villages in

    Punjab & Khyber PakhtoonKhwa are organized through 13 regional offices. Distribution systemconsists of 87,796 KM of pipeline. SNGPL has 4,174,342 consumers comprising Commercial,

    Domestic, General Industry, Fertilizer, and Power & Cement Sectors. Annual gas sales to these

    consumers were 597,056 MMCF worth Rs. 216,652 million during Jul 2011 - Jun 2012.

  • 8/10/2019 Tugasan Mis

    5/24

    4 | P a g e

    PROBLEM DEFINITION

    The SNGPL is operating its activities in two provinces (Punjab and KPK) in Pakistan. There are

    12 main regions from where all the activities are being monitored. Each Region containing

    multiple Sub Offices and activities performed under these Sub Offices are being controlled. Forthe MIS purpose, we are taking a small part i.e. from the New Customer Registration to the

    Installation of Meter only.

    The new customer registration process is initiated with the submission of gas connectionapplication by the customer at Sales department along with necessary documents and ends with

    the installation of meter at customer site by Distribution department. After receiving the

    application, usually the customer is informed of a tentative period when the survey will be

    performed. When the turn of customer comes according to first come first serve basis, survey ofthe site is conducted to determine if the connection is feasible or not. In case the connection is

    not feasible a regret letter is sent to the customer. The sketch of service lines is made along with

    details of lines that are required to determine cost of service line. Proposal Letter/ Demand Noteis generated. After the customer acknowledges the letter, payment is made after which request tolay service lines and install meter is sent to Distribution department. After meter installation and

    commissioning of gas, Billing is notified to create the Book No. and Route for the customer to be

    billed.

    The management of SNGPL is required to get the MIS to monitor/control the progress of these

    activities so that the company would perform its operations as per Oil and Gas Regulatory

    Authority (OGRA)s rules and regulations i.e. to maintain the progress defined by the OGRA

    with respect to Meter Installation.

    STUDY OF EXISTING SYSTEM

    The existing system is partially manually and partially computerized. The company has

    purchased a Billing System from ORACLE which is designed for the billing purposes only. This

    system captures all the required data but its architecture does not support the proper MIS.

    However some reports are being generated for this purpose using the schema of Billing System.

    As the architecture does not support MIS and the reports developed are not efficient enough to

    produce the results, however these reports meet the requirements.

    To improve the MIS of the company we have to develop a separate schema so that the

    management of the company could get reports efficiently and accurately. For this we have

    studied the existing reports generated from the Billing System.

  • 8/10/2019 Tugasan Mis

    6/24

    5 | P a g e

    REQUIREMENT ANALYSIS

    Due to the shortage of Gas, there is a huge backlog of gas connection application. To maintain

    the queue on first come first serve basis, there is a requirement to develop a Management

    Information System.

    The main requirement is to determine the turn of the issuance of the demand note and to

    determine the turn for the installation of meter on merit basis. Also the efficiency as well as

    accuracy should be considered.

    Currently the company is getting the information from the Billing System to whom the architect

    is not supporting MIS, due to which such reports are taking too much time to execute. It took 2

    days to complete. Also these reports are using the resources of the system which resulting slow

    other billing and daily processes.

    DATA GATHERINGData gathering activity is done based on the process document available in the company. Theextract of the document is given below:

    SYSTEM PROCESS DOCUMENT SP-SAL-01

    New Customer Registration - Domestic

    1. Overview

    1.1 Business Process Description

    The new customer registration process is initiated with submission of gas connection application

    by the customer at Sales department along with necessary documents and ends with theinstallation of meter at customer site by Distribution department. After receiving the application,

    usually the customer is informed of a tentative period when the survey will be performed. When

    the turn of customer comes according to first come first serve basis, survey of the site isconducted to determine if the connection is feasible or not. In case the connection is not feasible

    a regret letter is sent to the customer. The sketch of service lines is made along with details of

    lines that are required to determine cost of service line. Proposal Letter/ Demand Note is

    generated. After the customer acknowledges the letter, payment is made after which request tolay service lines and install meter is sent to Distribution department. After meter installation and

    commissioning of gas, Billing is notified to create the Book No. and Route for the customer to be

    billed. The same procedure is followed if a customer requests for additional meter with the onlydifference that the Person, Account and Premise already exist. Also the waiting time is not as

    much as it for new customers. Similarly the process for Address change is same as new customer

    registration process. Process Owner: Regional Sales Department:

  • 8/10/2019 Tugasan Mis

    7/24

    6 | P a g e

    2. Process Activities

    2.1 Activity SummaryProcess

    Activity

    Description Responsible

    1.

    Receive application

    form

    Customer submits the application form along with the

    required documents at Sales Department/ Customer Service

    Centers.

    CSR/Sales

    rep.

    2.

    Issue

    Acknowledgement

    Letter

    Sales rep creates a customer contact and issue the

    Acknowledgement letter to the customer.

    Regional

    Sales

    3.

    Select customers for

    survey

    Using Report, cases where the turn has reached are selected

    and field activity for survey is generated.

    Regional

    Sales

    4.

    Technical Vetting (If

    Applicable)

    Distribution dept. technically vets the application after sales

    visit.

    Distribution

    Dept.

    5.

    Note details if

    application is Non-

    Feasible/offline

    After survey, if application cannot be further processed due

    to non-feasibility, its details are recorded and through

    customer contact, regret/Intimation letter is sent to

    customer.

    Regional

    Sales

    6.

    Proposal Letter/

    Demand Note is

    issued.

    A Proposal Letter/ Demand Note is issued to the customer.

    Apreprinted House Line Contractors List

    is enclosed

    along with the Proposal Letter / Demand Note. Service line

    and security deposit charges would be assessed, outside

    CC&B, by the contractor.

    Regional

    Sales

    7.

    Bill is issued to

    customer

    When customer comes back acknowledging the proposal

    letter, a bill is issued so that he can pay the service line

    charges and deposit amount. Document Vetting is

    performed outside of CC&B.

    Regional

    Sales

    8.

    Customer pays the

    amount, raised in

    Bill.

    The customer makes payment at any bank / post office or

    any other payment center. Customer presents the proof of

    payment at the SNGPL. CMC would not be maintained,

    after CC&B. Rather all the information of the customer and

    premise will be maintained in the CC&B. Consumer

    number and account number would be maintained by the

    CC&B, in order to keep the track of the consumer.

    Customer

    9.

    Field Activities raised

    for Distribution

    After receiving proof of payment, Gas SA is created in

    CC&B that creates a field activity for Distribution.

    Regional

    Sales

    10.

    Ditching is done by

    Contractor

    After the Field Activity is generated for Distribution,

    ditching is done by Contractor.

    If Field Activity cancels, a ToDo would be generated

    intimating about the further actions to be taken.

    Third Party

    Contractor

  • 8/10/2019 Tugasan Mis

    8/24

    7 | P a g e

    SP-SAL-01 New Customer Registration v 1.3

    11.

    Service Lines are

    laid

    Service Lines are laid after ditching is completed by the

    Contractors. If Field Activity cancels, a ToDo would be

    generated intimating about the further actions to be taken

    Welding Team

    Development

    Section

    12.

    Meter is installed

    at customer site

    Meter is installed after the service lines are laid and Field

    Activity is completed. If Field Activity cancels, a ToDowould be generated intimating about the further actions to

    be taken and Gas SA would not be activated.

    Fitting Team

    DevelopmentSection

    13.

    Gas SA is

    activated

    A batch job of CC&B activates the Gas SA after meter is

    installed and FA is completed.

    CC&B

    14.

    ToDo for Service

    Point without

    Meter Read Cycle

    A ToDo is generated if the service point does not have

    Meter Read Cycle and Book Route.

    CC&B

    15.

    First Gas bill is

    generated

    After bill cycle on account is populated, the system will

    generate the gas bill when that cycle is scheduled.

    CC&B

    2.2 Activity Narrative

    2.2.1 Receive application form

    Customer submits the application form along with the required documents at Sales Department/

    Customer Service Centers. In CC&B, go to Order + and select the appropriate campaign. Detailsof name, phone, NIC, appropriate customer class and address are entered. Press the Save

    Information button. This will create the Person, Account and Premise of the customer in

    CC&B. CC&B would navigate to Case Management screen. Select the appropriate Case Type

    and save. Note: Account No. is generated for the customer that should be used as the reference

    for all future correspondence.

    2.2.2 Issue Acknowledgement Letter

    Select the existing case to create customer contact and print the Acknowledgement letter for thecustomer. Suggestion: Pre-printed stationary should be used to save time and resources.

  • 8/10/2019 Tugasan Mis

    9/24

    8 | P a g e

    2.2.3 Select customers for survey

    Using Report, cases where the turn has reached are selected according to First-Come-First-Serve

    basis by the Sales Rep. In CC&B, search for the customer using Account ID. Using dashboard,go to Premise (if premise does not appear, go to Account and using the Mailing Premise ID on

    Main Page, go to

    SP-SAL-01 New Customer Registration v 1.3Premise). To create field activity for survey, go to Field Activity + using service point menu.

    Select the appropriate FA Type and save. Go to the existing Case to update the status of theapplication.

    2.2.4 Technical Vetting (If Applicable)

    If technical vetting is required from the distribution dept. a field activity by sales dept. is created

    for distribution. The distribution dept. completes the field activity and a ToDois created for

    sales.

    2.2.5 Note details if application is Non-FeasibleAfter survey, if application cannot be further processed due to non-feasibility, the details arerecorded on Case. A customer contact is created and regret/intimation letter is sent to the

    customer.

    2.2.6 Proposal Letter/ Demand Note is issued

    A Proposal Letter/ Demand Note is issued to the customer. Preprinted House Line

    Contractors Listis enclosed along with the Proposal Letter / Demand Note. Service line and

    security deposit charges would be assessed, outside CC&B, by the contractor.

    2.2.7 Bill is issued to the customer

    When customer comes back acknowledging the proposal letter, a bill is issued so that he can pay

    the service line charges and deposit amount. Document Vetting is performed outside ofCC&B.

    2.2.8 Customer pays and produces the proof of payment

    After making the payment at bank, customer comes back with the proof of payment so thatapplication can be further processed. Note: Refer to Payments.doc for Online Cashiering if PayOrders are accepted at Sales Department.

    2.2.9 Field Activities raised for Distribution

    After receiving proof of payment, Gas SA is created in CC&B that creates two field activities,

    for Distributioni- Ditching and Service Line installation.

    ii- Install Meter.

  • 8/10/2019 Tugasan Mis

    10/24

    9 | P a g e

    2.2.10 Ditching is done by Contractor

    The field Activity for service line installation will be created by the system. Ditching is the first

    step of the FA. It is done by Contractor, outside of CC&B. Only Date of Completion andContractor Reference is updated on Field Activity steps for Service Installation after ditching is

    complete.

    2.2.11 Service Lines are laid by Welding Team

    Service Lines are laid by the Welding Team of Development Section after ditching is complete.After the work is done, information is updated on the Field Activity for Service Installation and

    FA is completed.

    2.2.12 Meter is installed at customer site

    This activity will always be generated. Meter is installed by the Fitting Team of DevelopmentSection after service lines are laid. This information is updated on the Field Activity for Meter

    Installation and FA is completed.

    2.2.13 Gas SA is activated

    A batch job of CC&B activates the Gas SA after service installation and/or meter installationfield activities are completed.

    2.2.14 ToDo for Service Point without Meter Read Cycle

    A ToDo is generated by CC&B if the service point does not have Meter Read Cycle and Book

    Route. Once this information is provided, the Bill Cycle on account is populated from the SPs

    meter read cycle. ToDo for accounts without bill cycle is also generated.

    2.2.15 First gas bill is generated

    After bill cycle on account is populated, the system will generate the first gas bill when that cycle

    is scheduled to be billed.

    3. APPENDICES

    Configuration: Identifier Type Phone Type Person Relationship Type Customer Class Service Point Type SA

    Type

    Algorithms: -

    Reports: Report of mature applications where survey has to be performed

    Interface: -

    Batch Job: SAACT

  • 8/10/2019 Tugasan Mis

    11/24

    10 | P a g e

    4. Document Information and Revision History

    File Name SP-SAL-01 New Customer Registration

    Original Author(s) Nadia Hasnain

    Version Date Author(s) Revision Notes

    V1.0 07-Oct-2008 Nadia Hasnain OriginalV1.1 04-Dec-2008 Nadia Hasnain Updated document with Case as part of designV 1.2 22-Dec-2008 AtifSaleem Updated document with Pipeline Extension ProcessV 1.3 29-Jan-2009 MobeenRiaz Updated document with reference to Domestic only.

    PROBLEM IN EXISTING SYSTEM

    The problem in existing system is only the efficiency of the reports for the management which

    needs to be fixed in the proposed system.

    PROPOSAL FOR THE NEW/IMPROVED SYSTEM1. Currently Sales system is the part of Billing System and the Billing Data is increasing

    day-by-day. Separate the Sales system from the Billing System to increase the efficiency

    on the part of Sales System.

    2. We proposed that a separate database is to be developed which should be populated with

    the data extracted from the Billing System on a daily basis. The data will be extracted

    through the auto scheduled scripts. Because of the simple structure of the database the

    reports will be executed efficiently.

    SUGGESTION FOR THE PROBLEM IN EXISTING SYSTEM

    As the Sales System is the built-in part of the billing system and it cannot be used

    separately, so we cannot use the option 1.

    The option 2 is the best that a separate database is to be developed and data should be

    extracted and populated the new database for the selected records on daily basis. This

    will probably be helpful to resolve the issue.

  • 8/10/2019 Tugasan Mis

    12/24

    11 | P a g e

    ORGANIZATIONAL CHART

  • 8/10/2019 Tugasan Mis

    13/24

    12 | P a g e

    LIST OF ENTITIES OF THE SYSTEM:

    The entities of the system are categorized in two groups External Entities and Internal

    Entities:

    External Entities:

    In the current system External Entities are used to show sources and recipient of data for

    the operation of the business. We extracted the following External Entities from the context

    level diagram. These are:

    1. Customer

    a. Customer will interact with the system for the submission of his Gas

    Connection Application, Receiving Letters and Receiving Bills etc.

    2. Collection Agency

    a. The collection agency will interact with the system when it will provide data

    of all the payment collected from the customers on behalf of the company and

    will submit the data for further processing in the system.

    3. Regulator/OGRA

    a. The Regulator/OGRA will need some reports from the system based on the

    customers and payment data.

    4. Management

    a. The management will require some MIS for the decision making.

    Internal Entities:

    The following entities will be used directly by the System.

    1. Agency(This entity will be used to maintain the main collection agencies like, NADRA,

    Post Offices and Banks)

    2. CollectingAgent(This entity will be used to maintain the information of Collecting

    Agent like if the Agency is BANK then collecting agent may be MCB, ABL, HBL etc.

    3. Branch(This entity will contain the detail of the branch of the collecting agent).

    4. Financials(This entity will contain the Financial Information like charging against any

    bill or received any payment from the customer via Collecting Agent).

    5. Bills(This entity will contain the Billing Information sent to the customer).

    6.

    Region(This entity will contain the information of all the regional offices).7. SubOffice (Any information related to sub-office will be maintained in using this entity).

    8. DemandNote (This entity will be used to store the amount of demand note against the

    size of plot)

    9. CustAccount (This entity will maintain the customer information)

    10.Staff (This entity will store the detail of staff who are responsible to complete the field

    activities)

  • 8/10/2019 Tugasan Mis

    14/24

    13 | P a g e

    11.Activity (This activity will store the data regarding activities to be performed for the

    customer like Survey of the Demand Note, Installation of Service Line and Installation of

    Meter)

    12.ActivityStatus (This entity will store the descriptions of the status)

    13.ActivityType(This entity will store the Type of Activity)

    14.

    ServicePoint (This entity will maintain the activities performed on the service point from

    time to time)

    15.Meters (This entity will be used to store the meter information to be installed on the

    customers service point)

    16.Reading (This entity will store the meter reading information)

    LIST OF PROCESSES IN THE SYSTEM

    Following are the processes in the system:

    1.

    New Customer Registrationa. Creation of Account

    b. Perform Survey

    c. Issuance of Proposal Letter

    d. Acceptance of Document and Issuance of Demand Note

    e. Verification of Payment

    f. Service Line/Meter Installation

    g. Activation of Customer

    2. Meter Reading

    3. Billing

    4.

    Collection

    DATA FLOW DIAGRAMS

    A data-flow diagram (DFD) is a graphical representation of the "flow" of data through an

    information system. DFDs can also be used for the visualization of data processing (structured

    design).

    On a DFD, data items flow from an external data source or an internal data store to an

    internal data store or an external data sink, via an internal process.

  • 8/10/2019 Tugasan Mis

    15/24

    14 | P a g e

    Context Level Diagram

    COLLECTION AGENCY CUSTOMER

    REGULATOR/OGRA

    MANAGEMENT

    0

    Customer Making Payment

    Outstanding Balance Data Issuance of invoice

    Transferring Payment info App./Doc Submission

    SNGPL

    (NEW CUSTOMER

    REGISTRATION)

    Reports

    Reports

    CONTEXT DIAGRAM

  • 8/10/2019 Tugasan Mis

    16/24

    15 | P a g e

    Zero Level Diagram

    COLLECTION AGENCY CUSTOMER

    MANAGEMENT

    1

    Customer Making Payment

    App./Doc Submission

    SNGPL

    (NEW CUSTOMER

    REGISTRATION)

    1.3

    1.2

    1.4

    REGULATORY/OGRA

    Reports

    Reports

    BILLING Clean Meter Reading Data

    METER

    READING

    COLLECTION

    INTERNAL

    DEPARTMENTS

    SUI NORTHERN GAS PIPELINES LIMITEDZERO LEVEL DIAGRAM

  • 8/10/2019 Tugasan Mis

    17/24

    16 | P a g e

    Level One Diagram

    CUSTOMER

    DATABASE

    1.1.1

    SNGPL

    (NEW CUSTOMER

    REGISTRATION)

    1.1.2

    DATABASE

    PERFORM

    SURVEY

    DATABASE

    1.1.3

    ISSUANCE

    OF

    PROPOSAL LETTER

    1.1.4

    ACCEPTANCE,

    DOCUMENT

    SUBMISSION AND

    ISSUANCE OF

    DEMAND NOTE

    DATABASE

    1.1.6

    DATABASESERVICE

    LINE/METER

    INSTALLATION

    DATABASE

    1.1.7

    ACTIVATION OFCUSTOMER

    DATABASE

    PAYMENT AT BANK BY

    THE CUSTOMER

    1.1.5

    VERIFICATION AND

    POSTING OF

    PAYMENT

    AGAINST

    CUSTOMER

    DATABASE

    YES

    Demand Note Bill

    LEVEL-ONE DIAGRAM

  • 8/10/2019 Tugasan Mis

    18/24

    17 | P a g e

    Entity Relationship Diagram

    Staff

    PK,I1 StaffId

    StaffName

    StaffDesignation

    Activity

    PK,I2 ActivityID

    ActivityStepSeq

    ActivityCreateDate

    FK1,I3 ActivityStatusID

    ActivityCompleteDate

    ActivityDependSeq

    FK2,I4,I1 AccountID

    FK3,I6,I5 StaffID

    ActivityTypeID

    SubOffice

    PK,I3 SubAreaID

    FK1,I2,I1 RegionID

    SubAreaDescription

    DemandNote

    PK,I1 PlotSizeID

    PlotSizeDesc

    DemandNote

    Financials

    PK,I5 FinancialI D

    TransactionDate

    Amount

    ArrearsDate

    FinancialType

    FK1,FK2,I3,I2,I6 SiblingID

    FK3,I4, I1 AccountID

    ActivityStatus

    PK,I1 StatusID

    StatusDesc

    Agency

    PK,I1 AgencyID

    AgencyDescription

    Bills

    PK,I2 BillID

    GenerateDate

    IssueDate

    DueDate

    I1 AccountID

    Meters

    PK,I1 MeterID

    BadgeNumber

    Reading

    PK,I3 ReadID

    FK1,I2,I1 MeterID

    ReadDate

    Reading

    Branch

    PK,I3 BranchID

    FK1,I2,I1 AgentID

    BranchAddress

    Region

    PK,I1 RegionID

    RegionName

    CollectingAgent

    PK,I3 AgentID

    FK1,I2,I1 AgencyID

    AgentName

    ServicePoint

    PK,I7 ServicePointID

    FK1,I3,I1 AccountID

    FK2,I5,I4 MeterID

    InstallDate

    I2 Instal lRead ID

    RemovalDate

    I6 Remova lRe ad ID

    CustAccount

    PK,I1 AccountID

    CustName

    CustAddress

    CustCNIC

    CustPhone

    AccountSetupDate

    FK1,I2 PlotSize

    FK2,I3 SubOffice

    ActivityType

    PK ActivityTypeID

    ActivityTypeName

    FK1 ActivityID

  • 8/10/2019 Tugasan Mis

    19/24

    18 | P a g e

    ACTIVITY PLANNING AND CONTROL

  • 8/10/2019 Tugasan Mis

    20/24

    19 | P a g e

  • 8/10/2019 Tugasan Mis

    21/24

    20 | P a g e

    OVERLOADING OF WORKER

  • 8/10/2019 Tugasan Mis

    22/24

    21 | P a g e

    GANTT CHART

  • 8/10/2019 Tugasan Mis

    23/24

    22 | P a g e

    PERT DIAGRAM

  • 8/10/2019 Tugasan Mis

    24/24

    23 | P a g e