adtec pre no.20 april 09

71
LAPORAN KEMAJUAN PROJEK NO.20 ‘APRIL 2009’ PROJEK ADTEC TAIPING KEMENTERIAN SUMBER MANUSIA JABATAN KERJA RAYA MALAYSIA KAMALBINA SDN. BHD PEMILIK PEGARAH PROJEK KONTRAKTOR R&B

Upload: muhammad-arkam

Post on 03-Nov-2014

19 views

Category:

Technology


3 download

DESCRIPTION

 

TRANSCRIPT

Page 1: Adtec Pre No.20   April 09

LAPORAN KEMAJUAN PROJEK NO.20

‘APRIL 2009’

PROJEK ADTEC TAIPING

KEMENTERIAN SUMBER MANUSIA

JABATAN KERJA RAYA MALAYSIA

KAMALBINA SDN. BHD

PEMILIK

PEGARAH PROJEK

KONTRAKTOR R&B

Page 2: Adtec Pre No.20   April 09

ADTEC TAIPING

LOKASI PROJEK

Page 3: Adtec Pre No.20   April 09

BANGUNAN PENTADBIRAN

BENGKEL TEK. MAKLUMAT& JAMIN KUALITI

DEWAN BESAR

PUSAT SUMBER

DEWAN KULIAH

LOBI UTAMA

KAFETERIA

MIKRO ELEKTRONIK

KOMPOSIT PLASTIK

M&E PLANT ROOM

1

TNB SUB

STATION

SERAMIK

M&E PLANT ROOM

2

GARAJ KENDERAAN

ASRAMA LELAKIASRAMA PEREMPUAN

DEWANMAKAN

SURAU

KELAS F

KELAS G

KUARTERSB, C, C&D

PELAN TAPAK ADTEC TAIPING

Page 4: Adtec Pre No.20   April 09

KEMAJUAN KERJA FIZIKAL

JADUAL : 99.14%SEBENAR : 73.45%KESELURUHAN : -25.69%

TARIKH LAPORAN : 16 APRIL 2009

Page 5: Adtec Pre No.20   April 09

KEMAJUAN KERJA KEWANGAN

JADUAL : 99.26%SEBENAR : 74.19%KESELURUHAN : -25.07% @ 182 HARI

(LEWAT )

TARIKH LAPORAN : 16 APRIL 2009

Page 6: Adtec Pre No.20   April 09
Page 7: Adtec Pre No.20   April 09

MONTH PLANNED ACTUAL AHEAD / DELAY

MAC 09’ 99.12% 74.17% - 24.95%

APRIL 09’ 100% 85.77% - 14.23%

MECHANICAL PLANNED

ACTUAL

AIR COND 100.00% 83.25%

FIRE FIGHTING 100.00% 42.40%

KITCHEN EQUIP. NA NA

LPG INSTALL. NA NA

COMPRES. AIR NA NA

DUST CONTROL NA NA

PROCESS COOLING

NA NA

KEMAJUAN KERJA FIZIKAL - DEWAN BESAR

BANGUNAN

ELECTRICAL PLANNED ACTUAL

WIRING 100.00% 87.50%

SUBMAIN CABLE 100.00% 80.00%

DB 100.00% 0.00%

LUMINAIRE 100.00% 55.00%

MAIN S/BOARD 100.00% 0.00%

LPS NA NA

PA 100.00% 38.17%

SMATV 100.00% 28.33%

CCTV NA NA

ICT 100.00% 0.00%

Page 8: Adtec Pre No.20   April 09

DEWAN BESAR

Page 9: Adtec Pre No.20   April 09

DEWAN BESAR

Page 10: Adtec Pre No.20   April 09

MONTH PLANNED ACTUAL AHEAD / DELAY

MAC 09’ 95.00% 89.22% -5.78%

APRIL 09’ 100.00% 94.30% -5.70%

MECHANICAL PLANNED

ACTUAL

AIR COND NA NA

FIRE FIGHTING NA NA

KITCHEN EQUIP. NA NA

LPG INSTALL. NA NA

COMPRES. AIR NA NA

DUST CONTROL NA NA

PROCESS COOLING

NA NA

KEMAJUAN KERJA FIZIKAL – LOBI

BANGUNAN

ELECTRICAL PLANNED ACTUAL

WIRING 100.00% 90.00%

SUBMAIN CABLE 100.00% 87.00%

DB 100.00% 0.00%

LUMINAIRE 100.00% 75.00%

MAIN S/BOARD NA NA

LPS NA NA

PA NA NA

SMATV NA NA

CCTV 100.00% 72.63%

ICT NA NA

Page 11: Adtec Pre No.20   April 09

LOBI UTAMA

Page 12: Adtec Pre No.20   April 09

MONTH PLANNED ACTUAL AHEAD / DELAY

MAC 09’ 94.20% 74.34% -19.87%

APRIL 09’ 99.45% 81.81% -17.64%

MECHANICAL PLANNED

ACTUAL

AIR COND 62.86% 82.50%

FIRE FIGHTING 86.64% 7.73%

KITCHEN EQUIP. NA NA

LPG INSTALL. NA NA

COMPRES. AIR NA NA

DUST CONTROL NA NA

PROCESS COOLING

NA NA

KEMAJUAN KERJA FIZIKAL – DEWAN KULIAH UTAMABANGUNAN

ELECTRICAL PLANNED ACTUAL

WIRING 100.00% 90.00%

SUBMAIN CABLE 56.25% 80.00%

DB 100.00% 0.00%

LUMINAIRE 100.00% 75.00%

MAIN S/BOARD 100.00% 0.00%

LPS 100.00% 80.61%

PA 100.00% 34.76%

SMATV NA NA

CCTV NA NA

ICT 100.00% 0.00%

Page 13: Adtec Pre No.20   April 09

DEWAN KULIAH UTAMA

Page 14: Adtec Pre No.20   April 09

MONTH PLANNED ACTUAL AHEAD / DELAY

MAC 09’ 96.79% 85.99% -10.80%

APRIL 09’ 100.00% 91.94% -8.06%

MECHANICAL PLANNED

ACTUAL

AIR COND 100.00% 82.76%

FIRE FIGHTING 100.00% 34.78%

KITCHEN EQUIP. NA NA

LPG INSTALL. NA NA

COMPRES. AIR NA NA

DUST CONTROL NA NA

PROCESS COOLING

NA NA

KEMAJUAN KERJA FIZIKAL – PUSAT SUMBER/PERPUSTAKAAN

BANGUNAN

ELECTRICAL PLANNED ACTUAL

WIRING 100.00% 90.00%

SUBMAIN CABLE 100.00% 87.00%

DB 100.00% 0.00%

LUMINAIRE 100.00% 75.00%

MAIN S/BOARD 100.00% 0.00%

LPS 100.00% 85.10%

PA 100.00% 41.75%

SMATV 100.00% 76.21%

CCTV NA NA

ICT 40.84% 4.84%

Page 15: Adtec Pre No.20   April 09

PUSAT SUMBER / PERPUSTAKAAN

Page 16: Adtec Pre No.20   April 09

MONTH PLANNED ACTUAL AHEAD / DELAY

MAC 09’ 96.07% 83.49% -12.58%

APRIL 09’ 100.00% 88.93% -11.07%

MECHANICAL PLANNED

ACTUAL

AIR COND 100.00% 82.44%

FIRE FIGHTING 100.00% 40.30%

KITCHEN EQUIP. NA NA

LPG INSTALL. NA NA

COMPRES. AIR NA NA

DUST CONTROL NA NA

PROCESS COOLING

NA NA

KEMAJUAN KERJA FIZIKAL – PENTADBIRAN & PENGURUSAN SUMBERBANGUNAN

ELECTRICAL PLANNED ACTUAL

WIRING 100.00% 90.00%

SUBMAIN CABLE 100.00% 85.00%

DB 100.00% 0.00%

LUMINAIRE 100.00% 55.00%

MAIN S/BOARD 100.00% 0.00%

LPS 100.00% 79.94%

PA 100.00% 19.15%

SMATV 100.00% 69.40%

CCTV 100.00% 2.36%

ICT 100.00% 4.36%

Page 17: Adtec Pre No.20   April 09

BANGUNAN PENTADBIRAN & PENGURUSAN SUMBER

Page 18: Adtec Pre No.20   April 09

MONTH PLANNED ACTUAL AHEAD / DELAY

MAC 09’ 94.82% 93.88% -0.95%

APRIL 09’ 100.00% 96.14% -03.86%

MECHANICAL PLANNED

ACTUAL

AIR COND 100.00% 0.00%

FIRE FIGHTING 100.00% 6.32%

KITCHEN EQUIP. 82.89% 18.00%

LPG INSTALL. NA NA

COMPRES. AIR NA NA

DUST CONTROL NA NA

PROCESS COOLING

NA NA

KEMAJUAN KERJA FIZIKAL - KAFETARIA

BANGUNAN

ELECTRICAL PLANNED ACTUAL

WIRING 100.00% 90.00%

SUBMAIN CABLE 100.00% 100.00%

DB 100.00% 10.00%

LUMINAIRE 100.00% 75.00%

MAIN S/BOARD NA NA

LPS 100.00% 66.47%

PA 100.00% 27.35%

SMATV 100.00% 67.06%

CCTV NA NA

ICT 100.00% 0.00%

Page 19: Adtec Pre No.20   April 09

KAFETERIA

Page 20: Adtec Pre No.20   April 09

MONTH PLANNED ACTUAL AHEAD / DELAY

MAC 09’ 95.07% 84.50% -10.56%

APRIL 09’ 99.67% 89.84% -9.82%

MECHANICAL PLANNED

ACTUAL

AIR COND 100.00% 66.97%

FIRE FIGHTING 100.00% 15.93%

KITCHEN EQUIP. NA NA

LPG INSTALL. NA NA

COMPRES. AIR NA NA

DUST CONTROL NA NA

PROCESS COOLING

NA NA

KEMAJUAN KERJA FIZIKAL – BENGKEL TEKNOLOGI MAKLUMATBANGUNAN

ELECTRICAL PLANNED ACTUAL

WIRING 100.00% 90.00%

SUBMAIN CABLE 100.00% 90.00%

DB 100.00% 90.00%

LUMINAIRE 100.00% 75.00%

MAIN S/BOARD 100.00% 0.00%

LPS 100.00% 84.62%

PA 100.00% 50.29%

SMATV 100.00% 78.82%

CCTV 100.00% 37.46%

ICT 100.00% 0.00%

Page 21: Adtec Pre No.20   April 09

BENGKEL TEKNOLOGI MAKLUMAT

Page 22: Adtec Pre No.20   April 09

MONTH PLANNED ACTUAL AHEAD / DELAY

MAC 09’ 88.52% 90.27% 1.75%

APRIL 09’ 99.20% 94.41% -4.79%

MECHANICAL PLANNED

ACTUAL

AIR COND 100.00% 80.11%

FIRE FIGHTING 100.00% 45.37%

KITCHEN EQUIP. NA NA

LPG INSTALL. NA NA

COMPRES. AIR 100.00% 75.00%

DUST CONTROL NA NA

PROCESS COOLING

100.00% 0.00%

KEMAJUAN KERJA FIZIKAL – BENGKEL KEJ. BAHAN TERMAJU (PLASTIK)BANGUNAN

ELECTRICAL PLANNED ACTUAL

WIRING 100.00% 90.00%

SUBMAIN CABLE 100.00% 90.00%

DB 100.00% 0.00%

LUMINAIRE 100.00% 85.00%

MAIN S/BOARD 100.00% 0.00%

LPS 100.00% 91.49%

PA 100.00% 56.22%

SMATV NA NA

CCTV 100.00% 55.21%

ICT 89.05% 2.35%

Page 23: Adtec Pre No.20   April 09

BENGKEL KEJ. BAHAN TERMAJU (PLASTIK)

Page 24: Adtec Pre No.20   April 09

MONTH PLANNED ACTUAL AHEAD / DELAY

MAC 09’ 87.48% 91.18% 3.70%

APRIL 09’ 99.13% 94.65% -4.48%

MECHANICAL PLANNED

ACTUAL

AIR COND 100.00% 78.34%

FIRE FIGHTING 100.00% 32.95%

KITCHEN EQUIP. NA NA

LPG INSTALL. NA NA

COMPRES. AIR 100.00% 75.00%

DUST CONTROL 100.00% 24.40%

PROCESS COOLING

100.00% 0.00%

KEMAJUAN KERJA FIZIKAL – BENGKEL KEJ. BAHAN TERMAJU (KOMPOSIT)BANGUNAN

ELECTRICAL PLANNED ACTUAL

WIRING 100.00% 90.00%

SUBMAIN CABLE 100.00% 87.00%

DB 100.00% 0.00%

LUMINAIRE 100.00% 85.00%

MAIN S/BOARD 100.00% 0.00%

LPS 100.00% 82.52%

PA 100.00% 48.47%

SMATV NA NA

CCTV 100.00% 56.15%

ICT 94.14% 1.16%

Page 25: Adtec Pre No.20   April 09

BENGKEL KEJ. BAHAN TERMAJU (KOMPOSIT)

Page 26: Adtec Pre No.20   April 09

MONTH PLANNED ACTUAL AHEAD / DELAY

MAC 09’ 81.17% 90.55% 9.38%

APRIL 09’ 98.21% 92.30% -5.91%

MECHANICAL PLANNED

ACTUAL

AIR COND 100.00% 78.29%

FIRE FIGHTING 98.01% 33.30%

KITCHEN EQUIP. NA NA

LPG INSTALL. NA NA

COMPRES. AIR 100.00% 75.00%

DUST CONTROL 100.00% 9.09%

PROCESS COOLING

100.00% 0.00%

KEMAJUAN KERJA FIZIKAL – BENGKEL KEJ. BAHAN TERMAJU (SERAMIK)BANGUNAN

ELECTRICAL PLANNED ACTUAL

WIRING 100.00% 90.00%

SUBMAIN CABLE 100.00% 90.00%

DB 100.00% 0.00%

LUMINAIRE 100.00% 85.00%

MAIN S/BOARD 100.00% 0.00%

LPS 100.00% 89.38%

PA 100.00% 49.95%

SMATV NA NA

CCTV 100.00% 63.51%

ICT 100.00% 2.36%

Page 27: Adtec Pre No.20   April 09

BENGKEL KEJ. BAHAN TERMAJU (SERAMIK)

Page 28: Adtec Pre No.20   April 09

MONTH PLANNED ACTUAL AHEAD / DELAY

MAC 09’ 91.91% 83.93% -7.97%

APRIL 09’ 99.71% 91.02% -8.70%

MECHANICAL PLANNED

ACTUAL

AIR COND 100.00% 59.54%

FIRE FIGHTING 100.00% 21.39%

KITCHEN EQUIP. NA NA

LPG INSTALL. NA NA

COMPRES. AIR 100.00% 75.00%

DUST CONTROL 100.00% 29.45%

PROCESS COOLING

NA NA

KEMAJUAN KERJA FIZIKAL – BENGKEL KEJ. JAMINAN KUALITIBANGUNAN

ELECTRICAL PLANNED ACTUAL

WIRING 100.00% 90.00%

SUBMAIN CABLE 100.00% 90.00%

DB 100.00% 90.00%

LUMINAIRE 100.00% 55.00%

MAIN S/BOARD 100.00% 0.00%

LPS 100.00% 81.69%

PA 100.00% 39.94%

SMATV 100.00% 45.52%

CCTV 100.00% 44.98%

ICT 100.00% 0.00%

Page 29: Adtec Pre No.20   April 09

BENGKEL KEJ. JAMINAN KUALITI

Page 30: Adtec Pre No.20   April 09

MONTH PLANNED ACTUAL AHEAD / DELAY

MAC 09’ 89.92% 87.86% -2.06%

APRIL 09’ 98.51% 90.05% -8.47%

MECHANICAL PLANNED

ACTUAL

AIR COND 100.00% 81.50%

FIRE FIGHTING 100.00% 11.16%

KITCHEN EQUIP. NA NA

LPG INSTALL. NA NA

COMPRES. AIR 100.00% 75.00%

DUST CONTROL NA NA

PROCESS COOLING

NA NA

KEMAJUAN KERJA FIZIKAL – BENGKEL MIKRO ELEKTRONIKBANGUNAN

ELECTRICAL PLANNED ACTUAL

WIRING 100.00% 90.00%

SUBMAIN CABLE 100.00% 90.00%

DB 100.00% 25.00%

LUMINAIRE 100.00% 55.00%

MAIN S/BOARD 100.00% 0.00%

LPS 100.00% 84.16%

PA 100.00% 47.63%

SMATV 100.00% 61.66%

CCTV 100.00% 58.47%

ICT 89.84% 0.00%

Page 31: Adtec Pre No.20   April 09

BENGKEL MIKRO ELEKTRONIK

Page 32: Adtec Pre No.20   April 09

MONTH PLANNED ACTUAL AHEAD / DELAY

MAC 09’ 95.86% 96.63% 0.77%

APRIL 09’ 100.00% 96.79% -3.21%

MECHANICAL PLANNED

ACTUAL

AIR COND 100.00% 90.00%

FIRE FIGHTING NA NA

KITCHEN EQUIP. NA NA

LPG INSTALL. NA NA

COMPRES. AIR NA NA

DUST CONTROL NA NA

PROCESS COOLING

NA NA

KEMAJUAN KERJA FIZIKAL – KUATERS KELAS ‘B’

BANGUNAN

ELECTRICAL PLANNED ACTUAL

WIRING 100.00% 90.00%

SUBMAIN CABLE 100.00% 90.00%

DB 100.00% 90.00%

LUMINAIRE 100.00% 90.00%

MAIN S/BOARD 100.00% 0.00%

LPS 100.00% 90.40%

PA NA NA

SMATV 100.00% 35.86%

CCTV 100.00% 37.80%

ICT 100.00% 90.00%

Page 33: Adtec Pre No.20   April 09

KUARTERS KELAS ‘B’

Page 34: Adtec Pre No.20   April 09

MONTH PLANNED ACTUAL AHEAD / DELAY

MAC 09’ 95.03% 96.71% 1.68%

APRIL 09’ 100.00% 96.94% -3.06%

MECHANICAL PLANNED

ACTUAL

AIR COND 100.00% 90.00%

FIRE FIGHTING NA NA

KITCHEN EQUIP. NA NA

LPG INSTALL. NA NA

COMPRES. AIR NA NA

DUST CONTROL NA NA

PROCESS COOLING

NA NA

KEMAJUAN KERJA FIZIKAL – KUATERS KELAS ‘C’

BANGUNAN

ELECTRICAL PLANNED ACTUAL

WIRING 100.00% 90.00%

SUBMAIN CABLE 100.00% 90.00%

DB 100.00% 90.00%

LUMINAIRE 100.00% 100.00%

MAIN S/BOARD 100.00% 0.00%

LPS 100.00% 90.63%

PA NA NA

SMATV 100.00% 27.51%

CCTV NA NA

ICT 100.00% 62.02%

Page 35: Adtec Pre No.20   April 09

KUARTERS KELAS ‘C’

Page 36: Adtec Pre No.20   April 09

MONTH PLANNED ACTUAL AHEAD / DELAY

MAC 09’ 92.69% 96.33% 3.63%

APRIL 09’ 100.00% 96.38% -3.62%

MECHANICAL PLANNED

ACTUAL

AIR COND 100.00% 90.00%

FIRE FIGHTING NA NA

KITCHEN EQUIP. NA NA

LPG INSTALL. NA NA

COMPRES. AIR NA NA

DUST CONTROL NA NA

PROCESS COOLING

NA NA

KEMAJUAN KERJA FIZIKAL – KUATERS KELAS ‘C+D’BANGUNAN

ELECTRICAL PLANNED ACTUAL

WIRING 100.00% 90.00%

SUBMAIN CABLE 100.00% 90.00%

DB 100.00% 90.00%

LUMINAIRE 100.00% 100.00%

MAIN S/BOARD 100.00% 0.00%

LPS 100.00% 91.85%

PA NA NA

SMATV 100.00% 35.86%

CCTV NA NA

ICT 100.00% 90.00%

Page 37: Adtec Pre No.20   April 09

KUARTERS KELAS ‘C’ + ‘D’

Page 38: Adtec Pre No.20   April 09

MONTH PLANNED ACTUAL AHEAD / DELAY

MAC 09’ 85.15% 94.13% 8.98%

APRIL 09’ 99.68% 94.20% -5.48%

MECHANICAL PLANNED

ACTUAL

AIR COND NA NA

FIRE FIGHTING NA NA

KITCHEN EQUIP. NA NA

LPG INSTALL. NA NA

COMPRES. AIR NA NA

DUST CONTROL NA NA

PROCESS COOLING

NA NA

KEMAJUAN KERJA FIZIKAL – KUATERS KELAS F ( 1 BLOK 4 TINGKAT & I BLOK 5 TINGKAT)BANGUNAN

ELECTRICAL PLANNED ACTUAL

WIRING 100.00% 90.00%

SUBMAIN CABLE 100.00% 90.00%

DB 100.00% 90.00%

LUMINAIRE 100.00% 100.00%

MAIN S/BOARD 100.00% 0.00%

LPS 100.00% 88.80%

PA NA NA

SMATV 100.00% 81.76%

CCTV NA NA

ICT 100.00% 67.18%

Page 39: Adtec Pre No.20   April 09

KUARTERS KELAS ‘F’ ( 4 TINGKAT )

Page 40: Adtec Pre No.20   April 09

KUARTERS KELAS ‘F’ ( 5 TINGKAT )

Page 41: Adtec Pre No.20   April 09

MONTH PLANNED ACTUAL AHEAD / DELAY

MAC 09’ 86.68% 93.87% 7.19%

APRIL 09’ 99.33% 93.98% -5.35%

MECHANICAL PLANNED

ACTUAL

AIR COND NA NA

FIRE FIGHTING NA NA

KITCHEN EQUIP. NA NA

LPG INSTALL. NA NA

COMPRES. AIR NA NA

DUST CONTROL NA NA

PROCESS COOLING

NA NA

KEMAJUAN KERJA FIZIKAL – KUATERS KELAS G

(1 BLOK 4 TINGKAT & 1 BLOK 5 TINGKAT)BANGUNAN

ELECTRICAL PLANNED ACTUAL

WIRING 100.00% 90.00%

SUBMAIN CABLE 100.00% 90.00%

DB 100.00% 90.00%

LUMINAIRE 77.27% 100.00%

MAIN S/BOARD 100.00% 0.00%

LPS 100.00% 88.80%

PA NA NA

SMATV 100.00% 81.76%

CCTV NA NA

ICT 100.00% 69.85%

Page 42: Adtec Pre No.20   April 09

KUARTERS KELAS ‘G’ ( 5 TINGKAT )

Page 43: Adtec Pre No.20   April 09

KUARTERS KELAS ‘G’ ( 4 TINGKAT )

Page 44: Adtec Pre No.20   April 09

MONTH PLANNED ACTUAL AHEAD / DELAY

MAC 09’ 98.39% 96.95% -1.44%

APRIL 09’ 100.00% 97.34% -2.66%

MECHANICAL PLANNED

ACTUAL

AIR COND 100.00% 75.00%

FIRE FIGHTING 100.00% 12.24%

KITCHEN EQUIP. 82.98% 18.00%

LPG INSTALL. NA NA

COMPRES. AIR NA NA

DUST CONTROL NA NA

PROCESS COOLING

NA NA

KEMAJUAN KERJA FIZIKAL – DEWAN MAKAN

BANGUNAN

ELECTRICAL PLANNED ACTUAL

WIRING 100.00% 90.00%

SUBMAIN CABLE 100.00% 90.00%

DB 100.00% 75.00%

LUMINAIRE 100.00% 80.00%

MAIN S/BOARD 100.00% 0.00%

LPS 100.00% 88.67%

PA 100.00% 51.18%

SMATV 100.00% 67.06%

CCTV NA NA

ICT 100.00% 1.40%

Page 45: Adtec Pre No.20   April 09

DEWAN MAKAN

Page 46: Adtec Pre No.20   April 09

MONTH PLANNED ACTUAL AHEAD / DELAY

MAC 09’ 92.69% 95.69% 3.00%

APRIL 09’ 100.00% 97.10% -2.90%

MECHANICAL PLANNED

ACTUAL

AIR COND 100.00% 10.00%

FIRE FIGHTING 100.00% 38.83%

KITCHEN EQUIP. NA NA

LPG INSTALL. NA NA

COMPRES. AIR NA NA

DUST CONTROL NA NA

PROCESS COOLING

NA NA

KEMAJUAN KERJA FIZIKAL – ASRAMA LELAKI A & BBANGUNAN

ELECTRICAL PLANNED ACTUAL

WIRING 100.00% 90.00%

SUBMAIN CABLE 90.48% 90.00%

DB 22.22% 50.00%

LUMINAIRE 62.50% 90.00%

MAIN S/BOARD 43.75% 0.00%

LPS 100.00% 84.86%

PA 100.00% 57.78%

SMATV 100.00% 60.98%

CCTV 100.00% 37.44%

ICT 100.00% 73.53%

Page 47: Adtec Pre No.20   April 09

ASRAMA LELAKI A & B

Page 48: Adtec Pre No.20   April 09

MONTH PLANNED ACTUAL AHEAD / DELAY

MAC 09’ 90.09% 96.91% 6.82%

APRIL 09’ 99.99% 97.67% -2.32%

MECHANICAL PLANNED

ACTUAL

AIR COND 100.00% 10.00%

FIRE FIGHTING 100.00% 46.61%

KITCHEN EQUIP. NA NA

LPG INSTALL. NA NA

COMPRES. AIR NA NA

DUST CONTROL NA NA

PROCESS COOLING

NA NA

KEMAJUAN KERJA FIZIKAL – ASRAMA PEREMPUAN C & DBANGUNAN

ELECTRICAL PLANNED ACTUAL

WIRING 100.00% 90.00%

SUBMAIN CABLE 100.00% 90.00%

DB 100.00% 55.00%

LUMINAIRE 100.00% 90.00%

MAIN S/BOARD 100.00% 0.00%

LPS 100.00% 85.86%

PA 100.00% 54.28%

SMATV 100.00% 60.98%

CCTV 100.00% 35.21%

ICT 100.00% 78.12%

Page 49: Adtec Pre No.20   April 09

ASRAMA PEREMPUAN C & D

Page 50: Adtec Pre No.20   April 09

MONTH PLANNED ACTUAL AHEAD / DELAY

MAC 09’ 86.10% 84.06% -2.04%

APRIL 09’ 98.65% 92.10% -6.55%

MECHANICAL PLANNED

ACTUAL

AIR COND NA NA

FIRE FIGHTING 100.00% 0.00%

KITCHEN EQUIP. NA NA

LPG INSTALL. NA NA

COMPRES. AIR NA NA

DUST CONTROL NA NA

PROCESS COOLING

NA NA

KEMAJUAN KERJA FIZIKAL - SURAU

BANGUNAN

ELECTRICAL PLANNED ACTUAL

WIRING 100.00% 90.00%

SUBMAIN CABLE 100.00% 85.00%

DB NA NA

LUMINAIRE 92.31% 25.00%

MAIN S/BOARD 100.00% 0.00%

LPS 95.12% 81.70%

PA 100.00% 27.47%

SMATV NA NA

CCTV NA NA

ICT NA NA

Page 51: Adtec Pre No.20   April 09

SURAU

Page 52: Adtec Pre No.20   April 09

MONTH PLANNED ACTUAL AHEAD / DELAY

MAC 09’ 99.03% 98.59% -0.45%

APRIL 09’ 100.00% 98.86% -1.14%

MECHANICAL PLANNED

ACTUAL

AIR COND NA NA

FIRE FIGHTING 100.00% 0.00%

KITCHEN EQUIP. NA NA

LPG INSTALL. NA NA

COMPRES. AIR NA NA

DUST CONTROL NA NA

PROCESS COOLING

NA NA

KEMAJUAN KERJA FIZIKAL - ASTAKA

BANGUNAN SOKONGAN

ELECTRICAL PLANNED ACTUAL

WIRING 100.00% 90.00%

SUBMAIN CABLE 100.00% 85.00%

DB 100.00% 0.00%

LUMINAIRE 100.00% 90.00%

MAIN S/BOARD 100.00% 0.00%

LPS 96.86% 69.95%

PA 100.00% 34.34%

SMATV NA NA

CCTV NA NA

ICT NA NA

Page 53: Adtec Pre No.20   April 09

BANGUNAN SOKONGAN

ASTAKA

Page 54: Adtec Pre No.20   April 09

MONTH PLANNED ACTUAL AHEAD / DELAY

APRIL 09’ 100.00% 99.77% -0.23%

MECHANICAL PLANNED

ACTUAL

AIR COND 98.48% 83.47%

FIRE FIGHTING 100.00% 0.00%

KITCHEN EQUIP. NA NA

LPG INSTALL. NA NA

COMPRES. AIR NA NA

DUST CONTROL NA NA

PROCESS COOLING

NA NA

KEMAJUAN KERJA FIZIKAL – M&E PLANT ROOM

BANGUNAN SOKONGAN

ELECTRICAL PLANNED ACTUAL

WIRING 100.00% 90.00%

SUBMAIN CABLE 100.00% 80.00%

DB 100.00% 0.00%

LUMINAIRE 100.00% 85.00%

MAIN S/BOARD 100.00% 0.00%

LPS NA NA

PA NA NA

SMATV NA NA

CCTV NA NA

ICT NA NA

Page 55: Adtec Pre No.20   April 09

BANGUNAN SOKONGAN

M&E PLANT ROOM – PUSAT SUMBER

Page 56: Adtec Pre No.20   April 09

BANGUNAN SOKONGAN

M&E PLANT ROOM - BENGKEL

Page 57: Adtec Pre No.20   April 09

DECORATIVE FENCE

Page 58: Adtec Pre No.20   April 09

BANGUNAN SOKONGAN

GARAJ KENDERAAN

Page 59: Adtec Pre No.20   April 09

ELEVATED WATER TANK, PUMP HOUSE & SUCTION TANK

Page 60: Adtec Pre No.20   April 09

WAKAF

Page 61: Adtec Pre No.20   April 09

LALUAN BERBUMBUNG

Page 62: Adtec Pre No.20   April 09

OPEN PLAZA

Page 63: Adtec Pre No.20   April 09

KERJA INFRA – JALAN UTAMA

Page 64: Adtec Pre No.20   April 09

GELANGGANG PERMAINAN

Page 65: Adtec Pre No.20   April 09

GELANGGANG PERMAINAN

Page 66: Adtec Pre No.20   April 09

M&E INSTALLATION

Page 67: Adtec Pre No.20   April 09

M&E INSTALLATION

Page 68: Adtec Pre No.20   April 09

M&E INSTALLATION

Page 69: Adtec Pre No.20   April 09

BENGKEL MIKROELEKTRONIK – CLEAN ROOM

Page 70: Adtec Pre No.20   April 09

BENGKEL MIKROELEKTRONIK – CLEAN ROOM

Page 71: Adtec Pre No.20   April 09

• SEKIAN TERIMA KASIH