LAPORAN KEMAJUAN PROJEK NO.19 ‘MAC 2009’ PROJEK ADTEC TAIPING KEMENTERIAN SUMBER MANUSIA JABATAN KERJA RAYA MALAYSIA KAMALBINA SDN. BHD PEMILIK PEGARAH PROJEK KONTRAKTOR R&B

Upload: arkam-munaaim-phd-peng-intpe

Post on 24-Jun-2015

416 views

Category:

Business


5 download

TRANSCRIPT

Page 1: Adtec Pre No.19   Mac 09

LAPORAN KEMAJUAN PROJEK NO.19

‘MAC 2009’

PROJEK ADTEC TAIPING

KEMENTERIAN SUMBER MANUSIA

JABATAN KERJA RAYA MALAYSIA

KAMALBINA SDN. BHD

PEMILIK

PEGARAH PROJEK

KONTRAKTOR R&B

Page 2: Adtec Pre No.19   Mac 09

ADTEC TAIPING

LOKASI PROJEK

Page 3: Adtec Pre No.19   Mac 09

BANGUNAN PENTADBIRAN

BENGKEL TEK. MAKLUMAT& JAMIN KUALITI

DEWAN BESAR

PUSAT SUMBER

DEWAN KULIAH

LOBI UTAMA

KAFETERIA

MIKRO ELEKTRONIK

KOMPOSIT PLASTIK

M&E PLANT ROOM

1

TNB SUB

STATION

SERAMIK

M&E PLANT ROOM

2

GARAJ KENDERAAN

ASRAMA LELAKIASRAMA PEREMPUAN

DEWANMAKAN

SURAU

KELAS F

KELAS G

KUARTERSB, C, C&D

PELAN TAPAK ADTEC TAIPING

Page 4: Adtec Pre No.19   Mac 09

KEMAJUAN KERJA FIZIKAL

JADUAL : 84.22%SEBENAR : 68.03%KESELURUHAN : -16.19%

TARIKH LAPORAN : 11 MAC 2009

Page 5: Adtec Pre No.19   Mac 09

KEMAJUAN KERJA KEWANGAN

JADUAL : 86.30%SEBENAR : 68.81%KESELURUHAN : -17.49% @ 136 HARI

(LEWAT )

TARIKH LAPORAN : 11 MAC 2009

Page 6: Adtec Pre No.19   Mac 09

Graf Kemajuan Kerja Keseluruhan Sehingga 11/3/2009

0.00

10.00

20.00

30.00

40.00

50.00

60.00

70.00

80.00

90.00

100.00

Bulan

Per

atu

s %

% Kem. Fizikal J adual % Kem. Fizikal Sebenar

% Kem. Kewangan J adual % Kem. Kewangan Sebenar

% Kem. Fizikal J adual 0.00 0.48 1.04 2.56 4.19 6.12 7.70 9.98 13.53 18.44 20.82 23.34 26.09 29.06 30.76 33.81 36.84 41.32 43.00 47.08 60.55 70.88 84.22 98.95 100.00

% Kem. Fizikal Sebenar 0.00 2.59 5.28 7.56 9.30 11.64 13.12 15.62 18.74 22.53 26.73 29.56 32.40 35.71 37.09 41.47 45.77 46.74 50.89 55.19 58.46 67.03 68.03

% Kem. Kewangan J adual 0.00 0.94 2.05 3.93 5.77 8.92 10.71 13.46 17.45 22.24 25.62 27.75 31.15 34.56 35.93 39.26 42.63 45.59 48.62 52.35 64.16 74.78 86.30 99.09 100.00

% Kem. Kewangan Sebenar 0.00 3.97 6.30 13.91 15.50 17.58 17.26 19.52 22.30 25.93 30.26 32.79 35.32 38.47 38.97 43.62 47.34 48.16 52.42 56.36 59.42 68.50 68.81

16-05-07 25-06-07 24-07-07 20-08-07 13-09-07 18-10-07 09-11-07 05-12-07 12-01-08 21-02-08 27-03-08 15-04-08 29-05-08 08-07-08 15-07-08 22-08-08 19-09-08 28-10-08 14-11-08 04-12-08 08-01-09 12-02-09 11-03-09 15-04-09 13-05-09

Actual Physical 68.03%

Actual Financial

68.81%

Page 7: Adtec Pre No.19   Mac 09

MONTH PLANNED ACTUAL AHEAD / DELAY

FEB 09’ 97.222% 65.52% - 31.70%

MAC 09’ 99.12% 74.17% - 24.95%

MECHANICAL PLANNED

ACTUAL

AIR COND 100.00% 50.00%

FIRE FIGHTING 100.00% 39.77%

KITCHEN EQUIP. NA NA

LPG INSTALL. NA NA

COMPRES. AIR NA NA

DUST CONTROL NA NA

PROCESS COOLING

NA NA

KEMAJUAN KERJA FIZIKAL - DEWAN BESAR

BANGUNAN

ELECTRICAL PLANNED ACTUAL

WIRING 100.00% 85.00%

SUBMAIN CABLE 100.00% 75.00%

DB 100.00% 0.00%

LUMINAIRE 100.00% 0.00%

MAIN S/BOARD 100.00% 0.00%

LPS NA NA

PA 100.00% 31.81%

SMATV 100.00% 25.00%

CCTV NA NA

ICT 100.00% 0.00%

Page 8: Adtec Pre No.19   Mac 09

DEWAN BESAR

Page 9: Adtec Pre No.19   Mac 09

DEWAN BESAR

Page 10: Adtec Pre No.19   Mac 09

MONTH PLANNED ACTUAL AHEAD / DELAY

FEB 09’ 82.83% 78.68% -4.15%

MAC 09’ 95.00% 89.22% -5,78%

MECHANICAL PLANNED

ACTUAL

AIR COND NA NA

FIRE FIGHTING NA NA

KITCHEN EQUIP. NA NA

LPG INSTALL. NA NA

COMPRES. AIR NA NA

DUST CONTROL NA NA

PROCESS COOLING

NA NA

KEMAJUAN KERJA FIZIKAL – LOBI

BANGUNAN

ELECTRICAL PLANNED ACTUAL

WIRING 100.00% 90.00%

SUBMAIN CABLE 100.00% 85.00%

DB 100.00% 0.00%

LUMINAIRE 100.00% 0.00%

MAIN S/BOARD NA NA

LPS NA NA

PA 100.00% 65.37%

SMATV NA NA

CCTV 100.00% 65.37%

ICT NA NA

Page 11: Adtec Pre No.19   Mac 09

LOBI UTAMA

Page 12: Adtec Pre No.19   Mac 09

MONTH PLANNED ACTUAL AHEAD / DELAY

FEB 09’ 83.03% 66.39% -16.64%

MAC 09’ 94.20% 74.34% -19.87%

MECHANICAL PLANNED

ACTUAL

AIR COND 62.86% 75.00%

FIRE FIGHTING 86.64% 3.87%

KITCHEN EQUIP. NA NA

LPG INSTALL. NA NA

COMPRES. AIR NA NA

DUST CONTROL NA NA

PROCESS COOLING

NA NA

KEMAJUAN KERJA FIZIKAL – DEWAN KULIAH UTAMABANGUNAN

ELECTRICAL PLANNED ACTUAL

WIRING 100.00% 90.00%

SUBMAIN CABLE 56.25% 75.00%

DB 100.00% 0.00%

LUMINAIRE 0.00% 50.00%

MAIN S/BOARD 100.00% 0.00%

LPS 100.00% 83.13%

PA 100.00% 28.96%

SMATV NA NA

CCTV NA NA

ICT 100.00% 0.00%

Page 13: Adtec Pre No.19   Mac 09

DEWAN KULIAH UTAMA

Page 14: Adtec Pre No.19   Mac 09

MONTH PLANNED ACTUAL AHEAD / DELAY

FEB 09’ 93.37% 84.41% -8.96%

MAC 09’ 96.79% 85.99% -10.80%

MECHANICAL PLANNED

ACTUAL

AIR COND 100.00% 75.00%

FIRE FIGHTING 79.40% 29.24%

KITCHEN EQUIP. NA NA

LPG INSTALL. NA NA

COMPRES. AIR NA NA

DUST CONTROL NA NA

PROCESS COOLING

NA NA

KEMAJUAN KERJA FIZIKAL – PUSAT SUMBER/PERPUSTAKAAN

BANGUNAN

ELECTRICAL PLANNED ACTUAL

WIRING 100.00% 90.00%

SUBMAIN CABLE 100.00% 85.00%

DB 100.00% 0.00%

LUMINAIRE 100.00% 75.00%

MAIN S/BOARD 100.00% 0.00%

LPS 100.00% 77.33%

PA 100.00% 41.75%

SMATV 100.00% 68.59%

CCTV NA NA

ICT 40.84% 0.00%

Page 15: Adtec Pre No.19   Mac 09

PUSAT SUMBER / PERPUSTAKAAN

Page 16: Adtec Pre No.19   Mac 09

MONTH PLANNED ACTUAL AHEAD / DELAY

FEB 09’ 91.35% 77.52% -13.83%

MAC 09’ 96.07% 83.49% -12.58%

MECHANICAL PLANNED

ACTUAL

AIR COND 95.68% 50.00%

FIRE FIGHTING 81.99% 40.30%

KITCHEN EQUIP. NA NA

LPG INSTALL. NA NA

COMPRES. AIR NA NA

DUST CONTROL NA NA

PROCESS COOLING

NA NA

KEMAJUAN KERJA FIZIKAL – PENTADBIRAN & PENGURUSAN SUMBERBANGUNAN

ELECTRICAL PLANNED ACTUAL

WIRING 100.00% 77.50%

SUBMAIN CABLE 100.00% 75.00%

DB 100.00% 0.00%

LUMINAIRE 100.00% 30.00%

MAIN S/BOARD 100.00% 0.00%

LPS 100.00% 72.59%

PA 100.00% 19.15%

SMATV 100.00% 62.46%

CCTV 99.86% 2.13%

ICT 82,62% 0.00%

Page 17: Adtec Pre No.19   Mac 09

BANGUNAN PENTADBIRAN & PENGURUSAN SUMBER

Page 18: Adtec Pre No.19   Mac 09

MONTH PLANNED ACTUAL AHEAD / DELAY

FEB 09’ 84.36% 89.11% -4.75%

MAC 09’ 94.82% 93.88% -0.95%

MECHANICAL PLANNED

ACTUAL

AIR COND 76.19% 0.00%

FIRE FIGHTING 14.60% 6.32%

KITCHEN EQUIP. 45.48% 0.00%

LPG INSTALL. NA NA

COMPRES. AIR NA NA

DUST CONTROL NA NA

PROCESS COOLING

NA NA

KEMAJUAN KERJA FIZIKAL - KAFETARIA

BANGUNAN

ELECTRICAL PLANNED ACTUAL

WIRING 100.00% 90.00%

SUBMAIN CABLE 100.00% 85.00%

DB 100.00% 0.00%

LUMINAIRE 100.00% 75.00%

MAIN S/BOARD NA NA

LPS 75.13% 66.47%

PA 100.00% 27.35%

SMATV 99.59% 60.35%

CCTV NA NA

ICT 100.00% 0.00%

Page 19: Adtec Pre No.19   Mac 09

KAFETERIA

Page 20: Adtec Pre No.19   Mac 09

MONTH PLANNED ACTUAL AHEAD / DELAY

FEB 09’ 85.84% 81.62% -4.22%

MAC 09’ 95.07% 84.50% -10.56%

MECHANICAL PLANNED

ACTUAL

AIR COND 57.23% 50.00%

FIRE FIGHTING 100.00% 15.93%

KITCHEN EQUIP. NA NA

LPG INSTALL. NA NA

COMPRES. AIR NA NA

DUST CONTROL NA NA

PROCESS COOLING

NA NA

KEMAJUAN KERJA FIZIKAL – BENGKEL TEKNOLOGI MAKLUMATBANGUNAN

ELECTRICAL PLANNED ACTUAL

WIRING 100.00% 90.00%

SUBMAIN CABLE 100.00% 90.00%

DB 100.00% 90.00%

LUMINAIRE 100.00% 50.00%

MAIN S/BOARD 100.00% 0.00%

LPS 100.00% 87.01%

PA 100.00% 42.43%

SMATV 100.00% 70.94%

CCTV 97.59% 33.71%

ICT 29.05% 0.00%

Page 21: Adtec Pre No.19   Mac 09

BENGKEL TEKNOLOGI MAKLUMAT

Page 22: Adtec Pre No.19   Mac 09

MONTH PLANNED ACTUAL AHEAD / DELAY

FEB 09’ 78.05% 86.03% 7.98%

MAC 09’ 88.52% 90.27% 1.75%

MECHANICAL PLANNED

ACTUAL

AIR COND 56.66% 75.00%

FIRE FIGHTING 49.72% 34.03%

KITCHEN EQUIP. NA NA

LPG INSTALL. NA NA

COMPRES. AIR 62.86% 75.00%

DUST CONTROL NA NA

PROCESS COOLING

35.30% 0.00%

KEMAJUAN KERJA FIZIKAL – BENGKEL KEJ. BAHAN TERMAJU (PLASTIK)BANGUNAN

ELECTRICAL PLANNED ACTUAL

WIRING 100.00% 90.00%

SUBMAIN CABLE 47.06% 85.00%

DB 0.00% 0.00%

LUMINAIRE 0.00% 75.00%

MAIN S/BOARD 0.00% 0.00%

LPS 86.70% 91.49%

PA 85.81% 56.22%

SMATV NA NA

CCTV 77.25% 49.69%

ICT 17.49% 1.34%

Page 23: Adtec Pre No.19   Mac 09

BENGKEL KEJ. BAHAN TERMAJU (PLASTIK)

Page 24: Adtec Pre No.19   Mac 09

MONTH PLANNED ACTUAL AHEAD / DELAY

FEB 09’ 79.39% 83.64% 4.25%

MAC 09’ 87.48% 91.18% 3.70%

MECHANICAL PLANNED

ACTUAL

AIR COND 62.87% 75.00%

FIRE FIGHTING 67.96% 32.95%

KITCHEN EQUIP. NA NA

LPG INSTALL. NA NA

COMPRES. AIR 68.57% 75.00%

DUST CONTROL 48.77% 23.77%

PROCESS COOLING

50.33% 0.00%

KEMAJUAN KERJA FIZIKAL – BENGKEL KEJ. BAHAN TERMAJU (KOMPOSIT)BANGUNAN

ELECTRICAL PLANNED ACTUAL

WIRING 100.00% 90.00%

SUBMAIN CABLE 58.22% 85.00%

DB 0.00% 0.00%

LUMINAIRE 35.71% 75.00%

MAIN S/BOARD 35.71% 0.00%

LPS 81.02% 82.52%

PA 83.73% 48.47%

SMATV NA NA

CCTV 92.94% 50.54%

ICT 15.86% 1.16%

Page 25: Adtec Pre No.19   Mac 09

BENGKEL KEJ. BAHAN TERMAJU (KOMPOSIT)

Page 26: Adtec Pre No.19   Mac 09

MONTH PLANNED ACTUAL AHEAD / DELAY

FEB 09’ 76.14% 79.96% 3.82%

MAC 09’ 81.17% 90.55% 9.38%

MECHANICAL PLANNED

ACTUAL

AIR COND 41.99% 75.00%

FIRE FIGHTING 43.45% 33.30%

KITCHEN EQUIP. NA NA

LPG INSTALL. NA NA

COMPRES. AIR 77.14% 75.00%

DUST CONTROL 16.46% 8.86%

PROCESS COOLING

41.29% 0.00%

KEMAJUAN KERJA FIZIKAL – BENGKEL KEJ. BAHAN TERMAJU (SERAMIK)BANGUNAN

ELECTRICAL PLANNED ACTUAL

WIRING 100.00% 90.00%

SUBMAIN CABLE 72.22% 85.00%

DB 0.00% 0.00%

LUMINAIRE 0.00% 75.00%

MAIN S/BOARD 0.00% 0.00%

LPS 76.32% 89.38%

PA 97.72% 49.95%

SMATV NA NA

CCTV 74.79% 57.16%

ICT 23.12% 1.58%

Page 27: Adtec Pre No.19   Mac 09

BENGKEL KEJ. BAHAN TERMAJU (SERAMIK)

Page 28: Adtec Pre No.19   Mac 09

MONTH PLANNED ACTUAL AHEAD / DELAY

FEB 09’ 80.11% 77.74% -2.37%

MAC 09’ 91.91% 83.93% -7.97%

MECHANICAL PLANNED

ACTUAL

AIR COND 53.50% 55.00%

FIRE FIGHTING 79.89% 14.81%

KITCHEN EQUIP. NA NA

LPG INSTALL. NA NA

COMPRES. AIR 100.00% 75.00%

DUST CONTROL 71.70% 19.13%

PROCESS COOLING

NA NA

KEMAJUAN KERJA FIZIKAL – BENGKEL KEJ. JAMINAN KUALITIBANGUNAN

ELECTRICAL PLANNED ACTUAL

WIRING 100.00% 82.50%

SUBMAIN CABLE 100.00% 90.00%

DB 100.00% 85.00%

LUMINAIRE 14.29% 45.00%

MAIN S/BOARD 100.00% 0.00%

LPS 91.41% 81.69%

PA 100.00% 33.28%

SMATV 98.53% 40.97%

CCTV 86.29% 40.48%

ICT 28.12% 0.00%

Page 29: Adtec Pre No.19   Mac 09

BENGKEL KEJ. JAMINAN KUALITI

Page 30: Adtec Pre No.19   Mac 09

MONTH PLANNED ACTUAL AHEAD / DELAY

FEB 09’ 79.37% 78.27% -1.10%

MAC 09’ 89.92% 87.86% -2.06%

MECHANICAL PLANNED

ACTUAL

AIR COND 58.27% 50.00%

FIRE FIGHTING 36.20% 11.16%

KITCHEN EQUIP. NA NA

LPG INSTALL. NA NA

COMPRES. AIR 94.29% 75.00%

DUST CONTROL NA NA

PROCESS COOLING

NA NA

KEMAJUAN KERJA FIZIKAL – BENGKEL MIKRO ELEKTRONIKBANGUNAN

ELECTRICAL PLANNED ACTUAL

WIRING 100.00% 90.00%

SUBMAIN CABLE 90.48% 85.00%

DB 0.00% 7.00%

LUMINAIRE 0.00% 45.00%

MAIN S/BOARD 0.00% 0.00%

LPS 83.20% 84.16%

PA 98.98% 39.69%

SMATV 80.65% 55.50%

CCTV 88.56% 52.62%

ICT 31.59% 0.00%

Page 31: Adtec Pre No.19   Mac 09

BENGKEL MIKRO ELEKTRONIK

Page 32: Adtec Pre No.19   Mac 09

MONTH PLANNED ACTUAL AHEAD / DELAY

FEB 09’ 90.43% 95.76% 5.33%

MAC 09’ 95.86% 96.63% 0.77%

MECHANICAL PLANNED

ACTUAL

AIR COND 100.00% 90.00%

FIRE FIGHTING NA NA

KITCHEN EQUIP. NA NA

LPG INSTALL. NA NA

COMPRES. AIR NA NA

DUST CONTROL NA NA

PROCESS COOLING

NA NA

KEMAJUAN KERJA FIZIKAL – KUATERS KELAS ‘B’

BANGUNAN

ELECTRICAL PLANNED ACTUAL

WIRING 100.00% 90.00%

SUBMAIN CABLE 100.00% 90.00%

DB 100.00% 90.00%

LUMINAIRE 100.00% 90.00%

MAIN S/BOARD 100.00% 0.00%

LPS 100.00% 90.40%

PA NA NA

SMATV 100.00% 32.27%

CCTV 100.00% 34.02%

ICT 100.00% 90.00%

Page 33: Adtec Pre No.19   Mac 09

KUARTERS KELAS ‘B’

Page 34: Adtec Pre No.19   Mac 09

MONTH PLANNED ACTUAL AHEAD / DELAY

FEB 09’ 88.42% 95.12% 6.70%

MAC 09’ 95.03% 96.71% 1.68%

MECHANICAL PLANNED

ACTUAL

AIR COND 100.00% 90.00%

FIRE FIGHTING NA NA

KITCHEN EQUIP. NA NA

LPG INSTALL. NA NA

COMPRES. AIR NA NA

DUST CONTROL NA NA

PROCESS COOLING

NA NA

KEMAJUAN KERJA FIZIKAL – KUATERS KELAS ‘C’

BANGUNAN

ELECTRICAL PLANNED ACTUAL

WIRING 100.00% 90.00%

SUBMAIN CABLE 100.00% 90.00%

DB 100.00% 90.00%

LUMINAIRE 100.00% 90.00%

MAIN S/BOARD 100.00% 0.00%

LPS 98.44% 90.63%

PA NA NA

SMATV 100.00% 24.75%

CCTV NA NA

ICT 100.00% 62.02%

Page 35: Adtec Pre No.19   Mac 09

KUARTERS KELAS ‘C’

Page 36: Adtec Pre No.19   Mac 09

MONTH PLANNED ACTUAL AHEAD / DELAY

FEB 09’ 84.31% 94.25% 9.94%

MAC 09’ 92.69% 96.33% 3.63%

MECHANICAL PLANNED

ACTUAL

AIR COND 100.00% 90.00%

FIRE FIGHTING NA NA

KITCHEN EQUIP. NA NA

LPG INSTALL. NA NA

COMPRES. AIR NA NA

DUST CONTROL NA NA

PROCESS COOLING

NA NA

KEMAJUAN KERJA FIZIKAL – KUATERS KELAS ‘C+D’BANGUNAN

ELECTRICAL PLANNED ACTUAL

WIRING 100.00% 90.00%

SUBMAIN CABLE 100.00% 90.00%

DB 100.00% 90.00%

LUMINAIRE 100.00% 90.00%

MAIN S/BOARD 100.00% 0.00%

LPS 100.00% 91.85%

PA NA NA

SMATV 100.00% 32.27%

CCTV NA NA

ICT 100.00% 90.00%

Page 37: Adtec Pre No.19   Mac 09

KUARTERS KELAS ‘C’ + ‘D’

Page 38: Adtec Pre No.19   Mac 09

MONTH PLANNED ACTUAL AHEAD / DELAY

FEB 09’ 77.45% 91.08% 13.63%

MAC 09’ 85.15% 94.13% 8.98%

MECHANICAL PLANNED

ACTUAL

AIR COND NA NA

FIRE FIGHTING NA NA

KITCHEN EQUIP. NA NA

LPG INSTALL. NA NA

COMPRES. AIR NA NA

DUST CONTROL NA NA

PROCESS COOLING

NA NA

KEMAJUAN KERJA FIZIKAL – KUATERS KELAS F ( 1 BLOK 4 TINGKAT & I BLOK 5 TINGKAT)BANGUNAN

ELECTRICAL PLANNED ACTUAL

WIRING 100.00% 90.00%

SUBMAIN CABLE 52.38% 90.00%

DB 0.00% 90.00%

LUMINAIRE 0.00% 90.00%

MAIN S/BOARD 0.00% 0.00%

LPS 100.00% 88.80%

PA NA NA

SMATV 100.00% 73.58%

CCTV NA NA

ICT 100.00% 65.58%

Page 39: Adtec Pre No.19   Mac 09

KUARTERS KELAS ‘F’ ( 4 TINGKAT )

Page 40: Adtec Pre No.19   Mac 09

KUARTERS KELAS ‘F’ ( 5 TINGKAT )

Page 41: Adtec Pre No.19   Mac 09

MONTH PLANNED ACTUAL AHEAD / DELAY

FEB 09’ 77.88% 92.63% 14.75%

MAC 09’ 86.68% 93.87% 7.19%

MECHANICAL PLANNED

ACTUAL

AIR COND NA NA

FIRE FIGHTING NA NA

KITCHEN EQUIP. NA NA

LPG INSTALL. NA NA

COMPRES. AIR NA NA

DUST CONTROL NA NA

PROCESS COOLING

NA NA

KEMAJUAN KERJA FIZIKAL – KUATERS KELAS G

(1 BLOK 4 TINGKAT & 1 BLOK 5 TINGKAT)BANGUNAN

ELECTRICAL PLANNED ACTUAL

WIRING 100.00% 90.00%

SUBMAIN CABLE 100.00% 90.00%

DB 44.44% 90.00%

LUMINAIRE 0.00% 90.00%

MAIN S/BOARD 26.67% 0.00%

LPS 100.00% 88.80%

PA NA NA

SMATV 100.00% 73.58%

CCTV NA NA

ICT 100.00% 69.85%

Page 42: Adtec Pre No.19   Mac 09

KUARTERS KELAS ‘G’ ( 5 TINGKAT )

Page 43: Adtec Pre No.19   Mac 09

KUARTERS KELAS ‘G’ ( 4 TINGKAT )

Page 44: Adtec Pre No.19   Mac 09

MONTH PLANNED ACTUAL AHEAD / DELAY

FEB 09’ 98.16% 94.87% -3.29%

MAC 09’ 98.39% 96.95% -1.44%

MECHANICAL PLANNED

ACTUAL

AIR COND 100.00% 75.00%

FIRE FIGHTING 100.00% 12.24%

KITCHEN EQUIP. 42.73% 0.00%

LPG INSTALL. NA NA

COMPRES. AIR NA NA

DUST CONTROL NA NA

PROCESS COOLING

NA NA

KEMAJUAN KERJA FIZIKAL – DEWAN MAKAN

BANGUNAN

ELECTRICAL PLANNED ACTUAL

WIRING 100.00% 90.00%

SUBMAIN CABLE 100.00% 85.00%

DB 100.00% 50.00%

LUMINAIRE 100.00% 75.00%

MAIN S/BOARD 100.00% 0.00%

LPS 100.00% 88.67%

PA 100.00% 51.18%

SMATV 100.00% 60.35%

CCTV NA NA

ICT 100.00% 0.00%

Page 45: Adtec Pre No.19   Mac 09

DEWAN MAKAN

Page 46: Adtec Pre No.19   Mac 09

MONTH PLANNED ACTUAL AHEAD / DELAY

FEB 09’ 86.42% 91.05% 4.63%

MAC 09’ 92.69% 95.69% 3.00%

MECHANICAL PLANNED

ACTUAL

AIR COND 100.00% 10.00%

FIRE FIGHTING 100.00% 29.58%

KITCHEN EQUIP. NA NA

LPG INSTALL. NA NA

COMPRES. AIR NA NA

DUST CONTROL NA NA

PROCESS COOLING

NA NA

KEMAJUAN KERJA FIZIKAL – ASRAMA LELAKI A & BBANGUNAN

ELECTRICAL PLANNED ACTUAL

WIRING 89.29% 86.25%

SUBMAIN CABLE 0.00% 85.00%

DB 0.00% 50.00%

LUMINAIRE 0.00% 75.00%

MAIN S/BOARD 0.00% 0.00%

LPS 93.12% 85.86%

PA 60.31% 54.28%

SMATV 60.53% 54.88%

CCTV 42.12% 31.69%

ICT 98.57% 78.12%

Page 47: Adtec Pre No.19   Mac 09

ASRAMA LELAKI A & B

Page 48: Adtec Pre No.19   Mac 09

MONTH PLANNED ACTUAL AHEAD / DELAY

FEB 09’ 81.04% 93.81% 12.77%

MAC 09’ 90.09% 96.91% 6.82%

MECHANICAL PLANNED

ACTUAL

AIR COND 17.86% 10.00%

FIRE FIGHTING 46.33% 20.18%

KITCHEN EQUIP. NA NA

LPG INSTALL. NA NA

COMPRES. AIR NA NA

DUST CONTROL NA NA

PROCESS COOLING

NA NA

KEMAJUAN KERJA FIZIKAL – ASRAMA PEREMPUAN C & DBANGUNAN

ELECTRICAL PLANNED ACTUAL

WIRING 100.00% 90.00%

SUBMAIN CABLE 100.00% 85.00%

DB 100.00% 50.00%

LUMINAIRE 100.00% 75.00%

MAIN S/BOARD 100.00% 0.00%

LPS 93.12% 85.86%

PA 60.31% 54.28%

SMATV 60.53% 54.88%

CCTV 42.12% 31.69%

ICT 98.57% 78.12%

Page 49: Adtec Pre No.19   Mac 09

ASRAMA PEREMPUAN C & D

Page 50: Adtec Pre No.19   Mac 09

MONTH PLANNED ACTUAL AHEAD / DELAY

FEB 09’ 77.94% 78.73% 0.79%

MAC 09’ 86.10% 84.06% -2.04%

MECHANICAL PLANNED

ACTUAL

AIR COND NA NA

FIRE FIGHTING 57.14% 0.00%

KITCHEN EQUIP. NA NA

LPG INSTALL. NA NA

COMPRES. AIR NA NA

DUST CONTROL NA NA

PROCESS COOLING

NA NA

KEMAJUAN KERJA FIZIKAL - SURAU

BANGUNAN

ELECTRICAL PLANNED ACTUAL

WIRING 100.00% 75.00%

SUBMAIN CABLE 41.67% 75.00%

DB NA NA

LUMINAIRE 0.00% 0.00%

MAIN S/BOARD 0.00% 0.00%

LPS 65.01% 81.70%

PA 87.81% 22.89%

SMATV NA NA

CCTV NA NA

ICT NA NA

Page 51: Adtec Pre No.19   Mac 09

SURAU

Page 52: Adtec Pre No.19   Mac 09

MONTH PLANNED ACTUAL AHEAD / DELAY

FEB 09’ 91.60% 87.62% 3.98%

MAC 09’ 99.03% 98.95% -0.45%

MECHANICAL PLANNED

ACTUAL

AIR COND NA NA

FIRE FIGHTING 0.00% 0.00%

KITCHEN EQUIP. NA NA

LPG INSTALL. NA NA

COMPRES. AIR NA NA

DUST CONTROL NA NA

PROCESS COOLING

NA NA

KEMAJUAN KERJA FIZIKAL - ASTAKA

BANGUNAN SOKONGAN

ELECTRICAL PLANNED ACTUAL

WIRING 100.00% 90.00%

SUBMAIN CABLE 100.00% 85.00%

DB 100.00% 0.00%

LUMINAIRE 100.00% 75.00%

MAIN S/BOARD 100.00% 0.00%

LPS 69.22% 37.93%

PA 100.00% 28.62%

SMATV NA NA

CCTV NA NA

ICT NA NA

Page 53: Adtec Pre No.19   Mac 09

BANGUNAN SOKONGAN

ASTAKA

Page 54: Adtec Pre No.19   Mac 09

MONTH PLANNED ACTUAL AHEAD / DELAY

MAC 09’ 91.00% 99.77% 8.77%

MECHANICAL PLANNED

ACTUAL

AIR COND 94.03% 77.59%

FIRE FIGHTING 79.72% 0.00%

KITCHEN EQUIP. NA NA

LPG INSTALL. 0.00% 0.00%

COMPRES. AIR NA NA

DUST CONTROL NA NA

PROCESS COOLING

NA NA

KEMAJUAN KERJA FIZIKAL – M&E PLANT ROOM

BANGUNAN SOKONGAN

ELECTRICAL PLANNED ACTUAL

WIRING 100.00% 90.00%

SUBMAIN CABLE 100.00% 75.00%

DB 100.00% 0.00%

LUMINAIRE 100.00% 75.00%

MAIN S/BOARD 100.00% 0.00%

LPS NA NA

PA NA NA

SMATV NA NA

CCTV NA NA

ICT NA NA

Page 55: Adtec Pre No.19   Mac 09

BANGUNAN SOKONGAN

M&E PLANT ROOM – PUSAT SUMBER

Page 56: Adtec Pre No.19   Mac 09

BANGUNAN SOKONGAN

M&E PLANT ROOM - BENGKEL

Page 57: Adtec Pre No.19   Mac 09

DECORATIVE FENCE

Page 58: Adtec Pre No.19   Mac 09

BANGUNAN SOKONGAN

GARAJ KENDERAAN

Page 59: Adtec Pre No.19   Mac 09

ELEVATED WATER TANK, PUMP HOUSE & SUCTION TANK

Page 60: Adtec Pre No.19   Mac 09

WAKAF

Page 61: Adtec Pre No.19   Mac 09

LALUAN BERBUMBUNG

Page 62: Adtec Pre No.19   Mac 09

OPEN PLAZA

Page 63: Adtec Pre No.19   Mac 09

KERJA INFRA – JALAN UTAMA

Page 64: Adtec Pre No.19   Mac 09

GELANGGANG PERMAINAN

Page 65: Adtec Pre No.19   Mac 09

M&E INSTALLATION

Page 66: Adtec Pre No.19   Mac 09

M&E INSTALLATION

Page 67: Adtec Pre No.19   Mac 09

M&E INSTALLATION

Page 68: Adtec Pre No.19   Mac 09

BENGKEL MIKROELEKTRONIK – CLEAN ROOM

Page 69: Adtec Pre No.19   Mac 09

BENGKEL MIKROELEKTRONIK – CLEAN ROOM

Page 70: Adtec Pre No.19   Mac 09

• SEKIAN TERIMA KASIH