LAPORAN KEMAJUAN PROJEK NO.18
‘FEBUARY 2009’
PROJEK ADTEC TAIPING
KEMENTERIAN SUMBER MANUSIA
JABATAN KERJA RAYA MALAYSIA
KAMALBINA SDN. BHD
PEMILIK
PEGARAH PROJEK
KONTRAKTOR R&B
ADTEC TAIPING
LOKASI PROJEK
BANGUNAN PENTADBIRAN
BENGKEL TEK. MAKLUMAT& JAMIN KUALITI
DEWAN BESAR
PUSAT SUMBER
DEWAN KULIAH
LOBI UTAMA
KAFETERIA
MIKRO ELEKTRONIK
KOMPOSIT PLASTIK
M&E PLANT ROOM
1
TNB SUB
STATION
SERAMIK
M&E PLANT ROOM
2
GARAJ KENDERAAN
ASRAMA LELAKIASRAMA PEREMPUAN
DEWANMAKAN
SURAU
KELAS F
KELAS G
KUARTERSB, C, C&D
PELAN TAPAK ADTEC TAIPING
KEMAJUAN KERJA FIZIKAL
JADUAL : 70.88%SEBENAR : 67.03%KESELURUHAN : -3.85%
TARIKH LAPORAN : 12 FEB 2009
KEMAJUAN KERJA KEWANGAN
JADUAL : 74.78%SEBENAR : 68.50%KESELURUHAN : -6.28% @ 45 HARI
(LEWAT )
TARIKH LAPORAN : 12 FEB 2009
MONTH PLANNED ACTUAL AHEAD / DELAY
JAN 09’ 98.98% 65.52% - 33.46%
FEB 09’ 99.12% 67.42% - 31.70%
MECHANICAL PLANNED
ACTUAL
AIR COND 100.00% 50.00%
FIRE FIGHTING 100.00% 26.74%
KITCHEN EQUIP. NA NA
LPG INSTALL. NA NA
COMPRES. AIR NA NA
DUST CONTROL NA NA
PROCESS COOLING
NA NA
KEMAJUAN KERJA FIZIKAL - DEWAN BESAR
BANGUNAN
ELECTRICAL PLANNED ACTUAL
WIRING 100.00% 65.00%
SUBMAIN CABLE 100.00% 71.00%
DB 100.00% 0.00%
LUMINAIRE 100.00% 0.00%
MAIN S/BOARD 100.00% 0.00%
LPS NA NA
PA 100.00% 2.12%
SMATV 100.00% 21.25%
CCTV NA NA
ICT 100.00% 12.65%
DEWAN BESAR
DEWAN BESAR
MONTH PLANNED ACTUAL AHEAD / DELAY
JAN 09’ 93.25% 78.68% -14.57%
FEB 09’ 95.00% 90.85% -4.15%
MECHANICAL PLANNED
ACTUAL
AIR COND NA NA
FIRE FIGHTING NA NA
KITCHEN EQUIP. NA NA
LPG INSTALL. NA NA
COMPRES. AIR NA NA
DUST CONTROL NA NA
PROCESS COOLING
NA NA
KEMAJUAN KERJA FIZIKAL – LOBI
BANGUNAN
ELECTRICAL PLANNED ACTUAL
WIRING 100.00% 75.00%
SUBMAIN CABLE 100.00% 90.00%
DB 100.00% 0.00%
LUMINAIRE 100.00% 0.00%
MAIN S/BOARD NA NA
LPS NA NA
PA 100.00% 65.37%
SMATV NA NA
CCTV 100.00% 0.00%
ICT NA NA
LOBI UTAMA
MONTH PLANNED ACTUAL AHEAD / DELAY
JAN 09’ 73.49% 66.39% -7.10%
FEB 09’ 83.03% 70.04% -12.99%
MECHANICAL PLANNED
ACTUAL
AIR COND 50.00% 74.50%
FIRE FIGHTING 41.70% 49.64%
KITCHEN EQUIP. NA NA
LPG INSTALL. NA NA
COMPRES. AIR NA NA
DUST CONTROL NA NA
PROCESS COOLING
NA NA
KEMAJUAN KERJA FIZIKAL – DEWAN KULIAH UTAMABANGUNAN
ELECTRICAL PLANNED ACTUAL
WIRING 100.00% 65.00%
SUBMAIN CABLE 56.25% 88.00%
DB 100.00% 0.00%
LUMINAIRE 0.00% 0.00%
MAIN S/BOARD 100.00% 0.00%
LPS 91.09% 0.00%
PA 100.00% 19.31%
SMATV NA NA
CCTV NA NA
ICT 97.21% 0.00%
DEWAN KULIAH UTAMA
MONTH PLANNED ACTUAL AHEAD / DELAY
JAN 09’ 84.29% 84.41% 0.12%
FEB 09’ 93.37% 89.98% -3.39%
MECHANICAL PLANNED
ACTUAL
AIR COND 87.60% 80.18%
FIRE FIGHTING 33.90% 90.24%
KITCHEN EQUIP. NA NA
LPG INSTALL. NA NA
COMPRES. AIR NA NA
DUST CONTROL NA NA
PROCESS COOLING
NA NA
KEMAJUAN KERJA FIZIKAL – PUSAT SUMBER/PERPUSTAKAAN
BANGUNAN
ELECTRICAL PLANNED ACTUAL
WIRING 100.00% 90.00%
SUBMAIN CABLE 100.00% 88.00%
DB 100.00% 0.00%
LUMINAIRE 100.00% 25.00%
MAIN S/BOARD 100.00% 0.00%
LPS 100.00% 73.47%
PA 100.00% 34.79%
SMATV 100.00% 57.16%
CCTV NA NA
ICT 29.27% 0.00%
PUSAT SUMBER / PERPUSTAKAAN
MONTH PLANNED ACTUAL AHEAD / DELAY
JAN 09’ 82.12% 77.52% -4.60%
FEB 09’ 91.35% 84.29% -7.06%
MECHANICAL PLANNED
ACTUAL
AIR COND 71.21% 63.09%
FIRE FIGHTING 45.46% 38.79%
KITCHEN EQUIP. NA NA
LPG INSTALL. NA NA
COMPRES. AIR NA NA
DUST CONTROL NA NA
PROCESS COOLING
NA NA
KEMAJUAN KERJA FIZIKAL – PENTADBIRAN & PENGURUSAN SUMBERBANGUNAN
ELECTRICAL PLANNED ACTUAL
WIRING 100.00% 82.50%
SUBMAIN CABLE 100.00% 78.00%
DB 100.00% 0.00%
LUMINAIRE 78.57% 25.00%
MAIN S/BOARD 100.00% 0.00%
LPS 93.03% 69.22%
PA 100.00% 15.96%
SMATV 100.00% 52.05%
CCTV 62.56% 2.13%
ICT 72.81% 0.00%
BANGUNAN PENTADBIRAN & PENGURUSAN SUMBER
MONTH PLANNED ACTUAL AHEAD / DELAY
JAN 09’ 72.24% 89.11% 16.88%
FEB 09’ 84.36% 94.85% 10.49%
MECHANICAL PLANNED
ACTUAL
AIR COND 0.00% 43.00%
FIRE FIGHTING 12.65% 29.54%
KITCHEN EQUIP. 0.00% 6.51%
LPG INSTALL. NA NA
COMPRES. AIR NA NA
DUST CONTROL NA NA
PROCESS COOLING
NA NA
KEMAJUAN KERJA FIZIKAL - KAFETARIA
BANGUNAN
ELECTRICAL PLANNED ACTUAL
WIRING 100.00% 90.00%
SUBMAIN CABLE 100.00% 90.00%
DB 83.33% 0.00%
LUMINAIRE 0.00% 25.00%
MAIN S/BOARD NA NA
LPS 64.46% 56.58%
PA 98.14% 22.79%
SMATV 81.61% 50.29%
CCTV NA NA
ICT 100.00% 0.00%
KAFETERIA
MONTH PLANNED ACTUAL AHEAD / DELAY
JAN 09’ 79.02% 84.02% 5.01%
FEB 09’ 85.84% 89.53% 3.69%
MECHANICAL PLANNED
ACTUAL
AIR COND 23.57% 66.78%
FIRE FIGHTING 27.70% 33.67%
KITCHEN EQUIP. NA NA
LPG INSTALL. NA NA
COMPRES. AIR NA NA
DUST CONTROL NA NA
PROCESS COOLING
NA NA
KEMAJUAN KERJA FIZIKAL – BENGKEL TEKNOLOGI MAKLUMATBANGUNAN
ELECTRICAL PLANNED ACTUAL
WIRING 100.00% 90.00%
SUBMAIN CABLE 100.00% 50.00%
DB 100.00% 25.00%
LUMINAIRE 0.00% 45.00%
MAIN S/BOARD 86.67% 0.00%
LPS 99.49% 74.62%
PA 100.00% 42.43%
SMATV 99.68% 59.11%
CCTV 54.53% 33.71%
ICT 20.74% 0.00%
BENGKEL TEKNOLOGI MAKLUMAT
MONTH PLANNED ACTUAL AHEAD / DELAY
JAN 09’ 68.69% 86.03% 17.33%
FEB 09’ 78.05% 93.28% 15.23%
MECHANICAL PLANNED
ACTUAL
AIR COND 30.27% 80.11%
FIRE FIGHTING 24.65% 53.54%
KITCHEN EQUIP. NA NA
LPG INSTALL. NA NA
COMPRES. AIR 14.29% 75.00%
DUST CONTROL NA NA
PROCESS COOLING
7.60% 0.00%
KEMAJUAN KERJA FIZIKAL – BENGKEL KEJ. BAHAN TERMAJU (PLASTIK)BANGUNAN
ELECTRICAL PLANNED ACTUAL
WIRING 53.57% 90.00%
SUBMAIN CABLE 0.00% 80.00%
DB 0.00% 0.00%
LUMINAIRE 0.00% 45.00%
MAIN S/BOARD 0.00% 0.00%
LPS 69.14% 74.65%
PA 22.31% 46.85%
SMATV NA NA
CCTV 37.46% 49.69%
ICT 4.96% 0.00%
BENGKEL KEJ. BAHAN TERMAJU (PLASTIK)
MONTH PLANNED ACTUAL AHEAD / DELAY
JAN 09’ 71.23% 83.64% 12.41%
FEB 09’ 79.39% 93.66% 14.27%
MECHANICAL PLANNED
ACTUAL
AIR COND 31.60% 79.74%
FIRE FIGHTING 31.64% 59.65%
KITCHEN EQUIP. NA NA
LPG INSTALL. NA NA
COMPRES. AIR 20.00% 75.00%
DUST CONTROL 17.20% 23.77%
PROCESS COOLING
12.06% 0.00%
KEMAJUAN KERJA FIZIKAL – BENGKEL KEJ. BAHAN TERMAJU (KOMPOSIT)BANGUNAN
ELECTRICAL PLANNED ACTUAL
WIRING 60.71% 90.00%
SUBMAIN CABLE 0.00% 75.00%
DB 0.00% 0.00%
LUMINAIRE 0.00% 45.00%
MAIN S/BOARD 0.00% 0.00%
LPS 64.14% 67.88%
PA 25.13% 40.39%
SMATV NA NA
CCTV 54.68% 50.54%
ICT 13.80% 0.00%
BENGKEL KEJ. BAHAN TERMAJU (KOMPOSIT)
MONTH PLANNED ACTUAL AHEAD / DELAY
JAN 09’ 71.02% 79.96% 8.84%
FEB 09’ 76.14% 93.08% 16.93%
MECHANICAL PLANNED
ACTUAL
AIR COND 15.58% 78.29%
FIRE FIGHTING 27.33% 55.87%
KITCHEN EQUIP. NA NA
LPG INSTALL. NA NA
COMPRES. AIR 28.57% 75.00%
DUST CONTROL 3.37% 28.75%
PROCESS COOLING
15.20% 0.00%
KEMAJUAN KERJA FIZIKAL – BENGKEL KEJ. BAHAN TERMAJU (SERAMIK)BANGUNAN
ELECTRICAL PLANNED ACTUAL
WIRING 71.43% 90.00%
SUBMAIN CABLE 0.00% 85.00%
DB 0.00% 0.00%
LUMINAIRE 0.00% 45.00%
MAIN S/BOARD 0.00% 0.00%
LPS 56.92% 73.14%
PA 39.65% 41.63%
SMATV NA NA
CCTV 43.10% 57.16%
ICT 11.76% 0.00%
BENGKEL KEJ. BAHAN TERMAJU (SERAMIK)
MONTH PLANNED ACTUAL AHEAD / DELAY
JAN 09’ 77.16% 77.74% 0.58%
FEB 09’ 80.11% 87.32% 7.21%
MECHANICAL PLANNED
ACTUAL
AIR COND 25.39% 55.00%
FIRE FIGHTING 37.17% 37.23%
KITCHEN EQUIP. NA NA
LPG INSTALL. NA NA
COMPRES. AIR 88.57% 75.00%
DUST CONTROL 33.88% 27.27%
PROCESS COOLING
NA NA
KEMAJUAN KERJA FIZIKAL – BENGKEL KEJ. JAMINAN KUALITIBANGUNAN
ELECTRICAL PLANNED ACTUAL
WIRING 100.00% 82.50%
SUBMAIN CABLE 94.44% 50.00%
DB 0.00% 0.00%
LUMINAIRE 0.00% 0.00%
MAIN S/BOARD 0.00% 0.00%
LPS 70.85% 71.76%
PA 97.59% 22.19%
SMATV 68.57% 34.14%
CCTV 44.98% 40.48%
ICT 16.57% 0.00%
BENGKEL KEJ. JAMINAN KUALITI
MONTH PLANNED ACTUAL AHEAD / DELAY
JAN 09’ 72.73% 78.27% 5.54%
FEB 09’ 79.37% 86.86% 7.49%
MECHANICAL PLANNED
ACTUAL
AIR COND 24.09% 75.00%
FIRE FIGHTING 16.09% 39.65%
KITCHEN EQUIP. NA NA
LPG INSTALL. NA NA
COMPRES. AIR 45.71% 75.00%
DUST CONTROL NA NA
PROCESS COOLING
NA NA
KEMAJUAN KERJA FIZIKAL – BENGKEL MIKRO ELEKTRONIKBANGUNAN
ELECTRICAL PLANNED ACTUAL
WIRING 92.86% 82.50%
SUBMAIN CABLE 9.52% 50.00%
DB 0.00% 0.00%
LUMINAIRE 0.00% 0.00%
MAIN S/BOARD 0.00% 0.00%
LPS 65.33% 72.28%
PA 56.33% 26.46%
SMATV 63.35% 46.25%
CCTV 58.47% 52.62%
ICT 18.14% 0.00%
BENGKEL MIKRO ELEKTRONIK
MONTH PLANNED ACTUAL AHEAD / DELAY
JAN 09’ 80.19% 96.63% 16.44%
FEB 09’ 90.43% 96.63% 6.20%
MECHANICAL PLANNED
ACTUAL
AIR COND 100.00% 90.00%
FIRE FIGHTING NA NA
KITCHEN EQUIP. NA NA
LPG INSTALL. NA NA
COMPRES. AIR NA NA
DUST CONTROL NA NA
PROCESS COOLING
NA NA
KEMAJUAN KERJA FIZIKAL – KUATERS KELAS ‘B’
BANGUNAN
ELECTRICAL PLANNED ACTUAL
WIRING 100.00% 90.00%
SUBMAIN CABLE 100.00% 90.00%
DB 100.00% 75.00%
LUMINAIRE 0.00% 65.00%
MAIN S/BOARD 100.00% 0.00%
LPS 97.60% 0.00%
PA NA NA
SMATV 100.00% 32.27%
CCTV 99.75% 34.02%
ICT 100.00% 75.00%
KUARTERS KELAS ‘B’
MONTH PLANNED ACTUAL AHEAD / DELAY
JAN 09’ 81.59% 96.76% 15.16%
FEB 09’ 88.42% 96.76% 8.33%
MECHANICAL PLANNED
ACTUAL
AIR COND 100.00% 90.00%
FIRE FIGHTING NA NA
KITCHEN EQUIP. NA NA
LPG INSTALL. NA NA
COMPRES. AIR NA NA
DUST CONTROL NA NA
PROCESS COOLING
NA NA
KEMAJUAN KERJA FIZIKAL – KUATERS KELAS ‘C’
BANGUNAN
ELECTRICAL PLANNED ACTUAL
WIRING 90.48% 90.00%
SUBMAIN CABLE 0.00% 90.00%
DB 100.00% 90.00%
LUMINAIRE 8.33% 90.00%
MAIN S/BOARD 100.00% 0.00%
LPS 83.45% 0.00%
PA NA NA
SMATV 89.67% 24.75%
CCTV NA NA
ICT 98.54% 51.68%
KUARTERS KELAS ‘C’
MONTH PLANNED ACTUAL AHEAD / DELAY
JAN 09’ 69.32% 96.38% 27.06%
FEB 09’ 84.31% 96.38% 12.07%
MECHANICAL PLANNED
ACTUAL
AIR COND 100.00% 90.00%
FIRE FIGHTING NA NA
KITCHEN EQUIP. NA NA
LPG INSTALL. NA NA
COMPRES. AIR NA NA
DUST CONTROL NA NA
PROCESS COOLING
NA NA
KEMAJUAN KERJA FIZIKAL – KUATERS KELAS ‘C+D’BANGUNAN
ELECTRICAL PLANNED ACTUAL
WIRING 100.00% 90.00%
SUBMAIN CABLE 100.00% 90.00%
DB 100.00% 90.00%
LUMINAIRE 85.71% 90.00%
MAIN S/BOARD 100.00% 0.00%
LPS 96.87% 0.00%
PA NA NA
SMATV 100.00% 32.27%
CCTV NA NA
ICT 100.00% 75.00%
KUARTERS KELAS ‘C’ + ‘D’
MONTH PLANNED ACTUAL AHEAD / DELAY
JAN 09’ 73.69% 91.08% 17.39%
FEB 09’ 77.45% 93.57% 16.12%
MECHANICAL PLANNED
ACTUAL
AIR COND NA NA
FIRE FIGHTING NA NA
KITCHEN EQUIP. NA NA
LPG INSTALL. NA NA
COMPRES. AIR NA NA
DUST CONTROL NA NA
PROCESS COOLING
NA NA
KEMAJUAN KERJA FIZIKAL – KUATERS KELAS F ( 1 BLOK 4 TINGKAT & I BLOK 5 TINGKAT)BANGUNAN
ELECTRICAL PLANNED ACTUAL
WIRING 90.48% 90.00%
SUBMAIN CABLE 0.00% 90.00%
DB 0.00% 75.00%
LUMINAIRE 0.00% 90.00%
MAIN S/BOARD 0.00% 0.00%
LPS 100.00% 83.97%
PA NA NA
SMATV 100.00% 73.58%
CCTV NA NA
ICT 100.00% 54.65%
KUARTERS KELAS ‘F’ ( 4 TINGKAT )
KUARTERS KELAS ‘F’ ( 5 TINGKAT )
MONTH PLANNED ACTUAL AHEAD / DELAY
JAN 09’ 73.24% 92.63% 19.39%
FEB 09’ 77.88% 93.41% 15.53%
MECHANICAL PLANNED
ACTUAL
AIR COND NA NA
FIRE FIGHTING NA NA
KITCHEN EQUIP. NA NA
LPG INSTALL. NA NA
COMPRES. AIR NA NA
DUST CONTROL NA NA
PROCESS COOLING
NA NA
KEMAJUAN KERJA FIZIKAL – KUATERS KELAS G
(1 BLOK 4 TINGKAT & 1 BLOK 5 TINGKAT)BANGUNAN
ELECTRICAL PLANNED ACTUAL
WIRING 100.00% 90.00%
SUBMAIN CABLE 38.10% 90.00%
DB 0.00% 75.00%
LUMINAIRE 0.00% 90.00%
MAIN S/BOARD 0.00% 0.00%
LPS 100.00% 83.97%
PA NA NA
SMATV 100.00% 73.58%
CCTV NA NA
ICT 100.00% 58.20%
KUARTERS KELAS ‘G’ ( 5 TINGKAT )
KUARTERS KELAS ‘G’ ( 4 TINGKAT )
MONTH PLANNED ACTUAL AHEAD / DELAY
JAN 09’ 96.42% 94.87% -1.55%
FEB 09’ 98.16% 97.32% -0.84%
MECHANICAL PLANNED
ACTUAL
AIR COND 100.00% 90.00%
FIRE FIGHTING 100.00% 45.63%
KITCHEN EQUIP. 0.00% 5.66%
LPG INSTALL. NA NA
COMPRES. AIR NA NA
DUST CONTROL NA NA
PROCESS COOLING
NA NA
KEMAJUAN KERJA FIZIKAL – DEWAN MAKAN
BANGUNAN
ELECTRICAL PLANNED ACTUAL
WIRING 100.00% 90.00%
SUBMAIN CABLE 100.00% 75.00%
DB 100.00% 0.00%
LUMINAIRE 100.00% 90.00%
MAIN S/BOARD 100.00% 0.00%
LPS 100.00% 84.63%
PA 100.00% 42.65%
SMATV 100.00% 60.35%
CCTV NA NA
ICT 100.00% 0.00%
DEWAN MAKAN
MONTH PLANNED ACTUAL AHEAD / DELAY
JAN 09’ 81.74% 91.05% 9.30%
FEB 09’ 86.42% 97.01% 10.59%
MECHANICAL PLANNED
ACTUAL
AIR COND 100.00% 25.53%
FIRE FIGHTING 91.54% 69.93%
KITCHEN EQUIP. NA NA
LPG INSTALL. NA NA
COMPRES. AIR NA NA
DUST CONTROL NA NA
PROCESS COOLING
NA NA
KEMAJUAN KERJA FIZIKAL – ASRAMA LELAKI A & BBANGUNAN
ELECTRICAL PLANNED ACTUAL
WIRING 64.29% 90.00%
SUBMAIN CABLE 0.00% 75.00%
DB 0.00% 0.00%
LUMINAIRE 0.00% 75.00%
MAIN S/BOARD 0.00% 0.00%
LPS 85.58% 80.71%
PA 99.21% 32.10%
SMATV 72.16% 54.88%
CCTV 37.44% 33.69%
ICT 99.85% 0.00%
ASRAMA LELAKI A & B
MONTH PLANNED ACTUAL AHEAD / DELAY
JAN 09’ 72.72% 93.81% 21.09%
FEB 09’ 81.04% 97.63% 16.58%
MECHANICAL PLANNED
ACTUAL
AIR COND 0.00% 10.00%
FIRE FIGHTING 24.94% 71.32%
KITCHEN EQUIP. NA NA
LPG INSTALL. NA NA
COMPRES. AIR NA NA
DUST CONTROL NA NA
PROCESS COOLING
NA NA
KEMAJUAN KERJA FIZIKAL – ASRAMA PEREMPUAN C & DBANGUNAN
ELECTRICAL PLANNED ACTUAL
WIRING 80.95% 90.00%
SUBMAIN CABLE 15.79% 75.00%
DB 0.00% 0.00%
LUMINAIRE 0.00% 90.00%
MAIN S/BOARD 0.00% 0.00%
LPS 79.12% 81.33%
PA 6.35% 30.15%
SMATV 5.81% 54.88%
CCTV 88.52% 0.00%
ICT 0.08% 16.54%
ASRAMA PEREMPUAN C & D
MONTH PLANNED ACTUAL AHEAD / DELAY
JAN 09’ 74.66% 78.73% 4.07%
FEB 09’ 77.94% 88.08% 10.14%
MECHANICAL PLANNED
ACTUAL
AIR COND NA NA
FIRE FIGHTING 0.00% 0.00%
KITCHEN EQUIP. NA NA
LPG INSTALL. NA NA
COMPRES. AIR NA NA
DUST CONTROL NA NA
PROCESS COOLING
NA NA
KEMAJUAN KERJA FIZIKAL - SURAU
BANGUNAN
ELECTRICAL PLANNED ACTUAL
WIRING 23.81% 75.00%
SUBMAIN CABLE 0.00% 50.00%
DB NA NA
LUMINAIRE 0.00% 0.00%
MAIN S/BOARD 0.00% 0.00%
LPS 43.92% 58.38%
PA 18.31% 4.58%
SMATV NA NA
CCTV NA NA
ICT NA NA
SURAU
MONTH PLANNED ACTUAL AHEAD / DELAY
JAN 09’ 79.98% 87.62% 7.64%
FEB 09’ 91.60% 98.95% 7.35%
MECHANICAL PLANNED
ACTUAL
AIR COND NA NA
FIRE FIGHTING 0.00% 0.00%
KITCHEN EQUIP. NA NA
LPG INSTALL. NA NA
COMPRES. AIR NA NA
DUST CONTROL NA NA
PROCESS COOLING
NA NA
KEMAJUAN KERJA FIZIKAL - ASTAKA
BANGUNAN SOKONGAN
ELECTRICAL PLANNED ACTUAL
WIRING 100.00% 90.00%
SUBMAIN CABLE 100.00% 90.00%
DB 100.00% 0.00%
LUMINAIRE 100.00% 50.00%
MAIN S/BOARD 100.00% 0.00%
LPS 59.67% 58.21%
PA 100.00% 5.72%
SMATV NA NA
CCTV NA NA
ICT NA NA
BANGUNAN SOKONGAN
ASTAKA
MONTH PLANNED ACTUAL AHEAD / DELAY
FEB 09’ 87.44% 97.52% 10.08%
MECHANICAL PLANNED
ACTUAL
AIR COND 91.70% 88.10%
FIRE FIGHTING 70.07% 0.00%
KITCHEN EQUIP. NA NA
LPG INSTALL. 0.00% 0.00%
COMPRES. AIR NA NA
DUST CONTROL NA NA
PROCESS COOLING
NA NA
KEMAJUAN KERJA FIZIKAL – M&E PLANT ROOM
BANGUNAN SOKONGAN
ELECTRICAL PLANNED ACTUAL
WIRING 100.00% 90.00%
SUBMAIN CABLE 100.00% 20.00%
DB 100.00% 0.00%
LUMINAIRE 100.00% 50.00%
MAIN S/BOARD 100.00% 0.00%
LPS NA NA
PA NA NA
SMATV NA NA
CCTV NA NA
ICT NA NA
BANGUNAN SOKONGAN
M&E PLANT ROOM – PUSAT SUMBER
BANGUNAN SOKONGAN
M&E PLANT ROOM - BENGKEL
DECORATIVE FENCE
BANGUNAN SOKONGAN
GARAJ KENDERAAN
ELEVATED WATER TANK, PUMP HOUSE & SUCTION TANK
WAKAF
LALUAN BERBUMBUNG
OPEN PLAZA
KERJA INFRA – JALAN UTAMA
GELANGGANG PERMAINAN - TENIS
M&E INSTALLATION
M&E INSTALLATION
M&E INSTALLATION
M&E INSTALLATION