Technical Requirements of Malaysiafor Nuclear Reactor Technology for
Near Term DeploymentMazleha Maskin, Julia Abdul Karim
Abdul Muin B. Abdul Rahman,DrMalaysian Nuclear Agency
8/13/2019 7 Malaysia Mazleha-technreqs Ws-smrdec2011
http://slidepdf.com/reader/full/7-malaysia-mazleha-technreqs-ws-smrdec2011 2/19
General criteria
•
National energy plan• National infrastructure: the grid, site, and environment
characteristics• Local conditions• National Participations• Regulatory and safety requirements• General technical and economics characteristics• Associated services and supports
8/13/2019 7 Malaysia Mazleha-technreqs Ws-smrdec2011
http://slidepdf.com/reader/full/7-malaysia-mazleha-technreqs-ws-smrdec2011 3/19
National Energy Plan: National FuelDiversification Policy
1981Four Fuel
2000Five Fuel
2012Six Fuel
oil, hydropower,natural gas &
coal
+renewable
energy
+nuclear energy
8/13/2019 7 Malaysia Mazleha-technreqs Ws-smrdec2011
http://slidepdf.com/reader/full/7-malaysia-mazleha-technreqs-ws-smrdec2011 4/19
National Infrastructure: The Grid
Available Grid• 500 kV o/h Lines : 890 km• 275 kV o/h Lines : 6,666 km• 132 kV o/h Lines : 10,280 km• 275 kV u/g Cables : 61 km• 132 kV u/g Cables : 680 km
Power supply stability and reliabilityperformance published annually by the Energy
Commission and available athttp://www.st.gov.my
*o/h: overhead; u/g: underground
SOURCE : http://www.geni.org/globalenergy/library/national_energy_grid/malaysia/malaysiannationalelectricitygrid.shtml
8/13/2019 7 Malaysia Mazleha-technreqs Ws-smrdec2011
http://slidepdf.com/reader/full/7-malaysia-mazleha-technreqs-ws-smrdec2011 5/19
National Infrastructure: The Grid
SOURCE : http://www.geni.org/globalenergy/library/national_energy_grid/malaysia/malaysiannationalelectricitygrid.shtml
8/13/2019 7 Malaysia Mazleha-technreqs Ws-smrdec2011
http://slidepdf.com/reader/full/7-malaysia-mazleha-technreqs-ws-smrdec2011 6/19
General Profile of Power Utilities
SOURCE : Mohd Yusof Rakob - Planning for Smart Grid in TNB System, PECon2010, 2010 IEEE Conference on Power andEnergy, Sunway Resort Hotel & Spa, Malaysia
TNB (P.Malaysia) SEB (Sarawak) SESB (Sabah)Logo
Installed Capacity(MW)
21,051 (2010) 1,230 (2009) 866.4 (2010)
Customer 7,593,684 499,618 413,983
Max Demand (MW) 15,072 1,036 760
Gen Mix: 2010 Gen Mix: 2009 Gen Mix: 2009
Gas: 54% Gas: 53% Oil: 57%
Coal: 40% Coal: 34% Coal: 31%Hydro: 5.2% Hydro: 8% Hydro: 9%
Distillate: 0.2% Diesel: 5% Biomass: 3%NOTE : Electricity supply industry in Malaysia is a fully regulated. TNB, SEB and SESB arevertically integrated and operate along with Independent Power Producers (IPPs)
8/13/2019 7 Malaysia Mazleha-technreqs Ws-smrdec2011
http://slidepdf.com/reader/full/7-malaysia-mazleha-technreqs-ws-smrdec2011 7/19
National Infrastructure: The Site
Malaysia is well positionedas a possible location for nuclear plants
LowEarthquakeRisk Zone
Public Safety & Heal th (50%)Radiation exposure, Population, Extreme
natural events, Hazardous installations
Enviro nm ent (20%)Ecology, Water quality
Socio -econ om ic (15%)Coastal resources, Land Use, Archaeology
Engin eer ing Costs (15%)Foundation, Accessibility, Proximity to grid,
Cooling water
Site Selection Weighting Factor
8/13/2019 7 Malaysia Mazleha-technreqs Ws-smrdec2011
http://slidepdf.com/reader/full/7-malaysia-mazleha-technreqs-ws-smrdec2011 8/19
Local Conditions
•
Nuclear Power Infrastructure Development Program• National Participation• Formation of NEPIO• Formation of TSO• International Tender for appointment of consultant:-
• Regulatory study (gap analysis leading to amended legislation)• Final Site study• Feasibility study• NPIDP study• Public acceptance programme
8/13/2019 7 Malaysia Mazleha-technreqs Ws-smrdec2011
http://slidepdf.com/reader/full/7-malaysia-mazleha-technreqs-ws-smrdec2011 9/19
Local Conditions: Nuclear PowerInfrastructure Development Program•
Nuclear Sector Development: July 16, 2010
8/13/2019 7 Malaysia Mazleha-technreqs Ws-smrdec2011
http://slidepdf.com/reader/full/7-malaysia-mazleha-technreqs-ws-smrdec2011 10/19
Local Conditions: Nuclear PowerInfrastructure Development Program•
Nuclear Sector Development: July 16, 2010
8/13/2019 7 Malaysia Mazleha-technreqs Ws-smrdec2011
http://slidepdf.com/reader/full/7-malaysia-mazleha-technreqs-ws-smrdec2011 11/19
Local Conditions: Form at ion o fNEPIO: MNPC
Jan 11, 2011• Y.A.B. Prime Minister announced
the establishment of Malaysia
Nuclear Power Corporation (MNPC)
8/13/2019 7 Malaysia Mazleha-technreqs Ws-smrdec2011
http://slidepdf.com/reader/full/7-malaysia-mazleha-technreqs-ws-smrdec2011 12/19
Local Conditions: Current A ct iv i t ieso f MNPC
International Tender for appointment of Consultant:-• Regulatory infrastructure study (Study in Progress)• Site study (awarded)• Feasibility study (awarded):
- Technology assessment and selection: maybe SMR or Bigger• Nuclear Power Infrastructure Development Program study (awarded)
• Industrial capability•
R&D Capability• Education & Training capability• ETC
• Public acceptance (awarded)SOURCE : Ir Dr Mohamad Puad Hji Abu; INPRO Dialogue Forum on Nuclear Energy Innovations: Common User Considerationfor Small and Medium-sized Nuclear PR, Vienna, 10 – 14 October 2011
8/13/2019 7 Malaysia Mazleha-technreqs Ws-smrdec2011
http://slidepdf.com/reader/full/7-malaysia-mazleha-technreqs-ws-smrdec2011 13/19
Local Conditions: Form at ion of TSO
•
Jan 1, 2011: Malaysia Nuclear Agency• TSO program / activities: Nuclear Malaysia involvement:-
• Public information• Siting: EIA, SIA, RIA• Feasibility Study: Technology assessment; Safety assessment;
Industrial capabilities• Education and Training: Reactor Operator Training; Radiation
Protection Officer Training; Nuclear Engineering Experimental Labfor academics and Industry
• Regulatory framework preparation: Licensing Regulation for Nuclear
Installation; Safety Analysis Report• Invitation and Evaluation of bids for nuclear power plants: Technical
Evaluation• Technology development, capacity building
SOURCE : Ir Dr Mohamad Puad Hji Abu; INPRO Dialogue Forum on Nuclear Energy Innovations: Common User Considerationfor Small and Medium-sized Nuclear PR, Vienna, 10 – 14 October 2011
8/13/2019 7 Malaysia Mazleha-technreqs Ws-smrdec2011
http://slidepdf.com/reader/full/7-malaysia-mazleha-technreqs-ws-smrdec2011 14/19
National ParticipationCabinet Committee on Energy
Nuclear Power DevelopmentSteering Committee (JPPKN)
Ministry of Finance (MOF); Ministry of Foreign Affairs (MOFA);Ministry of Science, Technology & Innovation (MOSTI);
Ministry of Natural Resources & the Environment (MNRE);Economic Planning Unit (EPU) of the Prime Minister’s Department; (JPM);
Nuclear Malaysia, AELB, ST & TNB.
MOF, Ministry of Education; MOFA, MOSTI, MNRE, KeTTHA; Ministry of Health (MOH);Ministry of International Trade & Industry (MITI); Ministry of Home Affairs (KDN);
Ministry of Higher Education (MOHE); Ministry of Housing & Local Government; (KPKT);
Ministry of Information, Culture & Communications (MICC);Ministry of Rural & Regional Development (MRRD); Ministry of Human Resources (MHR);
EPU; National Security Council (MKN); Attorney General’s Chambers (AGC);Public Services Dept. (JPA); Information Dept; ST; AELB; Dept. of Environment (JAS);
Dept. of Occupational Health & Safety (DOSH); Public Works Dept. (JKR);Drainage & Irrigation Dept. (DID); Mineral & Geoscience Dept. (JMG);Meteorology Dept (MMD); Urban & Country Planning Dept. (JPBD);
Khazanah Nasional Berhad (KNB); TNB; Small & Medium Enterprises (SME) Corporation;Malaysia Energy Centre (PTM); Federation of Malaysian Manufacturers (FMM);
Association of Consulting Engineers Malaysia (ACEM);Master Builders Association of Malaysia (MBAM)
KeTTHA, EPU, Nuclear Malaysia, DOE, DOSH, AELB, ST, PTM,SIRIM Berhad, Marine Dept.
MOSTI, KeTTHA, KDN, MOFA, KPKT, MKN, AGC, ST, JAS, DOSH, Nuclear Malaysia & TNB.
Member Agencies:
Nuclear Power ProgrammeDevelopment Working Committee
Nuclear Power ProjectDevelopment Working Committee
Nuclear Power LegislativeDevelopment Coordination
Working Committee
Ministry of Energy, Green Technology & Water(KeTTHA)
Malaysian Nuclear Agency(Nuclear Malaysia)
Tenaga Nasional Berhad (TNB)
Atomic Energy Licensing Board (AELB)& Energy Commission (ST)
8/13/2019 7 Malaysia Mazleha-technreqs Ws-smrdec2011
http://slidepdf.com/reader/full/7-malaysia-mazleha-technreqs-ws-smrdec2011 15/19
Regulatory and Safety Requirements
No. Activity:National Lead
Agency National Counterpart Agencies:
C.1 Development of legal & organisationalframework
AGC/AELB MOFA, MOSTI, KDN, AELB, ST, JAS, DOSH,Nuclear Malaysia, TNB & others.
C.2 Nuclear licensing & regulation AELB ST, JAS, DOSH, Nuclear Malaysia, TNB, MOFA, KPKT& others
C.3 Emergency planning AELB Nuclear Malaysia, MKN, KDN, MOSTI, TNB, AELB, ST, JAS,DOSH & others.
C.4 Safeguards & physical protection AELB Nuclear Malaysia, KDN, MOFA, MOSTI, KeTTHA, AGC, ST,MKN, AELB, TNB, & others.
8/13/2019 7 Malaysia Mazleha-technreqs Ws-smrdec2011
http://slidepdf.com/reader/full/7-malaysia-mazleha-technreqs-ws-smrdec2011 16/19
General Technical and EconomicCharacteristics•
Twin-units of NPP• Electrical capacity = 1000MWe or more• Power generation cost of NPP:
• less than 60% is desirable, as compared to most competitive
cost of generation from alternative plants, especially natural gas• 80-90% is tolerable
• Proven Technology• Safety & Security•
Costs
SOURCE : http://etp.pemandu.gov.my/About_ETP-@-Overview_of_ETP.aspx
8/13/2019 7 Malaysia Mazleha-technreqs Ws-smrdec2011
http://slidepdf.com/reader/full/7-malaysia-mazleha-technreqs-ws-smrdec2011 17/19
Associated Services and Supports
•
NPP project suppliers should involve user country in thearea of construction, manufacturing of regular equipmentand O&M
• Radioactive Waste Management
8/13/2019 7 Malaysia Mazleha-technreqs Ws-smrdec2011
http://slidepdf.com/reader/full/7-malaysia-mazleha-technreqs-ws-smrdec2011 18/19
Conclusion
•
Prospect for SMR unlikely in near term• Not yet proven technology• Might not meet demand• Maybe for future to meet peak demands or non-power
applications• To participate in R&D, technology development, knowledge
acquisition• Our priority now is capacity building, technology support
development, knowledge management• Impending retirements of experienced staffs• Knowledge gap• Lack of interest in S&T
8/13/2019 7 Malaysia Mazleha-technreqs Ws-smrdec2011
http://slidepdf.com/reader/full/7-malaysia-mazleha-technreqs-ws-smrdec2011 19/19
Mazleha MaskinNuclear Power DivisionMalaysian Nuclear Agency (Nuclear Malaysia)Bangi, 43000 Kajang, Selangor, Malaysia
E-mail: [email protected] Telephone: +60-3-8925-0510Facsimile: +60-3-8925-0755