#10 malaysia

Upload: rohizat

Post on 06-Apr-2018

232 views

Category:

Documents


0 download

TRANSCRIPT

  • 8/2/2019 #10 Malaysia

    1/36

  • 8/2/2019 #10 Malaysia

    2/36

    The Kajang WastetoEnergy Facility near Kuala

    Lumpur in Selangor

  • 8/2/2019 #10 Malaysia

    3/36

    Contents

    Execuve Summary 2

    Introducon 4

    Conceptual and Research Methods 4

    The Malaysian Electricity Sector 10

    The Small Renewable Energy Power (SREP)

    Programme 12

    Challenges to Implementaon 18

    Conclusions 23

    Appendix A: List of Research Interviews 24

    Appendix B: Small Renewable Energy Power

    (SREP) Programme Guidelines 26

    References 27

    Acknowledgements 28

    About the Authors 29

  • 8/2/2019 #10 Malaysia

    4/36

    2

    The Small Renewable Energy Power (SREP) Programme was the premier

    policy mechanism implemented by the naonal government of Malaysia to

    promote renewable electricity facilies less than ten megawas (MW) in ca-

    pacity from 2001 to 2010. The SREP aimed to install 500MW of total renew-

    able energy capacity by 2005, or about ve percent of naonal electricity

    capacity. Although eligible technologies included a wide array of renewable

    resources, SREP managed to install only 12MW by December 2005, less than

    three percent of its original goal. Moreover, most of these projects focused

    on only three types of renewable resources: byproducts from the palm oil

    industry, small-scale hydroelectric dams, and waste-to-energy facilies such

    as the one shown in Figure 1. Malaysian planners therefore modied and ex-

    tended the SREP for another ve years and lowered its target to 350MW by

    2010. However, by the end of December 2010 only 11 projects constung

    61.7MW of capacity had been installed.

    This study invesgates what happened. It explores the history of the SREP in

    Malaysia, its drivers and benets, and the challenges planners faced when

    implemenng it. It nds that the SREP largely failed to meet its targets be-

    cause of technical, economic, and instuonal barriers. Obstacles were part-

    ly technical, dealing with actual renewable electricity power plant design

    and training issues; in part due to an economic worldview in Malaysia that

    priorised low electricity taris, unaracve nancing rates, and connued

    subsidies to fossil fuel producers; and partly instuonal, involving aws in

    programme design, resistance, and regulatory failures.

    It concludes with overall lessons for energy development and policy more

    generally. SREP was weakened by capacity caps, a lengthy approval process,

    lack of monitoring, exclusion of stakeholders, and few (if any) pre-feasibil-

    ity studies. Its ecacy was diluted by fragmentaon and lack of cohesion

    with other Malaysian energy policies. Relying on the dominant state-owned

    electric ulity Tenaga Nasional Berhad proved to be a mistake, as was the

    willing seller, willing buyer model of renewable energy power purchase

    agreements. Electricity taris under SREP did not match true producon

    costs, were not based on sound economics, and did not provide cost recov-

    ery for project developers. Rather than abandon their renewable energy ef-

    forts, Malaysian planners seem to have learned from the dicules facing

    the SREP and are in the process of implemenng a progressive set of new

    policies. Though it is uncertain if such new policies will achieve their goals,

    the move is a sign that if you dont succeed at promong renewable energy

    at rst, try, try again.

  • 8/2/2019 #10 Malaysia

    5/36

    3

    Figure 1: The 8.9MW Kajang Waste-to-Energy facility converts trash from around the Kuala Lumpur area into

    electricity and other recycled products

  • 8/2/2019 #10 Malaysia

    6/36

    4

    The Malaysian Small Renewable Energy Power (SREP)

    Programme aempted to install 500MW of qualied

    biomass, biogas, municipal solid waste, solar photovol-

    taics, and mini-hydroelectric facilies by 2005, but end-

    ed up achieving only 12MW of capacity by that date.

    Malaysian planners altered the SREP by lowering its tar-

    get to 350MW and extending it for another ve years,

    but by the end of 2010 just 11 projects and 61.7MW of

    capacity had been built.

    This report asks: what in the world happened? It ex-

    plores the history of the SREP in Malaysia, its drivers and

    benets, and the challenges planners faced when imple-

    menng it. It then discusses what the experiences with

    the SREP tell us about how to design future energy proj-

    ects in developing economy contexts such as Malaysia.

    The SREP was a central component of Malaysian energy

    policy, and thus it provides an ideal situaon to explore

    the dynamics at work within naonal energy planning.

    The SREP was specically the cornerstone of the coun-

    trys Fih Fuel Diversicaon Plan and also featured

    prominently in the Eighth Malaysia Plan (2001 to 2005)

    and the Ninth Malaysia Plan (2006 to 2010). Invesgat-

    ing the drivers, benets, and challenges facing SREP of-

    fers a deeper understanding of the pressures and inter-

    ests related to Malaysian policymaking.

    To understand the impediments facing the SREP, and

    to be consistent with the other case studies, the au-

    thors selected a qualitave case study methodology to

    gain the richest possible level of insight into the dy-

    namics of the SREP in Malaysia. As methodological

    scholar Robert Yin has noted, such approaches allow

    researchers to aain deep knowledge about a given

    phenomenon and develop a highly descripve com-

    prehension of the subject under study.1 Aer conduct-

    ing a preliminary literature review of documents re-

    lated to the SREP to provide context, plans were made

    to conduct semi-structured research interviews and

    site visits.

    In designing the interview quesons, the authors em-

    ployed an inducve approach to minimise interpreta-

    ve bias caused by researchers trying to force answers

    into preset cognive categories.2 We implemented this

    approach by asking ve inial quesons for each inter-

    view and then allowing interview subjects to elaborate in

    as much detail as they wanted. The ve quesons were:

    1. What are the primary energy policy and security

    challenges facing Malaysia?

    2. What were the drivers behind the SREP in Malaysia?

    3. What were the major benets arising from the SREP?

    4. What were the signicant challenges to implementa-

    on?

    5. What lessons or insights does the SREP oer for the

    study of energy policy design and implementaon

    more generally?

    The authors supplemented these ve quesons with

    probing response techniques when claricaon or

    elaboraon was sought and reecng response tech-

    niques in order to elicit reecon when warranted.3 Be-

    cause of these interviewing strategies, parcipants oen

    introduced new topics into the conversaon not anci-

    pated by the authors. Interviews lasted between thirty

    and ninety minutes with the average me of 45 minutes.

    In total, 89 parcipants from 38 instuons from four

    Malaysian provinces Sarawak, Selangor, Johor, and

    Kedeah were interviewed over the course of March

    2010 to February 2011. Those interviewed were se-

    lected to represent the broadest possible array of stake-

    holders associated with the SREP, and included mem-

    bers of:

    Engineering and consulng rms such as the Ber-

    jaya Corporaon, Renewable Energy Berhad, Re-

    cycled Energy Berhad, Core Competencies Berhad,

    and Eco-Ideal Consulng;

    Government and regulatory agencies such as the

    Malaysian Energy Commission (Suruhanjaya Tena-

    ga), Ministry of Energy, Green Technology, and Wa-

    ter (Kementerian Tenaga, Teknologi Hijau dan Air),Malaysia Energy Centre (Pusat Tenaga Malaysia),

    and the Economic Planning Unit in the Prime Min-

    isters Department;

    Energy companies and electric ulies, including

    Petronas, Sime Darby, Tenaga Nasional Berhad,

    Sarawak Energy Berhad, and Syarikat Sesco Ber-

    had (formerly known as the Sarawak Electricity

    Supply Corporaon);

    Research instutes, civil society organisaons, and

    trade organisaons including the Centre for Envi-

    ronment, Technology, and Development Malaysia,

    Malaysian Palm Oil Board, and United Naons De-

    velopment Programme Malaysia.

  • 8/2/2019 #10 Malaysia

    7/36

    5

    Figure 2: Researcher Ira Marna Drupady at the Malaysian Palm Oil Board

    Figure 3: Researcher Ira Marna Drupady and Dr. Benjamin K. Sovacool at the Sungai Kerling Minihydro Plant

  • 8/2/2019 #10 Malaysia

    8/36

    6

    Figure 4: Researcher Drupady speaks with a manager of the Bell Palm Oil Mill

    Figure 5: Dr. Sovacool speaks with workers at the TDM Palm Oil Estate

  • 8/2/2019 #10 Malaysia

    9/36

    7

    Parcipants were guaranteed anonymity to encourage

    candor, respect condenality, and adhere to instu-

    onal review board guidelines at the authors instu-

    on; however, Appendix A lists all instuons visited.

    Figures 25 depict some of these visits and interviews.

    To ensure a degree of triangulaon and reliability, the

    literature review and interviews were augmented with

    direct observaon and site visits to thirteen renewable

    energy facilies in Malaysia over the course of July 2010

    to February 2011, some of them shown in Figures 610.

    Table 1: Summary of Malaysian renewable energy site visits

    Name Type of facility Capacity Owner / Operator Locaon Connecon

    Directly

    supported by

    SREP / 5th Fuel

    Policy

    Date

    visited

    Batang Ai

    Hydroelectric

    Staon

    Hydroelectric 108MW Sarawak Energy

    Bhd.

    Batang Ai,

    Sarawak

    On-grid No Jul

    2010

    Bakun

    Hydroelectric

    Project

    Hydroelectric 2,400MW Ministry of

    Finance/Sarawak

    Hydro Bhd.

    Bakun,

    Sarawak

    On-grid No Jul

    2010

    Murum

    Hydroelectric

    Project

    Hydroelectric 944MW Sarawak Energy

    Bhd.

    Murum,

    Sarawak

    On-grid No Jul

    2010

    Kg. Mudung

    Abun

    Microhydro

    Plant

    Microhydro 25kW Mudung Abun

    Community

    Denang,

    Sarawak

    O-grid No Jul

    2010

    Long Lawen

    MicrohydroPlant

    Microhydro 10kW Long Lawen

    Community

    Long Lawen,

    Sarawak

    O-grid No Jul

    2010

    Lubok Antu

    Palm Oil Mill

    Palm Oil 1MW Salcra Sdn. Bhd. Sri Aman,

    Sarawak

    O-grid No Jul

    2010

    Sungai Kerling

    Minihydro

    Plant

    Minihydro 2MW Renewable Power

    Sdn Bhd.

    Kerling,

    Selangor

    On-grid Yes Jan

    2011

    Langkawi Cable

    Car Solar-

    Diesel Hybrid

    Solar

    photovoltaics /

    Diesel

    109.5kW Langkawi

    Development

    Authority and

    Tenaga Nasional

    Bhd.

    Pulau

    Langkawi,

    Kedah

    O-grid Yes Jan

    2011

    HybridIntegrated

    Renewable

    Energy System

    Solar / Wind /Diesel

    400kW State Governmentof Terengganu and

    Tenaga Nasional

    Bhd.

    PulauPerhenan,

    Terengganu

    O-grid Yes Jan2011

    TDM Palm Oil

    Estate

    Palm Oil 1.0MW TDM Plantaon

    Sdn. Bhd.

    Dungun,

    Terengganu

    O-grid No Jan

    2011

    Kajang Waste-

    to-Energy Plant

    Waste

    Incineraon

    8.9MW Core Competences

    Sdn. Bhd., Recycle

    Energy Sdn. Bhd.

    Semenyih,

    Selangor

    On-grid Yes Jan

    2011

    Bukit Tagar

    Sanitary

    Landll

    Landll Gas

    Capture

    1MW Kub-Berjaya Enviro

    Sdn. Bhd.

    Bukit Tagar,

    Selangor

    On-grid Yes Jan

    2011

    Bell Palm Oil

    Mill

    Palm Oil Mill

    Euent (POME)

    Methane

    Capture

    and Empty

    Fruit Bunch

    Incineraon

    1.7MW gas

    capture,

    10MW

    Combuson

    (under

    construcon)

    Bell Eco Power

    Sdn. Bhd. and Bell

    Palm Industries

    Sdn. Bhd.

    Batu Pahat,

    Johor

    On-grid Yes Feb

    2011

  • 8/2/2019 #10 Malaysia

    10/36

    8

    Figure 6: The 2MW Kerling Minihydro Plant

    Figure 7: The 8.9MW Kajang Waste-to-Energy Plant

  • 8/2/2019 #10 Malaysia

    11/36

    9

    Figure 8: The 1MW Bukit Tagar Landll Gas Capture Plant

    Figure 9: The 1MW Lubok Antu Palm Oil Mill

  • 8/2/2019 #10 Malaysia

    12/36

    10

    As Table 1 summarises, these included a mix of hydro-electric, palm oil estate, landll gas capture, waste in-

    cineraon, and hybrid solar-diesel and solar-wind-diesel

    facilies that were both o-grid and on-grid, large and

    small in size, directly supported by the SREP and not sup-

    ported, throughout the states of Johor, Kedah, Sarawak,

    Selangor, and Terengganu. The authors also aended a

    Renewable Energy Power Purchase Agreement (REPPA)

    negoaon, the Bengkel Bersama Stakeholders Bagi Pe-

    nyediaan on January 27, 2011, hosted at the Marrio

    Hotel in Putrajaya, Malaysia.

    To beer understand the drivers pushing the creaon

    of the SREP, it is necessary to briey introduce readers

    to the Malaysian electricity sector. Though Table 2

    shows that prominent naonal policies related to en-

    ergy have existed since 1949, four are the most per-

    nent: the countrys Naonal Energy Policy of 1979, the

    1981 Four-Fuel Diversicaon Strategy, the Electricity

    Supply Act of 1990, and the Fih Fuel Diversicaon

    Policy of 2001.

    The Naonal Energy Policy of 1979 came aer the oilshocks of the 1970s, when Malaysia was heavily depen-

    dent on imported oil. It spulated three main objec-

    ves: (1) ensure an adequate and cost eecve supply,

    in essence maximum use of domesc resources; (2)

    ulise energy eciency and conservaon and eliminate

    wasteful consumpon; (3) protect the environment,

    or achieve the other two objecves without degrading

    Malaysias rich ecological and social heritage. The Four

    Fuel Diversicaon Strategy of 1981 explicitly promoted

    hydroelectricity, natural gas, and coal as an alternave

    to oil, and dropped naonal oil dependence from 90

    percent in 1980 to less than ten percent in 2003.4 The

    Electricity Supply Act, which one respondent called the

    bible and another the biggest umbrella, everything

    else comes underneath it, started the privasaon of

    the electricity sector and enabled independent power

    producers to enter the wholesale electricity generaon

    market. Aer a major blackout in 1993 followed by roll-

    ing brownouts in 1995, the government began planning

    its Fih Fuel Diversicaon Policy of 2001 intended to

    promote other forms of renewable energy. These mea-

    suresespecially privasaon and the fuel diversica-

    on policieshave seen oils share of naonal energy

    supply drop precipitously since the 1980s and the rise of

    Figure 10: The 109.5kW solar-diesel hybrid at the upper terrace of the Langkawi Cable Car

  • 8/2/2019 #10 Malaysia

    13/36

    11Date Event Descripon

    1949 Central Electricity

    Board formed

    Central Electricity Board (CEB) created by the government for electricity

    generaon, transmission, and distribuon in Malaysia.

    1965 Naonal Electricity

    Board formed

    CEB is renamed to the Naonal Electricity Board (NEB).

    1974 Petroleum

    Development Act

    The state-owned Petronas is given exclusive rights to own, explore, and produce

    petroleum and related products.

    1975 Naonal Petroleum

    Policy

    Sets regulaons for the oil and natural gas industries to ensure economic

    development needs are met.

    1979 Naonal Energy Policy Sets the three objecves of supply, ulisaon, and the environment.

    1980 Naonal Depleon

    Policy

    Naonal Petroleum Policy is augmented to extend the life of domesc energy

    reserves and lower reserve to producon raos.

    1981 Four-Fuel

    Diversicaon Strategy

    Strategy intends to develop non-oil based sources of energy such as natural gas,

    hydropower, and coal.

    1990 Electricity Supply Act Established the state-owned ulity Tenaga Nasional Berhad to be peninsular

    Malaysias naonal electricity provider, created by privasing and corporasingthe NEB.

    1999 Pusat Tenaga Malaysia

    formed

    Pusat Tenaga Malaysia (PTM) created to promote energy eciency and

    renewable energy.

    1999 Five-Fuel

    Diversicaon Strategy

    Renewable sources of energy recognised as the h primary fuel in naonal

    energy supply.

    2001 Small Renewable

    Energy Programme

    launched

    Small Renewable Energy Power (SREP) Programme created to achieve ve

    percent renewable electricity supply by 2005.

    2002 Malaysian Energy

    Commission formed

    Department of Electricity and Gas Supply at the Ministry of Energy transformed

    into a regulatory agency responsible for energy maers

    Table 2: Timeline of major energy policy events in Malaysia, 1949 to 2010

    Figure 11: Fuel mix for Malaysian electricity generaon, 1995 to 2010 (%)

  • 8/2/2019 #10 Malaysia

    14/36

    12

    coal and hydroelectricity in the naons electricity mix,

    depicted in Figure 11.

    Notwithstanding reliance on fossil fuels to meet most

    naonal energy and electricity demand, Malaysia is

    blessed with abundant renewable resources. One study

    esmates no less than 30,700MW of renewable energy

    potenal shown in Table 3, when in 2009 exisng in-

    stalled capacity was less than 23,000MW.5 Similarly, the

    Internaonal Energy Agency projected that realisablepotenal for renewables in Malaysia was about 130 Ter-

    rawa-hours (TWh) per year by 2030, but that in 2006

    the country generated only 101.3TWh. Both esmates

    imply that Malaysia could possibly be completely pow-

    ered by renewable resources.6

    Malaysian planners seem cognisant of this potenal, and

    embarked in 2001 to capture some of it through the

    Small Renewable Energy Power (SREP) Programme. One

    expert we interviewed explained the decision to pro-

    ceed with the SREP as follows:

    We had the four fuel policy operang for many

    years, and it was basically successful at promot-

    ing large hydro and a collecon of natural gas and

    coal-red power plants. But we saw the need to

    promote other types of renewable energy. Though

    we had some diesel power plants, these were inef-cient, costly, and pollung. Most of the large hy-

    dro potenal had either already been tapped, or

    were in places like Sabah and Sarawak, hundreds

    of kilometres away from major urban centres. In-

    creased reliance on coal was thought to be too

    environmentally damaging, and was somemes

    opposed by local communies. Natural gas was al-

    ready an uncomfortably large share of the naonal

    electricity porolio. Renewables were seen as the

    only viable alternave.

    The Malaysian government also recognised that a collec-

    on of pernicious barriers prevented the wider adopon

    of renewable energy in the late 1990s and early 2000s.

    These included lack of a naonal policy in support of

    renewable energy, the percepon that waste-to-energy

    and palm oil technologies were pollung, inability to

    cover project costs and lack of nancing, and poor coor-

    dinaon among dierent naonal players and ministries.

    One study went so far as to argue that renewable energy

    was looked upon as a primive and dirty fuel.7

    To address these issues, the Ministry of Energy, Green

    Technology, and Water announced the SREP on May 11,

    2001. It was intended to be the main vehicle to meet

    the renewable energy targets espoused by the Eighth

    and Ninth Malaysia Plans as well as the Third Outline

    Perspecve Plan. Eligible technologies for the SREP were

    limited to biomass, biogas, municipal solid waste, so-

    lar photovoltaics, and mini-hydroelectric facilies. The

    Ministry established a Special Commiee on Renewable

    Energy (SCORE) to oversee the programme and permit-

    ted projects up to 10MW of installed capacity. These

    projects could sell to two of the three major ulies in

    Malaysia: Tenaga Nasional Berhad (TNB) in peninsular

    Malaysia or Sabah Electricity Sendirian Berhad (SESB)

    in Borneo. Project developers had to negoate a REPPA

    with the relevant ulity according to a willing buyer,

    willing seller model and were granted a license for 21

    years aer the commissioning of a plant. Renewable en-

    ergy project developers were responsible for the costs

    of grid connecon and ulity system reinforcement in-

    cluding cables, transformers, switchgears, protecon

    equipment, and metres, and were required to distribute

    electricity into the network between 11 to 33 kV. Facili-

    es had to be within ten kilometres of the nearest in-

    terconnecon point to the grid, and all facilies had to

    meet regulaons set by the Department of Environment.

    Lastly, a minimum 30 percent equity had to be held in all

    projects by Bumiputera (indigenous Malaysian) stake-

    holders, and foreign companies were allowed to parci-

    pate only with a maximum equity of 30 percent. Project

    developers also had to go through a somewhat cumber-some and complicated process involving an applicaon

    for approval followed by an applicaon for license

    depicted in Figures 12 and 13. Ancillary support mecha-

    Sources MW

    Hydropower 22,000

    Solar photovoltaics 6,500

    Biomass and Biogas 1,300

    Mini-Hydro 500

    Municipal Solid Waste 400

    Total 30,700

    Table 3: Achievable renewable energypotenal for Malaysia (MW)

  • 8/2/2019 #10 Malaysia

    15/36

    13

    Figure 12: SREP Approval applicaon process owchart

  • 8/2/2019 #10 Malaysia

    16/36

    14

    Figure 13: SREP License applicaon process owchart

  • 8/2/2019 #10 Malaysia

    17/36

    15

    nisms, such as Pioneer Status or Income Tax Allowance

    and tax exempon on equipment, were implemented in

    tandem with the SREP. Appendix B provides the full list

    of project criteria.

    At the me the SREP was launched, it was believed

    that accomplishing a ve percent share of renewable

    electricity supply by 2005, or a total of 500 megawas

    (MW)the stated goal of the Eighth Malaysian Plan

    would save the country about US$2 billion over those

    ve years.8 Respondents told us that the SREP was de-

    signed to accomplish mulple goals.

    First, it was seen as a way to tap the waste energy po-

    tenal from the palm oil industry, one of the largest ag-

    ricultural sectors in the country. One parcipant told us

    that we thought we could get at least 600MW alone,

    100MW above the target, from the 400 plus palm oil

    mills producing millions of tons of empty fruit bunches,

    palm fronds, and palm oil mill euent each year. In-

    deed, at the price of only US$30 per barrel of oil, one

    study esmated the value of palm oil waste at more than

    US$200 billion.9 Given that the price of oil is three mes

    that amount in early 2011, ostensibly US$600 billion of

    value exists. A separate assessment calculated at least

    665MW of renewable energy capacity from biomass as

    well, gures presented in Table 4.10 Another study as-

    sessed a whopping 2,400MW of potenal,11 and yet an-

    other study calculated 2,059MW from the 71.3 million

    tons of empty fruit bunch produced each year along with

    the 19 million tons of crop residue.12

    Second, the SREP was heralded as a way to promote

    innovaon and technological learning in alternaves

    Malaysia had lile experience with, such as waste incin-

    eraon, small-scale hydro, and solar photovoltaic panels.

    Malaysians produce roughly 20,000 tons of waste every

    day, enough to bury the Petronas Towers under a pile of

    trash every four days, but also enough to create US$10

    billion of revenue if converted to electricity. Solar ener-

    gy potenal was cited as extremely favorable with 6.0

    to 6.5kWh of potenal energy per square metre, given

    Malaysias locaon on the equator.13

    Third, the SREP was seen as a mechanism to also help

    achieve the countrys remaining electricaon goals.

    While more than 99 percent of the countrys populaon

    has access to the exisng grid, about 150,000 to 200,000

    homes, mostly in the poorest and most rural parts of Ma-

    laysia, sll rely on diesel generators or receive no modern

    energy services at all. The SREP programme was partly

    hoped to develop smaller scale systems, especially mini-

    hydro and solar, which would reach hard-to-access popu-

    laons. Another respondent commented that hydro

    and solar provide a convenient and cost-eecve way to

    produce power in rural areas as it is near impossible to

    build transmission lines to cater for the small number of

    homes currently o-grid, and SREP was believed to help

    develop suitable o-grid and micro-grid technologies.

    Fourth and nally, SREP was conceived as a way to reduce

    Malaysias greenhouse gas emissions and environmental

    polluon, especially from the palm oil industry. Every

    single ton of palm oil creates six tons of palm fronds,

    ve tons of empty fruit bunches (EFB), one ton of palm

    trunks, one ton of mesocarp ber, 750 kilograms of palm

    kernel cake and endocarp, and a staggering 100 tons of

    palm oil mill euent (POME). Before it is discharged,

    POME is usually collected in open ponds or storage

    takes to degrade, a pracce that produces voluminous

    amounts of greenhouse gas emissions, as every ton cre-

    ates 28 cubic metres of methane.14 Taken together, such

    emissions from the palm oil industry account for roughly

    12 percent of naonal greenhouse gas emissions, and

    converts what is in essence a fugive emission into a

    source of electricity that was seen as aracve.

    Despite these reasons in favor of renewable energy,

    however, implementaon did not proceed as planned.

    In 2003 a study noted that major obstacles remained in

    Malaysia two years aer SREP had started, including lack

    of economies of scale, poor percepon of commercial vi-

    ability for projects, and higher risk premiums for nanc-

    ing.15 At the end of 2005, SREP had achieved a meager

    2.4 percent of its original goal. As the Minister of Energy,

    Tun Dr. Lim Keng Yaik, noted at the me:

    The SREP has not been able to connect the envis-

    aged 500MW of electricity generated from renew-

    SourcesQuanty

    (kton/yr)

    Potenal

    Generaon

    (GWh)

    Potenal

    Capacity

    (MW)

    Rice Mills 424 263 30

    Wood Industry 2,177 598 68

    Palm Oil Mills 17,980 3,197 365

    Bagasse 300 218 25

    Palm Oil

    Mill Euent

    (POME)

    31,500 1,587 177

    Total 72,962 5,863 665

    Table 4: Biomass electricity potenal in Malaysia

  • 8/2/2019 #10 Malaysia

    18/36

    16

    able sources to the naonal grid. What it has been

    able to deliver in the last four years is 12MW from

    two projects. The wide gap between policy and im-

    plementaon clearly indicates that there are barri-

    ers to the eecve transion from a convenonal

    to a sustainable model of energy development.16

    The Ministers comments were conrmed by an inde-

    pendent study which noted that the development of

    renewable energy technology was not suciently de-

    veloped in Malaysia.17 Costs of producon were sll

    higher than many other countries at 725 U.S. cents/

    kWh, compared to convenonal electricity costs of 46

    U.S. cents/kWh. Lack of informaon on renewable en-

    ergy was referenced as a major barrier, palm oil facilies

    were sll not converng their waste to electricity, and

    weak public awareness about the benets of renewable

    energy was widespread.

    Because of these problems, Malaysian planners extend-

    ed the SREP for another ve years but scaled down its

    targets to 350MW: 300MW in peninsular Malaysia, and

    50MW for Sabah in Borneo. When, yet again, implemen-

    taon lagged far behind targets, the SREP was revised

    at the end of 2006 to increase taris from 17 Malaysian

    sens/kWh to 19 sens/kWh and later 21 sens/kWh, though

    this was only for biomass and biogas technologies, not

    mini-hydro and solar system, as shown in Table 5.

    Even the revised taris, nonetheless, did not signicantly

    accelerate parcipaon in the programme. At the end

    of 2010, Table 6 shows that only 61.7MW of renewableenergy capacity had been connected to the grid from 11

    projects. Of these projects, roughly 80 percent were re-

    lated to waste and palm oil. As Table 7 illustrates, an addi-

    onal 33 projects with 210.85MW of capacity were in the

    pipeline but not yet approved or licensed. Total renewable

    energy supply, including projects supported by SREP as

    well as those from other programmes an incenves, was

    217MW,18 less than a one percent share for the country.

    Renewable

    electricity priceBiomass Biogas

    Mini

    hydro

    Solar

    Photovoltaics (PV)

    17 sen / kWh

    (2001)X X X X

    19 sen / kWh

    (2006)X X

    21 sen / kWh

    (2007)X X

    Table 5: Revised taris under the SREP, 2001 to 2009

    Project Developer Project Locaon Capacity (MW) Fuel Source

    TSH Bioenergy Sdn. Bhd. Tawau, Sabah 10Empty fruit

    bunches (EFB)

    Seguntor Bioenergy Sdn. Bhd. Jalan Seguntor, Sandakan Sabah 10 EFB

    Kina Biopower Sdn. Bhd. Lot 2, Jalan Seguntor, Labuk Road Sandakan Sabah 10 EFB

    Esajadi Power Sdn. Bhd. Sungai Kadamaian, Kundasang, Sabah 2 Mini hydro

    Esajadi Power Sdn. Bhd. Sungai Pangapuyan, Kota Marudu, Sabah 4.5 Mini hydro

    Recycle Energy Sdn. Bhd.Lot 3041 & 3042 Mukim Semenyih Daerah Hulu

    Langat Selangor5.5 Municipal waste

    MHES Asia Sdn. Bhd.HS(D) 12572, Lot PT No. 3226, Mukim Serng,

    Negeri Sembilan10 EFB

    AMDB Perng Hydro Sdn Bhd Sg. Perng, Bentong Pahang 4 Mini hydro

    Renewable Power Sdn. Bhd. Sg. Kerling , Selangor 2 Mini hydro

    Bell Eco Power Sdn. Bhd. Parit Ju, Batu Pahat, Johor 1.7 Biogas

    Jana Landll Sdn. Bhd. Puchong, Selangor 2 Biogas

    Table 6: Licensed and operaonal SREP projects (as of February, 2011)

  • 8/2/2019 #10 Malaysia

    19/36

    17

    For all intents and purposes, the SREP was subopmal.

    As one respondent told us:

    The SREP is not a success. From 2001 to 2008,

    most of the duraon of the programme, 50 proj-

    ects were approved for a capacity of 288MW,

    but 40 percent were cancelled, and one-quarter

    were issued with licenses but never started op-

    erang. One-third were not issued with licenses,

    and only 13MW was built for the rst eight years

    of the programme.

    Another parcipant calculated that about two-thirds

    of the projects proposed under SREP never progressedand that even today, the major players are not geng

    into the renewable energy business they just dont

    want to get involved. Sll others commented that our

    conclusion is that the SREP is a failure. The government

    needs to relook at it if they wish to see some success

    in the near future and the SREP experience has been

    dismal. A slew of recent studies have also implied the

    same, with one interviewing key stakeholders in Malay-

    sia and nding that regulators and investors commonly

    see renewable energy as immature, exoc, unproven,

    and risky.19 Another argued that ulisaon of renew-

    able energy [in Malaysia] is sll very low.20 The Inter-

    naonal Energy Agency documented that a lack of stan-

    dard codes and cercaon, inadequate training, and

    mistrust among nanciers and investors sll remained in

    Malaysia.21 Another study analogously argued that lim-

    ited local experience, improperly designed regulaons,

    and lack of awareness were impeding the diusion of re-

    newable energy.22 Yet another study concluded in their

    assessment that renewable energy in Malaysia is sll

    being generated on a small-scale basis [even though]

    Malaysia is blessed with abundant resources The

    progress in bringing renewable energy generaon into

    the mainstream has been slow.23

    Why, then, did the SREP fail to meet its targets, catalyze

    the growth of the renewable energy industry, and over-come the barriers it was intended to prevail against? This

    secon explains the challenges facing SREP implementa-

    on. It argues that obstacles were partly technical, dealing

    with actual renewable electricity power plant design and

    training issues; in part economic due to low electricity tar-

    is, unaracve nancing rates, and connued subsidies

    to fossil fuel producers; and partly instuonal, involving

    aws in programme design, resistance, and regulatory

    failures. Table 8 provides an overview of these barriers.

    Technical Obstacles

    One major technical obstacle involved developing re-

    newable electricity systems that would work in a Ma-

    laysian context. One respondent noted that the palm

    oil industry, for instance, had no experience with ad-

    vanced boiler technology and no understanding of bio-

    CategoryNumber of

    projectsCapacity

    Mini-Hydro 9 50.8MW

    Biomass 14 140MW

    Biogas 10 20.05MW

    Total 33 210.85MW

    Table 7: SREP projects under construcon and

    approved (but not yet licensed or operaonal)

    Dimension Explanaon

    Technical

    Lack of technology such as boilers that

    could combust empty fruit bunches and

    experience with digesters.

    Insucient educaon, training, and

    sharing of experience among all

    stakeholders (e.g. planners, developers,

    electric ulies, research instutes,

    nancial instuons)

    Expensive feasibility studies and high grid

    interconnecon costs.

    Economic

    Low electricity taris for renewable power

    producers.

    Unfamiliarity and resistance of nanciers

    and bankers.

    Subsidies to fossil fuels and the failure

    to include the cost of externalies in

    electricity prices.

    Instuonal

    Flaws in programme design including

    capacity caps, long lead mes for project

    approval, and no authority given to

    programme managers over enforcement.

    Disinterest and occasional hoslity

    from naonal ulies and convoluted

    Renewable Energy Power Purchase

    Agreements (REPPAs).

    Lack of adequate and strongly

    implemented naonal policy frameworks.

    Table 8: Summary of challenges facing theSREP in Malaysia

  • 8/2/2019 #10 Malaysia

    20/36

    18

    gas technology, meaning engineers encountered numer-ous problems related to how to combust empty fruit

    bunches or gasify palm oil euent. Thus, biomass proj-

    ects had to proceed with a lot of costly trial and error.

    Small hydroelectric projects had trouble because of the

    great uctuaon in water supply between the wet and

    dry seasons, and were also locaon dependent, given

    the ten kilometre restricon set by TNB. Most of the

    Malaysian landlls were not designed or well suited to

    capture methane gas, and the country had praccally

    no experience with designing and using solar panels to

    generate commercial electricity, which is why no solar

    projects were ever sponsored by SREP.

    The Bukit Tagar sanitary landll gas capture power plant

    we visited, took years to design and involved geo-syn-

    thec clay liners, high design polyethylene blankets, wa-

    ter treatment facilies, anaerobic closing ponds, gas ex-

    tracon wells, pumps, blowers, ame arresters, and are

    stacks. The Kajang waste incineraon plant we visited

    had to specially design a refuse derived fuel cycle that in-

    volved magnecally sorng waste, drying and shredding,

    spling and recycling non-combusble items, digesng

    organic waste, combusng the remaining material, and

    treang euent. One ocial at the Bell Palm Oil biogas

    facility we visited shown in Figure 14 called designing thedigester system as a nightmare, and also menoned

    how devastang palm oil plantaons could be to the lo-

    cal environment if managed improperly. As one respon-

    dent summed it up, when the SREP kicked o, not many

    people knew about renewable electricity, so we had to

    develop it all on our own.

    Another closely related obstacle was lack of skills and

    insucient educaon, training, and quality assurance.

    While it is clear that all stakeholders are making their own

    eorts to build their capacity in renewable energy, one

    respondent noted that there was no centralised training

    instuon, no place to learn about how to innovate tech-

    nology, instead we had to do our research on an ad hoc

    basis. Another respondent menoned that although his

    instute undertakes research in solar, biogas, waste and

    other renewable energy technologies, their ndings have

    contributed lile toward the SREP. It is therefore not sur-

    prising that there is a seeming imbalance when it comes

    to stakeholder capacity, with some real innovaons hap-

    pening in some places but not others.

    Such lack of capacity became apparent during two of

    the site visits we conducted to TNB renewable energy

    demonstraon plants. We showed up at the rst, a hy-

    Figure 14: The digester tanks of the 1.7MW Bell Palm Oil Facility

  • 8/2/2019 #10 Malaysia

    21/36

    19

    brid system at the Langkawi Cable consisng of 16kWpof solar panels and two 50kW diesel generators shown

    in Figure 15, only to nd that it was no longer working,

    despite being built in 2002. As one of the operators told

    us, all the solar panels are broken, lightning short cir-

    cuited the system, we cant get spare parts and wouldnt

    even know what to do with them if we did. The second,

    a TNB solar-wind hybrid project on Pulau Perhenan in

    Terengganu, was no longer operaonal due to lack of

    maintenance skills and interest from its operators.

    As one local community member told us, that system

    hasnt been working for years even though its sll fea-

    tured on the TNB website, its just decoraon now, its

    been long abandoned. Even at one of the operaonal

    SREP sites we visited, one of the facility managers told

    us that spare parts and maintenance is a big problem,

    we had to hire a full-me technician from China to live at

    the plant, because there was no one available to train us

    in what to do. One dimension to this issue of capacity is

    poor project feasibility assessments, with many sub-

    standard projects passing the approval stage that never

    should have. The reason is that planners didnt really

    have the experse to approve a project, but they did

    anyways because they wanted to be seen as cooperang

    with the new SREP. Clearly, the lack of a strong capac-

    ity building component within the SREP is a missed op-portunity for stakeholders to build experse, share their

    experiences, and propagate best pracces.

    A nal technical obstacle relates to onerous interconnec-

    on and feasibility requirements spulated by TNB. One

    project developer exclaimed that we were forever at the

    mercy of TNB to say which substaon to interconnect to,

    what type of circuit breakers and equipment we had to

    use, how much we had to spend on feasibility studies.

    That same project developer esmated that such com-

    plicaons accounted to a staggering 20 percent of the

    total project cost (though other project managers told us

    interconnecon costs amounted to only 25 percent of

    total costs). Another remarked that its hard connecng

    to TNBs grid, there is the legimate concern that our dis-

    tribuon system could damage their network, but they

    also set very stringent protecon requirements that re-

    ally complicated the technical eciency of our project.

    Economic and Financial Obstacles

    In the economic realm, insucient taris for renew-

    able electricity providers hobbled project develop-

    ers. One respondent noted that the taris paid to

    SREP developers were not based on sound economic

    principles, they were set with no consideraon of ac-

    Figure 15: The inoperable solar-diesel hybrid system at the Langkawi Cable Car in Kedah, Malaysia

  • 8/2/2019 #10 Malaysia

    22/36

    20

    tual cost recovery. The original tari of 17/sen perkWh was shockingly low, far below even the actual

    cost of operang SREP facilies. In the case of the

    Bukit Tagar sanitary landll, operators told us that it

    would have made more sense to just use the electricity

    onsite for the facility, since they were paying 30 sen/

    kWh for electricity but could only sell at 21 sen/kWh.

    This, however, was not allowed, forcing the landll

    in essence to sell electricity to TNB for 21 sen per unit

    that we then buy right back at 30 sen. Another project

    developer told us that SREP taris pay only enough to

    cover operaon costs and to run the plant, we make

    no money at all unless we get carbon credits under the

    CDM. A third project developer we spoke with con-

    curred, and noted that without CDM, projects would

    never make itSREP is insucient. At another facility,

    respondents argued that the tari is too low, we dont

    even get enough to cover operaons, we need extra

    income from pping fees, recycling, and making plas-

    c resin onsite. For solar projects, respondents men-

    oned that at least RM 1.70 per kWh would be needed

    to make projects viable, more than seven mes the

    rate currently oered by TNB. As another respondent

    noted, the SREP rate is way too low for such projects

    to be commercially viable.

    Because the tari was so low, respondents noted thatmany project developers could make more money do-

    ing other things with renewable fuels. Palm oil mill-

    ers, for example, can use wastes and residues to gen-

    erate grid electricity, or as a component of maresses

    and chipboards, for use in the paper and pulp industry,

    to make animal feed, or to manufacture compost fer-

    liser. SREP is just another opon for mills, one re-

    spondent told us, but its not a key factor, something

    extra, somemes a nuisance, somemes worth do-

    ing. Managers also spend much of their me focusing

    on acquiring land for the expansion of palm oil mills

    shown in Figure 16, rather than generang electricity.

    Landll gas, similarly, can be used to generate electric-

    ity, or when upgraded and sweetened used for a va-

    riety of other applicaons including heang, cooking,

    and a transport fuel.

    A separate economic obstacle dealt with lack of nanc-

    ing and the unfamiliarity of Malaysian banks with re-

    newable electricity projects. One respondent noted

    that when SREP started, local banks were unwilling

    and unready to give nancing. Project developers usu-

    ally had to go abroad to Chinese and Japanese nan-

    ciers. Another commented that bank managers had

    Figure 16: Land in Perak is cleared to make way for the expansion of palm oil mills

  • 8/2/2019 #10 Malaysia

    23/36

    21

    no idea about renewable energy, its hard for them to

    visualise what a landll gas capture or municipal solid

    waste plant looks like.

    Lastly, subsidies to natural gas and oil, along with energy

    prices that do not reect full costs result in an oversup-

    ply of electricity generated from fossil fuel sources andimpede the diusion of technologies under SREP, espe-

    cially as the country is already 99 percent electried. As

    one respondent put it, the marketplace in Malaysia is

    not fair, fossil fuels have been cross-subsidised for de-

    cades, eroding the move to go into renewables the

    playing eld isnt only uneven, its an enrely dierent

    game. Another argued that the explanaon behind

    SREPs poor performance is that other items and dam-

    ages associated with fossil fuels, such as carbon dioxide

    or acid rain, are not factored into taris, Malaysians are

    not paying the full cost of electricity. Such senments

    have been conrmed by other studies, with one study

    nong that in Malaysia there is sll massive support for

    convenonal energy sources in the forms of subsidies

    and export credits.24 The result is a lack of economies

    of scale for renewable energy, and arcially low pric-

    es for fossil fuel supply presented in Table 9.

    Polical and Instuonal Obstacles

    Just as signicant as technical and economic barriers,

    a collecon of instuonal obstacles wreaked havoc

    on the SREP. Our respondents idened no less than

    seven. First is that the capacity cap of 10MW was set

    too low, according to some respondents, for it ruled

    out economies of scale for hydroelectric, waste, and

    biomass projects. Another remarked that the 10MW

    cap created a no mans land where smaller projects

    had too many transacon costs such as interconnec-

    on fees and negoang with TNB, but larger proj-

    ects were funconally excluded. Yet another jokingly

    called the SREP the small-small renewable energy

    programme. The 10MW cap, one respondent told us,

    meant all we could do was generate peanuts, noth-

    ing more.

    Second, the inial ve percent and 500MW by 2005

    naonal target was set without any feasibility studies

    and chosen almost randomly, without consultaon with

    key stakeholders in the industry. One parcipant told

    us that they didnt know where either of the numbers

    came from, it surely wasnt by consulng the experts.

    Third, altering the taris in 2005 was seen as pickingwinners since it only applied to biomass and palm oil

    technologies, and not solar and hydro technologies. One

    respondent called the low tari for solar PV odd since

    that technology had the highest costs compared to all

    qualied systems.

    Fourth, REPPAs took too long to negoate and TNB

    had the ability to stall or delay whenever they wanted

    to, and the 21 year operang license was hard to meet

    given that many of the fuel contracts and nancing

    agreements for things like fruit bunches or waste weredone on ten and een year bases.

    Fih, all SREP projects had to be approved by SCORE,

    but the commiee met only twice a year, meaning if a

    project missed the rst session they would have to wait

    another six months to apply.

    Sixth, neither SCORE nor the Malaysian Energy Commis-

    sion had the authority to enforce SREP, or to reconcile

    complaints about TNB, or to expedite projects. Such or-

    ganisaon were also compromised and prone to con-

    icts of interest since their members included TNB and

    the Malaysian Palm Oil Board, but not solar and hydro

    developers or consumer advocate groups. One respon-

    dent went so far as to suggest that the Energy Commis-

    sion really does nothing, its just a surrogate for TNB and

    has their interests in mind.

    Seventh, the SREP had limited oversight and poor

    evaluaon, meaning problems like those above were

    not caught or remedied.

    Add all of these design aws up, and some projects took

    ve years or longer to get completed, some develop-

    ers never bothered to complete the process, and many

    more never bothered to start in the rst place. Another

    SourceElectricity

    generaon cost

    Gas and Coal Electricity 46

    Hydro 112

    Mini-Hydro 510

    Geothermal 710

    Biomass 715

    Solar 2025

    Table 9: Exisng levelised costs of electricity

    generaon in Malaysia (including subsidies),2009 (U.S. Cents/kWh)

  • 8/2/2019 #10 Malaysia

    24/36

    22

    project developer told us that it took a terribly longme to go through the SREP processit was supposed

    to be done in three months, and took us ten mes lon-

    ger. Furthermore, the ten kilometre restricon to the

    grid meant that many rural areas and Orang Aslicom-

    munies were sll too far from the grid to qualify for a

    project, and had to instead rely on inecient, expensive,

    and pollung diesel generators like the one in Figure 17.

    Another key instuonal problem was resistance from

    TNB, the only buyer in peninsular Malaysia that renew-

    able power producers could sell to. TNB had all the

    bargaining power, didnt need renewable energy, and

    saw the SREP as a threat to its revenue and prots. It

    was a recipe for disaster, another respondent told us,

    with TNB seng extremely low taris, seng perfor-

    mance provisions that facilies had to deliver electricity

    at precise capacity factors, levying penales for short-

    falls in expected generaon, demanding half of the sav-

    ings developers accrued from tax reducons, intenon-

    ally delaying the approval of projects to put pressure

    on developers to accept unfair provisions, and seng

    unfair standby taris for backup power. All three of thesite visits we undertook revealed that project develop-

    ers had asked for greater amounts of capacity but had

    been denied from TNB: Kajang could generate 10MW

    but was limited to exporng less than 7MW; Bukit Tagarcould do 6MW but was limited to 1MW; Bell could have

    done 4MW but was limited to 1.7MW. One respondent

    explained that:

    TNB sees independent renewable power produc-

    on as a lose-lose situaon because it displaces

    their capacity, and lowers their electricity sales.

    Pung them in charge of SREP was akin to let-

    ng a fox manage a chicken coop, or an atheist in

    charge of a church. TNB put up hurdles every way

    they could.

    A nal instuonal challenge related to the lack of a na-

    onal, cohesive, strongly implemented policy framework

    on renewable energy. As one respondent put it, SREP

    was designed and implemented with no thought or rela-

    onship to the various other ongoing renewable energy

    programmes, there was no harmonisaon, no coordina-

    on. The Ministry of Energy, for example, had to com-

    pete with the Malaysian Energy Commission and TNB

    over the direcon of naonal electricity policy in addi-

    on to actors like the Ministry of Housing taking chargeof waste, the Ministry of Science technological develop-

    ment, the Department of Environment regulaons, its

    a convoluted policy landscape. Another respondent

    Figure 17: A diesel generator provides electricity to the Long Wat Penan Selement in the interior of Sarawak

  • 8/2/2019 #10 Malaysia

    25/36

    23

    spoke about a mishmash between the SREP and local

    policies and regulaons that would sll impede projects

    even aer TNB would give approval, with hydroelectric

    projects, because they deal with water, and waste proj-

    ects, because they interfere with pping fees, especially

    polemic. Apparently communicaon between local and

    naonal governments was not good and requirements

    and standards diered state by state, with Johor having

    dierent requirements than Pahang which is sll dier-

    ent than Selangor.

    Even though SREP did not meet its targets, it oers

    many lessons for energy planners and policymakers. Atthe top of the list is beer design: SREP was hobbled

    from the start by capacity caps, a lengthy approval pro-

    cess, lack of monitoring, exclusion of stakeholders, and

    few (if any) pre-feasibility studies. Project developers

    had to pay the cost of interconnecon and had to build

    systems within ten kilometres of the exisng electricity

    grid. Operang licenses were spulated to be 21 years

    but nancing agreements and fuel contracts rarely ex-

    tended beyond ten years. Electricity taris were

    changed under the programme in 2001, 2006, and

    2007, and targets were revised downward in the middle

    of the programme. Projects supposed to take three

    months to design, approve, install, and connect ended

    up taking 35 years, and scores of project developers

    abandoned their eorts midstream. Each of these de-

    sign aws, especially the 10MW cap, arcially, and

    perhaps unnecessarily, prevented an organic renewable

    electricity market from taking hold.

    In addion, the ecacy of SREP was eroded by fragmen-

    taon and lack of cohesion with other Malaysian energy

    policies, notably connued subsidies for natural gas and

    oil as well as conicts with state guidelines and policies

    concerning hydroelectricity, waste-to-energy, and palm

    oil euent and waste. A sort of policy gap existed be-

    tween the loy targets enshrined in SREP and the local

    developers and ocials on the ground charged with re-

    alising those targets.

    Relying on the dominant state-owned electric ulity TNB

    also proved to be a mistake, as was the willing seller,

    willing buyer model of REPPAs. Rather than embrace re-

    newable energy, evidence from our pool of respondentsstrongly suggests that TNB opposed it and used a variety

    of taccs, such as interconnecon fees, costly feasibility

    studies, and delays, to discourage projects. Part of this is

    understandable, given that the structure of SREP meant

    that small-scale renewable electricity projects traded o

    with TNB revenues and prots.

    Equally important, electricity taris under SREP did not

    match true producon costs, were not based on sound

    economics, and did not provide cost recovery for projectdevelopers. Every single project we visited highlighted

    the need for extra streams of income, from CDM credits

    to pping fees and recycling, in order to be nancially

    viable. When taris under SREP were changed in 2006,

    this was made without cosng studies and created the

    percepon of picking winners of biomass and biogas.

    Finally, and perhaps the most important lesson of all:

    Malaysian planners could have given up aer SREP and

    abandoned the idea of renewable electricity overall,

    but they instead learned from its dicules are imple-

    menng a progressive set of new policies, including an

    ambious feed-in tari. Unlike the SREP, this new policy

    framework will guarantee access to the grid by requir-

    ing TNB and other ulies to accept all electricity from

    private renewable electricity producers. It will stream-

    line approval and sing procedures, and also set taris

    based on reasonable rates of return to project vendors.

    The new policy framework is seng up a single agency,

    the Sustainable Energy Development Authority (SEDA),

    to consult with stakeholders and then monitor and eval-uate progress. Planners in Malaysia expect total grid con-

    nected renewable energy capacity to grow from 219MW

    in 2011 to 4,000MW by 2030 and 21,370MW by 2050.25

    Such targets have also been incorporated into the 10th

    Malaysian Plan (20112015) and a Naonal Renewable

    Energy Policy and Acon Plan. Though it is uncertain if

    such ambious targets will be accomplished, the move is

    a sign that if you dont succeed at promong renewable

    energy at rst, try, try again. Ulmately, the experience

    with SREP implies that planners can learn just as much

    from project failures as successes.

  • 8/2/2019 #10 Malaysia

    26/36

    24

    Date Instuon LocaonNumber of

    interviews

    Mar 2010 Board of Naonal Economic Advisory Council Kuala Lumpur, Selangor 1

    Apr 2010 Ministry of Energy, Green Technology & Water Putrajaya, Selangor 1

    May 2010 United Naons Development Programme Malaysia Kuala Lumpur, Selangor 1

    May 2010 Instute of Strategic & Internaonal Studies Malaysia Kuala Lumpur, Selangor 1

    May 2010 Sarawak State Government Kuching, Sarawak 1

    May 2010 Ministry of Natural Resources and Environment Putrajaya, Selangor 1

    May 2010 Friends of the Earth Kuching, Sarawak 1

    May 2010 Global Environment Facility Kuala Lumpur, Selangor 1

    Jul 2010 Sarawak Hidro Sdn Bhd Kuala Lumpur, Selangor 3

    Jul 2010 United Naons Development Programme Malaysia Kuala Lumpur, Selangor 5

    Jul 2010 Economic Planning Unit, Prime Ministers Department Putrajaya, Selangor 2

    Jul 2010 Public Private Partnership Unit, Prime Ministers Department Putrajaya, Selangor 8

    Jul 2010 Corridor Development Unit, Prime Ministers Department Putrajaya, Selangor 1

    Jul 2010 Regional Corridor Development Authority Putrajaya, Selangor 2

    Jul 2010 Ministry of Tourism Kuala Lumpur, Selangor 1

    Jul 2010 Centre for Environment, Technology, and Development Malaysia Petaling Jaya, Selangor 1

    Jul 2010 OSK Research Kuala Lumpur , Selangor 1

    Jul 2010 Ministry of Energy, Green Technology & Water Putrajaya, Selangor 2

    Jul 2010 Sime Darby Kuala Lumpur, Selangor 2

    Jul 2010 Petronas Kuala Lumpur, Selangor 3

    Jul 2010 State Planning Unit, Sarawak State Government Kuching, Sarawak 1

    Jul 2010 Sarawak Energy Berhad Kuching, Sarawak 4

    Jul 2010 Universi Malaysia Sarawak Kuching, Sarawak 1

    Jul 2010 Sarawak Rivers Board Kuching, Sarawak 2

  • 8/2/2019 #10 Malaysia

    27/36

    25

    Date Instuon LocaonNumber of

    interviews

    Jul 2010 Natural Resources and Environment Board Sarawak Kuching, Sarawak 2

    Jul 2010 Sarawak Electricity Supply Company Kuching, Sarawak 2

    Jul 2010 Alstom Hydro Bakun, Sarawak 1

    Jul 2010 Sarawak Hidro Berhad Bakun, Sarawak 3

    Jul 2010 Borneo Resources Instute Malaysia Kg. Mudung Abun, Sarawak 1

    Jul 2010 PACOS Kg. Mudung Abun, Sarawak 1

    Jul 2010 Sarawak Energy Berhad Batang Ai, Sarawak 2

    Jul 2010 Sarawak Electricity Supply Company Batang Ai, Sarawak 3

    Jan 2011 Eco-Ideal Consulng Sdn. Bhd. Kuala Lumpur, Selangor 1

    Jan 2011 Malaysian Energy Commission Putrajaya, Selangor 2

    Jan 2011 Renewable Power Sdn. Bhd. Kerling, Selangor 2

    Jan 2011 Forest Research Instute Malaysia Kepong, Selangor 1

    Jan 2011 Ministry of Energy Putrajaya, Selangor 3

    Jan 2011 Tenaga Nasional Berhad Putrajaya, Selangor 1

    Jan 2011 Malaysian Palm Oil Board Kuala Lumpur, Selangor 5

    Jan 2011 Renewable Energy Research Centre (SIRIM) Kuala Lumpur, Selangor 1

    Jan 2011 JD Energy Systems Shah Alam, Selangor 1

    Jan 2011 Langkawi Development Authority Langkawi, Kedah 3

    Jan 2011 Bell Palm Industries Sdn. Bhd. Batu Pahat, Johor 1

    Feb 2011 United Naons Development Programme Bangkok, Thailand 1

    Feb 2011 Kub-Berjaya Enviro Sdn. Bhd.Bukit Tagar Sanitary Landll,

    Selangor1

    Feb 2011 Recycle Energy Sdn. Bhd. Semenyih, Selangor 4

  • 8/2/2019 #10 Malaysia

    28/36

    26

    SCORE will adopt the following Guidelines in promong

    the development of grid-connected small with regards

    to power plants:

    1. SREP shall apply to all types of renewable sources

    of energy, including biomass, biogas, municipal

    waste, solar, mini-hydro and wind.

    2. Project developers will have to negoate the Re-

    newable Electricity Purchase Agreement with

    the relevant Ulity, including the selling price on

    a willing-seller, willing buyer basis, based on take

    and pay.

    3. The RE electricity producer shall be given a licencefor a period of 21 years, to be eecve from the

    date of commissioning of the plant.

    4. RE electricity producers will be responsible for all

    the costs of the grid-connecon, the relevant Ul-

    ity system reinforcement (electric cables, trans-

    former, switchgears and other protecon equip-

    ment) and the necessary metreing installaon. The

    distribuon grid interconnecon shall be made at

    a voltage between 11 33 kV.

    5. The small RE power plant shall be located within adistance of 10km from the nearest interconnecon

    point. Excepon is given for hydro power genera-

    on project.

    6. No stand-by charges shall be levied. However, if

    back energy is requested by project developers,

    it will be charged accordingly with the prevailing

    tari.

    7. Power generaon through co-generaon technol-

    ogy shall be given special preference.

    8. Maximum capacity of a small RE power plant de-signed for sale of power to the grid shall be 10MW.

    A power plant can be more than 10MW in size,

    but the maximum capacity that will be allowed

    for power export to the distribuon grid will be no

    more than 10MW.

    9. The small RE power plant must be ready for grid-

    connecon within 12 months from the date of ap-

    proval for such grid connecon. This is applicable

    for exisng plant that wishes to connect to the

    grid. However, in the case of proposals for seng

    up new RE power plants (or where re-powering

    is proposed) that require the installaon of new

    boilers or turbo-generator systems, the plant shall

    be commissioned within 24 months. The spu-

    lated period of construcon unl commissioning

    shall be counted from the date of signing of the

    Renewable Electricity Purchase Agreement (REPA)

    between the developer and the ulity.

    10. The RE power plant must meet all environmental

    regulaons set by the Department of Environment

    (DoE), and the developer of the project is respon-

    sible for obtaining the necessary approval of DoE,

    and any other statutory approvals required.

    11. The minimum of 30% equity in an RE power plant

    project must be by Bumiputera shareholder(s). For-

    eign agency / company is allowed to parcipate in

    SREP project with maximum parcipaon equity of

    30%.

  • 8/2/2019 #10 Malaysia

    29/36

    27

    1. Yin RK. Case study research: Design and methods. 4

    ed. Newbury Park, USA: Sage Publishing; 2008.

    2. Blaikie N. Designing Social Research. UK: Polity Press;

    2000.

    3. Wheen DA, Cameron KS. Developing Management

    Skills. 8 ed. Upper Saddle River, NJ, USA: Prence Hall

    Publishing; 2010.

    4. Lim, Chin Haw, Elias Salleh, and Philip Jones. 2006.

    Renewable Energy Policy and Iniaves in Malay-

    sia. Internaonal Journal on Sustainable Tropical

    Design Research and Pracce 1(1) (December), pp.

    3340.

    5. Oh, Tick Hui, Shen Yee Pang, and Shing Chyli Chua.

    2010. Energy Policy and Alternave Energy in

    Malaysia: Issues and Challenges for Sustainable

    Growth, Renewable and Sustainable Energy Reviews

    14, pp. 12411252.

    6. Olz, Samantha and Milou Beerepoot. 2010. Deploy-

    ing Renewables in Southeast Asia: Trends and Poten-

    als (Paris: Internaonal Energy Agency/OECD).

    7. Koh, Mok Poh and Hoi Why Kong. 2002. Renewable

    Energy in Malaysia: A Policy Analysis, Energy for Sus-tainable Development6(3) (September), pp. 3139.

    8. Mohamed, Abdul Rahman and Keat Teong Lee. 2006.

    Energy for Sustainable Development in Malaysia:

    Energy Policy and Alternave Energy, Energy Policy

    34, pp. 23882397.

    9. Shigeoka, Hitoshi. 2004. Overview of Internaonal

    Renewable Energy Policies and Comparison with Ma-

    laysias Domesc Policy(Kuala Lumpur: Pusat Tenaga

    Malaysia).

    10. Ibrahim, Hassan. 2002. Small Renewable EnergyPower Programme for the Promoon of Renewable

    Energy Power Generaon, Presentaon to the First

    Meeng of ASEM Green IPPs Network, Bangkok, Oc-

    tober 2425.

    11. Lim et al 2006.

    12. Mohamed and Lee 2006.

    13. Ibid.

    14. Sovacool, BK and IM Drupady. Innovaon in the

    Malaysian Waste-to-Energy Sector: Applicaons

    with Global Potenal, Electricity Journal 24(5) (June,

    2011), pp. 29-41.

    15. Jaafar, Mohd. Zamzam, Wong Hwee Kheng, Norhaya-

    Kamaruddin. 2003. Greener Energy Soluons for a

    Sustainable Future: Issues and Challenges for Malay-

    sia. Energy Policy31, pp. 10611072.

    16. Lim Keng Yaik. Renewable Energy and Malaysia.

    Presentaon to the Regional Forum on Sustainable

    Energy, Marriot Hotel Putrajaya, April 11, 2005.

    17. Mohamad et al. 2006.

    18. Malek, Badriyah Abdul. 2010. Renewable Energy

    Development in Malaysia, Presentaon to EU-Ma-

    laysia Cooperaon in Green Technology, June 1.

    19. Sovacool, BK. A Comparave Analysis of Renewable

    Electricity Support Mechanisms for Southeast Asia,Energy35(4) (April, 2010), pp. 17791793.

    20. Lee, Chung Lau, Kok Tat Tan, Keat Teong Lee, Abdul

    Rahman Mohamad. 2009. A Comparave Study on

    the Energy Policies in Japan and Malaysia in Fullling

    Their Naons Obligaons Towards the Kyoto Proto-

    col, Energy Policy37, pp. 47714778.

    21. Olz and Beerepoot 2010.

    22. Mustapa, Si Inda, Leong Yow Peng, and Amir

    Hisham Hashim. 2010. Issues and Challenges of

    Renewable Energy Development: A Malaysian Ex-perience, Presentaon to the PEA-AIT Internaonal

    Conference on Energy and Sustainable Development,

    Empress Hotel, Chang Mai, Thailand, June 24.

    23. Oh et al. 2010: 1245, 1251.

    24. Oh et al. 2010: 1251.

    25. Malek 2010.

  • 8/2/2019 #10 Malaysia

    30/36

    28

    The authors are appreciave to the Centre on Asia and Globalisaon and

    the Lee Kuan Yew School of Public Policy for some of the nancial assistance

    needed to conduct the research interviews, eld research, and travel for this

    project. The authors are also extremely grateful to the Naonal University

    of Singapore for Faculty Start-up Grant 09-273 as well as the MacArthur

    Foundaon for Asia Security Iniave Grant 08-92777-000-GSS, which have

    supported elements of the work reported here. Any opinions, ndings, and

    conclusions or recommendaons expressed in this material are those of the

    authors and do not necessarily reect the views of the Centre on Asia and

    Globalisaon, Lee Kuan Yew School of Public Policy, Naonal University of

    Singapore, or MacArthur Foundaon. Also, the views of the author(s) ex-

    pressed in this study do not necessarily reect the views of the United States

    Agency for Internaonal Development or the United States Government.

  • 8/2/2019 #10 Malaysia

    31/36

    29

    Benjamin K. Sovacool is an Assistant Professor at the Lee

    Kuan Yew School of Public Policy. Dr Sovacool has worked

    as a researcher, professor and consultant on issues per-

    taining to energy policy, the environment and science and

    technology policy. He has served in advisory and research

    capacies at the U.S. Naonal Science Foundaons Elec-

    tric Power Networks Eciency and Security Programme, Virginia Tech Consor-

    um on Energy Restructuring, Virginia Centre for Coal and Energy Research,

    New York State Energy Research and Development Authority, Oak Ridge Na-

    onal Laboratory, Semiconductor Materials and Equipment Internaonal,

    U.S. Department of Energys Climate Change Technology Programme and the

    Internaonal Instute for Applied Systems and Analysis near Vienna, Austria.

    Dr Sovacool has published or edited six books, more than 100 academic ar-

    cles and presented at more than 60 internaonal conferences and symposia

    in the past few years. His email is [email protected]

    Ira Marna Drupady is currently a research associate at the

    Lee Kuan Yew School of Public Policy, where she also gradu-

    ated with a Masters in Public Policy in 2010. She currently

    researches energy security, rural electricaon, and energy

    development and poverty. Before joining the LKY School,

    she worked as a Project Assistant with the Asia-Europe

    Foundaon. She can be reached at [email protected]

  • 8/2/2019 #10 Malaysia

    32/36

    30

    A worker with a fresh batch

    of fruit bunches at a palm oil

    plantaon in Terengganu

  • 8/2/2019 #10 Malaysia

    33/36

    31Energy Governance Case

    Studies Series

    1. Lighng Laos: The governance implicaons

    of the Laos rural electrificaon programme

    2. Gers just want to have fun: Evaluang the

    renewable energy and rural electricity

    access project (REAP) in Mongolia

    3. Living up to energy governance

    benchmarks: The Xeketam hydropower

    project in Laos

    4. Seling the score: The implicaons of the

    Sarawak Corridor of Renewable Energy

    (SCORE) in Malaysia

    5. What went wrong? Examining the Teachers

    Solar Lighng Project in Papua New Guinea

    6. Summoning the sun: Evaluang Chinas

    Renewable Energy Development Project

    (REDP)

    7. Rural energy development on the Roofof the World: Lessons from microhydro

    village electrificaon in Nepal

    8. The radiance ofSoura Shakt: Installing two

    million solar home systems in Bangladesh

    9. Untapped potenal: The diffi cules of the

    Small Renewable Energy Power (SREP)

    Programme in Malaysia

  • 8/2/2019 #10 Malaysia

    34/36

    32

    The view from the top of the Langkawi Cable

    Car in Kedah, home to a hybrid dieselsolar

    power system no longer in operaon

  • 8/2/2019 #10 Malaysia

    35/36

    33

  • 8/2/2019 #10 Malaysia

    36/36

    The Lee Kuan Yew School of Public Policy is an autonomous,

    professional graduate school of the Naonal University of

    Singapore. Its mission is to help educate and train the next

    generaon of Asian policymakers and leaders, with the ob-

    jecve of raising the standards of governance throughout the

    region, improving the lives of its people and, in so doing, con-

    Strategic partners