LAPORAN KEMAJUAN PROJEK NO.13‘OGOS 2008’
PROJEK ADTEC TAIPING
KEMENTERIAN SUMBER MANUSIA
JABATAN KERJA RAYA MALAYSIA
KAMALBINA SDN. BHD
PEMILIK
PEGARAH PROJEK
KONTRAKTOR R&B
ADTEC TAIPING
LOKASI PROJEK
BANGUNAN PENTADBIRAN
BENGKEL TEK. MAKLUMAT& JAMIN KUALITI
DEWAN BESAR
PUSAT SUMBER
DEWAN KULIAH
LOBI UTAMA
KAFETERIA
MIKRO ELEKTRONIK
KOMPOSIT PLASTIK
M&E PLANT ROOM
1
TNB SUB
STATION
SERAMIK
M&E PLANT ROOM
2
GARAJ KENDERAAN
ASRAMA LELAKIASRAMA PEREMPUAN
DEWANMAKAN
SURAU
KELAS F
KELAS G
KUARTERSB, C, C&D
PELAN TAPAK ADTEC TAIPING
KEMAJUAN KERJA FIZIKAL
JADUAL : 33.81%SEBENAR : 41.47%KESELURUHAN : 7.66% ( 56 HARI )
TARIKH LAPORAN : 22 OGOS 2008
KEMAJUAN KERJA KEWANGAN
JADUAL : 39.26%SEBENAR : 43.62%KESELURUHAN : 4.36% ( 32 HARI )
TARIKH LAPORAN : 22 OGOS 2008
Graf Kemajuan Kerja Keseluruhan Sehingga 22/8/2008
0.00
10.00
20.00
30.00
40.00
50.00
60.00
70.00
80.00
90.00
100.00
Bulan
Pera
tus
%
% Ke m . F iz ik a l J a dua l
% Ke m . F iz ik a l S e b e na r
% Ke m . Ke wa ng a n J a dua l
% Ke m . Ke wa ng a n S e b e na r
% Ke m . F iz ik a l J a dua l 0.0 0 0 .48 1.04 2 .56 4.19 6 .12 7 .70 9 .98 13 .53 18.4 4 20.8 2 23 .34 26 .09 29.0 6 30 .76 33 .81 36 .00 40 .00 43 .0 0 49 .82 61.60 74 .17 87 .8 0 98 .95 100 .00
% Ke m . F iz ik a l S e be na r 0.0 0 2 .59 5 .28 7 .56 9.3 0 11.6 4 13 .12 15 .62 18 .74 22.5 3 26.7 3 29 .56 32 .40 35.7 1 37 .09 41.47
% Ke m . Ke wa ng a n J a dua l 0.0 0 0 .94 2 .05 3 .93 5.7 7 8 .92 10 .7 1 13 .46 17 .45 22.2 4 25.6 2 27 .75 31.15 34.5 6 35 .93 39 .26 41.07 44 .32 48 .6 2 56 .49 66 .72 77 .62 89 .3 9 99 .09 100 .00
% Ke m . Ke wa ng a n S e be na r 0.0 0 3 .97 6 .30 13 .91 15 .50 17 .5 8 17 .26 19 .52 22 .30 25.9 3 30.2 6 32 .79 35 .32 38.4 7 38 .97 43 .62
16/05/07 25/06/07 24/07/07 20/08/07 13/09/07 18/10/07 09/11/07 05/12/07 12/01/08 21/02/08 27/03/08 15/04/08 29/05/08 08/07/08 15/07/08 22/08/08 15/09/08 15/10/08 15/11/08 15/12/08 15/01/09 15/02/09 15/03/09 15/04/09 13/05/09
Actual Physical 41.47%Actual
Financial 43.62%
- 19.88%35.41%55.30%JULAI 08’
- 25.63%44.19%69.82%OGOS 08’
AHEAD / DELAYACTUALPLANNEDMONTH
KEMAJUAN KERJA FIZIKAL
DEWAN BESAR
BANGUNAN
DEWAN BESAR
- 17.57%44.76%62.33%JULAI 08’
- 14.27%51.90%66.17%OGOS 08’
AHEAD / DELAYACTUALPLANNEDMONTH
KEMAJUAN KERJA FIZIKAL
LOBI UTAMA
BANGUNAN
LOBI UTAMA
- 6.52%38.72%45.24%JULAI 08’
- 8.44%41.97%50.41%OGOS 08’
AHEAD / DELAYACTUALPLANNEDMONTH
KEMAJUAN KERJA FIZIKAL
DEWAN KULIAH UTAMA
BANGUNAN
DEWAN KULIAH UTAMA
- 4.16%59.46%63.62%JULAI 08’
2.58%68.80%66.22%OGOS 08’
AHEAD / DELAYACTUALPLANNEDMONTH
KEMAJUAN KERJA FIZIKAL
PUSAT SUMBER / PERPUSTAKAAN
BANGUNAN
PUSAT SUMBER / PERPUSTAKAAN
- 4.16%50.97%55.13%JULAI 08’
- 1.19%57.98%59.17%OGOS 08’
AHEAD / DELAYACTUALPLANNEDMONTH
KEMAJUAN KERJA FIZIKAL
PENTADBIRAN & PENGURUSAN SUMBER
BANGUNAN
BANGUNAN PENTADBIRAN & PENGURUSAN SUMBER
23.47%54.35%38.88%JULAI 08’
31.01%70.01%39.00%OGOS 08’
AHEAD / DELAYACTUALPLANNEDMONTH
KEMAJUAN KERJA FIZIKAL
KAFETERIA
BANGUNAN
KAFETERIA
4.09%59.54%55.45%JULAI 08’
4.82%66.38%61.56%OGOS 08’
AHEAD / DELAYACTUALPLANNEDMONTH
KEMAJUAN KERJA FIZIKAL
BENGKEL TEKNOLOGI MAKLUMAT(PENGATURCARAAN & MEKATRONIK)
BANGUNAN
BENGKEL TEKNOLOGI MAKLUMAT
14.92%54.79%39.87%JULAI 08’
15.13%63.31%48.17%OGOS 08’
AHEAD / DELAYACTUALPLANNEDMONTH
KEMAJUAN KERJA FIZIKAL
BENGKEL KEJURUTERAAN BAHAN TERMAJU(PLASTIK)
BANGUNAN
BENGKEL KEJ. BAHAN TERMAJU (PLASTIK)
16.84%53.93%37.09%JULAI 08’
15.12%58.85%43.73%OGOS 08’
AHEAD / DELAYACTUALPLANNEDMONTH
KEMAJUAN KERJA FIZIKAL
BENGKEL KEJURUTERAAN BAHAN TERMAJU(KOMPOSIT)
BANGUNAN
BENGKEL KEJ. BAHAN TERMAJU (KOMPOSIT)
10.81%51.32%40.50%JULAI 08’
6.62%56.74%50.11%OGOS 08’
AHEAD / DELAYACTUALPLANNEDMONTH
KEMAJUAN KERJA FIZIKAL
BENGKEL KEJURUTERAAN BAHAN TERMAJU(SERAMIK)
BANGUNAN
BENGKEL KEJ. BAHAN TERMAJU (SERAMIK)
2.33%53.49%51.17%JULAI 08’
3.50%62.31%58.81%OGOS 08’
AHEAD / DELAYACTUALPLANNEDMONTH
KEMAJUAN KERJA FIZIKAL
BENGKEL KEJURUTERAAN JAMINAN KUALITI
BANGUNAN
BENGKEL KEJ. JAMINAN KUALITI
3.26%48.19%44.93%JULAI 08’
0.03%54.53%54.49%OGOS 08’
AHEAD / DELAYACTUALPLANNEDMONTH
KEMAJUAN KERJA FIZIKAL
BENGKEL MIKRO ELEKTRONIK
BANGUNAN
BENGKEL MIKRO ELEKTRONIK
25.28%62.40%37.12%JULAI 08’
22.38%67.16%44.78%OGOS 08’
AHEAD / DELAYACTUALPLANNEDMONTH
KEMAJUAN KERJA FIZIKAL
KUARTERS KELAS ‘B’
BANGUNAN
KUARTERS KELAS ‘B’
37.15%67.26%30.11%JULAI 08’
33.19%73.25%40.06%OGOS 08’
AHEAD / DELAYACTUALPLANNEDMONTH
KEMAJUAN KERJA FIZIKAL
KUARTERS KELAS ‘C’
BANGUNAN
KUARTERS KELAS ‘C’
18.48%60.34%41.86%JULAI 08’
20.56%65.91%45.34%OGOS 08’
AHEAD / DELAYACTUALPLANNEDMONTH
KEMAJUAN KERJA FIZIKAL
KUARTERS KELAS ‘C & D’
BANGUNAN
KUARTERS KELAS ‘C & D’
16.55%57.82%41.27%JULAI 08’
22.74%68.24%45.50%OGOS 08’
AHEAD / DELAYACTUALPLANNEDMONTH
KEMAJUAN KERJA FIZIKAL
KUARTERS KELAS ‘F’(1 BLOK 4 TINGKAT & 1 BLOK 5 TINGKAT)
BANGUNAN
KUARTERS KELAS ‘F’ ( 4 TINGKAT )
KUARTERS KELAS ‘F’ ( 5 TINGKAT )
25.92%66.26%40.34%JULAI 08’
33.28%77.71%44.42%OGOS 08’
AHEAD / DELAYACTUALPLANNEDMONTH
KEMAJUAN KERJA FIZIKAL
KUARTERS KELAS ‘G’(1 BLOK 4 TINGKAT & 1 BLOK 5 TINGKAT)
BANGUNAN
KUARTERS KELAS ‘G’ ( 5 TINGKAT )
KUARTERS KELAS ‘G’ ( 4 TINGKAT )
16.68%64.13%47.44%JULAI 08’
14.85%73.35%58.50%OGOS 08’
AHEAD / DELAYACTUALPLANNEDMONTH
KEMAJUAN KERJA FIZIKAL
DEWAN MAKAN
BANGUNAN
DEWAN MAKAN
10.83%58.78%47.96%JULAI 08’
9.68%62.37%53.04%OGOS 08’
AHEAD / DELAYACTUALPLANNEDMONTH
KEMAJUAN KERJA FIZIKAL
ASRAMA LELAKI ‘A & B’
BANGUNAN
ASRAMA LELAKI A & B
23.25%60.89%37.65%JULAI 08’
24.48%69.77%45.29%OGOS 08’
AHEAD / DELAYACTUALPLANNEDMONTH
KEMAJUAN KERJA FIZIKAL
ASRAMA PEREMPUAN ‘C & D’
BANGUNAN
ASRAMA PEREMPUAN C & D
4.64%28.19%23.55%JULAI 08’
29.67%56.94%27.27%OGOS 08’
AHEAD / DELAYACTUALPLANNEDMONTH
KEMAJUAN KERJA FIZIKAL
SURAU
BANGUNAN
SURAU
BANGUNAN SOKONGAN
ASTAKA
9.21%54.73%45.53%OGOS 08’
AHEAD / DELAYACTUALPLANNEDMONTH
BANGUNAN SOKONGAN
M&E PLANT ROOM
6.57%33.00%26.43%OGOS 08’
AHEAD / DELAYACTUALPLANNEDMONTH
PEMBINAAN PAGAR HADAPAN
BANGUNAN SOKONGAN
GARAJ KENDERAAN
7.40%51.00%43.60%OGOS 08’
AHEAD / DELAYACTUALPLANNEDMONTH
ELEVATED WATER TANK, PUMP HOUSE & SECTION TANK
10.39%10.39%0.00%Compressed Air
0.00%0.00%0.00%Process Cooling System
-18.53%3.32%21.85%Plumbing & Sanitary
2.59%12.01%9.43%Fire Proc. Services
36.68%37.25%0.57%Air Conditioning System
AHEAD / DELAY
ACTUALPLANNEDDES
MECHANICAL SYSTEM
-1.30%32.38%33.68%Lightning Protec System
6.30%6.69%0.39%Public Address System
25.48%25.90%0.42%SMATV System
16.90%16.90%0.00%Security, Int Alarm & CCTV
59.09%59.09%0.00%External Lighting
0.12%0.12%0.00%Audio Visual System
80.00%80.00%0.00%External Telephone
7.78%7.96%0.18%Submain Cabling
48.11%49.69%1.57%Small Power & Lighting
AHEAD / DELAY
ACTUALPLANNEDDES
ELECTRICAL & ICT INSTALLATION
• SEKIAN TERIMA KASIH