form laporan tugas zaenur
TRANSCRIPT
1
KOMPETENSI MELAKSANAKAN RENCANA ANGGARAN BIAYA
KONSTRUKSI
TUGAS KE : ......... ............................................................................................................
Oleh : .............................
Kelas : XII TKBB1 Semester : 5
SMK Negeri 2 Kebumen Tahun Pelajaran 2014/2015
i
Daftar Isi
Daftar Isi.................................................................................................................................. i
DAFTAR GAMBAR ............................................................................................................. ii
Daftar Gambar ....................................................................................................................... iii
DAFTAR TABEL ................................................................................................................. iv
Bab I Pendahuluan ................................................................................................................1
A. Deskripsi Pekerjaan .................................................................................................1
1. Pengertian.............................................................................................................1
2. Fungsi...................................................................................................................1
B. Gambar – Gambar ...................................................................................................1
1. Gambar Detail ......................................................................................................2
Bab II Perhitungan – Perhitungan ..........................................................................................3
C. Daftar Satuan Bahan dan Upah Kerja .....................................................................3
D. Daftar Perhitungan Volume Pekerjaan ....................................................................3
E. Rekapitulasi Pekerjaan ............................................................................................4
F. Rencana Anggaran Biaya ............................................................................................4
G. Daftar Kebutuhan Material ......................................................................................5
H. Time Scedule ...........................................................................................................6
I. Daftar Analisa Satuan Pekerjaan .................................................................................7
Bab III Kesimpulan ..............................................................................................................14
A. Rekapitulasi Kebutuhan Bahan dan Upah Kerja .................................................14
ii
DAFTAR GAMBAR
iii
Daftar Gambar
Gambar 1: Denah ...................................................................................................................1
Gambar 2: Tampak .................................................................................................................2
Gambar 3: Gambar Detail ......................................................................................................2
Gambar 4: Gambar Penjelas...................................................................................................2
iv
DAFTAR TABEL
Tabel 2: Daftar Satuan Bahan/Material..................................................................................3
Tabel 3 : Daftar Satuan Upah Tenaga Kerja ..........................................................................3
Tabel 4: Perhitungan Volume Pekerjaan................................................................................4
Tabel 5: Rekapitulasi Pekerjaan .............................................................................................4
Tabel 6: Rencana Anggaran Biaya .........................................................................................5
Tabel 7: Time Schedule..........................................................................................................6
1
Bab I
Pendahuluan
A. Deskripsi Pekerjaan
1. Pengertian
Pekerjaan perkerasan jalan merupakan pekerjaan perbaikan kualitas jalan
menjadi lebih baik. Perkerasan jalan terdiri dari bagian pndasi bawah, pondasi
ats dan lapisan atas permukaan jalan dengan lapisan penetrasi (lapen) 7 cm.
Ukuran jalan adalah lebar 3M dengan lebar bahu 90 cm sepanjang 1050 M.
Pekerjaan ini terletak di desa Jatimulyo Kecamatan Alian Kabupaten
Kebumen. Bahan utama Batu Kali, Batu 5/7, batu 2/3, Batu ½, Batu 1/0,5,
Pasir, Aspal, Semen. Waktu pengerjaan mulai tanggal: 5 Agustus – 12
September 2012.
2. Fungsi
Pekerjaan Badan dan bahu jalan berfungsi sebagai :
a. Kelancaran lalu lintas kendaraan dan lalu lintas perekonomian
masyarakat.
b. Meningkatkan Sarana dan Prasarana Insftastruktur Jalan dan Saluran.
c. Memperindah lingkungan.
B. Gambar – Gambar
Gambar 1: Denah
2
Gambar 2: Tampak
1. Gambar Detail
Gambar 3: Gambar Detail
Gambar 4: Gambar Penjelas
3
Bab II
Perhitungan – Perhitungan
C. Daftar Satuan Bahan dan Upah Kerja
No Jenis Material/Bahan Satuan Harga
1 Pasir Urug M3 75.000
2 Pasir Pasang M3 100.000
Tabel 1: Daftar Satuan Bahan/Material
No Jenis Tenaga Kerja Satuan Harga
Pekerja OH 29.500
Tukang OH 35.000
Tabel 2 : Daftar Satuan Upah Tenaga Kerja
D. Daftar Perhitungan Volume Pekerjaan
No Uraian Ukuran (M)
Sketsa Gambar P L T
1 Pek. Galian Tanah Biasa
V=
12 0,15 0,20
4
Tabel 3: Perhitungan Volume Pekerjaan
E. Rekapitulasi Pekerjaan
Rekapitulasi Pekerjaan
Jenis Pekerjaan : Rumah Tinggal
Volume Pekerjaan : ........ M2
No Jenis Pekerjaan Biaya
1 Pekerjaan Persiapan Pengukuran
Bowplank
Rp.
2 Pekerjaan Tanah Galian Tanah Biasa
Pengurugan Kembali dan Pemadatan Pengurugan Pasir Bawah Pondasi di padatkan
Pengurugan Tanah Pengurugan Pasir Bawah Lantai
Rp.
3 Pekerjaan Pasangan Pasangan Batu Kosong 20 Cm
Pasangan Batu Kali 1:3:10
Rp.
4 Pekerjaan Beton Bertulang 150 Kg besi termasuk begisting Beton sloof 15/20
Rp.
Jumlah
Tabel 4: Rekapitulasi Pekerjaan
F. Rencana Anggaran Biaya
5
RENCANA ANGGARAN BIAYA
Jenis Pekerjaan : Rumah Tinggal Sederhana
Pekerjaan Pondasai
Volume Pekerjaan : ........ M2
Alamat : SMK Negeri 2 Kebumen
No Jenis Pekerjaan Volume Sat Analisa Harga Satuan
Jumlah Harga
1 Pekerjaan Persiapan
Pengukuran Bowplank
Rp. Rp.
........
2 Pekerjaan Tanah Galian Tanah Biasa Pengurugan Kembali dan
Pemadatan Pengurugan Pasir Bawah
Pondasi di padatkan Pengurugan Tanah Pengurugan Pasir Bawah
Lantai
Rp. Rp.
.....
3 Pekerjaan Pasangan Pasangan Batu Kosong 20 Cm
Pasangan Batu Kali 1:3:10
Rp.
4 Pekerjaan Beton Bertulang 150 Kg
Beton sloof 15/20
Rp.
Jumlah
Tabel 5: Rencana Anggaran Biaya
G. Daftar Kebutuhan Material
No Jenis Pekerjaan/Material Volume Satuan Keterangan
1 Pekerjaan Pasangan Batu Kali 1:3:10
a. Semen
b. Pasir c. Batu Kali d. Kapur
0,30 60x0,3=
M3 sak
6
H. Time Scedule
No Jenis Pekerjaan Bobot
%
Waktu Pelaksanaan Jumlah
Mg 1 Mg 2 Mg 3 Mg 4
1 Pekerjaan Persiapan 2 2 2
Pek. Tanah 25 5 15 5 25
Jumlah Mg Ini 7 15 5
Jumlah Samp Mg ini 100 7 22 27 27 100
Tabel 6: Time Schedule
7
I. Daftar Analisa Satuan Pekerjaan
DAFTAR ANALISA SNI
Pekerjaan Pondasi
KODE ANALISA URAIAN PEKERJAAN KOEFISIEN SAT
HARGA UPAH/BAHA
N
JUMLAH HARGA SATUAN
JUMLAH
(Rp.) (Rp.) (Rp.)
1 2 3 4 5 6 7
SNI 03-2836-2002-1
1 M3 PASANG PONDASI BATU KALI 1 PC : 1 PS 621.395,60
Bahan 561.245,60
Batu belah/batu gunung 1,100 m3 90.000,00 99.000,00
Semen Portland 392,000 kg 1.118,00 438.256,00
Pasir pasang 0,314 m3 76.400,00 3.989,60
Tenaga 60.150,00
Pekerja 1,500 oh
25.700,00
38.550,00
Tukang batu 0,600 oh
32.500,00
19.500,00
Kepala tukang 0,060 oh
35.000,00
2.100,00
Mandor 0,075 oh
-
-
SNI 03-2836-2002-2
1 M3 PASANG PONDASI BATU KALI 1 PC : 2 PS 490.278,80
Bahan 430.128,80
Batu belah/batu gunung 1,100 m3
90.000,00
99.000,00
Semen Portland 267,000 kg
1.118,00
298.506,00
Pasir pasang 0,427 m3
76.400,00
32.622,80
Tenaga 60.150,00
Pekerja 1,500 oh
25.700,00
38.550,00
Tukang batu 0,600 oh
32.500,00
19.500,00
Kepala tukang 0,060 oh
35.000,00
2.100,00
Mandor 0,075 oh
-
-
SNI 03-2836-2002-3
1 M3 PASANG PONDASI BATU KALI 1 PC : 2,5 PS 621.395,60
Bahan 561.245,60
8
Batu belah/batu gunung 1,100 m3
90.000,00
99.000,00
Semen Portland 392,000 kg
1.118,00
438.256,00
Pasir pasang 0,314 m3
76.400,00
23.989,60
Tenaga 60.150,00
Pekerja 1,500 oh
25.700,00
38.550,00
Tukang batu 0,600 oh
32.500,00
19.500,00
Kepala tukang 0,060 oh
35.000,00
2.100,00
Mandor 0,075 oh
-
-
SNI 03-2836-2002-4
1 M3 PASANG PONDASI BATU KALI 1 PC : 3 PS 422.040,00
Bahan 361.890,00
Batu belah/batu gunung 1,100 m3
90.000,00
99.000,00
Semen Portland 202,000 kg
1.118,00
225.836,00
Pasir pasang 0,485 m3
76.400,00
37.054,00
Tenaga 60.150,00
Pekerja 1,500 oh
25.700,00
38.550,00
Tukang batu 0,600 oh
32.500,00
19.500,00
Kepala tukang 0,060 oh
35.000,00
2.100,00
Mandor 0,075 oh
-
-
SNI 03-2836-2002-5
1 M3 PASANG PONDASI BATU KALI, 1 PC : 4 PS 381.112,00
Bahan 320.962,00
Batu belah/batu gunung 1,100 m3
90.000,00
99.000,00
Semen Portland 163,000 kg
1.118,00
182.234,00
Pasir pasang 0,520 m3
76.400,00
39.728,00
Tenaga 60.150,00
Pekerja 1,500 oh
25.700,00
38.550,00
Tukang batu 0,600 oh
32.500,00
19.500,00
Kepala tukang 0,060 oh
35.000,00
2.100,00
Mandor 0,075 oh
-
-
SNI 03-2836-2002-6
1 M3 PASANG PONDASI BATU KALI, 1 PC : 5 PS 352.759,60
Bahan 292.609,60
Batu belah/batu gunung 1,100 m3
90.000,00
99.000,00
Semen Portland 136,000 kg
1.118,00
152.048,00
Pasir pasang 0,544 m3
76.400,00
41.561,60
Tenaga 60.150,00
9
Pekerja 1,500 oh
25.700,00
38.550,00
Tukang batu 0,600 oh
32.500,00
19.500,00
Kepala tukang 0,060 oh
35.000,00
2.100,00
Mandor 0,075 oh
-
-
SNI 03-2836-2002-7
1 M3 PASANG PONDASI BATU KALI, 1 PC : 6 PS 332.816,40
Bahan 272.666,40
Batu belah/batu gunung 1,100 m3
90.000,00
99.000,00
Semen Portland 117,000 kg
1.118,00
130.806,00
Pasir pasang 0,561 m3
76.400,00
42.860,40
Tenaga 60.150,00
Pekerja 1,500 oh
25.700,00
38.550,00
Tukang batu 0,600 oh
32.500,00
19.500,00
Kepala tukang 0,060 oh
35.000,00
2.100,00
Mandor 0,075 oh
-
-
SNI 03-2836-2002-8
1 M3 PASANG PONDASI BATU KALI, 1 PC : 8 PS 303.748,40
Bahan 243.598,40
Batu belah/batu gunung 1,100 m3
90.000,00
99.000,00
Semen Portland 91,000 kg
1.118,00
101.738,00
Pasir pasang 0,561 m3
76.400,00
42.860,40
Tenaga 60.150,00
Pekerja 1,500 oh
25.700,00
38.550,00
Tukang batu 0,600 oh
32.500,00
19.500,00
Kepala tukang 0,060 oh
35.000,00
2.100,00
Mandor 0,075 oh
-
-
SNI 03-2836-2002-9
1 M3 PASANG PONDASI BATU KALI, 1 KP : 1 SM : 1 PS 296.319,10
Bahan 236.169,10
Batu belah/batu gunung 1,100 m3
90.000,00
99.000,00
Kapur Pasang 0,229 m3
157.700,00
36.113,30
Semen Merah 0,229 m3
259.800,00
59.494,20
Pasir pasang 0,544 m3
76.400,00
41.561,60
Tenaga 60.150,00
Pekerja 1,500 oh
25.700,00
38.550,00
Tukang batu 0,600 oh
32.500,00
19.500,00
Kepala tukang 0,060 oh
35.000,00
2.100,00
10
Mandor 0,075 oh
-
-
SNI 03-2836-2002-10
1 M3 PASANG PONDASI BATU KALI, 1 KP : 1 SM : 2 PS 256.101,00
Bahan 195.951,00
Batu belah/batu gunung 1,100 m3
90.000,00
99.000,00
Kapur Pasang 0,170 m3
157.700,00
26.809,00
Semen Merah 0,170 m3
259.800,00
44.166,00
Pasir pasang 0,340 m3
76.400,00
25.976,00
Tenaga 60.150,00
Pekerja 1,500 oh
25.700,00
38.550,00
Tukang batu 0,600 oh
32.500,00
19.500,00
Kepala tukang 0,060 oh
35.000,00
2.100,00
Mandor 0,075 oh
-
-
SNI 03-2836-2002-11
1 M3 PASANG PONDASI BATU KALI, 1 PC : 1/4 KP : 4 PS 383.222,00
Bahan 323.072,00
Batu belah/batu gunung 1,100 m3
90.000,00
99.000,00
Semen Portland 156,000 kg
1.118,00
174.408,00
Kapur Pasang 0,032 m3
157.700,00
5.046,40
Pasir pasang 0,584 m3
76.400,00
44.617,60
Tenaga 60.150,00
Pekerja 1,500 oh
25.700,00
38.550,00
Tukang batu 0,600 oh
32.500,00
19.500,00
Kepala tukang 0,060 oh
35.000,00
2.100,00
Mandor 0,075 oh
-
-
SNI 03-2836-2002-12
1 M3 PASANG PONDASI BATU KALI, 1 PC : 3 KP : 10 PS 288.118,70
Bahan 227.968,70
Batu belah/batu gunung 1,100 m3
90.000,00
99.000,00
Semen Portland 61,000 kg
1.118,00
68.198,00
Kapur pasang 0,147 m3
157.700,00
23.181,90
Pasir pasang 0,492 m3
76.400,00
37.588,80
Tenaga 60.150,00
Pekerja 1,500 oh
25.700,00
38.550,00
Tukang batu 0,600 oh
32.500,00
19.500,00
Kepala tukang 0,060 oh
35.000,00
2.100,00
11
Mandor 0,075 oh
-
-
SNI 03-2836-2002-13
1 M3 PASANG PONDASI BATU KALI, 1/4 PC : 1 KP : 4 PS 265.603,90
Bahan 205.453,90
Batu belah/batu gunung 1,100 m3
90.000,00
99.000,00
Semen Portland 41,000 kg
1.118,00
45.838,00
Kapur pasang 0,131 m3
157.700,00
20.658,70
Pasir pasang 0,523 m3
76.400,00
39.957,20
Tenaga 60.150,00
Pekerja 1,500 oh
25.700,00
38.550,00
Tukang batu 0,600 oh
32.500,00
19.500,00
Kepala tukang 0,060 oh
35.000,00
2.100,00
Mandor 0,075 oh
-
-
SNI 03-2836-2002-14
1 M3 PASANG PONDASI BATU KOSONG 160.086,00
Bahan 126.000,00
Batu belah/batu gunung 1,200 m3
90.000,00
108.000,00
Pasir urug 0,300 m3
60.000,00
18.000,00
Tenaga 34.086,00
Pekerja 0,780 oh
25.700,00
20.046,00
Tukang batu 0,390 oh
32.500,00
12.675,00
Kepala tukang 0,039 oh
35.000,00
1.365,00
Mandor 0,039 oh
-
-
SNI 03-2836-2002-15
1 M3 PASANG PONDASI SIKLOP 40% BATU KALI 1.181.407,00
Bahan 1.073.707,00
Besi beton 75,000 kg
10.000,00
750.000,00
Semen Portland 202,000 kg
1.118,00
225.836,00
Pasir beton 0,320 m3
76.400,00
24.448,00
Koral beton 0,490 m3
132.700,00
65.023,00
Kawat beton 0,800 kg
10.500,00
8.400,00
Tenaga 107.700,00
Pekerja 3,000 oh
25.700,00
77.100,00
Tukang batu 0,850 oh
32.500,00
27.625,00
Kepala tukang 0,085 oh
35.000,00
2.975,00
Mandor 0,150 oh
-
-
SNI 03-2836-2002- 1 M3 PASANG PONDASI 548.795,00
12
16 SUMURAN DIAMETER 100 CM
Bahan 476.829,00
Batu belah/batu gunung 0,450 kg
90.000,00
40.500,00
Semen portland 280,000 kg
1.118,00
313.040,00
Pasir beton 0,450 m3
76.400,00
34.380,00
Koral beton 0,670 m3
132.700,00
88.909,00
Tenaga 71.966,00
Pekerja 2,380 oh
25.700,00
61.166,00
Tukang batu 0,300 oh
32.500,00
9.750,00
Kepala tukang 0,030 oh
35.000,00
1.050,00
Mandor 0,080 oh
-
-
SNI 03-2836-2002-17
1 M' PEMBUATAN TIANG PANCANG (40 X 40) CM, BETON BERTULANG 753.977,60
Bahan 704.157,60
Pasir urug darat 0,019 m3
60.000,00
1.140,00
Pasir beton 0,094 m3
76.400,00
7.181,60
Koral beton 0,150 m3
132.700,00
19.905,00
Semen portland 60,500 kg
1.118,00
67.639,00
Besi beton 45,000 kg
10.000,00
450.000,00
Kawat beton 0,900 kg
10.500,00
9.450,00
Kayu kasao 5/7 kruing 0,032 m3
4.500.000,00
144.000,00
Paku 0,120 kg
10.400,00
1.248,00
Minyak bekisting / pelumas 0,090 lt
21.000,00
1.890,00
Plamur tembok 0,240 kg
7.100,00
1.704,00
Tenaga 49.820,00
Pekerja 1,000 oh
25.700,00
25.700,00
Tukang batu 0,670 oh
32.500,00
21.775,00
Kepala tukang 0,067 oh
35.000,00
2.345,00
Mandor 0,050 oh
-
-
SNI 03-2836-2002-18
1 M' PEMBUATAN TIANG PANCANG (35 X 35) CM, BETON BERTULANG 595.409,50
Bahan 556.849,50
Pasir urug darat 0,016 m3
60.000,00
960,00
Pasir beton 0,080 m3
76.400,00
6.112,00
Koral beton 0,125 m3
132.700,00
16.587,50
Semen portland 49,000 kg
1.118,00
54.782,00
Besi beton 34,500 kg
10.000,00
345.000,00
13
Kawat beton 0,700 kg
10.500,00
7.350,00
Kayu kasao 5/7 kruing 0,027 m3
4.500.000,00
121.500,00
Paku 0,120 kg
10.400,00
1.248,00
Minyak bekisting / pelumas 0,090 lt
21.000,00
1.890,00
Plamur tembok 0,200 kg
7.100,00
1.420,00
Tenaga 38.560,00
Pekerja 0,800 oh
25.700,00
20.560,00
Tukang batu 0,500 oh
32.500,00
16.250,00
Kepala tukang 0,050 oh
35.000,00
1.750,00
Mandor 0,040 oh
-
-
14
Bab III
Kesimpulan
A. Rekapitulasi Kebutuhan Bahan dan Upah Kerja