[2014] 1 LNS 1659 Legal Network Series
1
DALAM MAHKAMAH TINGGI MALAYA DI SHAH ALAM
DALAM NEGERI SELANGOR DARUL EHSAN, MALAYSIA
[GUAMAN SIVIL NO: 22-1850-2008]
ANTARA
KNJ WORLWIDE SDN BHD
(NO. SYARIKAT: 187337-H) .. . PLAINTIF
DAN
1. ONG KIEN TECK
(NO. K/P: 760728-10-5203)
2. NG SONG HUAT
(NO. K/P: 700324-02-5245) (Berniaga atas nama E Builder Engineering No. Perniagaan: 001427364-V) .. . DEFENDAN-
DEFENDAN
[2014] 1 LNS 1659 Legal Network Series
2
ALASAN PENGHAKIMAN
Pengenalan
1. Plaintif adalah sebuah syarikat yang ditubuhkan di Malaysia di
bawah Akta Syarikat 1960 yang mempunyai alamat perniagaan di No.
6A, Jalan Jelita Satu, Taman Jelita Off Jalan Reko, 43000 Kajang,
Selangor. Kedua-dua defendan pula adalah rakan kongsi yang
menjalankan perniagaan atas nama dan gaya E Builder Engineering
yang beralamat di No. 7, Jalan 7B, Taman Kajang Mewah, 43000
Kajang, Selangor.
2 Adalah fakta yang dipersetujui bahawa melalui satu Surat Awad
bertarikh 10.5.2005 (“Surat Awad”), E Builder Engineering melantik
Konajaya Sdn Bhd (nama terdahulu plaintif) sebagai sub-kontraktor
untuk menyiapkan kerja-kerja yang dikenali sebagai “Sungai Selangor
Phase 3 – Bukit Badong Distribution Works - From New FRIM
Reservoir To Dusun Kubung Reservoir - Package 2” (“Projek
tersebut”).
3. Adalah juga fakta yang dipersetujui bahawa bagi Projek tersebut :-
(a) Syarikat Bekalan Air Selangor Sdn Bhd
(“SYABAS”) adalah klien.
(b) L a m b a n g S e j a g a t S d n B h d ( “ L S S B ” )
a d a l a h k o n t r a k t o r u t a m a ; d a n
(c) S M HB Sdn Bhd ( “ S M H B ” ) pu l a a d a l a h
j u r u t e r a p e r und i ng ( kon su l t a n )
[2014] 1 LNS 1659 Legal Network Series
3
Kes Plaintif
4. Berdasarkan Surat Awad bertarikh 10.5.2005 tersebut, pihak
plaintif dikatakan telah menyempurnakan kerja-kerja dan obligasi
mereka di bawah perjanjian tersebut dan telah menghantar 14 tuntutan
progress (progress claim) kepada defendan untuk kerja-kerja yang telah
dilakukan dan juga selain daripada itu pihak plaintif telah membuat
kerja-kerja variasi sejumlah RM106,738.17. Defendan hanya membayar
kepada plaintif amaun sebanyak RM789,352.31 sebagai pembayaran
sebahagian terhadap amaun yang dituntut meninggalkan baki terhutang
RM848,395.97 dan ini menjadi asas kepada tuntutan plaintif terhadap
defendan.
Pembelaan Defendan dan Tuntutan Balas
5. Defendan pula menyatakan bahawa terdapat tuntutan progress
plaintif yang tidak dapat diterima atau diluluskan kerana memerlukan
dokumen sokongan yang gagal dikemukakan plaintif. Defendan juga
menafikan bahawa plaintif telah menjalankan kerja serta obligasinya
dengan baik kerana terdapat kerja-kerja rektifikasi yang diarahkan oleh
defendan kepada plaintif untuk dilakukan telah gagal dilakukan malah
mengikut defendan lagi, kerja-kerja yang sepatutnya dilakukan oleh
plaintif harus disiapkan pada atau sebelum 4.11.2005 tetapi plaintif telah
gagal menyiapkan kerja tersebut mengikut jadual dan kerja-kerja hanya
dapat disiapkan oleh plaintif pada 31.10.2006 iaitu kelewatan selama
361 hari. Oleh itu pihak defendan membuat tuntutan balas terhadap
plaintif untuk gantirugi jumlah tertentu dan ditetapkan (LAD) serta
gantirugi atas kerugian yang dialami dalam menggunakan perkhidmatan
kontraktor lain untuk menyelesaikan kerja-kerja rektifikasi tersebut.
[2014] 1 LNS 1659 Legal Network Series
4
Isu Untuk Diputuskan
6. Walaupun pihak-pihak menfailkan Ikatan D dengan 6 butiran
sebagai isu-isu untuk dibicarakan, tetapi setelah mendengar keterangan
saksi-saksi, hanya 4 isu utama yang perlu diputuskan iaitu:
(i) Samada plaintif telah menyempurnakan
tugas dan obligasinya di bawah Surat
Awad bertarikh 10.5.2005 tersebut.
(ii) Samada terdapat kelewatan dan kelewatan
tersebut disebabkan oleh pihak plaintif,
(iii) Samada defendan membenarkan plaintif
lanjutan masa untuk menyempurnakan
projek tersebut; dan
(iv) Samada defendan layak untuk menuntut
gantirugi jumlah tertentu dan ditetapkan
(LAD) di bawah surat awad daripada
plaintif.
(i) Samada plaintif telah menyempurnakan tugas dan obligasinya
dibawah Surat Awad bertarikh 10.5.2005 tersebut.
7. Dokumen penting yang perlu dirujuk adalah Surat Awad bertarikh
10.5.2010 itu sendiri yang terdapat di Ikatan Dokumen B1 di ms 1-39.
Klausa penting adalah Klausa 2, Klausa 5 dan Klausa 6. Untuk tujuan
rujukan, berikut adalah petikan klausa tersebut.
[2014] 1 LNS 1659 Legal Network Series
5
2. Form Of Contract
The form of contract shall be based on
Main Contract Agreement issued by
Syarikat Bekalan Air Selangor Sdn. Bhd.
5. Client/Main Contractor/Sub-Contractor
Under the main contract (“the contract”),
Syarikat Bekalan Air Selangor Sdn. Bhd.
(SYABAS) shall be the client, Lambang
Sejagat Sdn. Bhd (LSSB) is the Main
Contractor and your scope of works shall
be in relation to the Main Contract between
SYABAS and LSSB.
6. Project Details
In consideration of the aforesaid Sub-
Contract Sum, you shall execute and
complete the Works as mentioned above in
all respect to the reasonable satisfaction of
SYABAS and LSSB until handling over of
the works or upon issuance of the
Certificate of Practical Completion
…………..
8. Berdasarkan Klausa 6 di dalam Surat Awad tersebut, adalah jelas
bahawa pihak plaintif dikehendaki untuk menyempurnakan kerja atas
kepuashatian yang munasabah dari pihak SYABAS dan LSSB ataupun
apabila Certificate of Practical Completion dikeluarkan. Di dalam kes
ini, pihak SYABAS telah mengeluarkan dua sijil iaitu Certificate of
[2014] 1 LNS 1659 Legal Network Series
6
Practical Completion bertarikh 11.1.2007 (Ikatan Dokumen C1 di ms
1650-1651 - Exh. P1) dan juga Certificate of Completion of Making
Good Defects bertarikh 28.6.2008 (Ikatan Dokumen C1 di ms 1660-
1661- Exh. P2). Berdasarkan sijil - sijil ini, adalah jelas bahawa pihak
plaintif telah menyempurnakan kerja sepertimana dinyatakan di dalam
Klausa 6 tersebut. Malah pihak LSSB telah dibayar atas kerja-kerja
tersebut. Isu seterusnya adalah berkaitan samada terdapat kelewatan
dalam menyempurnakan kerja oleh plaintif.
(ii) Samada terdapat kelewatan dan kelewatan tersebut
disebabkan oleh pihak plaintif, dan
(iii) Samada defendan membenarkan plaintif lanjutan masa untuk
menyempurnakan projek tersebut; dan
9. Isu kedua dan ketiga akan dibincangkan bersekali. Pihak defendan
menyatakan bahawa berdasarkan Klausa 8 Surat Awad tersebut, tarikh
mula kerja adalah pada 12.5.2005 dan kerja-kerja sepatutnya disiapkan
pada 4.11.2005. Berdasarkan dua sijil iaitu Certificate of Practical
Completion bertarikh 11.1.2007 dan juga Certificate of Completion of
Making Good Defects bertarikh 28.6.2008 sememangnya terdapat
kelewatan dalam menyempurnakan kerja-kerja projek tersebut. Pihak
defendan menegaskan bahawa kelewatan tersebut adalah disebabkan
oleh pihak plaintif kerana gagal menyediakan peralatan dan mesin yang
mencukupi serta kekurangan pekerja dalam menjalankan projek
tersebut (PS-SD1-QA10). Plaintif pula mendakwa bahawa kelewatan
kerja projek tersebut adalah disebabkan bahawa pihak defendan
mengarahkan plaintif untuk melakukan kerja-kerja tambahan variasi
(additional variation work) seperti dalam Variation Order No 1 bertarikh
[2014] 1 LNS 1659 Legal Network Series
7
15.6.2006 (iaitu P5- Ikatan C2 di ms 2048-2050) dan Variation Order
No 2 bertarikh 30.5.2006 (Ikatan B2 di ms 614-615).
10. Daripada keterangan saksi-saksi adalah tidak dipertikaikan
bahawa kerja-kerja projek menurut surat awad bertarikh 10.5.2010 perlu
disiapkan pada atau sebelum 4.11.2005. Tetapi terdapat dua VO
masing-masing bertarikh 15.6.2006 dan 30.5.2006 yang mengarahkan
plaintif melakukan kerja tambahan. Jika diteliti juga Certificates Of
Delay and Extension Of Time No 1 (COD and EOT) bertarikh
25.1.2006, COD and EOT No. 2 bertarikh 16.5.2006 dan COD and EOT
No. 3 bertarikh 11.1.2007, SYABAS telah membenarkan lanjutan masa
sehingga 31.10.2006 (Ikatan C1 di ms 1652-1659). Pihak plaintif telah
menyiapkan kerja-kerja projek tersebut pada atau sekitar Oktober 2006
dan Syabas pula telah isu Certificate of Practical Completion bertarikh
11.1.2007 menyatakan bahawa projek telah disiapkan pada 31.10.2006.
Oleh itu walaupun terdapat kelewatan, kelewatan tersebut adalah di
dalam linkungan masa dibenarkan oleh SYABAS selaku klien di dalam
projek ini. Isu mengenai samada terdapat kebenaran daripada defendan
berkaitan permohonan plaintif untuk lanjutan masa akan dibincangkan
seterusnya.
(iv) Samada defendan layak untuk menuntut gantirugi jumlah
tertentu dan ditetapkan (LAD) dibawah surat awad daripada
plaintif.
11. Di dalam Klausa 8 (e) Surat Awad bertarikh 10.5.2005 tersebut
dicatatkan antara lainnya bahawa gantirugi jumlah tertentu dan
ditetapkan (LAD) pada kadar RM1,750.00 sehari. Defendan di dalam
tuntutan balasnya menuntut jumlah tersebut atas kelewatan pihak
[2014] 1 LNS 1659 Legal Network Series
8
plaintif menyiapkan kerjanya selama 361 hari dari 4.11.2005 hingga
31.10.2006 dan menuntut sejumlah RM631,750.00. Alasan pihak
defendan adalah bahawa pihak plaintif ada memohon untuk lanjutan
masa untuk kerja projek dan VO tetapi tidak dibenarkan oleh pihak
defendan. Lihat PS-SD1 di QA 38-40 (ms 998-999 Ikatan B4 dan
jawapan defendan di ms 1522 ikatan B5)
12. Seksyen 75 Akta Kontrak 1950 telah memperuntukkan bahawa:
When a contract has been broken, if a sum is
named in the contract as the amount to be paid
in case of such breach, or if the contract contains
any other stipulation by way of penalty, the party
complaining of the breach is entitled, whether or
not actual damage or loss is proved to have been
caused thereby, to receive from the party who
has broken the contract reasonable
compensation not exceeding the amount so
named or, as the case may be, the penalty
stipulated for.
13. Berkaitan isu seksyen 75 Akta Kontrak ini rujukan dibuat kepada
kes Mahkamah Persekutuan iaitu Selva Kumar a/l Murugaih v.
Thiagarajah a/l Retnasamy [1995] 1 MLJ 817, Hakim Peh Swee Chin
FCJ berkata bahawa:
[2014] 1 LNS 1659 Legal Network Series
9
We have long known the object for which the
section in question was enacted first in India and
later here in our country. Thomson J (as he then
was) in Maniam v. The State of Perak [1957] MLJ
75, commenting on arguments advanced before
him as to whether a certain sum was to be
regarded either as a penalty or as liquidated
damages, said [at p 76]:
In the first place, in this country there is no
difference between penalty and liquidated
damages. Section 75 of the Contract Ordinance
which is the same as s. 74 of the Indian Contract
Act reads as follows:
‘When a contract has been broken, if a sum is
named in the contract as the amount to be paid
in case of such breach, or if the contract contains
any other stipulation by way of penalty, the party
complaining of the breach is entitled, whether or
not actual damage or loss is proved to have been
caused thereby, to receive from the party who
has broken the contract reasonable
compensation not exceeding the amount so
named or, as the case may be, the penalty
stipulated for.’
As is said in Pollock and Mulla on the Indian
Contract Act (7 t h Ed) at p 410, ‘This section
[2014] 1 LNS 1659 Legal Network Series
10
boldly cuts the most troublesome knot in the
common law doctrine of damages’. In brief, in our
law in every case if a sum is named in a contract
as the amount to be paid in case of breach it is to
be treated as a penalty. See Bhai Panna Singh v.
Bhai Arjun Singh AIR [1929] PC 179.
14. Seterusnya di mukasurat 824 Hakim Peh Swee Chin FCJ
menyatakan lagi bahawa :
At common law, where there is no such section
in question, the effect of a sum being found as a
penalty, is therefore that the innocent party to a
breach of contract is not left with no remedy, he
can still recover damages or compensation which
he has however to prove, and it is immaterial that
such compensation if proved, exceeds or not, the
stipulated penalty.
15. Keputusan Mahkamah Persekutuan ini telah dikuiti oleh kes
Mahkamah Rayuan iaitu Krishnan Nair & Sons v. Ken Grouting
System Specialist Sdn Bhd [2010] MLJU 1694. Di dalam kes ini
faktanya lebih kurang sama dengan kes di mahkamah ini di mana
terdapat klausa gantirugi jumlah tertentu dan ditetapkan (LAD) jika
terdapat kelewatan di pihak sub-kontraktor dalam menyiapkan kerja-
kerja tersebut. YA Hakim Sulung Matjeraie HMR memutuskan bahawa :
[2014] 1 LNS 1659 Legal Network Series
11
[15] The Respondent also failed to produce
any documentary evidence of the actual loss
suffered and could not therefore, based on
the authority of the above cited Selva Kumar
(supra), be entitled to claim under the
Liquidated Ascertained Damages clause. It is
interesting to point out here that the ultimate
employer to the sub-contract, ie, the
Government of Malaysia, did not impose any
Liquidated Ascertained Damages on the
Respondent. Likewise there is therefore no
reason why the Appellant should now be
required to pay Liquidated Ascertained
Damages to the Respondent.
[17] We are of the considered view that by virtue
of the doctrine of stare decisis we are compelled
to stand by and follow what has been decided by
the Federal Court in Selva Kumar (supra). What
Arifin Zakaria FCJ (as his Lordship then was)
said in Johor Coastal Development Sdn Bhd v.
Constrajaya Sdn Bhd [2009] 4 MLJ 445 at page
460 fortified our view when he reaffirmed that
“…I am of the view that Selva Kumar is still good
law.
[2014] 1 LNS 1659 Legal Network Series
12
16 Rujuk juga kes Setegap Bhd (in creditors’ volountary winding
up) v. Ranhill Engineers and Constructors Sdn Bhd [2011] 6 MLJ
684. Oleh itu, berdasarkan kes-kes di atas adalah jelas bahawa pihak
defendan perlu membuktikan melalui keterangan bahawa mereka
sebenarnya telah mengalami kehilangan atau kerugian akibat kelewatan
kerja oleh plaintif. Di dalam kes ini, defendan di dalam keterangannya
(SD1) semasa disoal balas oleh peguam berkaitan kerugian yang beliau
(defendan) alami hanya menyatakan bahawa :
“HYK Ok, secondly my instruction is this ,
Mr Ng, you didn’t suffer any losses,
do you agree?
NG Disagree
HYK Do you have any document to show
what are the losses that you have
suffered in these Bundles can you
point to us?
NG This is not, it is common sense.
HYK Common sense, that means you
don’t have any documents to prove?
NG I don’t put in here but it is common
sense you see.
HYK Ok, no document, ok thak you, no
documents. Are you calling any other
witness other than you or you are the
only witness for defendant?
NG I did not call any witness.”
[2014] 1 LNS 1659 Legal Network Series
13
17. Berdasarkan keterangan yang diberikan oleh defendan,
mahkamah ini mendapati bahawa pihak defendan gagal membuktikan
sebarang kehilangan atau kerugian yang mereka alami akibat dari
kelewatan kerja oleh pihak plaintif. Apa yang menarik adalah pihak
SYABAS selaku pelanggan tidak pernah mengenakan apa-apa LAD
berdasarkan P8 dan P6. Lebih jelas adalah keterangan daripada saksi
SP3 iaitu Dato’ Ruslan Bin Hassan iaitu Pengarah Urusan SYABAS
yang mengesahkan bahawa tiada LAD dikenakan berkaitan dengan
projek ini. Oleh itu, secara kesimpulannya, pihak defendan telah gagal
membuktikan kerugian yang mereka alami untuk membolehkan
mahkamah ini membenarkan tuntutan mereka atas LAD ini.
18. Jika dilihat kepada tuntutan balas defendan terdapat juga tuntutan
atas Debit Note No 1 bernilai RM77,876.67 dan Debit Note No 2
bernilai RM9,870.00 serta bahan-bahan binaan yang tidak dikembalikan
bernilai RM61,860.00.
[2014] 1 LNS 1659 Legal Network Series
14
19. Berkaitan Debit Note No 1, perkara ini sepatutnya tidak lagi
menjadi isu. Jika dilihat kepada fakta-fakta yang dipersetujui Ikatan E,
telah dinyatakan bahawa:
4. Plaintif telah mengambil kira Nota Debit E
Builder Engineering No: 1 untuk jumlah
sebanyak RM77,876.67 dengan
menganggap jumlah ini sebagai
pembayaran sebahagian oleh E-Builder
Engineering. Oleh itu, ini menjadikan
jumlah pembayaran yang dibuat oleh E.
Builder Engineering kepada Plaintif
berjumlah sebanyak RM789,352.30.
Juga di dalam nota keterangan bertarikh 17.7.2014 di ms 96:
“HYK Okay. So. I ts paid. You are not
claiming Debit Note 1?
ANS N o . D eb i t n o t e 1 a nd 2 s udah
d i b a y a r . Y ang A r i f . T e l a h d i b a y a r .
Maksudnya Defendan ber i debi t note
kepada Plaint i f , te lah dibayar .”
20. Berkaitan Debit Note No 2, pihak defendan cuma menyatakan
bahawa jumlah tersebut digunakan untuk tujuan kerja-kerja pencucian
yang dilakukan oleh pihak ketiga tetapi tiada dokumen dikemukakan
untuk membuktikan jumlah tersebut ataupun kontraktor tersebut
dipanggil untuk membuktikan tuntutan tersebut (nota keterangan
bertarikh 5.8.2014 di ms 64-65 adalah berkaitan) padahal beban
[2014] 1 LNS 1659 Legal Network Series
15
adalah kepada defendan untuk membuktikan bahawa jumlah tersebut
telah dibelanjakan. Oleh itu, tuntutan atas Debit Note No 2 ini juga
gagal dibuktikan oleh pihak defendan.
21. Defendan juga menuntut atas barangan binaan bernilai
RM61,860.00 yang tidak dikembalikan oleh pihak plaintif. Di dalam
keterangan defendan di PS-SD1 QA33 di ms 15 beliau menyatakan
bahawa barangan tersebut bukan milik mereka. Seterusnya, semasa
disoal balas oleh peguam plaintif, beliau menyatakan bahawa barangan
binaan tersebut adalah milik kontraktor utama iaitu Lambang Sejagat
(Nota Keterangan bertarikh 5.8.2014 di ms 66). Berdasarkan kes
Mahkamah Agong di dalam Associated Pan Malaysia Cement Sdn
Bhd v. Syarikat Teknikal & Kejuruteraan Sdn Bhd [1990] 3 MLJ 287,
pihak defendan t idak boleh menuntut apa-apa kerugian
memandangkan bahawa mereka bukan tuanpunya barangan tersebut.
Keputusan tersebut didapati di ms 296:
“..As for the award of general damages of
$6,000,000, we also agreed with the appellant
that the award was wrong as the respondent was
not the owner of the machines and was merely
the lessee. It was entitled to the use and
possession of those machines provided that rent
was paid. We also agreed that as the respondent
was not the owner of those machines it could not
claim for the loss of the value of those goods in
respect of which it had no title. That award of
$6,000,000 is also therefore set aside….”
[2014] 1 LNS 1659 Legal Network Series
16
Kesimpulan
22. Oleh itu berdasarkan keseluruhan keterangan di dalam kes ini,
mahkamah mendapati bahawa pihak plaintif telah berjaya membuktikan
kes mereka atas imbangan kebarangkalian dan mahkamah
membenarkan tuntutan plaintif dengan kos untuk sejumlah
RM848,395.97 serta faedah 5% setahun dari tarikh writ difailkan hingga
penyelesaian. Tuntutan balas defendan dengan ini ditolak dengan kos.
Kos ditetapkan sejumlah RM20,000.00.
Tarikh: 29 SEPTEMBER 2014
(HASHIM HAMZAH)
HAKIM MAHKAMAH TINGGI MALAYA
SHAH ALAM
[2014] 1 LNS 1659 Legal Network Series
17
Kaunsel:
Bagi pihak plaintif - Heng Yee Keat (Chew Pei Ying, Christopher & Lee
Ong bersamanya); T/n Christopher & Lee Ong
Level 22, Quill 7
No. 9, Jalan Stesen Sentral 5
Kuala Lumpur Sentral
50470 Kuala Lumpur
[Ruj : CPYG/319540/01/KNJ/OKT&NSH]
Te : 03-2273 1919
Faks : 03-2273 8310
Bagi pihak defendan-defendan - Annou Xavier (S Nithiyawathi &
Elizabeth Goh bersamanya); T/n Azri, Lee Swee Seng & Co
Suite 3A-19-1
Level 19, Block 3A
Jalan Stesen Sentral 5
Kuala Lumpur Sentral
50470 Kuala Lumpur
[Ruj : ALSS/AX/3.1/3383/09/NIT]
Tel : 03-2273 5563
Faks : 03-2274 6776
Perundangan yang dirujuk:
Akta Kontrak 1950, s. 75