adtec jun 09

73
LAPORAN KEMAJUAN PROJEK NO.22 ‘JUN 2009’ PROJEK ADTEC TAIPING KEMENTERIAN SUMBER MANUSIA JABATAN KERJA RAYA MALAYSIA KAMALBINA SDN. BHD PEMILIK PEGARAH PROJEK KONTRAKTOR R&B

Upload: muhammad-arkam

Post on 03-Nov-2014

1.016 views

Category:

Business


5 download

DESCRIPTION

 

TRANSCRIPT

Page 1: ADTEC JUN 09

LAPORAN KEMAJUAN PROJEK NO.22

‘JUN 2009’

PROJEK ADTEC TAIPING

KEMENTERIAN SUMBER MANUSIA

JABATAN KERJA RAYA MALAYSIA

KAMALBINA SDN. BHD

PEMILIK

PEGARAH PROJEK

KONTRAKTOR R&B

Page 2: ADTEC JUN 09

ADTEC TAIPING

LOKASI PROJEK

Page 3: ADTEC JUN 09

BANGUNAN PENTADBIRAN

BENGKEL TEK. MAKLUMAT& JAMIN KUALITI

DEWAN BESAR

PUSAT SUMBER

DEWAN KULIAH

LOBI UTAMA

KAFETERIA

MIKRO ELEKTRONIK

KOMPOSIT PLASTIK

M&E PLANT ROOM

1

TNB SUB

STATION

SERAMIK

M&E PLANT ROOM

2

GARAJ KENDERAAN

ASRAMA LELAKIASRAMA PEREMPUAN

DEWANMAKAN

SURAU

KELAS F

KELAS G

KUARTERSB, C, C&D

PELAN TAPAK ADTEC TAIPING

Page 4: ADTEC JUN 09

KEMAJUAN KERJA FIZIKAL

JADUAL : 85.16 %SEBENAR : 87.59 %KESELURUHAN : 2.43 %

TARIKH LAPORAN : 12 JUN 2009

Page 5: ADTEC JUN 09

KEMAJUAN KERJA KEWANGAN

JADUAL : 85.09 %SEBENAR : 86.12 %KESELURUHAN : 1.03 %

TARIKH LAPORAN : 12 JUN 2009

Page 6: ADTEC JUN 09
Page 7: ADTEC JUN 09

MONTH PLANNED ACTUAL AHEAD / DELAY

MEI 09’ 88.35% 92.38% 4.03%

JUN 09’ 94.21% 96.74% 2.53%

MECHANICAL PLANNED

ACTUAL

AIR COND 94.85% 95.50%

FIRE FIGHTING 81.61% 95.74%

KITCHEN EQUIP. NA NA

LPG INSTALL. NA NA

COMPRES. AIR NA NA

DUST CONTROL NA NA

PROCESS COOLING

NA NA

KEMAJUAN KERJA FIZIKAL - DEWAN BESAR

BANGUNAN

ELECTRICAL PLANNED ACTUAL

WIRING 100.00% 100.00%

SUBMAIN CABLE 100.00% 100.00%

DB 100.00% 100.00%

LUMINAIRE 100.00% 90.00%

MAIN S/BOARD 100.00% 95.00%

LPS NA NA

PA 94.88% 67.17%

SMATV 83.38% 86.79%

CCTV NA NA

ICT 3.31% 74.25%

Page 8: ADTEC JUN 09

DEWAN BESAR

Page 9: ADTEC JUN 09

DEWAN BESAR

Page 10: ADTEC JUN 09

MONTH PLANNED ACTUAL AHEAD / DELAY

MEI 09’ 98.92% 94.90% -4.02%

JUN 09’ 99.68% 99.72% 0.04%

MECHANICAL PLANNED

ACTUAL

AIR COND NA NA

FIRE FIGHTING NA NA

KITCHEN EQUIP. NA NA

LPG INSTALL. NA NA

COMPRES. AIR NA NA

DUST CONTROL NA NA

PROCESS COOLING

NA NA

KEMAJUAN KERJA FIZIKAL – LOBI

BANGUNAN

ELECTRICAL PLANNED ACTUAL

WIRING 95.90% 100.00%

SUBMAIN CABLE 94.17% 100.00%

DB 75.00% 100.00%

LUMINAIRE 87.89% 100.00%

MAIN S/BOARD NA NA

LPS NA NA

PA NA NA

SMATV NA NA

CCTV 88.68% 92.58%

ICT NA NA

Page 11: ADTEC JUN 09

LOBI UTAMA

Page 12: ADTEC JUN 09

MONTH PLANNED ACTUAL AHEAD / DELAY

MEI 09’ 92.24% 91.71% -0.52%

JUN 09’ 98.54% 98.19% -0.35%

MECHANICAL PLANNED

ACTUAL

AIR COND 96.19% 95.00%

FIRE FIGHTING 81.51% 86.04%

KITCHEN EQUIP. NA NA

LPG INSTALL. NA NA

COMPRES. AIR NA NA

DUST CONTROL NA NA

PROCESS COOLING

NA NA

KEMAJUAN KERJA FIZIKAL – DEWAN KULIAH UTAMABANGUNAN

ELECTRICAL PLANNED ACTUAL

WIRING 100.00% 100.00%

SUBMAIN CABLE 100.00% 100.00%

DB 75.00% 100.00%

LUMINAIRE 91.65% 95.00%

MAIN S/BOARD 75.00% 95.00%

LPS 90.51% 92.01%

PA 37.88% 65.71%

SMATV NA NA

CCTV NA NA

ICT 0.91% 74.48%

Page 13: ADTEC JUN 09

DEWAN KULIAH UTAMA

Page 14: ADTEC JUN 09

MONTH PLANNED ACTUAL AHEAD / DELAY

MEI 09’ 95.30% 95.38% 0.09%

JUN 09’ 97.50% 98.54% 1.04%

MECHANICAL PLANNED

ACTUAL

AIR COND 93.54% 85.18%

FIRE FIGHTING 39.81% 81.59%

KITCHEN EQUIP. NA NA

LPG INSTALL. NA NA

COMPRES. AIR NA NA

DUST CONTROL NA NA

PROCESS COOLING

NA NA

KEMAJUAN KERJA FIZIKAL – PUSAT SUMBER/PERPUSTAKAAN

BANGUNAN

ELECTRICAL PLANNED ACTUAL

WIRING 97.53% 97.00%

SUBMAIN CABLE 93.31% 98.00%

DB 85.00% 100.00%

LUMINAIRE 92.27% 98.00%

MAIN S/BOARD 85.00% 95.00%

LPS 91.25% 96.92%

PA 44.70% 69.69%

SMATV 94.54% 88.33%

CCTV NA NA

ICT 18.16% 23.36%

Page 15: ADTEC JUN 09

PUSAT SUMBER / PERPUSTAKAAN

Page 16: ADTEC JUN 09

MONTH PLANNED ACTUAL AHEAD / DELAY

MEI 09’ 92.72% 92.73% 0.01%

JUN 09’ 96.42% 96.51% 0.09%

MECHANICAL PLANNED

ACTUAL

AIR COND 91.09% 94.96%

FIRE FIGHTING 47.94% 74.24%

KITCHEN EQUIP. NA NA

LPG INSTALL. NA NA

COMPRES. AIR NA NA

DUST CONTROL NA NA

PROCESS COOLING

NA NA

KEMAJUAN KERJA FIZIKAL – PENTADBIRAN & PENGURUSAN SUMBERBANGUNAN

ELECTRICAL PLANNED ACTUAL

WIRING 99.48% 97.00%

SUBMAIN CABLE 97.32% 98.00%

DB 85.00% 100.00%

LUMINAIRE 82.78% 95.00%

MAIN S/BOARD 75.00% 95.00%

LPS 87.80% 90.85%

PA 63.70% 58.92%

SMATV 95.99% 88.07%

CCTV 73.69% 70.43%

ICT 24.87% 51.37%

Page 17: ADTEC JUN 09

BANGUNAN PENTADBIRAN & PENGURUSAN SUMBER

Page 18: ADTEC JUN 09

MONTH PLANNED ACTUAL AHEAD / DELAY

MEI 09’ 98.36% 98.71% 0.08%

JUN 09’ 99.58% 99.23% -0.35%

MECHANICAL PLANNED

ACTUAL

AIR COND 100.00% 100.00%

FIRE FIGHTING 90.22% 74.56%

KITCHEN EQUIP. 65.55% 69.00%

LPG INSTALL. 40.84% 48.50%

COMPRES. AIR NA NA

DUST CONTROL NA NA

PROCESS COOLING

NA NA

KEMAJUAN KERJA FIZIKAL - KAFETARIA

BANGUNAN

ELECTRICAL PLANNED ACTUAL

WIRING 100.00% 100.00%

SUBMAIN CABLE 100.00% 100.00%

DB 100.00% 100.00%

LUMINAIRE 100.00% 100.00%

MAIN S/BOARD NA NA

LPS 100.00% 88.81%

PA 94.53% 62.91%

SMATV 92.47% 87.44%

CCTV NA NA

ICT 0.00% 75.00%

Page 19: ADTEC JUN 09

KAFETERIA

Page 20: ADTEC JUN 09

MONTH PLANNED ACTUAL AHEAD / DELAY

MEI 09’ 93.95% 95.49% 1.54%

JUN 09’ 98.05% 98.01% -0.05%

MECHANICAL PLANNED

ACTUAL

AIR COND 86.90% 91.36%

FIRE FIGHTING 31.85% 63.60%

KITCHEN EQUIP. NA NA

LPG INSTALL. NA NA

COMPRES. AIR NA NA

DUST CONTROL NA NA

PROCESS COOLING

NA NA

KEMAJUAN KERJA FIZIKAL – BENGKEL TEKNOLOGI MAKLUMATBANGUNAN

ELECTRICAL PLANNED ACTUAL

WIRING 99.23% 96.00%

SUBMAIN CABLE 98.21% 100.00%

DB 97.27% 100.00%

LUMINAIRE 92.51% 100.00%

MAIN S/BOARD 75.00% 95.00%

LPS 100.00% 96.80%

PA 100.00% 73.49%

SMATV 95.09% 89.00%

CCTV 79.13% 291.22%

ICT 8.53% 19.28%

Page 21: ADTEC JUN 09

BENGKEL TEKNOLOGI MAKLUMAT

Page 22: ADTEC JUN 09

MONTH PLANNED ACTUAL AHEAD / DELAY

MEI 09’ 96.82% 95.67% -1.14%

JUN 09’ 98.42% 98.30% -0.12%

MECHANICAL PLANNED

ACTUAL

AIR COND 93.36% 93.41%

FIRE FIGHTING 45.37% 72.69%

KITCHEN EQUIP. NA NA

LPG INSTALL. NA NA

COMPRES. AIR 87.25% 85.00%

DUST CONTROL NA NA

PROCESS COOLING

41.53% 0.00%

KEMAJUAN KERJA FIZIKAL – BENGKEL KEJ. BAHAN TERMAJU (PLASTIK)BANGUNAN

ELECTRICAL PLANNED ACTUAL

WIRING 100.00% 100.00%

SUBMAIN CABLE 100.00% 100.00%

DB 75.00% 100.00%

LUMINAIRE 100.00% 100.00%

MAIN S/BOARD 75.00% 95.00%

LPS 92.90% 96.80%

PA 62.47% 75.48%

SMATV 75.18% 74.39%

CCTV 83.97% 93.08%

ICT 26.23% 23.86%

Page 23: ADTEC JUN 09

BENGKEL KEJ. BAHAN TERMAJU (PLASTIK)

Page 24: ADTEC JUN 09

MONTH PLANNED ACTUAL AHEAD / DELAY

MEI 09’ 97.05% 95.65% -1.40%

JUN 09’ 98.46% 98.41% -0.05%

MECHANICAL PLANNED

ACTUAL

AIR COND 80.73% 78.34%

FIRE FIGHTING 43.93% 69.10%

KITCHEN EQUIP. NA NA

LPG INSTALL. NA NA

COMPRES. AIR 87.25% 85.00%

DUST CONTROL 31.69% 77.29%

PROCESS COOLING

38.45% 0.00%

KEMAJUAN KERJA FIZIKAL – BENGKEL KEJ. BAHAN TERMAJU (KOMPOSIT)BANGUNAN

ELECTRICAL PLANNED ACTUAL

WIRING 100.00% 100.00%

SUBMAIN CABLE 100.00% 100.00%

DB 100.00% 100.00%

LUMINAIRE 100.00% 100.00%

MAIN S/BOARD 100.00% 95.00%

LPS 97.29% 93.25%

PA 92.78% 72.21%

SMATV 75.26% 75.20%

CCTV 86.10% 92.75%

ICT 21.23% 18.81%

Page 25: ADTEC JUN 09

BENGKEL KEJ. BAHAN TERMAJU (KOMPOSIT)

Page 26: ADTEC JUN 09

MONTH PLANNED ACTUAL AHEAD / DELAY

MEI 09’ 95.12% 94.67% -0.46%

JUN 09’ 97.15% 97.14% -0.02%

MECHANICAL PLANNED

ACTUAL

AIR COND 91.33% 92.19%

FIRE FIGHTING 44.40% 69.54%

KITCHEN EQUIP. NA NA

LPG INSTALL. NA NA

COMPRES. AIR 87.25% 85.00%

DUST CONTROL 11.65% 72.95%

PROCESS COOLING

21.79% 0.00%

KEMAJUAN KERJA FIZIKAL – BENGKEL KEJ. BAHAN TERMAJU (SERAMIK)BANGUNAN

ELECTRICAL PLANNED ACTUAL

WIRING 100.00% 100.00%

SUBMAIN CABLE 99.29% 100.00%

DB 78.00% 100.00%

LUMINAIRE 96.30% 100.00%

MAIN S/BOARD 85.00% 95.00%

LPS 90.20% 96.49%

PA 96.64% 72.96%

SMATV 73.29% 74.70%

CCTV 90.23% 93.97%

ICT 33.22% 27.44%

Page 27: ADTEC JUN 09

BENGKEL KEJ. BAHAN TERMAJU (SERAMIK)

Page 28: ADTEC JUN 09

MONTH PLANNED ACTUAL AHEAD / DELAY

MEI 09’ 94.30% 95.17% -0.87%

JUN 09’ 96.50% 96.99% 0.48%

MECHANICAL PLANNED

ACTUAL

AIR COND 82.68% 59.54%

FIRE FIGHTING 26.16% 63.17%

KITCHEN EQUIP. NA NA

LPG INSTALL. NA NA

COMPRES. AIR 87.25% 85.00%

DUST CONTROL 38.25% 80.74%

PROCESS COOLING

NA NA

KEMAJUAN KERJA FIZIKAL – BENGKEL KEJ. JAMINAN KUALITIBANGUNAN

ELECTRICAL PLANNED ACTUAL

WIRING 97.67% 96.00%

SUBMAIN CABLE 95.02% 97.00%

DB 95.02% 95.00%

LUMINAIRE 77.98% 90.00%

MAIN S/BOARD 57.17% 95.00%

LPS 86.74% 96.20%

PA 42.25% 68.68%

SMATV 87.59% 85.36%

CCTV 80.71% 90.90%

ICT 7.17% 18.61%

Page 29: ADTEC JUN 09

BENGKEL KEJ. JAMINAN KUALITI

Page 30: ADTEC JUN 09

MONTH PLANNED ACTUAL AHEAD / DELAY

MEI 09’ 92.86% 94.80% 1.94%

JUN 09’ 95.58% 95.59% 0.01%

MECHANICAL PLANNED

ACTUAL

AIR COND 93.43% 91.50%

FIRE FIGHTING 22.33% 59.71%

KITCHEN EQUIP. NA NA

LPG INSTALL. NA NA

COMPRES. AIR 87.25% 85.00%

DUST CONTROL NA NA

PROCESS COOLING

NA NA

KEMAJUAN KERJA FIZIKAL – BENGKEL MIKRO ELEKTRONIKBANGUNAN

ELECTRICAL PLANNED ACTUAL

WIRING 100.00% 96.00%

SUBMAIN CABLE 96.67% 95.00%

DB 72.68% 100.00%

LUMINAIRE 100.00% 100.00%

MAIN S/BOARD 100.00% 95.00%

LPS 92.34% 96.70%

PA 52.92% 72.02%

SMATV 91.26% 86.86%

CCTV 84.11% 91.21%

ICT 6.84% 22.94%

Page 31: ADTEC JUN 09

BENGKEL MIKRO ELEKTRONIK

Page 32: ADTEC JUN 09

MONTH PLANNED ACTUAL AHEAD / DELAY

MEI 09’ 100.00% 100.00% 0.00%

JUN 09’ 100.00% 100.00% 0.00%

MECHANICAL PLANNED

ACTUAL

AIR COND 100.00% 100.00%

FIRE FIGHTING NA NA

KITCHEN EQUIP. NA NA

LPG INSTALL. NA NA

COMPRES. AIR NA NA

DUST CONTROL NA NA

PROCESS COOLING

NA NA

KEMAJUAN KERJA FIZIKAL – KUATERS KELAS ‘B’

BANGUNAN

ELECTRICAL PLANNED ACTUAL

WIRING 100.00% 100.00%

SUBMAIN CABLE 100.00% 100.00%

DB 100.00% 100.00%

LUMINAIRE 100.00% 100.00%

MAIN S/BOARD 100.00% 100.00%

LPS 100.00% 95.68%

PA NA NA

SMATV 84.58% 68.14%

CCTV 79.71% 93.15%

ICT 100.00% 90.00%

Page 33: ADTEC JUN 09

KUARTERS KELAS ‘B’

Page 34: ADTEC JUN 09

MONTH PLANNED ACTUAL AHEAD / DELAY

MEI 09’ 100.00% 100.00% 0.00%

JUN 09’ 100.00% 100.00% 100.00%

MECHANICAL PLANNED

ACTUAL

AIR COND 100.00% 100.00%

FIRE FIGHTING NA NA

KITCHEN EQUIP. NA NA

LPG INSTALL. NA NA

COMPRES. AIR NA NA

DUST CONTROL NA NA

PROCESS COOLING

NA NA

KEMAJUAN KERJA FIZIKAL – KUATERS KELAS ‘C’

BANGUNAN

ELECTRICAL PLANNED ACTUAL

WIRING 100.00% 100.00%

SUBMAIN CABLE 100.00% 100.00%

DB 100.00% 100.00%

LUMINAIRE 100.00% 100.00%

MAIN S/BOARD 100.00% 90.00%

LPS 100.00% 95.78%

PA NA NA

SMATV 82.56% 46.09%

CCTV NA NA

ICT 100.00% 84.06%

Page 35: ADTEC JUN 09

KUARTERS KELAS ‘C’

Page 36: ADTEC JUN 09

MONTH PLANNED ACTUAL AHEAD / DELAY

MEI 09’ 100.00% 100.00% 0.00%

JUN 09’ 100.00% 100.00% 0.00%

MECHANICAL PLANNED

ACTUAL

AIR COND 100.00% 100.00%

FIRE FIGHTING NA NA

KITCHEN EQUIP. NA NA

LPG INSTALL. NA NA

COMPRES. AIR NA NA

DUST CONTROL NA NA

PROCESS COOLING

NA NA

KEMAJUAN KERJA FIZIKAL – KUATERS KELAS ‘C+D’BANGUNAN

ELECTRICAL PLANNED ACTUAL

WIRING 100.00% 100.00%

SUBMAIN CABLE 100.00% 100.00%

DB 100.00% 100.00%

LUMINAIRE 100.00% 100.00%

MAIN S/BOARD 100.00% 90.00%

LPS 100.00% 96.33%

PA NA NA

SMATV 84.58% 86.14%

CCTV NA NA

ICT 100.00% 90.00%

Page 37: ADTEC JUN 09

KUARTERS KELAS ‘C’ + ‘D’

Page 38: ADTEC JUN 09

MONTH PLANNED ACTUAL AHEAD / DELAY

MEI 09’ 97.14% 98.49% 1.36%

JUN 09’ 98.63% 98.85% 0.12%

MECHANICAL PLANNED

ACTUAL

AIR COND NA NA

FIRE FIGHTING NA NA

KITCHEN EQUIP. NA NA

LPG INSTALL. NA NA

COMPRES. AIR NA NA

DUST CONTROL NA NA

PROCESS COOLING

NA NA

KEMAJUAN KERJA FIZIKAL – KUATERS KELAS F ( 1 BLOK 4 TINGKAT & I BLOK 5 TINGKAT)BANGUNAN

ELECTRICAL PLANNED ACTUAL

WIRING 100.00% 100.00%

SUBMAIN CABLE 100.00% 100.00%

DB 100.00% 100.00%

LUMINAIRE 100.00% 100.00%

MAIN S/BOARD 100.00% 90.00%

LPS 93.30% 96.98%

PA NA NA

SMATV 95.77% 93.31%

CCTV NA NA

ICT 96.04% 92.34%

Page 39: ADTEC JUN 09

KUARTERS KELAS ‘F’ ( 4 TINGKAT )

Page 40: ADTEC JUN 09

KUARTERS KELAS ‘F’ ( 5 TINGKAT )

Page 41: ADTEC JUN 09

MONTH PLANNED ACTUAL AHEAD / DELAY

MEI 09’ 97.58% 98.48% 0.90%

JUN 09’ 99.57% 99.58% 0.01%

MECHANICAL PLANNED

ACTUAL

AIR COND NA NA

FIRE FIGHTING NA NA

KITCHEN EQUIP. NA NA

LPG INSTALL. NA NA

COMPRES. AIR NA NA

DUST CONTROL NA NA

PROCESS COOLING

NA NA

KEMAJUAN KERJA FIZIKAL – KUATERS KELAS G

(1 BLOK 4 TINGKAT & 1 BLOK 5 TINGKAT)BANGUNAN

ELECTRICAL PLANNED ACTUAL

WIRING 100.00% 100.00%

SUBMAIN CABLE 100.00% 100.00%

DB 100.00% 100.00%

LUMINAIRE 100.00% 100.00%

MAIN S/BOARD 100.00% 90.00%

LPS 100.00% 96.98%

PA NA NA

SMATV 95.77% 93.31%

CCTV NA NA

ICT 100.00% 98.37%

Page 42: ADTEC JUN 09

KUARTERS KELAS ‘G’ ( 5 TINGKAT )

Page 43: ADTEC JUN 09

KUARTERS KELAS ‘G’ ( 4 TINGKAT )

Page 44: ADTEC JUN 09

MONTH PLANNED ACTUAL AHEAD / DELAY

MEI 09’ 99.42% 99.60% 0.18%

JUN 09’ 99.83% 96.63% 0.01%

MECHANICAL PLANNED

ACTUAL

AIR COND 90.95% 100.00%

FIRE FIGHTING 57.40% 72.89%

KITCHEN EQUIP. 65.55% 69.00%

LPG INSTALL. 40.84% 48.50%

COMPRES. AIR NA NA

DUST CONTROL NA NA

PROCESS COOLING

NA NA

KEMAJUAN KERJA FIZIKAL – DEWAN MAKAN

BANGUNAN

ELECTRICAL PLANNED ACTUAL

WIRING 100.00% 100.00%

SUBMAIN CABLE 100.00% 98.00%

DB 100.00% 95.00%

LUMINAIRE 100.00% 80.00%

MAIN S/BOARD 100.00% 90.00%

LPS 100.00% 97.32%

PA 56.87% 73.23%

SMATV 92.47% 90.79%

CCTV NA NA

ICT 100.00% 75.35%

Page 45: ADTEC JUN 09

DEWAN MAKAN

Page 46: ADTEC JUN 09

MONTH PLANNED ACTUAL AHEAD / DELAY

MEI 09’ 98.70% 99.43% 0.73%

JUN 09’ 99.39% 99.55% 0.16%

MECHANICAL PLANNED

ACTUAL

AIR COND 89.66% 100.00%

FIRE FIGHTING 39.31% 84.41%

KITCHEN EQUIP. NA NA

LPG INSTALL. NA NA

COMPRES. AIR NA NA

DUST CONTROL NA NA

PROCESS COOLING

NA NA

KEMAJUAN KERJA FIZIKAL – ASRAMA LELAKI A & BBANGUNAN

ELECTRICAL PLANNED ACTUAL

WIRING 99.33% 100.00%

SUBMAIN CABLE 94.80% 97.00%

DB 100.00% 90.00%

LUMINAIRE 100.00% 95.00%

MAIN S/BOARD 100.00% 90.00%

LPS 98.56% 97.48%

PA 64.19% 76.16%

SMATV 72.72% 89.94%

CCTV 79.47% 92.93%

ICT 97.72% 92.43%

Page 47: ADTEC JUN 09

ASRAMA LELAKI A & B

Page 48: ADTEC JUN 09

MONTH PLANNED ACTUAL AHEAD / DELAY

MEI 09’ 98.95% 99.37% 0.52%

JUN 09’ 99.44% 99.50% 0.06%

MECHANICAL PLANNED

ACTUAL

AIR COND 76.12% 100.00%

FIRE FIGHTING 81.16% 85.89%

KITCHEN EQUIP. NA NA

LPG INSTALL. NA NA

COMPRES. AIR NA NA

DUST CONTROL NA NA

PROCESS COOLING

NA NA

KEMAJUAN KERJA FIZIKAL – ASRAMA PEREMPUAN C & DBANGUNAN

ELECTRICAL PLANNED ACTUAL

WIRING 99.23`% 100.00%

SUBMAIN CABLE 98.85% 97.00%

DB 94.81% 90.00%

LUMINAIRE 92.21% 95.00%

MAIN S/BOARD 100.00% 90.00%

LPS 100.00% 97.64%

PA 60.31% 74.66%

SMATV 72.35% 89.94%

CCTV 84.84% 92.62%

ICT 99.49% 91.62%

Page 49: ADTEC JUN 09

ASRAMA PEREMPUAN C & D

Page 50: ADTEC JUN 09

MONTH PLANNED ACTUAL AHEAD / DELAY

MEI 09’ 95.20% 92.10% 0.69%

JUN 09’ 96.94% 96.63% -0.31%

MECHANICAL PLANNED

ACTUAL

AIR COND NA NA

FIRE FIGHTING 100.00% 75.00%

KITCHEN EQUIP. NA NA

LPG INSTALL. NA NA

COMPRES. AIR NA NA

DUST CONTROL NA NA

PROCESS COOLING

NA NA

KEMAJUAN KERJA FIZIKAL - SURAU

BANGUNAN

ELECTRICAL PLANNED ACTUAL

WIRING 100.00% 100.00%

SUBMAIN CABLE 100.00% 100.00%

DB 100.00% 100.00%

LUMINAIRE 76.89% 100.00%

MAIN S/BOARD 85.00% 95.00%

LPS 91.35% 96.24%

PA 30.52% 64.71%

SMATV NA NA

CCTV NA NA

ICT NA NA

Page 51: ADTEC JUN 09

SURAU

Page 52: ADTEC JUN 09

MONTH PLANNED ACTUAL AHEAD / DELAY

MEI 09’ 99.80% 99.83% 0.04%

JUN 09’ 99.99% 99.83% -0.16%

MECHANICAL PLANNED

ACTUAL

AIR COND NA NA

FIRE FIGHTING 100.00% 75.00%

KITCHEN EQUIP. NA NA

LPG INSTALL. NA NA

COMPRES. AIR NA NA

DUST CONTROL NA NA

PROCESS COOLING

NA NA

KEMAJUAN KERJA FIZIKAL - ASTAKA

BANGUNAN SOKONGAN

ELECTRICAL PLANNED ACTUAL

WIRING 100.00% 100.00%

SUBMAIN CABLE 100.00% 100.00%

DB 100.00% 100.00%

LUMINAIRE 100.00% 100.00%

MAIN S/BOARD 100.00% 90.00%

LPS 97.85% 93.89%

PA 38.16% 67.38%

SMATV NA NA

CCTV NA NA

ICT NA NA

Page 53: ADTEC JUN 09

BANGUNAN SOKONGAN

ASTAKA

Page 54: ADTEC JUN 09

MONTH PLANNED ACTUAL AHEAD / DELAY

JUN 09’ 100.00% 100.00% 0.00%

MECHANICAL PLANNED

ACTUAL

AIR COND 100.00% 99.53%

FIRE FIGHTING 32.54% 90.34%

KITCHEN EQUIP. NA NA

LPG INSTALL. NA NA

COMPRES. AIR NA NA

DUST CONTROL NA NA

PROCESS COOLING

NA NA

KEMAJUAN KERJA FIZIKAL – M&E PLANT ROOM

BANGUNAN SOKONGAN

ELECTRICAL PLANNED ACTUAL

WIRING 100.00% 97.00%

SUBMAIN CABLE 100.00% 90.00%

DB 100.00% 0.00%

LUMINAIRE 92.72% 90.00%

MAIN S/BOARD 54.00% 100.00%

LPS NA NA

PA NA NA

SMATV NA NA

CCTV NA NA

ICT NA NA

Page 55: ADTEC JUN 09

BANGUNAN SOKONGAN

M&E PLANT ROOM – PUSAT SUMBER

Page 56: ADTEC JUN 09

BANGUNAN SOKONGAN

M&E PLANT ROOM - BENGKEL

Page 57: ADTEC JUN 09

DECORATIVE FENCE

Page 58: ADTEC JUN 09

BANGUNAN SOKONGAN

GARAJ KENDERAAN

Page 59: ADTEC JUN 09

ELEVATED WATER TANK, PUMP HOUSE & SUCTION TANK

Page 60: ADTEC JUN 09

RUMAH SAMPAH

Page 61: ADTEC JUN 09

LALUAN BERBUMBUNG

Page 62: ADTEC JUN 09

OPEN PLAZA

Page 63: ADTEC JUN 09

KERJA INFRA – JALAN UTAMA

Page 64: ADTEC JUN 09

GELANGGANG PERMAINAN

Page 65: ADTEC JUN 09

GELANGGANG PERMAINAN

Page 66: ADTEC JUN 09

GELANGGANG PERMAINAN

Page 67: ADTEC JUN 09

BENGKEL MIKRO - CLEANROON

Page 68: ADTEC JUN 09

M&E : FIRE FIGHTING

Page 69: ADTEC JUN 09

STAGE : DEWAN KULIAH

Page 70: ADTEC JUN 09

BENGKEL JAMINAN KULITI

Page 71: ADTEC JUN 09

KITCHEN HOOD : CAFETERIA

Page 72: ADTEC JUN 09

M&E

Page 73: ADTEC JUN 09

• SEKIAN TERIMA KASIH