mata kuliah: s0892 – ground improvement method tahun: 2010 case study session 12 - 13
TRANSCRIPT
Bina Nusantara
COURSE 5
Content:• Case Study 1 – Jordan Hall of Science
University of Notre Dame• Case Study 2 – Commercial Complex Kuala
Lumpur City• Case Study 3 – Interchange at Kampung
Pasir Dalam Malaysia• Case Study 4 – Road Construction Thailand
Bina Nusantara
CASE STUDY 1
PROJECT REQUIREMENTS
• Four-story building with slab on-grade and small basement area for mechanical
• Structural concrete and steel framing with concrete masonry units and brick facade/cast stone detailing
• Column loads: 800 to 1,000 kips • Building footprint of 75,000 sq ft. • Two 250 – seat lecture halls • Greenhouse • Teaching labs • Office Space • Roof top observatory • Existing utility tunnel
Bina Nusantara
CASE STUDY 1
FOUNDATION ALTERNATIVES
• Spread Foundation Scheme – 2 ksf – 1 to 2 in. settlement
• Deep Foundation Scheme (driven or drilled elements) • Ground Improvement Technique
– Vibro-compaction and use spread foundations designed for 10 ksf with 1/2 in. settlement
GROUND IMPROVEMENT WAS CHOSEN
Bina Nusantara
CASE STUDY 2
Soil Condition
• The subsoil comprised of loose silty sand deposits and ex-mining soils with SPT values in the range of 5 blows/ft to 12 blows/ft.
• Underlying this loose soil layers, karstic limestone formation was found with extremely varying rock-head levels ranging between 3m and 15m below existing ground level. Overhanging boulders and pinnacles are common; hence the founding level of the bedrock formation was unpredictable.
• The ground water table was found to be at about 1m to 2m below existing ground level.
Bina Nusantara
CASE STUDY 2RESULT• Excavation works proceeded upon
completion of DSM installation works and subsequent curing period of only 14days.
• Bedrock underneath the DSM columns was excavated using the hydraulic breaker and blasting works.
• The installed DSM columns were able to withstand the high vibration induced by rock excavation works.
• As part of quality control procedure, cores from DSM columns were extracted and tested in a laboratory for UCS. The test results indicated an UCS in the range of 1MPa to 3MPa.
• In addition, wall movement was monitored during excavation works, which showed a maximum horizontal movement of about 30mm to 40mm.
Bina Nusantara
CASE STUDY 4
Location : South Thailand
Purpose : Road Construction
Ground Improvement Type : Jet Grouting
Type of Nature Soil : Soft Clay