    Negotiated cost-plus-a-fee contract, In negotiated cost plus contract,the contractor to perform

    the work for fixed or variable fee covering profit and home office costs, with all field costs

    being reimbursable at actual cost. Common variations will a fixed fee to cover profit and

    general and administrative costs only, with both direct home-office costs being

    reimbursable.incentive fees where some or all of the fee is dependent upon achieving certaincost or schedule goals, are becoming increasingly popular. Cost- plus-percentage- fee

    contract are generally not favored, except for extra work or for minor work where the scope

    is inderminate

    Negosiasi biaya-plus-a-biaya kontrak, biaya Dalam negosiasi ditambah kontrak, kontraktor

    untuk melakukan pekerjaan untuk biaya tetap atau variabel yang mencakup keuntungan dan

    biaya rumah kantor, dengan semua biaya lapangan yang ditagih kembali dengan biaya yang

    sebenarnya. Variasi umum akan biaya tetap untuk menutupi biaya keuntungan dan umum dan

    administrasi saja, dengan kedua langsung rumah-kantor biaya menjadi biaya

    reimbursable.incentive mana beberapa atau semua biaya tersebut tergantung pada pencapaian

    biaya tertentu atau tujuan jadwal, menjadi semakin populer. Biaya-plus-persentase-biayakontrak umumnya tidak disukai, kecuali untuk pekerjaan ekstra atau untuk pekerjaan kecil di

    mana lingkup adalah tak tentu

    Advantages from the owners point of view include the following

    1. These contract system also accepted and hystorically supported2. They permit reduction of design-construct time by utilizing phased construction.3. This approach enables the contractor to react quickly to major design changes and

    unforeseen condition and in part, minimizes the adversary position4. There is an opportunity to utilize contractor expertise during the design phase to helpminimal overall costs

    5. The owner pays for the actual cost of the work plus a negotiated fee which may resultin savings in periods of high demand for construction work.

    6. The owner and general contractor can still subcontract a subtantial portion of thework to prequalified subcontractors, thus achieving fixed prices for specialty work

    7. The owner may participate fully in the management and control of the project to theextent that he has qualified personnel and may exercise control of expenditures in

    advance, may participate in major decisions or acctually supply certain services or

    materials to the contractor

    8. Under the guaranteed maximum price option, the owner may pass on some portion ofthe construction risk to the contractor.

    1. sistem kontrak ini juga diterima dan didukung hystorically

    2. Mereka mengizinkan pengurangan desain-waktu membangun dengan

    memanfaatkan konstruksi bertahap.

    3. Pendekatan ini memungkinkan kontraktor untuk bereaksi dengan cepat terhadap

    perubahan desain besar dan kondisi yang tak terduga dan sebagian, meminimalkan

    posisi musuh

    4. Ada kesempatan untuk memanfaatkan keahlian kontraktor selama fase desain untukmembantu biaya keseluruhan minimal

  • 7/31/2019 Hub Kontrak

    2/2

    5. Pemilik membayar biaya yang sebenarnya dari pekerjaan ditambah biaya negosiasi

    yang dapat mengakibatkan tabungan di periode permintaan tinggi untuk pekerjaan

    konstruksi.

    6. Pemilik dan kontraktor umum masih dapat mensubkontrakkan sebagian subtantial

    pekerjaan kepada subkontraktor prequalified, sehingga mencapai harga tetap untuk

    pekerjaan khusus7. Pemilik dapat berpartisipasi penuh dalam pengelolaan dan pengendalian proyek

    untuk sejauh bahwa ia memiliki teknisi ahli dan dapat melakukan kontrol pengeluaran

    di muka, dapat berpartisipasi dalam keputusan-keputusan besar atau acctually

    menyediakan layanan tertentu atau materi kepada kontraktor

    8. Di bawah pilihan harga maksimum yang dijamin, pemilik dapat menyampaikan

    beberapa bagian dari risiko konstruksi untuk kontraktor.

    Disadvantages from the owners point of view include the following

    1. Costs plus a fixed fee may not be the most economical alternative in a competitivemarket

    2. Disreputable