QUALITY ASSESSMENT SYSTEM FOR BUILDINGCONSTRUCTION WORKS STANDARD INDUSTRI PEMBINAAN (CONSTRUCTION INDUSTRY STANDARD) CIS 23:20## (First revision) SAFE USE OF FALSEWORK IN CONSTRUCTION Descriptors: falsework products standards, certification, marking and quality check. © Copyright CONSTRUCTION INDUSTRY DEVELOPMENT BOARD Construction Industry Development Board Malaysia LEMBAGA PEMBANGUNAN INDUSTRI PEMBINAAN MALAYSIA IbuPejabat CIDB, Tingkat 10, Menara Dato’ Onn, Pusat Dagangan Dunia No 45, Jalan Tun Ismail, 50480 Kuala Lumpur, Malaysia Tel:603-40477000 Faks:603-40477020 http://www.cidb.gov.my

Upload: others

Post on 03-Oct-2021

6 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: STANDARD PEMBINAAN

QUALITY ASSESSMENT SYSTEM FOR BUILDINGCONSTRUCTION WORKS

STANDARD INDUSTRI PEMBINAAN (CONSTRUCTION INDUSTRY STANDARD)

CIS 23:20## (First revision)

SAFE USE OF FALSEWORK IN CONSTRUCTION Descriptors: falsework products standards, certification, marking and quality check.

© Copyright

CONSTRUCTION INDUSTRY DEVELOPMENT BOARD

Construction Industry Development Board Malaysia LEMBAGA PEMBANGUNAN INDUSTRI PEMBINAAN MALAYSIA IbuPejabat CIDB,

Tingkat 10, Menara Dato’ Onn, Pusat Dagangan Dunia No 45, Jalan Tun Ismail, 50480 Kuala Lumpur, Malaysia Tel:603-40477000 Faks:603-40477020 http://www.cidb.gov.my

Page 2: STANDARD PEMBINAAN

CIS 23: 20## Safe Use of Scaffolding in Construction © Construction Industry Development Board Malaysia 20##

All enquiries regarding this book should be forwarded to: Chief Executive Construction Industry Development Board Malaysia Level 10, Menara Dato’ Onn, Pusat Dagangan Dunia, No 45, Jalan Tun Ismail, 50480 Kuala Lumpur, Malaysia. Tel : 603-4047 7000 Fax : 603-4047 7070 Email : [email protected] Website : www.cidb.gov.my No part of this publication may be reproduced or transmitted in any form or by any means, whether mechanical or electronic including photocopying and recording without the written consent of CIDB. Perpustakaan Negara Malaysia Cataloguing-in-Publication Data

Page 3: STANDARD PEMBINAAN

ii

Page 4: STANDARD PEMBINAAN

iii

TABLE OF CONTENTS

Committee representation iv

Preface v

SECTION 1: GENERAL 1

1.1 Scope 1

1.2 Normative References 2

1.3 Terms and Definitions 2

SECTION 2: ACTS AND REGULATION

2.1 General Requirements 3

2.1.1 CIDB Act 520 (Amendment 2011) – Fourth Schedule – Standard for Certification of Construction Material

3

2.1.2 Occupational Safety and Health Act 1994 (Act 514) 3

2.1.3 Factories and Machinery Act 1967 [ACT 139] P.U. (A) 328/86 3

2.1.4 Perintah Khas Ketua Pemeriksa, Bilangan 1 Tahun 2020, Pengurusan Keselamatan Struktur Sementara

3

SECTION 3: PRODUCTS AND PRODUCT STANDARDS, CERTIFICATION AND MARKING

3.1 Product with Product Standards 4

3.2 Proprietary Falsework System 4

3.3 Product Certification/ Test Report 5

3.4 Product Marking 5

SECTION 4: PLANNING, PRODUCT APPROVAL, DESIGN AND SUBMISSION, MATERIAL SELECTION AND SUBMISSION

5

4.1 Planning for temporary work and Hazard Identification, Risk Assessment and Risk Control (HIRARC)

6

4.2 CIDB Approval for Product - Perakuan Pematuhan Standard (PPS) 6

4.3 Design and Submission 6

SECTION 5: MATERIAL RECEIVING, QUALITY CHECK, TESTING, ERECTION, SUPERVISION, INSPECTION, MAINTENANCE, MODIFICATION, DISMANTLING, STORAGE AND CARE

5.1 Material Receiving 7

5.2 Quality Check for PPS Issuance 7

5.2.1 Initial Site Quality Check (ISQC) 7

5.2.2 Scheduled Site Quality Check (SSQC) 8

5.3 Erection, Supervision, Inspection, Maintenance, Modifications, Dismantling, Storage and Care

8

Appendix A Examples of a typical set up of falsework 11

Appendix B Process A: Flowchart for Design and Drawing Approval for Construction of Falsework

12

Appendix C Process B: Flowchart for Receiving and Selection of Material, Quality Check, Erection, Modification, Dismantling, Storage and Care of Falsework

13

Appendix D Falsework Receiving Inspection Checklist Form

14

Appendix E Falsework Inspection Checklist Form 15

ACKNOWLEDGEMENT 16

Page 5: STANDARD PEMBINAAN

iv

COMMITTEE REPRESENTATION

This Construction Industry Standard (CIS) was managed and developed by the Construction Industry

Development Board Malaysia with the assistance of the Technical Committee of Temporary Works,

which comprises representatives from the following organisations:

Association of Consulting Engineers Malaysia

Board of Engineers Malaysia

BW Scaffold Industries Sdn Bhd

Construction Research Institute of Malaysia

Doka Formwork Malaysia Sdn. Bhd.

Dscaff Engineering Sdn Bhd

Institution of Engineers Malaysia

IQRAMXPERT Sdn. Bhd.

Jabatan Kerja Raya Malaysia

Jabatan Keselamatan dan Kesihatan Pekerjaan Malaysia

Malaysian Iron & Steel Industry Federation

Master Builders Association Malaysia

Malaysian Occupational Scaffolding Association

PERI Formwork Malaysia Sdn. Bhd.

PLYTEC Formwork System Industry

Persatuan Kontraktor Bumiputra Malaysia

Real Estate and Housing Developers Association

SGS Malaysia Sdn. Bhd.

Technologies Association Malaysia

Page 6: STANDARD PEMBINAAN

v

PREFACE

This Construction Industry Standard (CIS) was reviewed by the Technical Committee of CIS 22 and

CIS 23. The review of this CIS is to compliment the scaffolding product compliance requirement which

regulated under Lembaga Pembangunan Industri Pembinaan Malaysia Act 1994 (Amendmend 2011)

(Act 520) CIDB Act 520 (Amendment 2011) - Fourth Schedule - Standards for Certification of

Construction Materials.

This second edition cancel and replaces the 1st edition, of which it constitutes major revisions of:

1. scope of the standard, which focuses on the products standards regulated under the Fourth

Schedule - Standards for Certification of Construction Materials;

2. the falsework quality check, which include Initial Site Quality Check and Schedule Site Quality

Check; and

3. product marking.

Compliance with this document does not in itself confer immunity from legal obligations.

Page 7: STANDARD PEMBINAAN

1

SAFE USE OF FALSEWORK IN CONSTRUCTION

SECTION 1: GENERAL

1.1 Scope

This Construction Industry Standard covers the use of falsework products with product standards and

proprietary falsework system in construction1.

Prefabricated steel frame scaffolding according to MS 1462-1 is prohibited to be used as falsework.

The product standard for steel frame only cover the usage of prefabricated steel frame scaffolding for

working access and platform purpose which is covered under CIS 22: Safe Use of Scaffolding.

It is in compliance with the regulatory requirements under Lembaga Pembangunan Industri Pembinaan

Malaysia Act 1994 (Amendmend 2011) (Act 520) CIDB Act 520 (Amendment 2011) - Fourth Schedule

- Standards for Certification of Construction Materials2.

It also covers:

a) The engagement of Professional Engineers Temporary Works (PETW) in the design of falsework

(includes analysis and design calculation, specification and working drawing);

b) The declaration of Pendaftaran Pengendalian Bangunan dan Kerja Binaan Kejuruteraan to DOSH

by the Contractor3 and;

c) The engagement of Temporary Works Coordinator (TWC) in the supervision of the erection,

modification and dismantling of the falsework by the Contractor. Note: 1 Typical example of falsework setup is shown in Appendix A. 2 Product and standard listed in CIDB Act 520 (Amendment 2011) - Fourth Schedule shall obtain the Perakuan Pematuhan standard (PPS) by CIDB before it could be used in the construction industries.

3 Refer to the Guidelines for Approval of Design Scaffolding, DOSH, 2016.

1.2 Normative References

This CIS incorporates dated and undated references as well as provision from other publications. For dated

references, subsequent amendments to and/or revisions of any of the following publications are only

applicable to this CIS when they are incorporated accordingly. For undated references, the latest edition

of the normative references (including amendments) referred are applicable.

1. Board of Engineers Malaysia (BEM) Guidelines No. 001 - The Role and Responsibility of

Professional Engineers for Temporary Works During Construction Stage

2. BS 5975 - Code of practice for temporary works procedures and the permissible stress design of

falsework

3. BS EN 12812 - Falsework. Performance requirements and general design

4. BS EN 12813 - Temporary works equipment. Load bearing towers of prefabricated components.

Particular methods of structural design

5. BS EN 13377 - Prefabricated timber formwork beams. Requirements, classification and

assessment

6. BS EN 13670 - Execution of concrete structures

7. BS EN 16031 - Adjustable telescopic aluminium props. Product specifications, design and

assessment by calculation and tests

Page 8: STANDARD PEMBINAAN

2

8. Factories and Machinery Act 1967 [ACT 139] P.U. (A) 328/86 - Factories and Machinery (Building

Operations and Works of Engineering Construction - BOWEC) (Safety)

9. Lembaga Pembangunan Industri Pembinaan Malaysia Act 1994 (Amendmend 2011) (Act 520) CIDB

Act 520 (Amendment 2011) - Fourth Schedule - Standards for Certification of Construction

Materials

10. Occupational Safety and Health Act 1994 (Act 514)

11. Perintah Khas Ketua Pemeriksa, Bilangan 1 Tahun 2020, Pengurusan Keselamatan Struktur

Sementara (Perancah, Acuan dan Penyangga), Department of Occupational Safety and Health

(DOSH)

12. Registration of Engineers Act 1967 (Amendments up to 2015) (Act 138)

1.3 Terms and Definitions

For the purpose of this CIS, the terms and definitions given in the Acts cited in this CIS, and the following

apply:

1. “Adjustable telescopic steel prop” refers to a prop consisting of two tubes, which are telescopically

displaceable within each other.

2. “Back propping” refers to propping installed at levels below the slabs that supports the falsework

in order to distribute the load on the uppermost slab to suitable supports such as slabs or the

foundations.

3. “Component” refers to part of the temporary works structure used and identifiable as a distinct unit.

4. “Consultant” refers to Professional Engineers with Practising Certificate (PEPC) registered with the

Board of Engineers Malaysia (BEM) who are the Submitting Person (Qualified Person) to the

Authority and Specialists and PEPC whose names appear in the drawings used for tender or

construction.

5. “Falsework system” refers to a manufactured proprietary falsework owned by a person,

manufacturer or supplier.

6. “Falsework” refers to temporary structure used to support a permanent structure, material, plant,

equipment and people while it is not self-supporting.

7. “Formwork” refers to structure, usually temporary, but in some cases wholly or partly permanent,

used to contain poured concrete to mould it to the required dimensions and support it until it is able

to support itself.

8. “Hazard” refers to a source or a situation with a potential for harm in terms of human injury or ill

health, damage to property, damage to the environment or a combination of these.

9. “Perakuan Pematuhan Standard (PPS)” refers to the certificate issued by CIDB for a particular

product that complies with the standard(s) specified by CIDB for regulatory purpose under

Schedule IV of CIDB Act 520 (Amendment 2011).

10. “Product standard” refers to a normative standard, which prescribed specification for a product.

11. “Professional Engineer for Temporary Works” (PETW) refers to the Professional Engineer with

Practicing Certificate (PEPC) employed by contractors to carry out design, endorsement and

supervision of temporary works.

12. “Prop” refers to compression member used as a temporary support.

13. “Re-propping” refers to system used during construction in which the temporary support to a

recently cast slab is removed and replaced in a planned sequence.

14. “Re-shoring” has the same meaning as re-propping.

15. “Shoring” in this CIS has the same meaning as propping.

16. “Standard compliance” refers to conformity to standards specified in Fourth Schedule of CIDB ACT 520 (Amendment 2011) or compliance to this CIS.

17. “Temporary Works Coordinator (TWC)" refers to a person appointed by a contractor and approved

by PETW to carry out any supervision or inspection or to perform any task or prescribe duty for the

erection, maintenance, modification and dismantling of falsework.

Page 9: STANDARD PEMBINAAN

3

18. “Temporary works” refers to parts of the works that allow or enable construction of, protect, support

or provide access to the permanent works and which may or may not remain in place at the

completion of the works.

SECTION 2: ACTS AND REGULATIONS

2.1 GENERAL REQUIREMENTS The manufacturers, suppliers, Contractors, PETW and the consultants shall follow the requirements in

this CIS to ensure compliance to the acts and regulations, standards and design practice for safe use

of falsework in construction.

2.1.1 Lembaga Pembangunan Industri Pembinaan Malaysia Act 1994 (Amendmend 2011) (Act 520) CIDB Act 520 (Amendment 2011) - Fourth Schedule - Standards for Certification of Construction Materials

CIDB is authorised to enforce and regulate construction products with the provisions of the CIDB Act

5204

. All construction materials/ products listed in the CIDB Act 520 (Amendment 2011) - Fourth

Schedule are required to obtain CIDB’s Perakuan Pematuhan Standard (PPS).

Note: 4 The related provisions of the CIDB Act 520 (Amendment 2011) are:

a) “Section 33C - The Board shall, in the manner determined by the Board, certify the construction material used in the construction industry and specified in the Fourth Schedule is in accordance with the standard specified in that Schedule”.

b) “Section 33D (1) - A person shall not deal or undertake to deal, whether directly or indirectly, with the construction materials specified in the Fourth Schedule unless the construction materials have been certified by the Board”.

c) “Section 33D (2) - Any person who deals or undertakes to deal with the construction materials specified in the Fourth Schedule

without the certification of the Board shall be guilty of an offence and shall, on conviction, be liable to a fine of not less than

RM10,000 but not more than RM500,000”.

2.1.2 Occupational Safety and Health Act 1994 (Act 514)

Occupational Safety and Health Act (OSHA)5

specifies responsibilities to the Contractor to ensure the

safety, health and welfare at work, and to the designers, manufacturers and suppliers on the safety and

risk on the use of product at the work site.

Note: 5 Part V of OSHA specified general duties of designers, manufacturers and suppliers under Section 20, Section 21 and

Section 23 as follows:

Section 20. General duties of manufacturers, etc. as regards plant for use at work.

Section 21. General duties of manufacturers, etc. as regards substances for use at work.

Section 23. Penalty for an offence under section 20 or 21.

2.1.3 Factories and Machinery Act 1967 [ACT 139] P.U. (A) 328/86

Factories and Machinery (Building Operations and Works of Engineering Construction – (BOWEC)

(Safety) - Regulation 1986 under Parts 4 of BOWEC, every Contractor and employer have the

obligation:

a) To comply with such of the requirements of these Regulations as affect him or any person employed

by him. b) To comply with such of the requirements of these Regulations as relate to any work, act or operations

performed or about to be performed by any such Contractor or employer.

A contractor need to comply with this Act and engage PETW in the design (includes analysis and

design calculation, specification and working drawing) and Temporary Works Coordinator (TWC) in

Page 10: STANDARD PEMBINAAN

4

the erection and modification of falsework.

2.1.4 Perintah Khas Ketua Pemeriksa, Bilangan 1 Tahun 2020, Pengurusan Keselamatan Struktur Sementara (Perancah, Acuan dan Penyangga), Department of Occupational Safety and Health (DOSH)

The order specify the Project Manager have the obligation to ensure the appointment of PETW, Designated Person and other employees to carry out the duties specified in Parts Ill and X, of BOWEC. The order also specifies no scaffolding, formwork and supports shall be used before being inspected and secured by a Designated Person. All documents and records relating to temporary structures (scaffolding, formwork and supports) are updated and kept at the workplace for inspection purposes at any time.

SECTION 3: PRODUCTS CERTIFICATION AND MARKING

3.1 Products with Product Standard

The manufacturer, supplier, Contractor or owner of falsework shall be responsible for the compliance

of product and system to the relevant standards and shall make arrangements with an independent

third-party certification body, which is recognised by CIDB for product certification.

3.2 Proprietary Falsework System

For falsework system which are proprietary-design base, the product compliance are as follows:

a) The compliance shall be based on appropriate design standards and code of practice applicable

for a falsework system. BS 5975 - on Initial testing, quality control and inspection of falsework

equipment, should be used as basis for the evaluation.

b) The falsework, as declared by the manufacturer, shall consists of:

i. A set of complete components of the falsework system

ii. Design, calculation and drawing endorsed and certified by PETW

iii. The assessed standard set of system configurations

iv. The product manual

v. Necessary testing on materials and components to acceptable and relevant similar standards

The use of Steel Modular System, Steel/ Aluminium Tubular System or any other proprietary system

for the purpose of falsework or shoring shall be subjected to design and analysis by PETW and comply

to BS 5975 or equivalent.

The system shall be tested according to BS EN 12813 and the assembly shall be subjected to full

capacity testing. The components of Steel Modular System, Steel/ Aluminium Tubular System or any

other proprietary system shall be subjected to Clause 5. 2 Quality Check.

3.3 Product Certification/ Test Report

Any used falsework system shall comply to the test and sampling required in Clause 5.2: Quality Check and PPS Issuance. A product certificate or test report issued by the certification body for new products and used products shall contain at least the following information:

New Product Used Product

a) Name and address of the manufacturer b) Type of falsework system

a) Name and address of the manufacturer, supplier, Contractor or owner of falsework of the products

Page 11: STANDARD PEMBINAAN

5

c) Standard complied b) Type of falsework system

c) Standard complied

d) Initial PPS Certification from the falsework manufacturer

e) Project name and location

f) Falsework stock quantity

g) Delivery order of the falsework

Other relevant information may be included, subject to mutual agreement between the certificate holder and the certification body. 3.4 Product Marking

The manufacturer, supplier, Contractor or owner of the products shall be responsible for the product marking. Each falsework component and its accessory shall be legibly marked on the body (either embossed or using waterproof sticker) with the following information6: a) The manufacturer’s or supplier’s name (embossed on body) b) Year of manufacture (embossed on body) c) Standard number (either embossed or using waterproof sticker) d) CIDB PPS number (either embossed or using waterproof sticker) Marking shall be so arranged that it will remain legible for the life of the component. The size of the

lettering may take into account the size of the component.

For small items, where it is not practical to mark even with a sticker on the component and already

approved by CIDB, these items may be used and subjected to inspection by the Temporary Works

Coordinator and approval by PETW.

Note: 6 For product manufactured before 01.01.2017 or before the date of enforcement of this CIS, whichever is earlier, and where the actual date is not available, the date should be marked as “before 2017” (either embossed or using waterproof sticker). Any components and accessories at a construction site with illegible markings shall not be used and shall be removed from the site.

Page 12: STANDARD PEMBINAAN

6

SECTION 4: PLANNING, PRODUCT APPROVAL, DESIGN AND DRAWING, MATERIAL SELECTION AND SUBMISSION

The Appendix B and C provides a flowchart for design and drawing construction of falsework.

4.1 Planning for temporary work and Hazard Identification, Risk Assessment and Risk Control (HIRARC)

A Contractor shall be equipped with proper planning and conduct HIRARC7 to ensure safety in the use

of scaffolding. The risk level of scaffolding activities should be established and appropriate action should

be taken.

Note: 7 The risk level is referred to “Handbook for Hazard Identification, Risk Analysis & Risk Control”. The risk levels are as follows:

a) HIGH: A HIGH risk requires immediate action to control the hazard as detailed in the hierarchy of control, Actions taken must

be documented on the risk assessment form including date of completion.

b) MEDIUM: A MEDIUM risk requires a planned approach to controlling the hazard and applies temporary measure if required.

Any action taken must be documented on the risk assessment form, including date of completion.

c) LOW: A risk identified as LOW may be considered as acceptable and further reduction may not be necessary. However, if

the risk can be resolved quickly and efficiently, control measures should be implemented and recorded.

Contractors shall engage a PETW to deal with the design (which includes analysis and design

calculation, specification and working drawing), endorsement and supervision of the falsework.

4.2 CIDB Approval for Product - Perakuan Pematuhan Standard (PPS)

The manufacturer, supplier, contractor or owner shall be responsible to obtain ‘Perakuan Pematuhan Standard’ (PPS) by providing a valid product certification or test report (for new or used falsework system) and other valid documents required by CIDB.

4.3 Design and Submission The structural analysis, design calculation, specifications and drawings of falsework shall be performed

and endorsed by a PETW.

Where required, refer to BOWEC Part III, Regulation 30 (4)8, a copy of design and calculation shall be

submitted to DOSH before commencement of work.

Note: 8 BOWEC Part III, Regulation 30 (4),

(4) Where the floor to ceiling heights exceeds 9.14 metres or where the formwork deck is supported by shores constructed in two or more tiers, or where the dead, live and impact loads on the formwork exceed 732,2 kg per square metre the formwork structure shall be designated by a Professional Engineer and the specification and drawings shall be kept on the job for use by an Inspector and a copy of the said design and drawing shall be submitted to the Chief Inspector before work commences.

Page 13: STANDARD PEMBINAAN

7

SECTION 5: MATERIAL RECEIVING, QUALITY CHECK, TESTING, ERECTION, SUPERVISION, INSPECTION, MAINTENANCE, MODIFICATION, DISMANTLING, STORAGE AND CARE

In general, falsework material and system are likely to be used repeatedly in its life cycle. Appendix D

illustrates the flowchart from the process of receiving until the process of storage or scrapping the

falsework.

5.1 Material Receiving

All falsework components and materials received at a construction site shall be visually inspected for

damages and proper markings by the Contractor’s Temporary Works Coordinator.

Damaged or not marked component shall be rejected and shall be removed from the construction site. The results of inspection shall be recorded in the Falsework Receiving Inspection Form as illustrate in Appendix E. 5.2 Quality Check for PPS Issuance

There are two types of checks, which are:

a) Initial Site Quality Check (ISQC) and;

b) Schedule Site Quality Check (SSQC).

5.2.1 Initial Site Quality Check (ISQC)

ISQC is only applicable to used falsework system and shall be carried out upon mobilization of

falsework system to the site. The ISQC is not required for components with valid PPS.

The selection of sample shall be conducted by PETW. The number of sampling and testing shall

comply with the requirement in Table 6.

Table 6: Testing and sampling for ISQC

Testing Falsework System/

Component No. of Sampling

Sampling

Place Sampling

By

Testing

required as in

Appendix D

Steel Modular System

Sampling size required

as in Appendix D

Construction

site

PETW

Steel/ Aluminium Tubular System

Proprietary product as falsework

Steel and Aluminium Prop

1 sampling for each

component

for

every 30,000 pieces or

less of each component

The test report shall be submitted by the Contractor to PETW, who shall review the test results. All

tested component shall comply with the requirements in Appendix D before the falsework system is

allowed to be erected at the construction site. The Contractor shall ensure the falsework comply to

PETW design specifications.

Page 14: STANDARD PEMBINAAN

8

If the sample fails the ISQC, a second test shall be carried out on a new sample randomly selected by

PETW. Should the second test fail too, the falsework system at the construction site shall be removed

by the Contractor from the construction site.

5.2.2 Scheduled Site Quality Check (SSQC)

SSQC is only required for the used falsework system from the same project after a year PPS issuance

obtained during ISQC. The sample size, frequency and testing shall comply with the requirement in

Table 7.

Table 7. Testing, frequency and sampling for SSQC

Testing Falsework System/

Component No. of Sampling

Sampling

Place Sampling

By

Testing

required as in

Appendix D

Steel Modular System

Sampling size required

as in Appendix D

Construction

site

PETW

Steel/ Aluminium Tubular System

Proprietary product as falsework

Steel and Aluminium Prop

Number of sample:

1 sampling for each

component

For every 60,000

pieces or less of each

component

Frequency:

Every

twelve (12) months

The test report shall be submitted by the Contractor to PETW, who shall review the test results. All

tested component shall comply with the requirements in Appendix E before the falsework system is

allowed to be erected at the construction site.

If the sample fails the SSQC, a second test shall be carried out on a new sample randomly selected by

PETW. Should the second test fail too, the falsework system at the construction site shall be removed

by the Contractor from the construction site.

5.3 Erection, Supervision, Inspection, Maintenance, Modifications, Dismantling, Storage and Care

The erection, modification and maintenance of falsework system shall be performed by the Temporary

Works Coordinator under a direct supervision of a PETW.

The falsework system shall be inspected by the Temporary Works Coordinator, approved by PETW

and the inspection record as example in Appendix F shall be maintained.

The dismantling, shall be under direct supervision by the Temporary Works Coordinator. The Contractor

or falsework owner should provide good storage and care for the dismantled components.

Page 15: STANDARD PEMBINAAN

9

Any component that are badly corroded or damaged that could not be refurbished should be removed

from the site and scrapped.

Page 16: STANDARD PEMBINAAN

10

REFERENCES

1. Handbook for Hazard Identification, Risk Assessment & Risk Control (HIRARC) (2nd reprint

2015) - Master Builders Association Malaysia

2. The Institution of Engineers Malaysia (IEM) - Revised Position Statement January 2015 -

Prevention of Collapse of Part A: Falsework and Part B: Falsework - prepared by the Civil and

Structural Technical Division

Page 17: STANDARD PEMBINAAN

11

ANNEX A

(Informative)

Examples of a typical set up of falsework

Secondary Beam

/Joist

Falsework Member

U-Head /Forkhead

Primary Beam /Bearer

Shuttering Board

Fals

ew

ork

F

orm

work

Side Form

Jack base

Page 18: STANDARD PEMBINAAN

12

Appendix B (Normative)

Process A: Flowchart for Design and Drawing Approval for Construction of Falsework

Note: 9 Design includes analysis and design calculation, specification and working drawing. The Temporary Works Coordinator (TWC) engaged shall carry out the supervision of the erection, modification and dismantling of the falsework.

(1) Contractor shall plan for Temporary Work & HIRARC and engage TWC and PETW

(2) Is falsework with valid PPS?

(4) Contractor submit endorsed design and drawing to DOSH

(6) Any modification or change in use?

Conduct ISQC (Refer 5.2.1) to apply/ renew

PPS

(5) Process for erection of falsework. Go to Process B in Appendix C

No

Yes

(3) PETW design the falsework according to the test report of the latest PPS*. Falsework design9 endorsed by PETW

Yes

No

End of Process A

Process A Start

Page 19: STANDARD PEMBINAAN

13

Appendix C (Normative)

Process B: Flowchart for Receiving and Selection of Material, Quality Check, Erection,

Modification, Dismantling, Storage and Care of Falsework

Note: 10 Process (9), (10) and (11) shall be under the responsibility of the contractor or falsework owner to ensure good care for the falsework in anticipation of its repeated use.

No Damages

Process B

At construction site

Damage

Comply

(4) Acceptance of components for falsework erection by TWC and approved by PETW

(5) Random sampling of components by PETW for Initial Site Quality Check (Refer 5.2.1) and Scheduled Site Quality Check (Refer 5.2.2)

according to clause 5.4.2.1 (ISQC) & clause 5.4.2.2 (SSQC)

(7) Erection, Supervision, Inspection, Maintenance & Modification (Under direct supervision by the TWC)

(8) Dismantling (Under direct supervision by the TWC)

Not Complying

(2) Receving and recording of falsework components by TWC and approved by PETW (Falsework receiving inspection checklist form as in Appendix E)

(6) Result of quality check

Starts

(1) PETW design and endorsement of the falsework is compulsory and the design calculations and drawings shall be made available at construction site

Badly corroded, damaged and cannot be repaired Not

Damaged

(11) Scrap (Full responsibility of contractor or falsework owner) 10

End

(3) Visual inspection by TWC

(9) Storage & Care (Full responsibility of contractor or falsework owner)10

(10) Condition of components10

Page 20: STANDARD PEMBINAAN

14

Appendix D

(Normative)

No. Falsework Type Standard Clause Type of Test Sampling Size (minimum)

Compliance/ Characteristic Value

1. Steel Tubular System BS EN 12813

5 6.4 Annex B

Detail tests and global tests

1 set of load bearing tower Note: Max. height of bearing tower: 3 – 6 meters

Compliance to: Manufacturer’s/Professional Engineer’s design calculation and drawing General requirement: Comply to Manufacturer’s specifications

2. Steel and Aluminium Modular system OR Proprietary system

BS EN 12813

5 6.4 Annex B

Detail tests and global tests

1 set of load bearing tower Note: Max. height of bearing tower: 3 – 6 meters

Compliance to: Manufacturers/Professional Engineer’s design calculation and drawing General requirement: Comply to Manufacturer’s specifications

3 Steel props MS EN 1065 9.1 Table 5 9.3

Verification of the actual characteristic strength

3 units Compliance to: Clause 4 Table 2 - Classification

4. Aluminium props BS EN 16031 9.1 Table 1 Table 3 10.4.2

Actual characteristic strength

3 units Compliance to: Clause 5 Table 1 - Classification

Page 21: STANDARD PEMBINAAN

15

Appendix E

(Normative)

Falsework Receiving Inspection Checklist Form

FALSEWORK RECEIVING INSPECTION CHECKLIST FORM

Name of Project

Location/Address

CIDB PPS NO.

Supplier’s Name

Delivery Date D. O Number Delivery Time

No. Item Quantity Acceptability Checking

Remarks

(pieces) Accepted Not

Accepted

Total

Checked by Temporary Works Coordinator

Approved by PETW:

Signature: Signature:

Name : BEM Registration Stamp:

Designation: Name:

Date: Date:

*This form is a typical example of a checklist form. It shall have at least the information as shown in

the example.

Page 22: STANDARD PEMBINAAN

16

Appendix F (Normative)

Falsework Inspection Checklist Form*

FALSEWORK ERECTION/ MODIFICATION INSPECTION CHECKLIST Inspection No. : Date : Contractor : Time : Project & Address. : Area : Location : Drawing No. :

No Description Yes No Remark

1 PETW ENDORSED DRAWINGS AND CALCULATION

a) Falsework erected as PETW endorsed drawings

2 FOUNDATION

a) Falsework erected on firm ground

b) Ground properly compacted

c) Falsework not endangered by open excavation

3 SOLE PLATES

a) Proper sole plates used

4 BASE PLATES

a) Base plates are fitted to all standards

5 ALIGNMENT OF FALSEWORK

a) Standards or frames vertical

b) Ledgers and transoms levelled

6 FALSEWORK COMPONENT CONNECTION

a) Connections are tightened and secured

7 BRACING

a) Braces are tightened and secured

8 WALL TIE

a) Wall tie placed in position as per drawing.

9 SOFFIT FORMWORK

a) Soffit formwork is installed as per drawing

10 RE-SHORING/ BACK PROP

a) Re-shoring/ back prop is erected as per drawing

General comments:

Inspected by Temporary Works Coordinator: Approved by PETW:

Signature: BEM Registration Stamp:

Name : Name:

Date : Date:

*This form is a typical example of a checklist form. It shall have at least the information as shown in

the example.

Page 23: STANDARD PEMBINAAN

17

ACKNOWLEDGMENT Construction Industry Development Board, Malaysia would like to extend our sincere appreciation to all those involved in the development of this standard. Honorary Advisor of Construction Industry Standard

Datuk Ir. Ahmad 'Asri Abdul Hamid Chief Executive, CIDB Malaysia

Chairman of Construction Industry Standard Main Committee Datuk Ir. Elias Ismail Deputy Chief Executive I, CIDB Malaysia

Technical Committee

Ir. Dr. Zuhairi Abd Hamid,FASc (Chairman) Construction Industry Development Board Malaysia En. Mohd Idrus Din Ir. M. Ramuseren Pn. Nor Hamiza Zahar Secretariat:

Pn. Nur Hanis Amsari En. Md Zahari Ab Rahman

Ir. Che Mimi Suriyani Ismail Jabatan Kerja Raya Malaysia

En. Mokhtar Zamimi Ranjan Jabatan Keselamatan & Kesihatan Pekerjaan Malaysia En. Ahmad Syahrin Yusof

Ir. Dr. Tan Yean Chin Lembaga Jurutera Malaysia

Ir. Lee Kee Bau Institut of Engineers Malaysia

Ir. K. Sundraraj Persatuan Jurutera Perunding Malaysia Ir. Sin Wai Ho Ts. Syed Hazni Abd Gani Construction Research Institute of Malaysia En. Ahmad Hazim Abdul Rahim En. Iylia Arif Datuk Ir. Elias En. Muhammed Asraff Abdul Rahman En. Michael Yap Kok Wai Master Builders Association Malaysia

Ir. Vincent Teng Yue Hoong Malaysian Iron & Steel Industry Federation En. Ng Boon Liam

Prof. Dato’ Ir. Jamaludin Non Persatuan Kontraktor Bumiputra Malaysia

Datuk Zaini Yusoff Real Estate and Housing Developer’s Association Ir. Tiah Oon Ling

Dato’ Dr. Saravanan Karrupayah Malaysian Occupational Scaffolding Association

Ts Louis Tay Chee Siong Technological Association Malaysia

Ir. Ng Kian Seng BW Scaffold Industries Sdn Bhd En. Mohd Rifaai Che Rani

Page 24: STANDARD PEMBINAAN

18

En. Martin Tham DOKA Formwork Malaysia Sdn Bhd Pn. Muhammad Somari Norshida

En. Sunderaj Nagalingam DSCAFF Group (DXS Engineering Sdn Bhd)

En. Jeyaraj Nair Mallor PERI Formwork Malaysia Sdn Bhd

Pn. Marshidah Mustapa SGS Malaysia Sdn Bhd En. Syahmi Abd Jalil

En. Chu Wei Yew PLYTEC Formwork System Industry Sdn Bhd

Ir. Hj. Yahya Hj. Ariffin IQRAMXPERT Sendirian Berhad

Hj. Sazali Che Amat Subject Matter Facilitator