LAPORAN KEMAJUAN PROJEK NO.17
‘JANUARI 2009’
PROJEK ADTEC TAIPING
KEMENTERIAN SUMBER MANUSIA
JABATAN KERJA RAYA MALAYSIA
KAMALBINA SDN. BHD
PEMILIK
PEGARAH PROJEK
KONTRAKTOR R&B
ADTEC TAIPING
LOKASI PROJEK
BANGUNAN PENTADBIRAN
BENGKEL TEK. MAKLUMAT& JAMIN KUALITI
DEWAN BESAR
PUSAT SUMBER
DEWAN KULIAH
LOBI UTAMA
KAFETERIA
MIKRO ELEKTRONIK
KOMPOSIT PLASTIK
M&E PLANT ROOM
1
TNB SUB
STATION
SERAMIK
M&E PLANT ROOM
2
GARAJ KENDERAAN
ASRAMA LELAKIASRAMA PEREMPUAN
DEWANMAKAN
SURAU
KELAS F
KELAS G
KUARTERSB, C, C&D
PELAN TAPAK ADTEC TAIPING
KEMAJUAN KERJA FIZIKAL
JADUAL : 60.55%SEBENAR : 58.46%KESELURUHAN : -2.09% (-3 HARI @LEWAT )
Jumlah Hari (Kontrak) : 729 hari
Jumlah Hari Terpakai : 604 hari
Baki Hari Tinggal : 125 hari
TARIKH LAPORAN : 08 JAN 2009
KEMAJUAN KERJA KEWANGAN
JADUAL : 64.16%SEBENAR : 59.42%KESELURUHAN : -4.74% (-16 HARI@LEWAT
)
TARIKH LAPORAN : 08 JAN 2009
Graf Kemajuan Kerja Keseluruhan Sehingga 8/1/2009
0.00
10.00
20.00
30.00
40.00
50.00
60.00
70.00
80.00
90.00
100.00
Bulan
Pera
tus
%
% Kem. Fizikal J adual % Kem. Fizikal Sebenar
% Kem. Kewangan J adual % Kem. Kewangan Sebenar
% Kem. Fizikal J adual 0.00 0.48 1.04 2.56 4.19 6.12 7.70 9.98 13.53 18.44 20.82 23.34 26.09 29.06 30.76 33.81 36.84 41.32 43.00 47.08 60.55 74.17 87.80 98.95 100.00
% Kem. Fizikal Sebenar 0.00 2.59 5.28 7.56 9.30 11.64 13.12 15.62 18.74 22.53 26.73 29.56 32.40 35.71 37.09 41.47 45.77 46.74 50.89 55.19 58.46
% Kem. Kewangan J adual 0.00 0.94 2.05 3.93 5.77 8.92 10.71 13.46 17.45 22.24 25.62 27.75 31.15 34.56 35.93 39.26 42.63 45.59 48.62 52.35 64.16 77.62 89.39 99.09 100.00
% Kem. Kewangan Sebenar 0.00 3.97 6.30 13.91 15.50 17.58 17.26 19.52 22.30 25.93 30.26 32.79 35.32 38.47 38.97 43.62 47.34 48.16 52.42 56.36 59.42
16-05-07 25-06-07 24-07-07 20-08-07 13-09-07 18-10-07 09-11-07 05-12-07 12-01-08 21-02-08 27-03-08 15-04-08 29-05-08 08-07-08 15-07-08 22-08-08 19-09-08 28-10-08 14-11-08 04-12-08 08-01-09 15-02-09 15-03-09 15-04-09 13-05-09
Actual Physical 58.46%
Actual Financial
59.42%
MONTH PLANNED ACTUAL AHEAD / DELAY
DEC 08’ 96.48% 63.63% - 32.85%
JAN 09’ 98.98% 65.52% - 33.46%
MECHANICAL PLANNED
ACTUAL
AIR COND 100.00% 41.23%
FIRE FIGHTING 100.00% 15.85%
KITCHEN EQUIP. NA NA
LPG INSTALL. NA NA
COMPRES. AIR NA NA
DUST CONTROL NA NA
PROCESS COOLING
NA NA
KEMAJUAN KERJA FIZIKAL - DEWAN BESAR
BANGUNAN
ELECTRICAL PLANNED ACTUAL
WIRING 100.00% 21.87%
SUBMAIN CABLE 100.00% 76.86%
DB 100.00% 0.00%
LUMINAIRE 100.00% 0.00%
MAIN S/BOARD 100.00% 0.00%
LPS NA NA
PA 100.00% 4.65%
SMATV 100.00% 17.63%
CCTV NA NA
ICT 100.00% 12.65%
DEWAN BESAR
DEWAN BESAR
MONTH PLANNED ACTUAL AHEAD / DELAY
DEC 08’ 88.19% 75.93% -12.26%
JAN 09’ 93.25% 78.68% -14.57%
MECHANICAL PLANNED
ACTUAL
AIR COND NA NA
FIRE FIGHTING NA NA
KITCHEN EQUIP. NA NA
LPG INSTALL. NA NA
COMPRES. AIR NA NA
DUST CONTROL NA NA
PROCESS COOLING
NA NA
KEMAJUAN KERJA FIZIKAL – LOBI
BANGUNAN
ELECTRICAL PLANNED ACTUAL
WIRING 100.00% 34.87%
SUBMAIN CABLE 100.00% 90.00%
DB 100.00% 0.00%
LUMINAIRE 100.00% 0.00%
MAIN S/BOARD NA NA
LPS NA NA
PA NA NA
SMATV NA NA
CCTV 100.00% 0.00%
ICT NA NA
LOBI UTAMA
MONTH PLANNED ACTUAL AHEAD / DELAY
DEC 08’ 66.43% 64.09% -2.34%
JAN 09’ 73.49% 66.39% -7.10%
MECHANICAL PLANNED
ACTUAL
AIR COND 27.78% 74.50%
FIRE FIGHTING 7.73% 44.64%
KITCHEN EQUIP. NA NA
LPG INSTALL. NA NA
COMPRES. AIR NA NA
DUST CONTROL NA NA
PROCESS COOLING
NA NA
KEMAJUAN KERJA FIZIKAL – DEWAN KULIAH UTAMA
BANGUNAN
ELECTRICAL PLANNED ACTUAL
WIRING 100.00% 15.98%
SUBMAIN CABLE 56.25% 90.00%
DB 0.00% 0.00%
LUMINAIRE 0.00% 0.00%
MAIN S/BOARD 0.00% 0.00%
LPS 68.63% 6.36%
PA 0.00% 1.13%
SMATV NA NA
CCTV NA NA
ICT 87.16% 12.43%
DEWAN KULIAH UTAMA
MONTH PLANNED ACTUAL AHEAD / DELAY
DEC 08’ 77.77% 79.99% 2.22%
JAN 09’ 84.29% 84.41% 0.12%
MECHANICAL PLANNED
ACTUAL
AIR COND 53.14% 79.23%
FIRE FIGHTING 20.20% 87.69%
KITCHEN EQUIP. NA NA
LPG INSTALL. NA NA
COMPRES. AIR NA NA
DUST CONTROL NA NA
PROCESS COOLING
NA NA
KEMAJUAN KERJA FIZIKAL – PUSAT SUMBER/PERPUSTAKAAN
BANGUNAN
ELECTRICAL PLANNED ACTUAL
WIRING 100.00% 54.76%
SUBMAIN CABLE 100.00% 88.87%
DB 100.00% 0.00%
LUMINAIRE 100.00% 0.00%
MAIN S/BOARD 100.00% 0.00%
LPS 87.53% 74.87%
PA 100.00% 2.53%
SMATV 98.41% 32.43%
CCTV NA NA
ICT 18.66% 5.42%
PUSAT SUMBER / PERPUSTAKAAN
MONTH PLANNED ACTUAL AHEAD / DELAY
DEC 08’ 74.06% 76.86% 2.80%
JAN 09’ 82.12% 77.52% -4.60%
MECHANICAL PLANNED
ACTUAL
AIR COND 38.59% 57.68%
FIRE FIGHTING 38.79% 32.97%
KITCHEN EQUIP. NA NA
LPG INSTALL. NA NA
COMPRES. AIR NA NA
DUST CONTROL NA NA
PROCESS COOLING
NA NA
KEMAJUAN KERJA FIZIKAL – PENTADBIRAN & PENGURUSAN SUMBER
BANGUNAN
ELECTRICAL PLANNED ACTUAL
WIRING 100.00% 65.76%
SUBMAIN CABLE 100.00% 79.76%
DB 28.57% 0.00%
LUMINAIRE 0.00% 0.00%
MAIN S/BOARD 16.67% 25.87%
LPS 64.21% 55.82%
PA 97.25% 18.30%
SMATV 78.64% 27.76%
CCTV 2.36% 4.54%
ICT 47.46% 1.23%
BANGUNAN PENTADBIRAN & PENGURUSAN SUMBER
MONTH PLANNED ACTUAL AHEAD / DELAY
DEC 08’ 68.75% 88.90% 20.15%
JAN 09’ 72.24% 89.11% 16.88%
MECHANICAL PLANNED
ACTUAL
AIR COND 0.00% 43.00%
FIRE FIGHTING 12.65% 24.86%
KITCHEN EQUIP. 0.00% 0.00%
LPG INSTALL. NA NA
COMPRES. AIR NA NA
DUST CONTROL NA NA
PROCESS COOLING
NA NA
KEMAJUAN KERJA FIZIKAL - KAFETARIA
BANGUNAN
ELECTRICAL PLANNED ACTUAL
WIRING 50.00% 79.65%
SUBMAIN CABLE 0.00% 90.00%
DB 0.00% 0.00%
LUMINAIRE 0.00% 0.00%
MAIN S/BOARD NA NA
LPS 39.17% 1.19%
PA 16.36% 14.65%
SMATV 33.53% 12.54%
CCTV NA NA
ICT 0.00% 67.65%
KAFETERIA
MONTH PLANNED ACTUAL AHEAD / DELAY
DEC 08’ 75.87% 83.53% 7.66%
JAN 09’ 79.02% 84.02% 5.01%
MECHANICAL PLANNED
ACTUAL
AIR COND 23.57% 66.78%
FIRE FIGHTING 27.70% 33.67%
KITCHEN EQUIP. NA NA
LPG INSTALL. NA NA
COMPRES. AIR NA NA
DUST CONTROL NA NA
PROCESS COOLING
NA NA
KEMAJUAN KERJA FIZIKAL – BENGKEL TEKNOLOGI MAKLUMAT
BANGUNAN
ELECTRICAL PLANNED ACTUAL
WIRING 100.00% 62.65%
SUBMAIN CABLE 42.86% 28.96%
DB 0.00% 2.00%
LUMINAIRE 0.00% 0.00%
MAIN S/BOARD 0.00% 0.00%
LPS 70.13% 52.65%
PA 77.09% 32.65%
SMATV 81.24% 27.54%
CCTV 30.77% 33.65%
ICT 18.50% 7.53%
BENGKEL TEKNOLOGI MAKLUMAT
MONTH PLANNED ACTUAL AHEAD / DELAY
DEC 08’ 67.06% 84.11% 17.06%
JAN 09’ 68.69% 86.03% 17.33%
MECHANICAL PLANNED
ACTUAL
AIR COND 11.35% 64.16%
FIRE FIGHTING 20.14% 50.54%
KITCHEN EQUIP. NA NA
LPG INSTALL. NA NA
COMPRES. AIR 0.00% 47.85%
DUST CONTROL NA NA
PROCESS COOLING
0.00% 0.00%
KEMAJUAN KERJA FIZIKAL – BENGKEL KEJ. BAHAN TERMAJU (PLASTIK)
BANGUNAN
ELECTRICAL PLANNED ACTUAL
WIRING 0.00% 67.43%
SUBMAIN CABLE 0.00% 78.87%
DB 0.00% 0.00%
LUMINAIRE 0.00% 0.00%
MAIN S/BOARD 0.00% 0.00%
LPS 42.64% 52.87%
PA 0.00% 22.54%
SMATV NA NA
CCTV 0.00% 28.64%
ICT 0.00% 17.54%
BENGKEL KEJ. BAHAN TERMAJU (PLASTIK)
MONTH PLANNED ACTUAL AHEAD / DELAY
DEC 08’ 67.85% 80.57% 12.73%
JAN 09’ 71.23% 83.64% 12.41%
MECHANICAL PLANNED
ACTUAL
AIR COND 14.75% 56.54%
FIRE FIGHTING 15.26% 58.27%
KITCHEN EQUIP. NA NA
LPG INSTALL. NA NA
COMPRES. AIR 0.00% 56.64%
DUST CONTROL 0.00% 23.76%
PROCESS COOLING
0.00 0.00%
KEMAJUAN KERJA FIZIKAL – BENGKEL KEJ. BAHAN TERMAJU (KOMPOSIT)
BANGUNAN
ELECTRICAL PLANNED ACTUAL
WIRING 0.00% 76.00%
SUBMAIN CABLE 0.00% 53.76%
DB 0.00% 0.00%
LUMINAIRE 0.00% 0.00%
MAIN S/BOARD 0.00% 2.00%
LPS 38.74% 55.87%
PA 0.00% 23.75%
SMATV NA NA
CCTV 0.00% 29.76%
ICT 0.00% 13.43%
BENGKEL KEJ. BAHAN TERMAJU (KOMPOSIT)
MONTH PLANNED ACTUAL AHEAD / DELAY
DEC 08’ 68.02% 79.88% 11.86%
JAN 09’ 71.02% 79.96% 8.84%
MECHANICAL PLANNED
ACTUAL
AIR COND 3.41% 43.14%
FIRE FIGHTING 17.84% 53.54%
KITCHEN EQUIP. NA NA
LPG INSTALL. NA NA
COMPRES. AIR 0.00% 57.62%
DUST CONTROL 0.00% 25.76%
PROCESS COOLING
0.00% 0.00%
KEMAJUAN KERJA FIZIKAL – BENGKEL KEJ. BAHAN TERMAJU (SERAMIK)
BANGUNAN
ELECTRICAL PLANNED ACTUAL
WIRING 0.00% 65.64%
SUBMAIN CABLE 0.00% 84.78%
DB 0.00% 0.00%
LUMINAIRE 0.00% 0.00%
MAIN S/BOARD 0.00% 0.00%
LPS 35.83% 56.98%
PA 0.00% 19.64%
SMATV NA NA
CCTV 0.00% 32.65%
ICT 0.00% 17.84%
BENGKEL KEJ. BAHAN TERMAJU (SERAMIK)
MONTH PLANNED ACTUAL AHEAD / DELAY
DEC 08’ 70.13% 73.47% 3.35%
JAN 09’ 77.16% 77.74% 0.58%
MECHANICAL PLANNED
ACTUAL
AIR COND 6.16% 53.26%
FIRE FIGHTING 16.68% 35.74%
KITCHEN EQUIP. NA NA
LPG INSTALL. NA NA
COMPRES. AIR 17.14% 12.00%
DUST CONTROL 6.56% 16.76%
PROCESS COOLING
NA NA
KEMAJUAN KERJA FIZIKAL – BENGKEL KEJ. JAMINAN KUALITI
BANGUNAN
ELECTRICAL PLANNED ACTUAL
WIRING 71.43% 67.45%
SUBMAIN CABLE 0.00% 79.65%
DB 0.00% 0.00%
LUMINAIRE 0.00% 0.00%
MAIN S/BOARD 0.00% 2.00%
LPS 40.33% 63.75%
PA 17.55% 27.43%
SMATV 19.51% 22.31%
CCTV 9.64% 29.64%
ICT 5.05% 13.56%
BENGKEL KEJ. JAMINAN KUALITI
MONTH PLANNED ACTUAL AHEAD / DELAY
DEC 08’ 68.59% 77.02% 8.07%
JAN 09’ 72.73% 78.27% 5.54%
MECHANICAL PLANNED
ACTUAL
AIR COND 0.00% 65.87%
FIRE FIGHTING 7.77% 35.36%
KITCHEN EQUIP. NA NA
LPG INSTALL. NA NA
COMPRES. AIR 0.00% 34.76%
DUST CONTROL NA NA
PROCESS COOLING
NA NA
KEMAJUAN KERJA FIZIKAL – BENGKEL MIKRO ELEKTRONIK
BANGUNAN
ELECTRICAL PLANNED ACTUAL
WIRING 17.86% 45.76%
SUBMAIN CABLE 0.00% 12.87%
DB 0.00% 0.00%
LUMINAIRE 0.00% 0.00%
MAIN S/BOARD 0.00% 0.00%
LPS 35.43% 55.75%
PA 0.00% 23.75%
SMATV 0.00% 24.05%
CCTV 10.44% 26.75%
ICT 0.00% 8.65%
BENGKEL MIKRO ELEKTRONIK
MONTH PLANNED ACTUAL AHEAD / DELAY
DEC 08’ 74.99% 95.35% 20.37%
JAN 09’ 80.19% 96.63% 16.44%
MECHANICAL PLANNED
ACTUAL
AIR COND 100.00% 100.00%
FIRE FIGHTING NA NA
KITCHEN EQUIP. NA NA
LPG INSTALL. NA NA
COMPRES. AIR NA NA
DUST CONTROL NA NA
PROCESS COOLING
NA NA
KEMAJUAN KERJA FIZIKAL – KUATERS KELAS ‘B’
BANGUNAN
ELECTRICAL PLANNED ACTUAL
WIRING 100.00% 90.00%
SUBMAIN CABLE 100.00% 90.00%
DB 100.00% 75.00%
LUMINAIRE 0.00% 65.00%
MAIN S/BOARD 71.43% 0.00%
LPS 75.01% 0.00%
PA NA NA
SMATV 66.12% 37.53%
CCTV 52.44% 12.65%
ICT 100.00% 57.76%
KUARTERS KELAS ‘B’
MONTH PLANNED ACTUAL AHEAD / DELAY
DEC 08’ 67.99% 96.06% 28.07%
JAN 09’ 81.59% 96.76% 15.16%
MECHANICAL PLANNED
ACTUAL
AIR COND 100.00% 100.00%
FIRE FIGHTING NA NA
KITCHEN EQUIP. NA NA
LPG INSTALL. NA NA
COMPRES. AIR NA NA
DUST CONTROL NA NA
PROCESS COOLING
NA NA
KEMAJUAN KERJA FIZIKAL – KUATERS KELAS ‘C’
BANGUNAN
ELECTRICAL PLANNED ACTUAL
WIRING 90.48% 90.00%
SUBMAIN CABLE 0.00% 90.00%
DB 0.00% 75.00%
LUMINAIRE 0.00% 65.00%
MAIN S/BOARD 0.00% 0.00%
LPS 56.21% 0.00%
PA NA NA
SMATV 31.94% 42.53%
CCTV NA NA
ICT 74.38% 17.85%
KUARTERS KELAS ‘C’
MONTH PLANNED ACTUAL AHEAD / DELAY
DEC 08’ 64.72% 95.45% 30.73%
JAN 09’ 69.32% 96.38% 27.06%
MECHANICAL PLANNED
ACTUAL
AIR COND 100.00% 100.00%
FIRE FIGHTING NA NA
KITCHEN EQUIP. NA NA
LPG INSTALL. NA NA
COMPRES. AIR NA NA
DUST CONTROL NA NA
PROCESS COOLING
NA NA
KEMAJUAN KERJA FIZIKAL – KUATERS KELAS ‘C+D’
BANGUNAN
ELECTRICAL PLANNED ACTUAL
WIRING 100.00% 90.00%
SUBMAIN CABLE 91.67% 90.00%
DB 0.00% 75.00%
LUMINAIRE 0.00% 65.00%
MAIN S/BOARD 0.00% 0.00%
LPS 76.69% 0.00%
PA NA NA
SMATV 63.36% 42.86%
CCTV NA NA
ICT 100.00% 65.65%
KUARTERS KELAS ‘C’ + ‘D’
MONTH PLANNED ACTUAL AHEAD / DELAY
DEC 08’ 70.42% 89.51% 19.09%
JAN 09’ 73.69% 91.08% 17.39%
MECHANICAL PLANNED
ACTUAL
AIR COND NA NA
FIRE FIGHTING NA NA
KITCHEN EQUIP. NA NA
LPG INSTALL. NA NA
COMPRES. AIR NA NA
DUST CONTROL NA NA
PROCESS COOLING
NA NA
KEMAJUAN KERJA FIZIKAL – KUATERS KELAS F ( 1 BLOK 4 TINGKAT & I BLOK 5 TINGKAT)
BANGUNAN
ELECTRICAL PLANNED ACTUAL
WIRING 70.48% 90.00%
SUBMAIN CABLE 0.00% 90.00%
DB 0.00% 0.00%
LUMINAIRE 0.00% 80.00%
MAIN S/BOARD 0.00% 0.00%
LPS 88.27% 43.58%
PA NA NA
SMATV 93.03% 55.64%
CCTV NA NA
ICT 100.00% 33.12%
KUARTERS KELAS ‘F’ ( 4 TINGKAT )
KUARTERS KELAS ‘F’ ( 5 TINGKAT )
MONTH PLANNED ACTUAL AHEAD / DELAY
DEC 08’ 71.62% 92.42% 20.80%
JAN 09’ 73.24% 92.63% 19.39%
MECHANICAL PLANNED
ACTUAL
AIR COND NA NA
FIRE FIGHTING NA NA
KITCHEN EQUIP. NA NA
LPG INSTALL. NA NA
COMPRES. AIR NA NA
DUST CONTROL NA NA
PROCESS COOLING
NA NA
KEMAJUAN KERJA FIZIKAL – KUATERS KELAS G (1 BLOK 4 TINGKAT & 1 BLOK 5 TINGKAT)
BANGUNAN
ELECTRICAL PLANNED ACTUAL
WIRING 77.14% 90.00%
SUBMAIN CABLE 0.00% 90.00%
DB 0.00% 0.00%
LUMINAIRE 0.00% 90.00%
MAIN S/BOARD 0.00% 0.00%
LPS 97.10% 56.32%
PA NA NA
SMATV 97.10% 56.32%
CCTV NA NA
ICT 100.00% 29.36%
KUARTERS KELAS ‘G’ ( 5 TINGKAT )
KUARTERS KELAS ‘G’ ( 4 TINGKAT )
MONTH PLANNED ACTUAL AHEAD / DELAY
DEC 08’ 93.89% 92.14% -1.75%
JAN 09’ 96.42% 94.87% -1.55%
MECHANICAL PLANNED
ACTUAL
AIR COND 80.00% 85.00%
FIRE FIGHTING 48.65% 39.65%
KITCHEN EQUIP. 0.00% 0.00%
LPG INSTALL. NA NA
COMPRES. AIR NA NA
DUST CONTROL NA NA
PROCESS COOLING
NA NA
KEMAJUAN KERJA FIZIKAL – DEWAN MAKAN
BANGUNAN
ELECTRICAL PLANNED ACTUAL
WIRING 100.00% 78.76%
SUBMAIN CABLE 100.00% 5.87%
DB 100.00% 0.00%
LUMINAIRE 0.00% 0.00%
MAIN S/BOARD 100.00% 0.00%
LPS 100.00% 0.00%
PA 100.00% 8.53%
SMATV 100.00% 58.65%
CCTV NA NA
ICT 100.00% 0.00%
DEWAN MAKAN
MONTH PLANNED ACTUAL AHEAD / DELAY
DEC 08’ 76.37% 89.04% 12.68%
JAN 09’ 81.74% 91.05% 9.30%
MECHANICAL PLANNED
ACTUAL
AIR COND 50.00% 12.34%
FIRE FIGHTING 38.16% 67.75%
KITCHEN EQUIP. NA NA
LPG INSTALL. NA NA
COMPRES. AIR NA NA
DUST CONTROL NA NA
PROCESS COOLING
NA NA
KEMAJUAN KERJA FIZIKAL – ASRAMA LELAKI A & B
BANGUNAN
ELECTRICAL PLANNED ACTUAL
WIRING 39.29% 80.43%
SUBMAIN CABLE 0.00% 25.97%
DB 0.00% 0.00%
LUMINAIRE 0.00% 0.00%
MAIN S/BOARD 0.00% 0.00%
LPS 60.27% 32.87%
PA 49.93% 17.74%
SMATV 38.80% 43.53%
CCTV 18.72% 21.65%
ICT 81.53% 7.32%
ASRAMA LELAKI A & B
MONTH PLANNED ACTUAL AHEAD / DELAY
DEC 08’ 65.45% 90.09% 24.63%
JAN 09’ 72.72% 93.81% 21.09%
MECHANICAL PLANNED
ACTUAL
AIR COND 0.00% 12.43%
FIRE FIGHTING 21.14% 68.94%
KITCHEN EQUIP. NA NA
LPG INSTALL. NA NA
COMPRES. AIR NA NA
DUST CONTROL NA NA
PROCESS COOLING
NA NA
KEMAJUAN KERJA FIZIKAL – ASRAMA PEREMPUAN C & D
BANGUNAN
ELECTRICAL PLANNED ACTUAL
WIRING 55.95% 90.56%
SUBMAIN CABLE 0.00% 32.87%
DB 0.00% 0.00%
LUMINAIRE 0.00% 45.87%
MAIN S/BOARD 0.00% 0.00%
LPS 51.58% 32.53%
PA 0.00% 21.43%
SMATV 0.00% 42.56%
CCTV 0.00% 24.65%
ICT 0.08% 16.54%
ASRAMA PEREMPUAN C & D
MONTH PLANNED ACTUAL AHEAD / DELAY
DEC 08’ 63.83% 71.39% 7.57%
JAN 09’ 74.66% 78.73% 4.07%
MECHANICAL PLANNED
ACTUAL
AIR COND NA NA
FIRE FIGHTING 0.00% 0.00%
KITCHEN EQUIP. NA NA
LPG INSTALL. NA NA
COMPRES. AIR NA NA
DUST CONTROL NA NA
PROCESS COOLING
NA NA
KEMAJUAN KERJA FIZIKAL - SURAU
BANGUNAN
ELECTRICAL PLANNED ACTUAL
WIRING 0.00% 16.89%
SUBMAIN CABLE 0.00% 90.00%
DB NA NA
LUMINAIRE 0.00% 0.00%
MAIN S/BOARD 0.00% 0.00%
LPS 32.45% 34.93%
PA 0.00% 3.25%
SMATV NA NA
CCTV NA NA
ICT NA NA
SURAU
MONTH PLANNED ACTUAL AHEAD / DELAY
JAN 09’ 79.98% 87.62% 7.64%
MECHANICAL PLANNED
ACTUAL
AIR COND NA NA
FIRE FIGHTING 0.00% 0.00%
KITCHEN EQUIP. NA NA
LPG INSTALL. NA NA
COMPRES. AIR NA NA
DUST CONTROL NA NA
PROCESS COOLING
NA NA
KEMAJUAN KERJA FIZIKAL - ASTAKA
BANGUNAN SOKONGAN
ELECTRICAL PLANNED ACTUAL
WIRING 100.00% 90.00%
SUBMAIN CABLE 100.00% 90.00%
DB 85.71% 0.00%
LUMINAIRE 0.00% 0.00%
MAIN S/BOARD 50.00% 0.00%
LPS 59.67% 0.00%
PA 100.00% 1.91%
SMATV NA NA
CCTV NA NA
ICT NA NA
BANGUNAN SOKONGAN
ASTAKA
MONTH PLANNED ACTUAL AHEAD / DELAY
JAN 09’ 73.27% 88.10% 14.83%
MECHANICAL PLANNED
ACTUAL
AIR COND 89.98% 60.96%
FIRE FIGHTING 2.78% 0.00%
KITCHEN EQUIP. NA NA
LPG INSTALL. 0.00% 0.00%
COMPRES. AIR NA NA
DUST CONTROL NA NA
PROCESS COOLING
NA NA
KEMAJUAN KERJA FIZIKAL – M&E PLANT ROOM
BANGUNAN SOKONGAN
ELECTRICAL PLANNED ACTUAL
WIRING 100.00% 87.76%
SUBMAIN CABLE 100.00% 0.00%
DB 100.00% 0.00%
LUMINAIRE 0.00% 15.00%
MAIN S/BOARD 87.50% 35.67%
LPS NA NA
PA NA NA
SMATV NA NA
CCTV NA NA
ICT NA NA
BANGUNAN SOKONGAN
M&E PLANT ROOM - BENGKEL
BANGUNAN SOKONGAN
M&E PLANT ROOM – PUSAT SUMBER
PEMBINAAN PINTU MASUK UTAMA
BANGUNAN SOKONGAN
GARAJ KENDERAAN
ELEVATED WATER TANK, PUMP HOUSE & SUCTION TANK
WAKAF
LALUAN BERBUMBUNG
OPEN PLAZA
KERJA INFRA – JALAN UTAMA
GELANGGANG PERMAINAN - FUTSAL
COATED CHAIN LINK FENCING
M&E INSTALLATION
M&E INSTALLATION
M&E INSTALLATION
M&E INSTALLATION