LAPORAN KEMAJUAN MINGGUAN BIL.115 CADANGAN MENAIKTARAF DAN MEMBAIKPULIH BANGUNAN PARLIMEN MALAYSIA FASA 3B CAWANGAN KERJA BANGUNAN AM, IBU PEJABAT JKR MALAYSIA 1 CADANGAN MENAIKTARAF DAN MEMBAIKPULIH BANGUNAN PARLIMEN FASA 3B MAKLUMAT PROJEK LOKASI : Tapak Parlimen, Kuala Lumpur KOMPONEN PROJEK : Blok Ahli Parlimen (MP) Dewan Serbaguna Link Bridge Gelanggang Tenis Pembesaran Pondok Pengawal Kerja-kerja Luar Service tunnel, Pintu & Pagar Berhias, Tapak Semaian & Pangkin Nurser, Jalan & Perparitan Pengalihan utiliti Force Main & Pump House KOS PROJEK : RM 200,700,000.00 (ATDA) KOS KONTRAK ASAL : RM 181,578,000.00 KOS KONTRAK SEMASA : RM 181,726,675.28 KAEDAH PELAKSANAAN : Konvensional JKR KAEDAH PEROLEHAN : Tender Terbuka KONTRAKTOR UTAMA : DKLS Construction Sdn Bhd TEMPOH PEMBINAAN : 39 Bulan TARIKH MILIK TAPAK : 28 September 2015 TARIKH SIAP ASAL : 27 Disember 2018 LANJUTAN MASA : TIADA KEMAJUAN KERJA KESELURUHAN SEHINGGA 1 Mac 2018* KEMAJUAN % JADUAL % SEBENAR BEZA Hari Awal (+) / Lewat (-) FIZIKAL 42.79 37.20 -5.59 -38 KEWANGAN 94,185,471 (51.81%) 86,661,373 (47.67%) 7,524,098 (-4.14%) (Berdasarkan Rujukan SKALA pada 1 Mac 2018 : 25 Hari Lewat) STATUS KEWANGAN BERAKHIR 1 MAC 2018 Bayaran kepada Kontraktor RM 60,557,833.07 (36.61%) Wang Jaminan Pelaksanaan : Belum Dilepaskan Wang Pendahuluan : RM 10,000,000.00 Bayaran Balik Wang Pendahuluan (Recoupment) : RM 6,001,352.19 Liquidated & Ascertained Damages (LAD) : RM 34,137.00 / hari *Berdasarkan Recovery CPM Terkini (14/12/2017)

Upload: vudien

Post on 07-May-2018

230 views

Category:

Documents


3 download

TRANSCRIPT

Page 1: CADANGAN MENAIKTARAF DAN MEMBAIKPULIH … projek pembangunan/Lap… · Interior Design 2.04% 0 0 0 ... 6. Pondok Pengawal Brickwork Pemasangan cable tray dan conduit. LAPORAN KEMAJUAN

LAPORAN KEMAJUAN MINGGUAN BIL.115

CADANGAN MENAIKTARAF DAN MEMBAIKPULIH BANGUNAN PARLIMEN MALAYSIA FASA 3B

C A W A N G A N K E R J A B A N G U N A N A M , I B U P E J A B A T J K R M A L A Y S I A

1

CADANGAN MENAIKTARAF DAN MEMBAIKPULIH BANGUNAN PARLIMEN FASA 3B

MAKLUMAT PROJEK

LOKASI : Tapak Parlimen, Kuala Lumpur KOMPONEN PROJEK :

Blok Ahli Parlimen (MP)

Dewan Serbaguna

Link Bridge

Gelanggang Tenis

Pembesaran Pondok Pengawal

Kerja-kerja Luar Service tunnel, Pintu & Pagar Berhias, Tapak Semaian & Pangkin Nurser, Jalan & Perparitan Pengalihan utiliti Force Main & Pump House

KOS PROJEK : RM 200,700,000.00 (ATDA)

KOS KONTRAK ASAL : RM 181,578,000.00

KOS KONTRAK SEMASA : RM 181,726,675.28

KAEDAH PELAKSANAAN : Konvensional JKR

KAEDAH PEROLEHAN : Tender Terbuka

KONTRAKTOR UTAMA : DKLS Construction Sdn Bhd

TEMPOH PEMBINAAN : 39 Bulan

TARIKH MILIK TAPAK : 28 September 2015

TARIKH SIAP ASAL : 27 Disember 2018

LANJUTAN MASA : TIADA

KEMAJUAN KERJA KESELURUHAN SEHINGGA 1 Mac 2018*

KEMAJUAN % JADUAL % SEBENAR BEZA Hari Awal (+) /

Lewat (-)

FIZIKAL 42.79 37.20 -5.59 -38

KEWANGAN 94,185,471

(51.81%) 86,661,373

(47.67%) 7,524,098 (-4.14%)

(Berdasarkan Rujukan SKALA pada 1 Mac 2018 : 25 Hari Lewat)

STATUS KEWANGAN BERAKHIR 1 MAC 2018

Bayaran kepada Kontraktor RM 60,557,833.07 (36.61%)

Wang Jaminan Pelaksanaan : Belum Dilepaskan Wang Pendahuluan : RM 10,000,000.00

Bayaran Balik Wang Pendahuluan (Recoupment) : RM 6,001,352.19 Liquidated & Ascertained Damages (LAD) : RM 34,137.00 / hari

*Berdasarkan Recovery CPM Terkini (14/12/2017)

Page 2: CADANGAN MENAIKTARAF DAN MEMBAIKPULIH … projek pembangunan/Lap… · Interior Design 2.04% 0 0 0 ... 6. Pondok Pengawal Brickwork Pemasangan cable tray dan conduit. LAPORAN KEMAJUAN

LAPORAN KEMAJUAN MINGGUAN BIL.115

CADANGAN MENAIKTARAF DAN MEMBAIKPULIH BANGUNAN PARLIMEN MALAYSIA FASA 3B

C A W A N G A N K E R J A B A N G U N A N A M , I B U P E J A B A T J K R M A L A Y S I A

2

KEMAJUAN KERJA SEMASA DI TAPAK SEHINGGA 1 MAC 2018

ITEM WEIGHTAGE % PLANNING % ACTUAL %BEZA SEBAB-SEBAB KELEWATAN

PRELIMINARIES 5.66% 76.92 76.92 0

PILING WORKS 9.02% 100 100 0

BUILDING WORKS & INFRA STRUCTURE (36.67%)

BESMEN 3.57% 69.63 66.87 -2.76

BLOK MP 30.11% 47.59 50.98 +3.39

LINK BRIDGE 0.56% 24.57 19.56 -5.01

DEWAN SERBAGUNA 2.15% 41.11 27.91 -13.20

TAPAK SEMAIAN 0.12% 64.21 31.58 -32.63

TEMPAT LETAK BAS BERBUMBUNG

0.16% 0 0 0

INTERNAL SERVICES (PC SUMS) (32.98%)

Mechanical Works

AC System (PC Sums) 7.43% 22.44 16.94 -5.50

Fire Fighting (PC Sums) 1.55% 32.34 15.23 -17.11

Lift System (PC Sums) 1.24% 4.82 0 -4.82

BAS (PC Sums) 1.24% 16.27 2.35 -13.92

Kitchen Equipments (PC Sums) 0.25% 45.06 8.65 -36.41

Electrical Works

Electrical Installation (PC Sums) 10.09% 27.31 23.25 -4.06

ELV (PC Sums) 8.29% 39.94 30.90 -9.04

ICT (PC Sums) 2.91% 37.22 19.97 -17.25

EXTERNAL WORKS (5.14%)

Site Preparation & Earthworks 0.57% 100 100 0

SI & Geotechnical I&M 0.19% 100 100 0

Roadworks 0.09% 0 0 0

Surface Water Drainage 0.82% 31.63 0 -31.63

Permanent Water Reticulation 0.06% 0 0 0

Temporary Water Reticulation 0.12% 100 100 0

Sewerage 0.28% 80.49 63.41 -17.08

Turfing 0.06% 77.50 42.50 -35.00

Fencing & Gates 0.23% 0 0 0

Infra Works for Electrical 0.05% 44.00 62.00 +18.00

Terowong Utiliti 0.08% 100 100 0

Page 3: CADANGAN MENAIKTARAF DAN MEMBAIKPULIH … projek pembangunan/Lap… · Interior Design 2.04% 0 0 0 ... 6. Pondok Pengawal Brickwork Pemasangan cable tray dan conduit. LAPORAN KEMAJUAN

LAPORAN KEMAJUAN MINGGUAN BIL.115

CADANGAN MENAIKTARAF DAN MEMBAIKPULIH BANGUNAN PARLIMEN MALAYSIA FASA 3B

C A W A N G A N K E R J A B A N G U N A N A M , I B U P E J A B A T J K R M A L A Y S I A

3

KEMAJUAN KERJA SEMASA DI TAPAK SEHINGGA 1 MAC 2018

ITEM WEIGHTAGE % PLANNING % ACTUAL %BEZA SEBAB-SEBAB KELEWATAN

RE Wall System 1.86% 100 98.29 -1.71

Trench for Mechanical Pipes 0.09% 0 0 0

External Staircases 0.01% 0 0 0

OTHERS (10.53%)

Gelanggang Tenis G1 0.12% 0 0 0

Pondok Pengawal G2 0.19% 80.19 32.28 -47.91

Built-in Furnitures 0.88% 0 0 0

Loose Furnitures 0.58% 0 0 0

Office Furnitures 1.46% 0 0 0

Landschapping Works 0.29% 0 0 0

Interior Design 2.04% 0 0 0

Acoustic Works 0.35% 0 0 0

Forensic Works 0.15% 100 100 0

Equipment at Gymnasium 0.09% 0 0 0

Equipment at Sauna Room 0.09% 0 0 0

Signages 0.26% 0 0 0

Energy Efficiency 0.23% 100 100 0

Rainwater Harvesting System 0.12% 0 0 0

Pump House & Force Main 1.75% 35.35 14.43 -20.92

OSD Pond 1.17% 55.95 46.38 -9.57

Relocation of Services & Utility 0.18% 100 100 0

BWIC 0.58%

KESELURUHAN 100.00% 42.79% 37.20% -5.59%

Page 4: CADANGAN MENAIKTARAF DAN MEMBAIKPULIH … projek pembangunan/Lap… · Interior Design 2.04% 0 0 0 ... 6. Pondok Pengawal Brickwork Pemasangan cable tray dan conduit. LAPORAN KEMAJUAN

LAPORAN KEMAJUAN MINGGUAN BIL.115

CADANGAN MENAIKTARAF DAN MEMBAIKPULIH BANGUNAN PARLIMEN MALAYSIA FASA 3B

C A W A N G A N K E R J A B A N G U N A N A M , I B U P E J A B A T J K R M A L A Y S I A

4

AKTIVITI SEMASA DI TAPAK

1. BlOK MP

Kerja Struktur - Pemasangan rebar flat roof Aras LMR - Kerja cat fire cut Aras 3 - Pemasangan steel column bagi link brigde

Kerja Arkitek - Brickwork Aras 3 - Kerja floor rendering Aras 2 - Kerja Plastering Aras 2 - Pemasangan frame pintu Aras 3

Kerja Mekanikal - Pemasangan Internal sanitary piping di Aras 3 dan 4 - Pemasangan fire fighting piping Aras Tanah dan Aras 1 - Pemasangan Aircond Ducting Aras Basemen, Aras Tanah, Aras 1

Kerja Elektrikal - Pemasangan cable tray dan conduit Aras Tanah, Aras 1, Aras 2 & Aras 3

2. BLOK DEWAN SERBAGUNA

Brickwork

3. RE Retaining Wall

Kerja tanah di CH 220 – CH 326 Level 58m.

4. Internal Sewerage

Kerja pembinaan jajaran MH8a – MH7

5. External Sewerage (Force Main & Pump House)

Pipe jacking jajaran MH 9 – MH 10 6. Pondok Pengawal

Brickwork

Pemasangan cable tray dan conduit

Page 5: CADANGAN MENAIKTARAF DAN MEMBAIKPULIH … projek pembangunan/Lap… · Interior Design 2.04% 0 0 0 ... 6. Pondok Pengawal Brickwork Pemasangan cable tray dan conduit. LAPORAN KEMAJUAN

LAPORAN KEMAJUAN MINGGUAN BIL.115

CADANGAN MENAIKTARAF DAN MEMBAIKPULIH BANGUNAN PARLIMEN MALAYSIA FASA 3B

C A W A N G A N K E R J A B A N G U N A N A M , I B U P E J A B A T J K R M A L A Y S I A

5

ISU-ISU/MASALAH SEMASA

- Tiada