LAPORAN KEMAJUAN PROJEK NO.18

‘FEBUARY 2009’

PROJEK ADTEC TAIPING

KEMENTERIAN SUMBER MANUSIA

JABATAN KERJA RAYA MALAYSIA

KAMALBINA SDN. BHD

PEMILIK

PEGARAH PROJEK

KONTRAKTOR R&B

ADTEC TAIPING

LOKASI PROJEK

BANGUNAN PENTADBIRAN

BENGKEL TEK. MAKLUMAT& JAMIN KUALITI

DEWAN BESAR

PUSAT SUMBER

DEWAN KULIAH

LOBI UTAMA

KAFETERIA

MIKRO ELEKTRONIK

KOMPOSIT PLASTIK

M&E PLANT ROOM

1

TNB SUB

STATION

SERAMIK

M&E PLANT ROOM

2

GARAJ KENDERAAN

ASRAMA LELAKIASRAMA PEREMPUAN

DEWANMAKAN

SURAU

KELAS F

KELAS G

KUARTERSB, C, C&D

PELAN TAPAK ADTEC TAIPING

KEMAJUAN KERJA FIZIKAL

JADUAL : 70.88%SEBENAR : 67.03%KESELURUHAN : -3.85%

TARIKH LAPORAN : 12 FEB 2009

KEMAJUAN KERJA KEWANGAN

JADUAL : 74.78%SEBENAR : 68.50%KESELURUHAN : -6.28% @ 45 HARI

(LEWAT )

TARIKH LAPORAN : 12 FEB 2009

MONTH PLANNED ACTUAL AHEAD / DELAY

JAN 09’ 98.98% 65.52% - 33.46%

FEB 09’ 99.12% 67.42% - 31.70%

MECHANICAL PLANNED

ACTUAL

AIR COND 100.00% 50.00%

FIRE FIGHTING 100.00% 26.74%

KITCHEN EQUIP. NA NA

LPG INSTALL. NA NA

COMPRES. AIR NA NA

DUST CONTROL NA NA

PROCESS COOLING

NA NA

KEMAJUAN KERJA FIZIKAL - DEWAN BESAR

BANGUNAN

ELECTRICAL PLANNED ACTUAL

WIRING 100.00% 65.00%

SUBMAIN CABLE 100.00% 71.00%

DB 100.00% 0.00%

LUMINAIRE 100.00% 0.00%

MAIN S/BOARD 100.00% 0.00%

LPS NA NA

PA 100.00% 2.12%

SMATV 100.00% 21.25%

CCTV NA NA

ICT 100.00% 12.65%

DEWAN BESAR

DEWAN BESAR

MONTH PLANNED ACTUAL AHEAD / DELAY

JAN 09’ 93.25% 78.68% -14.57%

FEB 09’ 95.00% 90.85% -4.15%

MECHANICAL PLANNED

ACTUAL

AIR COND NA NA

FIRE FIGHTING NA NA

KITCHEN EQUIP. NA NA

LPG INSTALL. NA NA

COMPRES. AIR NA NA

DUST CONTROL NA NA

PROCESS COOLING

NA NA

KEMAJUAN KERJA FIZIKAL – LOBI

BANGUNAN

ELECTRICAL PLANNED ACTUAL

WIRING 100.00% 75.00%

SUBMAIN CABLE 100.00% 90.00%

DB 100.00% 0.00%

LUMINAIRE 100.00% 0.00%

MAIN S/BOARD NA NA

LPS NA NA

PA 100.00% 65.37%

SMATV NA NA

CCTV 100.00% 0.00%

ICT NA NA

LOBI UTAMA

MONTH PLANNED ACTUAL AHEAD / DELAY

JAN 09’ 73.49% 66.39% -7.10%

FEB 09’ 83.03% 70.04% -12.99%

MECHANICAL PLANNED

ACTUAL

AIR COND 50.00% 74.50%

FIRE FIGHTING 41.70% 49.64%

KITCHEN EQUIP. NA NA

LPG INSTALL. NA NA

COMPRES. AIR NA NA

DUST CONTROL NA NA

PROCESS COOLING

NA NA

KEMAJUAN KERJA FIZIKAL – DEWAN KULIAH UTAMABANGUNAN

ELECTRICAL PLANNED ACTUAL

WIRING 100.00% 65.00%

SUBMAIN CABLE 56.25% 88.00%

DB 100.00% 0.00%

LUMINAIRE 0.00% 0.00%

MAIN S/BOARD 100.00% 0.00%

LPS 91.09% 0.00%

PA 100.00% 19.31%

SMATV NA NA

CCTV NA NA

ICT 97.21% 0.00%

DEWAN KULIAH UTAMA

MONTH PLANNED ACTUAL AHEAD / DELAY

JAN 09’ 84.29% 84.41% 0.12%

FEB 09’ 93.37% 89.98% -3.39%

MECHANICAL PLANNED

ACTUAL

AIR COND 87.60% 80.18%

FIRE FIGHTING 33.90% 90.24%

KITCHEN EQUIP. NA NA

LPG INSTALL. NA NA

COMPRES. AIR NA NA

DUST CONTROL NA NA

PROCESS COOLING

NA NA

KEMAJUAN KERJA FIZIKAL – PUSAT SUMBER/PERPUSTAKAAN

BANGUNAN

ELECTRICAL PLANNED ACTUAL

WIRING 100.00% 90.00%

SUBMAIN CABLE 100.00% 88.00%

DB 100.00% 0.00%

LUMINAIRE 100.00% 25.00%

MAIN S/BOARD 100.00% 0.00%

LPS 100.00% 73.47%

PA 100.00% 34.79%

SMATV 100.00% 57.16%

CCTV NA NA

ICT 29.27% 0.00%

PUSAT SUMBER / PERPUSTAKAAN

MONTH PLANNED ACTUAL AHEAD / DELAY

JAN 09’ 82.12% 77.52% -4.60%

FEB 09’ 91.35% 84.29% -7.06%

MECHANICAL PLANNED

ACTUAL

AIR COND 71.21% 63.09%

FIRE FIGHTING 45.46% 38.79%

KITCHEN EQUIP. NA NA

LPG INSTALL. NA NA

COMPRES. AIR NA NA

DUST CONTROL NA NA

PROCESS COOLING

NA NA

KEMAJUAN KERJA FIZIKAL – PENTADBIRAN & PENGURUSAN SUMBERBANGUNAN

ELECTRICAL PLANNED ACTUAL

WIRING 100.00% 82.50%

SUBMAIN CABLE 100.00% 78.00%

DB 100.00% 0.00%

LUMINAIRE 78.57% 25.00%

MAIN S/BOARD 100.00% 0.00%

LPS 93.03% 69.22%

PA 100.00% 15.96%

SMATV 100.00% 52.05%

CCTV 62.56% 2.13%

ICT 72.81% 0.00%

BANGUNAN PENTADBIRAN & PENGURUSAN SUMBER

MONTH PLANNED ACTUAL AHEAD / DELAY

JAN 09’ 72.24% 89.11% 16.88%

FEB 09’ 84.36% 94.85% 10.49%

MECHANICAL PLANNED

ACTUAL

AIR COND 0.00% 43.00%

FIRE FIGHTING 12.65% 29.54%

KITCHEN EQUIP. 0.00% 6.51%

LPG INSTALL. NA NA

COMPRES. AIR NA NA

DUST CONTROL NA NA

PROCESS COOLING

NA NA

KEMAJUAN KERJA FIZIKAL - KAFETARIA

BANGUNAN

ELECTRICAL PLANNED ACTUAL

WIRING 100.00% 90.00%

SUBMAIN CABLE 100.00% 90.00%

DB 83.33% 0.00%

LUMINAIRE 0.00% 25.00%

MAIN S/BOARD NA NA

LPS 64.46% 56.58%

PA 98.14% 22.79%

SMATV 81.61% 50.29%

CCTV NA NA

ICT 100.00% 0.00%

KAFETERIA

MONTH PLANNED ACTUAL AHEAD / DELAY

JAN 09’ 79.02% 84.02% 5.01%

FEB 09’ 85.84% 89.53% 3.69%

MECHANICAL PLANNED

ACTUAL

AIR COND 23.57% 66.78%

FIRE FIGHTING 27.70% 33.67%

KITCHEN EQUIP. NA NA

LPG INSTALL. NA NA

COMPRES. AIR NA NA

DUST CONTROL NA NA

PROCESS COOLING

NA NA

KEMAJUAN KERJA FIZIKAL – BENGKEL TEKNOLOGI MAKLUMATBANGUNAN

ELECTRICAL PLANNED ACTUAL

WIRING 100.00% 90.00%

SUBMAIN CABLE 100.00% 50.00%

DB 100.00% 25.00%

LUMINAIRE 0.00% 45.00%

MAIN S/BOARD 86.67% 0.00%

LPS 99.49% 74.62%

PA 100.00% 42.43%

SMATV 99.68% 59.11%

CCTV 54.53% 33.71%

ICT 20.74% 0.00%

BENGKEL TEKNOLOGI MAKLUMAT

MONTH PLANNED ACTUAL AHEAD / DELAY

JAN 09’ 68.69% 86.03% 17.33%

FEB 09’ 78.05% 93.28% 15.23%

MECHANICAL PLANNED

ACTUAL

AIR COND 30.27% 80.11%

FIRE FIGHTING 24.65% 53.54%

KITCHEN EQUIP. NA NA

LPG INSTALL. NA NA

COMPRES. AIR 14.29% 75.00%

DUST CONTROL NA NA

PROCESS COOLING

7.60% 0.00%

KEMAJUAN KERJA FIZIKAL – BENGKEL KEJ. BAHAN TERMAJU (PLASTIK)BANGUNAN

ELECTRICAL PLANNED ACTUAL

WIRING 53.57% 90.00%

SUBMAIN CABLE 0.00% 80.00%

DB 0.00% 0.00%

LUMINAIRE 0.00% 45.00%

MAIN S/BOARD 0.00% 0.00%

LPS 69.14% 74.65%

PA 22.31% 46.85%

SMATV NA NA

CCTV 37.46% 49.69%

ICT 4.96% 0.00%

BENGKEL KEJ. BAHAN TERMAJU (PLASTIK)

MONTH PLANNED ACTUAL AHEAD / DELAY

JAN 09’ 71.23% 83.64% 12.41%

FEB 09’ 79.39% 93.66% 14.27%

MECHANICAL PLANNED

ACTUAL

AIR COND 31.60% 79.74%

FIRE FIGHTING 31.64% 59.65%

KITCHEN EQUIP. NA NA

LPG INSTALL. NA NA

COMPRES. AIR 20.00% 75.00%

DUST CONTROL 17.20% 23.77%

PROCESS COOLING

12.06% 0.00%

KEMAJUAN KERJA FIZIKAL – BENGKEL KEJ. BAHAN TERMAJU (KOMPOSIT)BANGUNAN

ELECTRICAL PLANNED ACTUAL

WIRING 60.71% 90.00%

SUBMAIN CABLE 0.00% 75.00%

DB 0.00% 0.00%

LUMINAIRE 0.00% 45.00%

MAIN S/BOARD 0.00% 0.00%

LPS 64.14% 67.88%

PA 25.13% 40.39%

SMATV NA NA

CCTV 54.68% 50.54%

ICT 13.80% 0.00%

BENGKEL KEJ. BAHAN TERMAJU (KOMPOSIT)

MONTH PLANNED ACTUAL AHEAD / DELAY

JAN 09’ 71.02% 79.96% 8.84%

FEB 09’ 76.14% 93.08% 16.93%

MECHANICAL PLANNED

ACTUAL

AIR COND 15.58% 78.29%

FIRE FIGHTING 27.33% 55.87%

KITCHEN EQUIP. NA NA

LPG INSTALL. NA NA

COMPRES. AIR 28.57% 75.00%

DUST CONTROL 3.37% 28.75%

PROCESS COOLING

15.20% 0.00%

KEMAJUAN KERJA FIZIKAL – BENGKEL KEJ. BAHAN TERMAJU (SERAMIK)BANGUNAN

ELECTRICAL PLANNED ACTUAL

WIRING 71.43% 90.00%

SUBMAIN CABLE 0.00% 85.00%

DB 0.00% 0.00%

LUMINAIRE 0.00% 45.00%

MAIN S/BOARD 0.00% 0.00%

LPS 56.92% 73.14%

PA 39.65% 41.63%

SMATV NA NA

CCTV 43.10% 57.16%

ICT 11.76% 0.00%

BENGKEL KEJ. BAHAN TERMAJU (SERAMIK)

MONTH PLANNED ACTUAL AHEAD / DELAY

JAN 09’ 77.16% 77.74% 0.58%

FEB 09’ 80.11% 87.32% 7.21%

MECHANICAL PLANNED

ACTUAL

AIR COND 25.39% 55.00%

FIRE FIGHTING 37.17% 37.23%

KITCHEN EQUIP. NA NA

LPG INSTALL. NA NA

COMPRES. AIR 88.57% 75.00%

DUST CONTROL 33.88% 27.27%

PROCESS COOLING

NA NA

KEMAJUAN KERJA FIZIKAL – BENGKEL KEJ. JAMINAN KUALITIBANGUNAN

ELECTRICAL PLANNED ACTUAL

WIRING 100.00% 82.50%

SUBMAIN CABLE 94.44% 50.00%

DB 0.00% 0.00%

LUMINAIRE 0.00% 0.00%

MAIN S/BOARD 0.00% 0.00%

LPS 70.85% 71.76%

PA 97.59% 22.19%

SMATV 68.57% 34.14%

CCTV 44.98% 40.48%

ICT 16.57% 0.00%

BENGKEL KEJ. JAMINAN KUALITI

MONTH PLANNED ACTUAL AHEAD / DELAY

JAN 09’ 72.73% 78.27% 5.54%

FEB 09’ 79.37% 86.86% 7.49%

MECHANICAL PLANNED

ACTUAL

AIR COND 24.09% 75.00%

FIRE FIGHTING 16.09% 39.65%

KITCHEN EQUIP. NA NA

LPG INSTALL. NA NA

COMPRES. AIR 45.71% 75.00%

DUST CONTROL NA NA

PROCESS COOLING

NA NA

KEMAJUAN KERJA FIZIKAL – BENGKEL MIKRO ELEKTRONIKBANGUNAN

ELECTRICAL PLANNED ACTUAL

WIRING 92.86% 82.50%

SUBMAIN CABLE 9.52% 50.00%

DB 0.00% 0.00%

LUMINAIRE 0.00% 0.00%

MAIN S/BOARD 0.00% 0.00%

LPS 65.33% 72.28%

PA 56.33% 26.46%

SMATV 63.35% 46.25%

CCTV 58.47% 52.62%

ICT 18.14% 0.00%

BENGKEL MIKRO ELEKTRONIK

MONTH PLANNED ACTUAL AHEAD / DELAY

JAN 09’ 80.19% 96.63% 16.44%

FEB 09’ 90.43% 96.63% 6.20%

MECHANICAL PLANNED

ACTUAL

AIR COND 100.00% 90.00%

FIRE FIGHTING NA NA

KITCHEN EQUIP. NA NA

LPG INSTALL. NA NA

COMPRES. AIR NA NA

DUST CONTROL NA NA

PROCESS COOLING

NA NA

KEMAJUAN KERJA FIZIKAL – KUATERS KELAS ‘B’

BANGUNAN

ELECTRICAL PLANNED ACTUAL

WIRING 100.00% 90.00%

SUBMAIN CABLE 100.00% 90.00%

DB 100.00% 75.00%

LUMINAIRE 0.00% 65.00%

MAIN S/BOARD 100.00% 0.00%

LPS 97.60% 0.00%

PA NA NA

SMATV 100.00% 32.27%

CCTV 99.75% 34.02%

ICT 100.00% 75.00%

KUARTERS KELAS ‘B’

MONTH PLANNED ACTUAL AHEAD / DELAY

JAN 09’ 81.59% 96.76% 15.16%

FEB 09’ 88.42% 96.76% 8.33%

MECHANICAL PLANNED

ACTUAL

AIR COND 100.00% 90.00%

FIRE FIGHTING NA NA

KITCHEN EQUIP. NA NA

LPG INSTALL. NA NA

COMPRES. AIR NA NA

DUST CONTROL NA NA

PROCESS COOLING

NA NA

KEMAJUAN KERJA FIZIKAL – KUATERS KELAS ‘C’

BANGUNAN

ELECTRICAL PLANNED ACTUAL

WIRING 90.48% 90.00%

SUBMAIN CABLE 0.00% 90.00%

DB 100.00% 90.00%

LUMINAIRE 8.33% 90.00%

MAIN S/BOARD 100.00% 0.00%

LPS 83.45% 0.00%

PA NA NA

SMATV 89.67% 24.75%

CCTV NA NA

ICT 98.54% 51.68%

KUARTERS KELAS ‘C’

MONTH PLANNED ACTUAL AHEAD / DELAY

JAN 09’ 69.32% 96.38% 27.06%

FEB 09’ 84.31% 96.38% 12.07%

MECHANICAL PLANNED

ACTUAL

AIR COND 100.00% 90.00%

FIRE FIGHTING NA NA

KITCHEN EQUIP. NA NA

LPG INSTALL. NA NA

COMPRES. AIR NA NA

DUST CONTROL NA NA

PROCESS COOLING

NA NA

KEMAJUAN KERJA FIZIKAL – KUATERS KELAS ‘C+D’BANGUNAN

ELECTRICAL PLANNED ACTUAL

WIRING 100.00% 90.00%

SUBMAIN CABLE 100.00% 90.00%

DB 100.00% 90.00%

LUMINAIRE 85.71% 90.00%

MAIN S/BOARD 100.00% 0.00%

LPS 96.87% 0.00%

PA NA NA

SMATV 100.00% 32.27%

CCTV NA NA

ICT 100.00% 75.00%

KUARTERS KELAS ‘C’ + ‘D’

MONTH PLANNED ACTUAL AHEAD / DELAY

JAN 09’ 73.69% 91.08% 17.39%

FEB 09’ 77.45% 93.57% 16.12%

MECHANICAL PLANNED

ACTUAL

AIR COND NA NA

FIRE FIGHTING NA NA

KITCHEN EQUIP. NA NA

LPG INSTALL. NA NA

COMPRES. AIR NA NA

DUST CONTROL NA NA

PROCESS COOLING

NA NA

KEMAJUAN KERJA FIZIKAL – KUATERS KELAS F ( 1 BLOK 4 TINGKAT & I BLOK 5 TINGKAT)BANGUNAN

ELECTRICAL PLANNED ACTUAL

WIRING 90.48% 90.00%

SUBMAIN CABLE 0.00% 90.00%

DB 0.00% 75.00%

LUMINAIRE 0.00% 90.00%

MAIN S/BOARD 0.00% 0.00%

LPS 100.00% 83.97%

PA NA NA

SMATV 100.00% 73.58%

CCTV NA NA

ICT 100.00% 54.65%

KUARTERS KELAS ‘F’ ( 4 TINGKAT )

KUARTERS KELAS ‘F’ ( 5 TINGKAT )

MONTH PLANNED ACTUAL AHEAD / DELAY

JAN 09’ 73.24% 92.63% 19.39%

FEB 09’ 77.88% 93.41% 15.53%

MECHANICAL PLANNED

ACTUAL

AIR COND NA NA

FIRE FIGHTING NA NA

KITCHEN EQUIP. NA NA

LPG INSTALL. NA NA

COMPRES. AIR NA NA

DUST CONTROL NA NA

PROCESS COOLING

NA NA

KEMAJUAN KERJA FIZIKAL – KUATERS KELAS G

(1 BLOK 4 TINGKAT & 1 BLOK 5 TINGKAT)BANGUNAN

ELECTRICAL PLANNED ACTUAL

WIRING 100.00% 90.00%

SUBMAIN CABLE 38.10% 90.00%

DB 0.00% 75.00%

LUMINAIRE 0.00% 90.00%

MAIN S/BOARD 0.00% 0.00%

LPS 100.00% 83.97%

PA NA NA

SMATV 100.00% 73.58%

CCTV NA NA

ICT 100.00% 58.20%

KUARTERS KELAS ‘G’ ( 5 TINGKAT )

KUARTERS KELAS ‘G’ ( 4 TINGKAT )

MONTH PLANNED ACTUAL AHEAD / DELAY

JAN 09’ 96.42% 94.87% -1.55%

FEB 09’ 98.16% 97.32% -0.84%

MECHANICAL PLANNED

ACTUAL

AIR COND 100.00% 90.00%

FIRE FIGHTING 100.00% 45.63%

KITCHEN EQUIP. 0.00% 5.66%

LPG INSTALL. NA NA

COMPRES. AIR NA NA

DUST CONTROL NA NA

PROCESS COOLING

NA NA

KEMAJUAN KERJA FIZIKAL – DEWAN MAKAN

BANGUNAN

ELECTRICAL PLANNED ACTUAL

WIRING 100.00% 90.00%

SUBMAIN CABLE 100.00% 75.00%

DB 100.00% 0.00%

LUMINAIRE 100.00% 90.00%

MAIN S/BOARD 100.00% 0.00%

LPS 100.00% 84.63%

PA 100.00% 42.65%

SMATV 100.00% 60.35%

CCTV NA NA

ICT 100.00% 0.00%

DEWAN MAKAN

MONTH PLANNED ACTUAL AHEAD / DELAY

JAN 09’ 81.74% 91.05% 9.30%

FEB 09’ 86.42% 97.01% 10.59%

MECHANICAL PLANNED

ACTUAL

AIR COND 100.00% 25.53%

FIRE FIGHTING 91.54% 69.93%

KITCHEN EQUIP. NA NA

LPG INSTALL. NA NA

COMPRES. AIR NA NA

DUST CONTROL NA NA

PROCESS COOLING

NA NA

KEMAJUAN KERJA FIZIKAL – ASRAMA LELAKI A & BBANGUNAN

ELECTRICAL PLANNED ACTUAL

WIRING 64.29% 90.00%

SUBMAIN CABLE 0.00% 75.00%

DB 0.00% 0.00%

LUMINAIRE 0.00% 75.00%

MAIN S/BOARD 0.00% 0.00%

LPS 85.58% 80.71%

PA 99.21% 32.10%

SMATV 72.16% 54.88%

CCTV 37.44% 33.69%

ICT 99.85% 0.00%

ASRAMA LELAKI A & B

MONTH PLANNED ACTUAL AHEAD / DELAY

JAN 09’ 72.72% 93.81% 21.09%

FEB 09’ 81.04% 97.63% 16.58%

MECHANICAL PLANNED

ACTUAL

AIR COND 0.00% 10.00%

FIRE FIGHTING 24.94% 71.32%

KITCHEN EQUIP. NA NA

LPG INSTALL. NA NA

COMPRES. AIR NA NA

DUST CONTROL NA NA

PROCESS COOLING

NA NA

KEMAJUAN KERJA FIZIKAL – ASRAMA PEREMPUAN C & DBANGUNAN

ELECTRICAL PLANNED ACTUAL

WIRING 80.95% 90.00%

SUBMAIN CABLE 15.79% 75.00%

DB 0.00% 0.00%

LUMINAIRE 0.00% 90.00%

MAIN S/BOARD 0.00% 0.00%

LPS 79.12% 81.33%

PA 6.35% 30.15%

SMATV 5.81% 54.88%

CCTV 88.52% 0.00%

ICT 0.08% 16.54%

ASRAMA PEREMPUAN C & D

MONTH PLANNED ACTUAL AHEAD / DELAY

JAN 09’ 74.66% 78.73% 4.07%

FEB 09’ 77.94% 88.08% 10.14%

MECHANICAL PLANNED

ACTUAL

AIR COND NA NA

FIRE FIGHTING 0.00% 0.00%

KITCHEN EQUIP. NA NA

LPG INSTALL. NA NA

COMPRES. AIR NA NA

DUST CONTROL NA NA

PROCESS COOLING

NA NA

KEMAJUAN KERJA FIZIKAL - SURAU

BANGUNAN

ELECTRICAL PLANNED ACTUAL

WIRING 23.81% 75.00%

SUBMAIN CABLE 0.00% 50.00%

DB NA NA

LUMINAIRE 0.00% 0.00%

MAIN S/BOARD 0.00% 0.00%

LPS 43.92% 58.38%

PA 18.31% 4.58%

SMATV NA NA

CCTV NA NA

ICT NA NA

SURAU

MONTH PLANNED ACTUAL AHEAD / DELAY

JAN 09’ 79.98% 87.62% 7.64%

FEB 09’ 91.60% 98.95% 7.35%

MECHANICAL PLANNED

ACTUAL

AIR COND NA NA

FIRE FIGHTING 0.00% 0.00%

KITCHEN EQUIP. NA NA

LPG INSTALL. NA NA

COMPRES. AIR NA NA

DUST CONTROL NA NA

PROCESS COOLING

NA NA

KEMAJUAN KERJA FIZIKAL - ASTAKA

BANGUNAN SOKONGAN

ELECTRICAL PLANNED ACTUAL

WIRING 100.00% 90.00%

SUBMAIN CABLE 100.00% 90.00%

DB 100.00% 0.00%

LUMINAIRE 100.00% 50.00%

MAIN S/BOARD 100.00% 0.00%

LPS 59.67% 58.21%

PA 100.00% 5.72%

SMATV NA NA

CCTV NA NA

ICT NA NA

BANGUNAN SOKONGAN

ASTAKA

MONTH PLANNED ACTUAL AHEAD / DELAY

FEB 09’ 87.44% 97.52% 10.08%

MECHANICAL PLANNED

ACTUAL

AIR COND 91.70% 88.10%

FIRE FIGHTING 70.07% 0.00%

KITCHEN EQUIP. NA NA

LPG INSTALL. 0.00% 0.00%

COMPRES. AIR NA NA

DUST CONTROL NA NA

PROCESS COOLING

NA NA

KEMAJUAN KERJA FIZIKAL – M&E PLANT ROOM

BANGUNAN SOKONGAN

ELECTRICAL PLANNED ACTUAL

WIRING 100.00% 90.00%

SUBMAIN CABLE 100.00% 20.00%

DB 100.00% 0.00%

LUMINAIRE 100.00% 50.00%

MAIN S/BOARD 100.00% 0.00%

LPS NA NA

PA NA NA

SMATV NA NA

CCTV NA NA

ICT NA NA

BANGUNAN SOKONGAN

M&E PLANT ROOM – PUSAT SUMBER

BANGUNAN SOKONGAN

M&E PLANT ROOM - BENGKEL

DECORATIVE FENCE

BANGUNAN SOKONGAN

GARAJ KENDERAAN

ELEVATED WATER TANK, PUMP HOUSE & SUCTION TANK

WAKAF

LALUAN BERBUMBUNG

OPEN PLAZA

KERJA INFRA – JALAN UTAMA

GELANGGANG PERMAINAN - TENIS

M&E INSTALLATION

M&E INSTALLATION

M&E INSTALLATION

M&E INSTALLATION

• SEKIAN TERIMA KASIH