seafield selangor 2013 m3(a)
TRANSCRIPT
-
8/13/2019 SEAFIELD SELANGOR 2013 M3(A)
1/5
STPM 950/3 (2013)
MARKING SCHEME
No. Solution Marks
1 (a)
(i) The balance after 10 years,
08.0
108.01
10
10 xA
(ii) The balance after 20 years,
10
10
20 08.0108.0
108.01
xA
(iii) The balance after 40 years,
08.0
108.0130008.0108.01
08.0
108.01 20
201010
40 xA
08.0
108.0130008.0108.0
108.01
20
30
10
x
(b)
10000008.0
108.0130008.01
08.0
108.01 20
3010
x
82.591
1000005893.137287733.145
x
x
The value ofxis RM591.82.
B1
B1
M1A1
M1
A1
6 marks
2 (a) 2901 p
p
0109090
2
pp
pp
8
09
q
pp
Hence, equilibrium quantity is 8 units and equilibrium price is
RM9.
(b)
M1
M1
A1
A1A1
D1
D1
D1
8 marks
q
p
8
1 pq
290
p
q
0 1 9 45
-
8/13/2019 SEAFIELD SELANGOR 2013 M3(A)
2/5
STPM950/3 (2013) 2
3 (a) The initial basic feasible solution is:
0,200,120,0,04321 Zxxxx .
(b)
Basic 1x 2x 3x 4x Z Solution
2x 1 1/8 0 0 15
4x 45/4 0 -5/8 1 0 125
Z 0 0 1/2 0 1 60
Optimal solution is 60,125,0,15,04321 Zxxxx
B1
B1
B1
B2
5 marks
4 (a)
(b)
Path Total Duration (days)
A-B-D-G-H 5+8+3+4+9 = 29
A-B-E-D1-G-H 5+8+10+0+4+9 = 36
A-B-E-D2-F-H 5+8+10+0+6+9 = 38A-C-F-H 5+3+6+9 = 23
Critical path is A-B-E-D2-F-H and minimum time required is 38
days.
D3
M1
A1
B1B1
7 marks
5(a) Economic order quantity =
05.0
256002
units775
6.774
(b) Number of orders per year =775
52600
orders41
26.40
(c) Total weekly cost = 25775
60005.0
2
7756003
= RM 1838.73
M1
A1
M1
A1
B2M1
A1
8 marks
A
B
C
D3
24 7
E10
3
8
6
3
F
5
G
4
6
18
5
H
9
D1
D2
-
8/13/2019 SEAFIELD SELANGOR 2013 M3(A)
3/5
STPM950/3 (2013) 3
6
614
153
(a) Minimax pure strategy for B is to play column 1.
Value of the game = 45.035.0
5.3 (b) (i) Let As strategy be pp 1 .Bs strategy As expected pay-off
Column 1 41431 pppy Column 2 1615
2 pppy
Column 3 67163 pppy Using graphical method,
At the maximin point,
13
7
6716
p
pp
Hence, the optimal mixed strategy for A is to play row 1 with
probability13
7and row 2 with probability
13
6.
(ii) Value of the game =13
291
13
76
.
B1
M1
A1
M1
A1
D2
M1
A1
M1A1
11 marks
7 (a) Revenue function, 22400 qqr
Profit function, 40042.02400 22 qqqqP 4003962.2
2 qq
(b) 03964.4 qdq
dP
90q
04.42
2
dq
Pd
Hence, profit is maximum when the level of output is 90 units.
(c) At maximum profit, 90q .
Price, 220RM902400 p
B1M1
A1
M1
A1
A1
M1A1
6
5
4
3
2
1
0
1
p1
1y
2y
3y
-
8/13/2019 SEAFIELD SELANGOR 2013 M3(A)
4/5
STPM950/3 (2013) 4
(d) Maximum profit 40090396902.2 2 17420RM
(e) With a tax of RM22 per unit on the product,
400262.0
2240042.0
2
2
qq
qqqc
400262.02400 22 qqqqP
4003742.2 2 qq
03744.4 qdq
dP
85q
04.42
2
dq
Pd
Profit is maximum when the level of output is 85 units.
New price, 230RM852400 p
M1
A1
B1
B1
M1
M1A115 marks
8. (a)
D1Sequence
D1All arrows
D1All correct
B1at least 5 EST correctB1all EST correct
B1at least 5 LST correct
B1all LST correct
(b) Critical activities are B, D, G, I. B1
Minimum time to complete the project is 21 days. B1
Finish
21 21
A 7
0 4
B 5
0 0
Start
0 0
C 4
7 11
D 7
5 5
E 4
12 15
H 2
16 19
F 6
5 6
G 5
12 12
I 4
17 17
J 3
11 18
Act Dur
EST LST
-
8/13/2019 SEAFIELD SELANGOR 2013 M3(A)
5/5
STPM950/3 (2013) 5
(c) Minimum project completion time is 22 days. B1
Time (day)
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22
B(5) D(4) C(2) E(3) H(3)A(3) F(3) G(5) I(3)
J(2)
8 8 8 8 8 7 7 7 7 7 7 7 5 7 7 7 8 8 8 8 8 6
J
A
F
G I
B D
C E H
Gantt chart:
D1precedence relationship
D1number of workers not more than 8 men/day
D1complete in 22 days
Resource histogram:
D2his values
8
7
6
5
4
3
2
1
0Resourcerequirement(men/day)