Technical Session

Bunga Pakma A Development

A success story and its challenges

Asrul Rahim Abdul Hadi

Sayed A SaniRepsol Oil and Gas Malaysia Limited

Open

Latifah Rohaniah SelamatPETRONAS GTS/PD&T

Ahmad Azwan ShaipulahPETRONAS MPM/Upstream

Page 2: Technical Session Bunga Pakma A Developmenticep.com.my/wp-content/uploads/2018/12/UPEC-2018-TS-4-3-Asrul-R… · (Drilling, Hook Up, Commissioning & Start-up) Maintained schedule

Bunga Pakma A Development: A success story and its challenges

Copyright UPEC 2018

System / Type Platform design parameters

Design Life 15 Years

Topside Design Integrated Deck

Substructure Conventional 4-leg Jacket

Water depth 57 meters

Well Bay9 conductor slots for 15 Wells

with 6 Initial Gas Wells

Well Test

FacilityWet Gas Venturi Meter

Pipeline 24” FWS Gas – 9 km to BO-D

Power Supply Subsea Cable + Fibre Optic

Well

InterventionConventional CTU capability

UtilitiesVent & Drain, Chemical Injection, Wash

Water, Hydraulic system

OthersPlatform Crane, Elect& Instr / Shelter

Room

Platform Access Boat (Helideck not required)

Manning Normally unmanned

Introduction - Design Basis

Open

To achieve first gas by May 2018 (2 years after

project sanction)

Page 3: Technical Session Bunga Pakma A Developmenticep.com.my/wp-content/uploads/2018/12/UPEC-2018-TS-4-3-Asrul-R… · (Drilling, Hook Up, Commissioning & Start-up) Maintained schedule

Copyright UPEC 2018

LTI FreeOver 1.66

million man hours

HSE Performances

Bunga Pakma A Development: A success story and its challenges

Open

Page 4: Technical Session Bunga Pakma A Developmenticep.com.my/wp-content/uploads/2018/12/UPEC-2018-TS-4-3-Asrul-R… · (Drilling, Hook Up, Commissioning & Start-up) Maintained schedule

Copyright UPEC 2018

PAKMAFirst Commercial Production

4.5 monthsahead of schedule

2013 2014 2015 2016 2017 2018

Activity Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4

Key milestones

PETRONAS Milestone reviews

MR1

MR2

MR3

MR4

MR5

OCS Approved

FDP Approval

Start execute

First gas

First Commercial Production

Concept / Contracting / FEED

Concept / Select

FEED Engineering

Contracts tendering

Procure critical long leads

EPC Scope

Detailed Engineering

Substructure fabrication

Topside fabrication

Post Construction

Transport , install & pipe-lay

Hook up and commissioning

Drilling program

Plan Actual Float Monsoon

POST AFC / VDI

Schedule Performance

Bunga Pakma A Development: A success story and its challenges

Open

Page 5: Technical Session Bunga Pakma A Developmenticep.com.my/wp-content/uploads/2018/12/UPEC-2018-TS-4-3-Asrul-R… · (Drilling, Hook Up, Commissioning & Start-up) Maintained schedule

Copyright UPEC 2018

Below approved budget

(FDP vs Latest Estimate)

- 45%

Cost Performance

Bunga Pakma A Development: A success story and its challenges

Copyright UPEC 2018

Field Dev Plan (FDP) Cost

Latest Estimate Cost

Final Investment

Approval (FIA) Cost

- 29%

Open

Page 6: Technical Session Bunga Pakma A Developmenticep.com.my/wp-content/uploads/2018/12/UPEC-2018-TS-4-3-Asrul-R… · (Drilling, Hook Up, Commissioning & Start-up) Maintained schedule

Copyright UPEC 2018

<1.0% KPI

0.22%Structural

0.10%Piping (Duplex)

Legend:

P – Piping

S – Structure

PL - Pipeline

0.61%Pipeline

Quality Performances

Bunga Pakma A Development: A success story and its challenges

Open

Page 7: Technical Session Bunga Pakma A Developmenticep.com.my/wp-content/uploads/2018/12/UPEC-2018-TS-4-3-Asrul-R… · (Drilling, Hook Up, Commissioning & Start-up) Maintained schedule

Copyright UPEC 2018

PMT

Organization:

Project’s

“Cradle to

Grave” PMT

approach

Fabrication

Commissioning & Start-up

Engineering

Project Execution Approach:

• Integrated Project Team

• Collaboration with Partners

(MPM/ PCSB JV/ PVEP)

• Life replication & Lessons

Learnt from concurrence

Repsol’s project

• Early Intervention for critical

issues

CONTRACTOR (1st time EPC)

Sub Contractor

PMT

100% Local PMT

How did we achieve this?

Bunga Pakma A Development: A success story and its challenges

Open

Page 8: Technical Session Bunga Pakma A Developmenticep.com.my/wp-content/uploads/2018/12/UPEC-2018-TS-4-3-Asrul-R… · (Drilling, Hook Up, Commissioning & Start-up) Maintained schedule

How did we achieve this?

Bunga Pakma A Development: A success story and its challenges

Copyright UPEC 2018

Project Cost

-49%• Drilling

-47%• T&I

-36%• EPC & HUC

-42%• Procurement LLI

• Optimization on rig rates &

services resulted from open

bidding Malaysia/ Vietnamese

drilling contractors

• T&I - Revised Overall

Contracting Strategy from unit

rate to lump sum competitive

bid due to interest from

Vietnamese partner.

• Multiple cost negotiations

for gaining 20% reduction

prior to award

• Revised OCS to capture low

market environment; low HUC

rate on competitive bid strategy

Open

Page 9: Technical Session Bunga Pakma A Developmenticep.com.my/wp-content/uploads/2018/12/UPEC-2018-TS-4-3-Asrul-R… · (Drilling, Hook Up, Commissioning & Start-up) Maintained schedule

Copyright UPEC 2018

Drilling Cost Optimization:

How did we achieve this?

Bunga Pakma A Development: A success story and its challenges

Open

RUSHMORE Data

New Industry

BENCHMARK!

Page 10: Technical Session Bunga Pakma A Developmenticep.com.my/wp-content/uploads/2018/12/UPEC-2018-TS-4-3-Asrul-R… · (Drilling, Hook Up, Commissioning & Start-up) Maintained schedule

Copyright UPEC 2018

Project Cost Performance Benchmark

Bunga Pakma A Development: A success story and its challenges

Open

Page 11: Technical Session Bunga Pakma A Developmenticep.com.my/wp-content/uploads/2018/12/UPEC-2018-TS-4-3-Asrul-R… · (Drilling, Hook Up, Commissioning & Start-up) Maintained schedule

Bunga Pakma A Development: A success story and its challenges

Key Challenges

Open

Page 12: Technical Session Bunga Pakma A Developmenticep.com.my/wp-content/uploads/2018/12/UPEC-2018-TS-4-3-Asrul-R… · (Drilling, Hook Up, Commissioning & Start-up) Maintained schedule

Bunga Pakma A Development: A success story and its challenges

Challenges – how did we manage it?

• Delay in project execution phase due to PSC Contract

Extension Agreement Negotiation

• Turn this to opportunity by optimizing cost capturing

lower oil price effect which subsequently resulted with

overall project cost reduction

• Newly enforced CIDB requirement

• Early engagement and rigorous follow-up with CIDB at

their Head Office in KL and site office in Kuching

Commercial Nego

Engagement

Open

Page 13: Technical Session Bunga Pakma A Developmenticep.com.my/wp-content/uploads/2018/12/UPEC-2018-TS-4-3-Asrul-R… · (Drilling, Hook Up, Commissioning & Start-up) Maintained schedule

Copyright UPEC 2018

• First time experience for EPC Contractor

(Shared resources with another project & less experience

manpower for EPC Contractor)

Strong Client

PMT

Early

Intervention

Coach/

Guide

Form

Integrated

Team

Close schedule

monitoring

• Engineering• Procurement• Fabrication• HSE• Quality

• Cradle tograveapproach

• Back tobackdisciplinesupport

Early

Intervention

• Live replication of lesson learnt from concurrent Repsol’s project

Challenges – how did we manage it?

Bunga Pakma A Development: A success story and its challenges

Open

Page 14: Technical Session Bunga Pakma A Developmenticep.com.my/wp-content/uploads/2018/12/UPEC-2018-TS-4-3-Asrul-R… · (Drilling, Hook Up, Commissioning & Start-up) Maintained schedule

Bunga Pakma A Development: A success story and its challenges

Challenges – how did we manage it?

Copyright UPEC 2018

T&I Works completed prior to

monsoon

Offshore team integration (Drilling, Hook Up,

Commissioning & Start-up)

Maintained schedule alignment with Drilling/Start-up

Include HUC activity in IOP for bedspace

requirements

Completed utility systems onshore with

Zero Carry-over• Execute HUC during monsoon

to maintain schedule

Open

Page 15: Technical Session Bunga Pakma A Developmenticep.com.my/wp-content/uploads/2018/12/UPEC-2018-TS-4-3-Asrul-R… · (Drilling, Hook Up, Commissioning & Start-up) Maintained schedule

Bunga Pakma A Development: A success story and its challenges

Recommendation for future projects (Best Practices)

Copyright UPEC 2018Open

Page 16: Technical Session Bunga Pakma A Developmenticep.com.my/wp-content/uploads/2018/12/UPEC-2018-TS-4-3-Asrul-R… · (Drilling, Hook Up, Commissioning & Start-up) Maintained schedule

Bunga Pakma A Development: A success story and its challenges

Copyright UPEC 2018

Special thanks to MPM, PCSB JV and PVEP

Thank You