adtec pre no.18 feb 09

69
LAPORAN KEMAJUAN PROJEK NO.18 ‘FEBUARY 2009’ PROJEK ADTEC TAIPING KEMENTERIAN SUMBER MANUSIA JABATAN KERJA RAYA MALAYSIA KAMALBINA SDN. BHD PEMILIK PEGARAH PROJEK KONTRAKTOR R&B

Upload: arkam-munaaim-phd-peng-intpe

Post on 24-Jun-2015

434 views

Category:

Technology


7 download

TRANSCRIPT

Page 1: Adtec Pre No.18   Feb 09

LAPORAN KEMAJUAN PROJEK NO.18

‘FEBUARY 2009’

PROJEK ADTEC TAIPING

KEMENTERIAN SUMBER MANUSIA

JABATAN KERJA RAYA MALAYSIA

KAMALBINA SDN. BHD

PEMILIK

PEGARAH PROJEK

KONTRAKTOR R&B

Page 2: Adtec Pre No.18   Feb 09

ADTEC TAIPING

LOKASI PROJEK

Page 3: Adtec Pre No.18   Feb 09

BANGUNAN PENTADBIRAN

BENGKEL TEK. MAKLUMAT& JAMIN KUALITI

DEWAN BESAR

PUSAT SUMBER

DEWAN KULIAH

LOBI UTAMA

KAFETERIA

MIKRO ELEKTRONIK

KOMPOSIT PLASTIK

M&E PLANT ROOM

1

TNB SUB

STATION

SERAMIK

M&E PLANT ROOM

2

GARAJ KENDERAAN

ASRAMA LELAKIASRAMA PEREMPUAN

DEWANMAKAN

SURAU

KELAS F

KELAS G

KUARTERSB, C, C&D

PELAN TAPAK ADTEC TAIPING

Page 4: Adtec Pre No.18   Feb 09

KEMAJUAN KERJA FIZIKAL

JADUAL : 70.88%SEBENAR : 67.03%KESELURUHAN : -3.85%

TARIKH LAPORAN : 12 FEB 2009

Page 5: Adtec Pre No.18   Feb 09

KEMAJUAN KERJA KEWANGAN

JADUAL : 74.78%SEBENAR : 68.50%KESELURUHAN : -6.28% @ 45 HARI

(LEWAT )

TARIKH LAPORAN : 12 FEB 2009

Page 6: Adtec Pre No.18   Feb 09
Page 7: Adtec Pre No.18   Feb 09

MONTH PLANNED ACTUAL AHEAD / DELAY

JAN 09’ 98.98% 65.52% - 33.46%

FEB 09’ 99.12% 67.42% - 31.70%

MECHANICAL PLANNED

ACTUAL

AIR COND 100.00% 50.00%

FIRE FIGHTING 100.00% 26.74%

KITCHEN EQUIP. NA NA

LPG INSTALL. NA NA

COMPRES. AIR NA NA

DUST CONTROL NA NA

PROCESS COOLING

NA NA

KEMAJUAN KERJA FIZIKAL - DEWAN BESAR

BANGUNAN

ELECTRICAL PLANNED ACTUAL

WIRING 100.00% 65.00%

SUBMAIN CABLE 100.00% 71.00%

DB 100.00% 0.00%

LUMINAIRE 100.00% 0.00%

MAIN S/BOARD 100.00% 0.00%

LPS NA NA

PA 100.00% 2.12%

SMATV 100.00% 21.25%

CCTV NA NA

ICT 100.00% 12.65%

Page 8: Adtec Pre No.18   Feb 09

DEWAN BESAR

Page 9: Adtec Pre No.18   Feb 09

DEWAN BESAR

Page 10: Adtec Pre No.18   Feb 09

MONTH PLANNED ACTUAL AHEAD / DELAY

JAN 09’ 93.25% 78.68% -14.57%

FEB 09’ 95.00% 90.85% -4.15%

MECHANICAL PLANNED

ACTUAL

AIR COND NA NA

FIRE FIGHTING NA NA

KITCHEN EQUIP. NA NA

LPG INSTALL. NA NA

COMPRES. AIR NA NA

DUST CONTROL NA NA

PROCESS COOLING

NA NA

KEMAJUAN KERJA FIZIKAL – LOBI

BANGUNAN

ELECTRICAL PLANNED ACTUAL

WIRING 100.00% 75.00%

SUBMAIN CABLE 100.00% 90.00%

DB 100.00% 0.00%

LUMINAIRE 100.00% 0.00%

MAIN S/BOARD NA NA

LPS NA NA

PA 100.00% 65.37%

SMATV NA NA

CCTV 100.00% 0.00%

ICT NA NA

Page 11: Adtec Pre No.18   Feb 09

LOBI UTAMA

Page 12: Adtec Pre No.18   Feb 09

MONTH PLANNED ACTUAL AHEAD / DELAY

JAN 09’ 73.49% 66.39% -7.10%

FEB 09’ 83.03% 70.04% -12.99%

MECHANICAL PLANNED

ACTUAL

AIR COND 50.00% 74.50%

FIRE FIGHTING 41.70% 49.64%

KITCHEN EQUIP. NA NA

LPG INSTALL. NA NA

COMPRES. AIR NA NA

DUST CONTROL NA NA

PROCESS COOLING

NA NA

KEMAJUAN KERJA FIZIKAL – DEWAN KULIAH UTAMABANGUNAN

ELECTRICAL PLANNED ACTUAL

WIRING 100.00% 65.00%

SUBMAIN CABLE 56.25% 88.00%

DB 100.00% 0.00%

LUMINAIRE 0.00% 0.00%

MAIN S/BOARD 100.00% 0.00%

LPS 91.09% 0.00%

PA 100.00% 19.31%

SMATV NA NA

CCTV NA NA

ICT 97.21% 0.00%

Page 13: Adtec Pre No.18   Feb 09

DEWAN KULIAH UTAMA

Page 14: Adtec Pre No.18   Feb 09

MONTH PLANNED ACTUAL AHEAD / DELAY

JAN 09’ 84.29% 84.41% 0.12%

FEB 09’ 93.37% 89.98% -3.39%

MECHANICAL PLANNED

ACTUAL

AIR COND 87.60% 80.18%

FIRE FIGHTING 33.90% 90.24%

KITCHEN EQUIP. NA NA

LPG INSTALL. NA NA

COMPRES. AIR NA NA

DUST CONTROL NA NA

PROCESS COOLING

NA NA

KEMAJUAN KERJA FIZIKAL – PUSAT SUMBER/PERPUSTAKAAN

BANGUNAN

ELECTRICAL PLANNED ACTUAL

WIRING 100.00% 90.00%

SUBMAIN CABLE 100.00% 88.00%

DB 100.00% 0.00%

LUMINAIRE 100.00% 25.00%

MAIN S/BOARD 100.00% 0.00%

LPS 100.00% 73.47%

PA 100.00% 34.79%

SMATV 100.00% 57.16%

CCTV NA NA

ICT 29.27% 0.00%

Page 15: Adtec Pre No.18   Feb 09

PUSAT SUMBER / PERPUSTAKAAN

Page 16: Adtec Pre No.18   Feb 09

MONTH PLANNED ACTUAL AHEAD / DELAY

JAN 09’ 82.12% 77.52% -4.60%

FEB 09’ 91.35% 84.29% -7.06%

MECHANICAL PLANNED

ACTUAL

AIR COND 71.21% 63.09%

FIRE FIGHTING 45.46% 38.79%

KITCHEN EQUIP. NA NA

LPG INSTALL. NA NA

COMPRES. AIR NA NA

DUST CONTROL NA NA

PROCESS COOLING

NA NA

KEMAJUAN KERJA FIZIKAL – PENTADBIRAN & PENGURUSAN SUMBERBANGUNAN

ELECTRICAL PLANNED ACTUAL

WIRING 100.00% 82.50%

SUBMAIN CABLE 100.00% 78.00%

DB 100.00% 0.00%

LUMINAIRE 78.57% 25.00%

MAIN S/BOARD 100.00% 0.00%

LPS 93.03% 69.22%

PA 100.00% 15.96%

SMATV 100.00% 52.05%

CCTV 62.56% 2.13%

ICT 72.81% 0.00%

Page 17: Adtec Pre No.18   Feb 09

BANGUNAN PENTADBIRAN & PENGURUSAN SUMBER

Page 18: Adtec Pre No.18   Feb 09

MONTH PLANNED ACTUAL AHEAD / DELAY

JAN 09’ 72.24% 89.11% 16.88%

FEB 09’ 84.36% 94.85% 10.49%

MECHANICAL PLANNED

ACTUAL

AIR COND 0.00% 43.00%

FIRE FIGHTING 12.65% 29.54%

KITCHEN EQUIP. 0.00% 6.51%

LPG INSTALL. NA NA

COMPRES. AIR NA NA

DUST CONTROL NA NA

PROCESS COOLING

NA NA

KEMAJUAN KERJA FIZIKAL - KAFETARIA

BANGUNAN

ELECTRICAL PLANNED ACTUAL

WIRING 100.00% 90.00%

SUBMAIN CABLE 100.00% 90.00%

DB 83.33% 0.00%

LUMINAIRE 0.00% 25.00%

MAIN S/BOARD NA NA

LPS 64.46% 56.58%

PA 98.14% 22.79%

SMATV 81.61% 50.29%

CCTV NA NA

ICT 100.00% 0.00%

Page 19: Adtec Pre No.18   Feb 09

KAFETERIA

Page 20: Adtec Pre No.18   Feb 09

MONTH PLANNED ACTUAL AHEAD / DELAY

JAN 09’ 79.02% 84.02% 5.01%

FEB 09’ 85.84% 89.53% 3.69%

MECHANICAL PLANNED

ACTUAL

AIR COND 23.57% 66.78%

FIRE FIGHTING 27.70% 33.67%

KITCHEN EQUIP. NA NA

LPG INSTALL. NA NA

COMPRES. AIR NA NA

DUST CONTROL NA NA

PROCESS COOLING

NA NA

KEMAJUAN KERJA FIZIKAL – BENGKEL TEKNOLOGI MAKLUMATBANGUNAN

ELECTRICAL PLANNED ACTUAL

WIRING 100.00% 90.00%

SUBMAIN CABLE 100.00% 50.00%

DB 100.00% 25.00%

LUMINAIRE 0.00% 45.00%

MAIN S/BOARD 86.67% 0.00%

LPS 99.49% 74.62%

PA 100.00% 42.43%

SMATV 99.68% 59.11%

CCTV 54.53% 33.71%

ICT 20.74% 0.00%

Page 21: Adtec Pre No.18   Feb 09

BENGKEL TEKNOLOGI MAKLUMAT

Page 22: Adtec Pre No.18   Feb 09

MONTH PLANNED ACTUAL AHEAD / DELAY

JAN 09’ 68.69% 86.03% 17.33%

FEB 09’ 78.05% 93.28% 15.23%

MECHANICAL PLANNED

ACTUAL

AIR COND 30.27% 80.11%

FIRE FIGHTING 24.65% 53.54%

KITCHEN EQUIP. NA NA

LPG INSTALL. NA NA

COMPRES. AIR 14.29% 75.00%

DUST CONTROL NA NA

PROCESS COOLING

7.60% 0.00%

KEMAJUAN KERJA FIZIKAL – BENGKEL KEJ. BAHAN TERMAJU (PLASTIK)BANGUNAN

ELECTRICAL PLANNED ACTUAL

WIRING 53.57% 90.00%

SUBMAIN CABLE 0.00% 80.00%

DB 0.00% 0.00%

LUMINAIRE 0.00% 45.00%

MAIN S/BOARD 0.00% 0.00%

LPS 69.14% 74.65%

PA 22.31% 46.85%

SMATV NA NA

CCTV 37.46% 49.69%

ICT 4.96% 0.00%

Page 23: Adtec Pre No.18   Feb 09

BENGKEL KEJ. BAHAN TERMAJU (PLASTIK)

Page 24: Adtec Pre No.18   Feb 09

MONTH PLANNED ACTUAL AHEAD / DELAY

JAN 09’ 71.23% 83.64% 12.41%

FEB 09’ 79.39% 93.66% 14.27%

MECHANICAL PLANNED

ACTUAL

AIR COND 31.60% 79.74%

FIRE FIGHTING 31.64% 59.65%

KITCHEN EQUIP. NA NA

LPG INSTALL. NA NA

COMPRES. AIR 20.00% 75.00%

DUST CONTROL 17.20% 23.77%

PROCESS COOLING

12.06% 0.00%

KEMAJUAN KERJA FIZIKAL – BENGKEL KEJ. BAHAN TERMAJU (KOMPOSIT)BANGUNAN

ELECTRICAL PLANNED ACTUAL

WIRING 60.71% 90.00%

SUBMAIN CABLE 0.00% 75.00%

DB 0.00% 0.00%

LUMINAIRE 0.00% 45.00%

MAIN S/BOARD 0.00% 0.00%

LPS 64.14% 67.88%

PA 25.13% 40.39%

SMATV NA NA

CCTV 54.68% 50.54%

ICT 13.80% 0.00%

Page 25: Adtec Pre No.18   Feb 09

BENGKEL KEJ. BAHAN TERMAJU (KOMPOSIT)

Page 26: Adtec Pre No.18   Feb 09

MONTH PLANNED ACTUAL AHEAD / DELAY

JAN 09’ 71.02% 79.96% 8.84%

FEB 09’ 76.14% 93.08% 16.93%

MECHANICAL PLANNED

ACTUAL

AIR COND 15.58% 78.29%

FIRE FIGHTING 27.33% 55.87%

KITCHEN EQUIP. NA NA

LPG INSTALL. NA NA

COMPRES. AIR 28.57% 75.00%

DUST CONTROL 3.37% 28.75%

PROCESS COOLING

15.20% 0.00%

KEMAJUAN KERJA FIZIKAL – BENGKEL KEJ. BAHAN TERMAJU (SERAMIK)BANGUNAN

ELECTRICAL PLANNED ACTUAL

WIRING 71.43% 90.00%

SUBMAIN CABLE 0.00% 85.00%

DB 0.00% 0.00%

LUMINAIRE 0.00% 45.00%

MAIN S/BOARD 0.00% 0.00%

LPS 56.92% 73.14%

PA 39.65% 41.63%

SMATV NA NA

CCTV 43.10% 57.16%

ICT 11.76% 0.00%

Page 27: Adtec Pre No.18   Feb 09

BENGKEL KEJ. BAHAN TERMAJU (SERAMIK)

Page 28: Adtec Pre No.18   Feb 09

MONTH PLANNED ACTUAL AHEAD / DELAY

JAN 09’ 77.16% 77.74% 0.58%

FEB 09’ 80.11% 87.32% 7.21%

MECHANICAL PLANNED

ACTUAL

AIR COND 25.39% 55.00%

FIRE FIGHTING 37.17% 37.23%

KITCHEN EQUIP. NA NA

LPG INSTALL. NA NA

COMPRES. AIR 88.57% 75.00%

DUST CONTROL 33.88% 27.27%

PROCESS COOLING

NA NA

KEMAJUAN KERJA FIZIKAL – BENGKEL KEJ. JAMINAN KUALITIBANGUNAN

ELECTRICAL PLANNED ACTUAL

WIRING 100.00% 82.50%

SUBMAIN CABLE 94.44% 50.00%

DB 0.00% 0.00%

LUMINAIRE 0.00% 0.00%

MAIN S/BOARD 0.00% 0.00%

LPS 70.85% 71.76%

PA 97.59% 22.19%

SMATV 68.57% 34.14%

CCTV 44.98% 40.48%

ICT 16.57% 0.00%

Page 29: Adtec Pre No.18   Feb 09

BENGKEL KEJ. JAMINAN KUALITI

Page 30: Adtec Pre No.18   Feb 09

MONTH PLANNED ACTUAL AHEAD / DELAY

JAN 09’ 72.73% 78.27% 5.54%

FEB 09’ 79.37% 86.86% 7.49%

MECHANICAL PLANNED

ACTUAL

AIR COND 24.09% 75.00%

FIRE FIGHTING 16.09% 39.65%

KITCHEN EQUIP. NA NA

LPG INSTALL. NA NA

COMPRES. AIR 45.71% 75.00%

DUST CONTROL NA NA

PROCESS COOLING

NA NA

KEMAJUAN KERJA FIZIKAL – BENGKEL MIKRO ELEKTRONIKBANGUNAN

ELECTRICAL PLANNED ACTUAL

WIRING 92.86% 82.50%

SUBMAIN CABLE 9.52% 50.00%

DB 0.00% 0.00%

LUMINAIRE 0.00% 0.00%

MAIN S/BOARD 0.00% 0.00%

LPS 65.33% 72.28%

PA 56.33% 26.46%

SMATV 63.35% 46.25%

CCTV 58.47% 52.62%

ICT 18.14% 0.00%

Page 31: Adtec Pre No.18   Feb 09

BENGKEL MIKRO ELEKTRONIK

Page 32: Adtec Pre No.18   Feb 09

MONTH PLANNED ACTUAL AHEAD / DELAY

JAN 09’ 80.19% 96.63% 16.44%

FEB 09’ 90.43% 96.63% 6.20%

MECHANICAL PLANNED

ACTUAL

AIR COND 100.00% 90.00%

FIRE FIGHTING NA NA

KITCHEN EQUIP. NA NA

LPG INSTALL. NA NA

COMPRES. AIR NA NA

DUST CONTROL NA NA

PROCESS COOLING

NA NA

KEMAJUAN KERJA FIZIKAL – KUATERS KELAS ‘B’

BANGUNAN

ELECTRICAL PLANNED ACTUAL

WIRING 100.00% 90.00%

SUBMAIN CABLE 100.00% 90.00%

DB 100.00% 75.00%

LUMINAIRE 0.00% 65.00%

MAIN S/BOARD 100.00% 0.00%

LPS 97.60% 0.00%

PA NA NA

SMATV 100.00% 32.27%

CCTV 99.75% 34.02%

ICT 100.00% 75.00%

Page 33: Adtec Pre No.18   Feb 09

KUARTERS KELAS ‘B’

Page 34: Adtec Pre No.18   Feb 09

MONTH PLANNED ACTUAL AHEAD / DELAY

JAN 09’ 81.59% 96.76% 15.16%

FEB 09’ 88.42% 96.76% 8.33%

MECHANICAL PLANNED

ACTUAL

AIR COND 100.00% 90.00%

FIRE FIGHTING NA NA

KITCHEN EQUIP. NA NA

LPG INSTALL. NA NA

COMPRES. AIR NA NA

DUST CONTROL NA NA

PROCESS COOLING

NA NA

KEMAJUAN KERJA FIZIKAL – KUATERS KELAS ‘C’

BANGUNAN

ELECTRICAL PLANNED ACTUAL

WIRING 90.48% 90.00%

SUBMAIN CABLE 0.00% 90.00%

DB 100.00% 90.00%

LUMINAIRE 8.33% 90.00%

MAIN S/BOARD 100.00% 0.00%

LPS 83.45% 0.00%

PA NA NA

SMATV 89.67% 24.75%

CCTV NA NA

ICT 98.54% 51.68%

Page 35: Adtec Pre No.18   Feb 09

KUARTERS KELAS ‘C’

Page 36: Adtec Pre No.18   Feb 09

MONTH PLANNED ACTUAL AHEAD / DELAY

JAN 09’ 69.32% 96.38% 27.06%

FEB 09’ 84.31% 96.38% 12.07%

MECHANICAL PLANNED

ACTUAL

AIR COND 100.00% 90.00%

FIRE FIGHTING NA NA

KITCHEN EQUIP. NA NA

LPG INSTALL. NA NA

COMPRES. AIR NA NA

DUST CONTROL NA NA

PROCESS COOLING

NA NA

KEMAJUAN KERJA FIZIKAL – KUATERS KELAS ‘C+D’BANGUNAN

ELECTRICAL PLANNED ACTUAL

WIRING 100.00% 90.00%

SUBMAIN CABLE 100.00% 90.00%

DB 100.00% 90.00%

LUMINAIRE 85.71% 90.00%

MAIN S/BOARD 100.00% 0.00%

LPS 96.87% 0.00%

PA NA NA

SMATV 100.00% 32.27%

CCTV NA NA

ICT 100.00% 75.00%

Page 37: Adtec Pre No.18   Feb 09

KUARTERS KELAS ‘C’ + ‘D’

Page 38: Adtec Pre No.18   Feb 09

MONTH PLANNED ACTUAL AHEAD / DELAY

JAN 09’ 73.69% 91.08% 17.39%

FEB 09’ 77.45% 93.57% 16.12%

MECHANICAL PLANNED

ACTUAL

AIR COND NA NA

FIRE FIGHTING NA NA

KITCHEN EQUIP. NA NA

LPG INSTALL. NA NA

COMPRES. AIR NA NA

DUST CONTROL NA NA

PROCESS COOLING

NA NA

KEMAJUAN KERJA FIZIKAL – KUATERS KELAS F ( 1 BLOK 4 TINGKAT & I BLOK 5 TINGKAT)BANGUNAN

ELECTRICAL PLANNED ACTUAL

WIRING 90.48% 90.00%

SUBMAIN CABLE 0.00% 90.00%

DB 0.00% 75.00%

LUMINAIRE 0.00% 90.00%

MAIN S/BOARD 0.00% 0.00%

LPS 100.00% 83.97%

PA NA NA

SMATV 100.00% 73.58%

CCTV NA NA

ICT 100.00% 54.65%

Page 39: Adtec Pre No.18   Feb 09

KUARTERS KELAS ‘F’ ( 4 TINGKAT )

Page 40: Adtec Pre No.18   Feb 09

KUARTERS KELAS ‘F’ ( 5 TINGKAT )

Page 41: Adtec Pre No.18   Feb 09

MONTH PLANNED ACTUAL AHEAD / DELAY

JAN 09’ 73.24% 92.63% 19.39%

FEB 09’ 77.88% 93.41% 15.53%

MECHANICAL PLANNED

ACTUAL

AIR COND NA NA

FIRE FIGHTING NA NA

KITCHEN EQUIP. NA NA

LPG INSTALL. NA NA

COMPRES. AIR NA NA

DUST CONTROL NA NA

PROCESS COOLING

NA NA

KEMAJUAN KERJA FIZIKAL – KUATERS KELAS G

(1 BLOK 4 TINGKAT & 1 BLOK 5 TINGKAT)BANGUNAN

ELECTRICAL PLANNED ACTUAL

WIRING 100.00% 90.00%

SUBMAIN CABLE 38.10% 90.00%

DB 0.00% 75.00%

LUMINAIRE 0.00% 90.00%

MAIN S/BOARD 0.00% 0.00%

LPS 100.00% 83.97%

PA NA NA

SMATV 100.00% 73.58%

CCTV NA NA

ICT 100.00% 58.20%

Page 42: Adtec Pre No.18   Feb 09

KUARTERS KELAS ‘G’ ( 5 TINGKAT )

Page 43: Adtec Pre No.18   Feb 09

KUARTERS KELAS ‘G’ ( 4 TINGKAT )

Page 44: Adtec Pre No.18   Feb 09

MONTH PLANNED ACTUAL AHEAD / DELAY

JAN 09’ 96.42% 94.87% -1.55%

FEB 09’ 98.16% 97.32% -0.84%

MECHANICAL PLANNED

ACTUAL

AIR COND 100.00% 90.00%

FIRE FIGHTING 100.00% 45.63%

KITCHEN EQUIP. 0.00% 5.66%

LPG INSTALL. NA NA

COMPRES. AIR NA NA

DUST CONTROL NA NA

PROCESS COOLING

NA NA

KEMAJUAN KERJA FIZIKAL – DEWAN MAKAN

BANGUNAN

ELECTRICAL PLANNED ACTUAL

WIRING 100.00% 90.00%

SUBMAIN CABLE 100.00% 75.00%

DB 100.00% 0.00%

LUMINAIRE 100.00% 90.00%

MAIN S/BOARD 100.00% 0.00%

LPS 100.00% 84.63%

PA 100.00% 42.65%

SMATV 100.00% 60.35%

CCTV NA NA

ICT 100.00% 0.00%

Page 45: Adtec Pre No.18   Feb 09

DEWAN MAKAN

Page 46: Adtec Pre No.18   Feb 09

MONTH PLANNED ACTUAL AHEAD / DELAY

JAN 09’ 81.74% 91.05% 9.30%

FEB 09’ 86.42% 97.01% 10.59%

MECHANICAL PLANNED

ACTUAL

AIR COND 100.00% 25.53%

FIRE FIGHTING 91.54% 69.93%

KITCHEN EQUIP. NA NA

LPG INSTALL. NA NA

COMPRES. AIR NA NA

DUST CONTROL NA NA

PROCESS COOLING

NA NA

KEMAJUAN KERJA FIZIKAL – ASRAMA LELAKI A & BBANGUNAN

ELECTRICAL PLANNED ACTUAL

WIRING 64.29% 90.00%

SUBMAIN CABLE 0.00% 75.00%

DB 0.00% 0.00%

LUMINAIRE 0.00% 75.00%

MAIN S/BOARD 0.00% 0.00%

LPS 85.58% 80.71%

PA 99.21% 32.10%

SMATV 72.16% 54.88%

CCTV 37.44% 33.69%

ICT 99.85% 0.00%

Page 47: Adtec Pre No.18   Feb 09

ASRAMA LELAKI A & B

Page 48: Adtec Pre No.18   Feb 09

MONTH PLANNED ACTUAL AHEAD / DELAY

JAN 09’ 72.72% 93.81% 21.09%

FEB 09’ 81.04% 97.63% 16.58%

MECHANICAL PLANNED

ACTUAL

AIR COND 0.00% 10.00%

FIRE FIGHTING 24.94% 71.32%

KITCHEN EQUIP. NA NA

LPG INSTALL. NA NA

COMPRES. AIR NA NA

DUST CONTROL NA NA

PROCESS COOLING

NA NA

KEMAJUAN KERJA FIZIKAL – ASRAMA PEREMPUAN C & DBANGUNAN

ELECTRICAL PLANNED ACTUAL

WIRING 80.95% 90.00%

SUBMAIN CABLE 15.79% 75.00%

DB 0.00% 0.00%

LUMINAIRE 0.00% 90.00%

MAIN S/BOARD 0.00% 0.00%

LPS 79.12% 81.33%

PA 6.35% 30.15%

SMATV 5.81% 54.88%

CCTV 88.52% 0.00%

ICT 0.08% 16.54%

Page 49: Adtec Pre No.18   Feb 09

ASRAMA PEREMPUAN C & D

Page 50: Adtec Pre No.18   Feb 09

MONTH PLANNED ACTUAL AHEAD / DELAY

JAN 09’ 74.66% 78.73% 4.07%

FEB 09’ 77.94% 88.08% 10.14%

MECHANICAL PLANNED

ACTUAL

AIR COND NA NA

FIRE FIGHTING 0.00% 0.00%

KITCHEN EQUIP. NA NA

LPG INSTALL. NA NA

COMPRES. AIR NA NA

DUST CONTROL NA NA

PROCESS COOLING

NA NA

KEMAJUAN KERJA FIZIKAL - SURAU

BANGUNAN

ELECTRICAL PLANNED ACTUAL

WIRING 23.81% 75.00%

SUBMAIN CABLE 0.00% 50.00%

DB NA NA

LUMINAIRE 0.00% 0.00%

MAIN S/BOARD 0.00% 0.00%

LPS 43.92% 58.38%

PA 18.31% 4.58%

SMATV NA NA

CCTV NA NA

ICT NA NA

Page 51: Adtec Pre No.18   Feb 09

SURAU

Page 52: Adtec Pre No.18   Feb 09

MONTH PLANNED ACTUAL AHEAD / DELAY

JAN 09’ 79.98% 87.62% 7.64%

FEB 09’ 91.60% 98.95% 7.35%

MECHANICAL PLANNED

ACTUAL

AIR COND NA NA

FIRE FIGHTING 0.00% 0.00%

KITCHEN EQUIP. NA NA

LPG INSTALL. NA NA

COMPRES. AIR NA NA

DUST CONTROL NA NA

PROCESS COOLING

NA NA

KEMAJUAN KERJA FIZIKAL - ASTAKA

BANGUNAN SOKONGAN

ELECTRICAL PLANNED ACTUAL

WIRING 100.00% 90.00%

SUBMAIN CABLE 100.00% 90.00%

DB 100.00% 0.00%

LUMINAIRE 100.00% 50.00%

MAIN S/BOARD 100.00% 0.00%

LPS 59.67% 58.21%

PA 100.00% 5.72%

SMATV NA NA

CCTV NA NA

ICT NA NA

Page 53: Adtec Pre No.18   Feb 09

BANGUNAN SOKONGAN

ASTAKA

Page 54: Adtec Pre No.18   Feb 09

MONTH PLANNED ACTUAL AHEAD / DELAY

FEB 09’ 87.44% 97.52% 10.08%

MECHANICAL PLANNED

ACTUAL

AIR COND 91.70% 88.10%

FIRE FIGHTING 70.07% 0.00%

KITCHEN EQUIP. NA NA

LPG INSTALL. 0.00% 0.00%

COMPRES. AIR NA NA

DUST CONTROL NA NA

PROCESS COOLING

NA NA

KEMAJUAN KERJA FIZIKAL – M&E PLANT ROOM

BANGUNAN SOKONGAN

ELECTRICAL PLANNED ACTUAL

WIRING 100.00% 90.00%

SUBMAIN CABLE 100.00% 20.00%

DB 100.00% 0.00%

LUMINAIRE 100.00% 50.00%

MAIN S/BOARD 100.00% 0.00%

LPS NA NA

PA NA NA

SMATV NA NA

CCTV NA NA

ICT NA NA

Page 55: Adtec Pre No.18   Feb 09

BANGUNAN SOKONGAN

M&E PLANT ROOM – PUSAT SUMBER

Page 56: Adtec Pre No.18   Feb 09

BANGUNAN SOKONGAN

M&E PLANT ROOM - BENGKEL

Page 57: Adtec Pre No.18   Feb 09

DECORATIVE FENCE

Page 58: Adtec Pre No.18   Feb 09

BANGUNAN SOKONGAN

GARAJ KENDERAAN

Page 59: Adtec Pre No.18   Feb 09

ELEVATED WATER TANK, PUMP HOUSE & SUCTION TANK

Page 60: Adtec Pre No.18   Feb 09

WAKAF

Page 61: Adtec Pre No.18   Feb 09

LALUAN BERBUMBUNG

Page 62: Adtec Pre No.18   Feb 09

OPEN PLAZA

Page 63: Adtec Pre No.18   Feb 09

KERJA INFRA – JALAN UTAMA

Page 64: Adtec Pre No.18   Feb 09

GELANGGANG PERMAINAN - TENIS

Page 65: Adtec Pre No.18   Feb 09

M&E INSTALLATION

Page 66: Adtec Pre No.18   Feb 09

M&E INSTALLATION

Page 67: Adtec Pre No.18   Feb 09

M&E INSTALLATION

Page 68: Adtec Pre No.18   Feb 09

M&E INSTALLATION

Page 69: Adtec Pre No.18   Feb 09

• SEKIAN TERIMA KASIH