Page 1: Kerja-kerja Memasang Formwork Dan Besi Untuk Ground Beam ... · SOBIRIN, DIATAS LOT PT 20045, JALAN 3/15, BANDAR TASIK PUTERI 48020 RAWANG, SELANGOR. Pinnacle Urban Engineering Kerja-kerja

PROJEK PEMBINAAN SURAU AS-SOBIRIN, DIATAS LOT PT 20045,

JALAN 3/15, BANDAR TASIK PUTERI 48020 RAWANG, SELANGOR.

Pinnacle Urban Engineering

Sebahagian Lubang Pad Footing Siap Dengan Hardcore

Kerja-kerja Memasang Formwork Dan Besi Untuk Ground Beam

Semua Gambar Dikemaskini Sehingga 11/10/2009

Page 2: Kerja-kerja Memasang Formwork Dan Besi Untuk Ground Beam ... · SOBIRIN, DIATAS LOT PT 20045, JALAN 3/15, BANDAR TASIK PUTERI 48020 RAWANG, SELANGOR. Pinnacle Urban Engineering Kerja-kerja

PROJEK PEMBINAAN SURAU AS-SOBIRIN, DIATAS LOT PT 20045,

JALAN 3/15, BANDAR TASIK PUTERI 48020 RAWANG, SELANGOR.

Pinnacle Urban Engineering

Sebahagian Reinforcement UntukStump Siap Diikat

Sebahagian Lubang Pad Footing Siap Dengan Hardcore

Semua Gambar Dikemaskini Sehingga 11/10/2009

Kerja-kerja Memasang Formwork Dan Besi Untuk Ground Beam

Page 3: Kerja-kerja Memasang Formwork Dan Besi Untuk Ground Beam ... · SOBIRIN, DIATAS LOT PT 20045, JALAN 3/15, BANDAR TASIK PUTERI 48020 RAWANG, SELANGOR. Pinnacle Urban Engineering Kerja-kerja

PROJEK PEMBINAAN SURAU AS-SOBIRIN, DIATAS LOT PT 20045,

JALAN 3/15, BANDAR TASIK PUTERI 48020 RAWANG, SELANGOR.

Pinnacle Urban Engineering Semua Gambar Dikemaskini Sehingga 11/10/2009

Kerja-kerja Menuang Konkrit Ground Beam

Page 4: Kerja-kerja Memasang Formwork Dan Besi Untuk Ground Beam ... · SOBIRIN, DIATAS LOT PT 20045, JALAN 3/15, BANDAR TASIK PUTERI 48020 RAWANG, SELANGOR. Pinnacle Urban Engineering Kerja-kerja

PROJEK PEMBINAAN SURAU AS-SOBIRIN, DIATAS LOT PT 20045,

JALAN 3/15, BANDAR TASIK PUTERI 48020 RAWANG,

SELANGOR.

Pinnacle Urban Engineering

Kerja-kerja Menyembur Racun Anai-anai Untuk Ground Beam Dan Slab

Semua Gambar Dikemaskini Sehingga 11/10/2009

Page 5: Kerja-kerja Memasang Formwork Dan Besi Untuk Ground Beam ... · SOBIRIN, DIATAS LOT PT 20045, JALAN 3/15, BANDAR TASIK PUTERI 48020 RAWANG, SELANGOR. Pinnacle Urban Engineering Kerja-kerja

PROJEK PEMBINAAN SURAU AS-SOBIRIN, DIATAS LOT PT 20045,

JALAN 3/15, BANDAR TASIK PUTERI 48020 RAWANG,

SELANGOR.

Pinnacle Urban Engineering

Kerja-kerja Menuang Konkrit Ke Pad footing

Semua Gambar Dikemaskini Sehingga 11/10/2009

Kerja-kerja Menuang Konkrit Ground Slab

Page 6: Kerja-kerja Memasang Formwork Dan Besi Untuk Ground Beam ... · SOBIRIN, DIATAS LOT PT 20045, JALAN 3/15, BANDAR TASIK PUTERI 48020 RAWANG, SELANGOR. Pinnacle Urban Engineering Kerja-kerja

PROJEK PEMBINAAN SURAU AS-SOBIRIN, DIATAS LOT PT 20045,

JALAN 3/15, BANDAR TASIK PUTERI 48020 RAWANG, SELANGOR.

Pinnacle Urban Engineering Semua Gambar Dikemaskini Sehingga 11/10/2009

Kerja-kerja Menuang Konkrit Ground Slab

Page 7: Kerja-kerja Memasang Formwork Dan Besi Untuk Ground Beam ... · SOBIRIN, DIATAS LOT PT 20045, JALAN 3/15, BANDAR TASIK PUTERI 48020 RAWANG, SELANGOR. Pinnacle Urban Engineering Kerja-kerja

PROJEK PEMBINAAN SURAU AS-SOBIRIN, DIATAS LOT PT 20045,

JALAN 3/15, BANDAR TASIK PUTERI 48020 RAWANG, SELANGOR.

Pinnacle Urban Engineering

Kerja-kerja Memasang Formwork Dan Besi Untuk Tiang

Semua Gambar Dikemaskini Sehingga 11/10/2009

Page 8: Kerja-kerja Memasang Formwork Dan Besi Untuk Ground Beam ... · SOBIRIN, DIATAS LOT PT 20045, JALAN 3/15, BANDAR TASIK PUTERI 48020 RAWANG, SELANGOR. Pinnacle Urban Engineering Kerja-kerja

PROJEK PEMBINAAN SURAU AS-SOBIRIN, DIATAS LOT PT 20045,

JALAN 3/15, BANDAR TASIK PUTERI 48020 RAWANG, SELANGOR.

Pinnacle Urban Engineering

Kerja-kerja Memasang FormworkUntuk Ground Beam

Semua Gambar Dikemaskini Sehingga 11/10/2009

Kerja-kerja Menuang Konkrit Roof Beam

Page 9: Kerja-kerja Memasang Formwork Dan Besi Untuk Ground Beam ... · SOBIRIN, DIATAS LOT PT 20045, JALAN 3/15, BANDAR TASIK PUTERI 48020 RAWANG, SELANGOR. Pinnacle Urban Engineering Kerja-kerja

PROJEK PEMBINAAN SURAU AS-SOBIRIN, DIATAS LOT PT 20045,

JALAN 3/15, BANDAR TASIK PUTERI 48020 RAWANG, SELANGOR.

Pinnacle Urban Engineering

Kerja-kerja Memasang FormworkUntuk Ground Beam

Semua Gambar Dikemaskini Sehingga 11/10/2009

Kerja-kerja Menuang Konkrit Untuk Upper Roof Beam

Page 10: Kerja-kerja Memasang Formwork Dan Besi Untuk Ground Beam ... · SOBIRIN, DIATAS LOT PT 20045, JALAN 3/15, BANDAR TASIK PUTERI 48020 RAWANG, SELANGOR. Pinnacle Urban Engineering Kerja-kerja

PROJEK PEMBINAAN SURAU AS-SOBIRIN, DIATAS LOT PT 20045,

JALAN 3/15, BANDAR TASIK PUTERI 48020 RAWANG, SELANGOR.

Pinnacle Urban Engineering

Kerja-kerja Memasang FormworkUntuk Ground Beam

Semua Gambar Dikemaskini Sehingga 11/10/2009

Kerja-kerja Menuang Konkrit Untuk Lintol