LOH & LOH CONSTRUCTION SDN.BHD.
CADANGAN PEMBANGUNAN :1 BLOK A PANGSAPURI 23 TINGKAT (87) UNIT DAN 1 BLOK PANGSAPURI 30 TINGKAT (113) DENGAN 3 TINGKAT PODIUM TEMPAT LETAK KERETA , BESERTA KEMUDAHAN PENDUDUK TINGKAT 4 DAN TINGKAT 1 TEMPAT LETAK KERETA SUB-BASEMEN DI ATAS LOT 1843,JALAN DUTAMAS RAYA,MUKIM BATU,DAERAH KUALA LUMPUR.
OCCUPATIONAL SAFETY & HEALTH INSPECTION/OBSERVATION REPORT
Inspection date: 2nd week April 2015Area covered: ALL SITE AREA.Inspected by: ADIFIKRI B. MAT SAH & NATHANKUMAR (Safety & Health Supervisors).
RISK RATINGS.NoSeverity RatingDeficiencyConsequencesNumerical Rating
1REDMajorCondition that could result in Death / Permanent Disability or Major Structural Damage20
2YELLOWModerateCondition that could result in Temporary Disability or Minor Structural Damage and Any Failure of Statutory Requirement15
3BLUEMinorCondition that could result in Minor Injury / First Aid / Near Miss Incident10
4MAGENTAImprovement RequiredCondition that can be still improved
5
GREENPositive Observation -
No.Issue highlightedstatus Action by remarksColor code & risk rating
1
Air compressor have no valid PMT CLOSEDPMT no:
PMT 105016
Global Con Builders
-Nil-
2Improper support scaffold practices.ON-GOING
Competent erector/inspector appointed. Competency cert submitted.
Approved drawing not submitted yet
Global Con Builders
Memo has been issued;Ref no: NKR/SAFETY/001/2015 20
3
No tagline used in lifting activities.
No first aid box present at GCB site cabinON-GOING
Memo issued
Ref: NKR/SAFETY/002/2015
Global Con Builders
-Nil-15
4Global Con Builder S/BStockpiling dirt until blocking access. CLOSED
GCB has provided a earth mover truck to remove dirt
Global Con Builders
-Nil-
5IMPROPER WORK PROCEDURE:
1.Work past 7pm w/o DBKL permit.
2.Employing illegal worker.ON-GOING
Memo issued
Ref: NKR/SAFETY/003/2015
Global Con Builders
-Nil-15
6Adjacent site septic tank leakage & pouring to our site.CLOSED.Septic tank concealed. No more leakage from adjacent site
Safety dept.Loh & Loh construction
-Nil-
7 Crusher run placed at site entrance to control the dirt from site to public road.
Global Con Builders
-Nil-
8Drainage cleaned from rubbish & stones to prevent blockage at drain.
Global Con Builders
-Nil-
Page 3of 4
9Toolbox talk on 9/4/15
Refer :
Toolbox checklist 9/4/14
Global Con Builders
-Nil-
10TC 1 substitute operator have no valid competency certCLOSEDoperator I/C:810626-08-6745
Validity:15/1/2017
Global Con Builders
-Nil-
11Improper diesel storage practice
To be discussed with GCB site team
Global Con Builders
-Nil-15
12GCB new excavator.
To conduct a safe excavation training to all excavator operator.
Safety dept.Loh & Loh construction
-Nil-5
Inspected by,Adi Fikri & NathanKumar(Site Safety Supervisor)Verified by,Mr.Mahmud(Safety & Health Officer)
Page 4 of 4