KEMENTERIAN PENDIDIKAN TINGGI POLITEKNIK JELI KELANTAN DOKUMEN SEBUTHARGA PROJEK : KERJA-KERJA PENYENGGARAAN BERKALA BAGI SISTEM PENYAMAN UDARA DAN PENGUDARAAN MEKANIKAL SERTA KERJA-KERJA BERKAITAN DI POLITEKNIK JELI, KELANTAN. (MULAI OKTOBER 2015 HINGGA OKTOBER 2016) NO. SEBUTHARGA : PJK(S)/SH/04/2015 PENGARAH, POLITEKNIK JELI JALAN RAYA TIMUR-BARAT 17600 JELI, KELANTAN

Upload: nguyenminh

Post on 01-Feb-2018

315 views

Category:

Documents


11 download

TRANSCRIPT

Page 1: DOKUMEN SEBUTHARGA - pjk.edu.my · PDF fileBerjaya seperti di lampiran beserta dengan *Surat Setuju Terima/Borang Perjanjian Inden Kerja yang telah ditandatangani di mana ia ... SUB-SEWA

KEMENTERIAN PENDIDIKAN TINGGI POLITEKNIK JELI KELANTAN

DOKUMEN SEBUTHARGA

PROJEK : KERJA-KERJA PENYENGGARAAN

BERKALA BAGI SISTEM PENYAMAN UDARA DAN PENGUDARAAN MEKANIKAL SERTA KERJA-KERJA BERKAITAN DI POLITEKNIK JELI, KELANTAN. (MULAI OKTOBER 2015 HINGGA OKTOBER 2016)

NO. SEBUTHARGA

: PJK(S)/SH/04/2015

PENGARAH, POLITEKNIK JELI

JALAN RAYA TIMUR-BARAT 17600 JELI, KELANTAN

Page 2: DOKUMEN SEBUTHARGA - pjk.edu.my · PDF fileBerjaya seperti di lampiran beserta dengan *Surat Setuju Terima/Borang Perjanjian Inden Kerja yang telah ditandatangani di mana ia ... SUB-SEWA

KANDUNGAN

NO. ITEM

1. ARAHAN KEPADA PENYEBUTHARGA

2. SYARAT-SYARAT SEBUTHARGA

3. BORANG SEBUTHARGA

4. SURAT AKUAN PEMBIDA

5. SPESIFIKASI AM

SPESIFIKASI TEKNIKAL

6. JADUAL SEBUTHARGA

Jadual Sebutharga

Lampiran A : Chilled Water System (Building Automation

System - BAS)

Lampiran B : Water-Cooled Package Unit Air Conditioning

Lampiran C : Air-Cooled Split Unit Air Conditioning

Lampiran D : Split Unit Aircond

Lampiran E : Exhaust Fan

7. LAMPIRAN

Page 3: DOKUMEN SEBUTHARGA - pjk.edu.my · PDF fileBerjaya seperti di lampiran beserta dengan *Surat Setuju Terima/Borang Perjanjian Inden Kerja yang telah ditandatangani di mana ia ... SUB-SEWA

SENARAI SEMAKAN

(BEKALAN/PERKHIDMATAN/KERJA)

Sila tandakan √ Bagi Dokumen-dokumenYang Disertakan.

Bil. Perkara/Dokumen

Untuk

Ditanda

Oleh Syarikat

Untuk Ditanda

Oleh Jawatankuasa

Pembuka Sebut

Harga

1. Salinan Sijil Akuan Pendaftaran Dari

Kementerian Kewangan (Bekalan/Perkhidmatan)

2. Salinan Sijil Akuan Bumiputera Dari

Kementerian Kewangan (Bekalan/Perkhidmatan)

3. Salinan Sijil Akuan Pembuat Dari Kementerian

Kewangan (Bekalan/Perkhidmatan)

4. Salinan Perakuan Pendaftaran Dari CIDB (Kerja)

5. Salinan Sijil Perolehan Kerja Kerajaan Dari

CIDB (Kerja)

6. Salinan Sijil Taraf Bumiputera Dari Pusat

Khidmat Kontraktor (Kerja)

7. Borang Sebut Harga Telah Diisi Dengan Lengkap

(termasuk nilai tawaran dan tempoh siap) dan

Ditandatangani

8. Borang Maklumat Penyebut Harga

9. Pematuhan Kepada Spesifikasi

10. Borang Penyerahan Contoh Dan Katalog (jika

berkaitan)

11. Cadangan Penyelenggaraan/Penyenggaraan

(jika perlu)

12. Senarai Kakitangan Teknikal (jika berkaitan)

Page 4: DOKUMEN SEBUTHARGA - pjk.edu.my · PDF fileBerjaya seperti di lampiran beserta dengan *Surat Setuju Terima/Borang Perjanjian Inden Kerja yang telah ditandatangani di mana ia ... SUB-SEWA

Bil. Perkara/Dokumen

Untuk

Ditanda

Oleh Syarikat

Untuk Ditanda

Oleh Jawatankuasa

Pembuka Sebut

Harga

13. Salinan Penyata Bulanan Akaun Bank bagi Tiga

(3) Bulan Terakhir

14. Lain-lain Sekiranya Ada

PENGESAHAN OLEH SYARIKAT

Dengan ini saya mengesahkan bahawa saya

telah membaca dan memahami semua syarat-

syarat dan terma yang dinyatakan di dalam

dokumen sebut harga. Semua maklumat yang

dikemukakan adalah benar.

UNTUK KEGUNAAN JABATAN

Jawatankuasa Pembuka Sebut Harga

mengesahkan penerimaan dokumen bertanda

kecuali bagi perkara bil. ................... (jika ada).

Tandatangan

: Tandatangan :

Nama : Nama

:

Jawatan

: Jawatan

:

Tarikh

: Tarikh

:

Tandatangan

:

Nama

:

Jawatan

:

Tarikh

:

Page 5: DOKUMEN SEBUTHARGA - pjk.edu.my · PDF fileBerjaya seperti di lampiran beserta dengan *Surat Setuju Terima/Borang Perjanjian Inden Kerja yang telah ditandatangani di mana ia ... SUB-SEWA

ARAHAN KEPADA PENYEBUTHARGA

1. HAK POLITEKNIK JELI KELANTAN (PJK) UNTUK MENERIMA /

MENOLAK SEBUTHARGA

Politeknik Jeli Kelantan (PJK) adalah tidak terikat untuk menerima Sebutharga yang

terendah atau mana-mana Sebutharga atau memberi apa-apa sebab di atas penolakan

sesuatu Sebutharga. Keputusan Jawatankuasa Sebutharga adalah muktamad.

2. CARA–CARA MELENGKAPKAN DOKUMEN SEBUTHARGA

2.1. Penyediaan Sebutharga

Kontraktor adalah dikehendaki mengisi segala maklumat berikut dengan

sepenuhnya:-

a) Harga dan tandatangan Kontraktor di Ringkasan Sebutharga,

b) Harga, tempoh dan tandatangan dalam Borang Sebutharga,

c) Senarai Kerja Dalam Tangan,

d) Jadual Kadar Harga (Jika ada),

e) Butir–butir Spesifikasi. (Jika ada)

f) Lampiran

Jika berlaku kesilapan dalam mengisi maklumat-maklumat di atas Kontraktor

hendaklah menandatangani ringkas semua pembetulan.

2.2. Penyerahan Dokumen Sebutharga

a) Dokumen Sebutharga yang telah diisi dengan lengkap hendaklah

dimasukkan ke dalam sampul surat berlakri yang dicatatkan dengan

Bilangan Sebutharga PJK(S)/SH/04/2015 serta Tajuk Sebutharga dan

hendaklah dimasukkan ke dalam Peti Sebutharga pada atau sebelum 20

September 2015, 12.30 tengahari.

b) Jika Dokumen Sebutharga tidak diserahkan dengan tangan,

Penyebutharga hendaklah menghantar Dokumen tersebut dengan pos

supaya tiba pada atau sebelum masa dan di tempat yang ditetapkan.

c) Sebutharga yang diserahkan selepas masa yang ditetapkan, berbangkit

dari sebarang sebab, tidak akan dipertimbangkan.

Kegagalan Kontraktor mengembalikan Dokumen Sebutharga pada tarikh tutup

Sebutharga akan membolehkan sebutharga tersebut akan ditolak.

Page 6: DOKUMEN SEBUTHARGA - pjk.edu.my · PDF fileBerjaya seperti di lampiran beserta dengan *Surat Setuju Terima/Borang Perjanjian Inden Kerja yang telah ditandatangani di mana ia ... SUB-SEWA

2.3. Penjelasan Lanjut

Sekiranya terdapat maklumat dalam Dokumen Sebutharga yang tidak jelas

atau bercanggah, Kontraktor boleh menghubungi pejabat ini untuk penjelasan

lanjut.

3. PERBELANJAAN PENYEDIAAN DOKUMEN SEBUTHARGA

Semua perbelanjaan bagi penyediaan Sebutharga ini hendaklah ditanggung oleh

Penyebutharga sendiri.

4. TEMPOH SAH SEBUTHARGA

Sebutharga ini sah selama 90 hari dari tarikh tutup Sebutharga. Kontraktor tidak boleh

menarik balik Sebutharganya sebelum tamat tempoh sah Sebutharga. Pengesyoran

tindakan tatatertib akan diambil sekiranya Kontraktor menarik balik Sebutharganya

sebelum tamat tempoh sah Sebutharga.

5. PERINGATAN MENGENAI KESALAHAN RASUAH

5.1 Sebarang perbuatan atau percubaan rasuah untuk menawar atau memberi,

meminta atau menerima apa-apa suapan secara rasuah kepada dan daripada

mana-mana orang berkaitan perolehan ini merupakan suatu kesalahan jenayah

di bawah Akta Pencegahan Rasuah 1997.

5.2 Sekiranya mana-mana pihak ada menawar atau memberi apa-apa suapan

kepada mana-mana anggota pentadbiran awam, maka pihak yang ditawar atau

diberi suapan dikehendaki membuat aduan dengan segera ke pejabat

Suruhanjaya Pencegah Rasuah Malaysia (SPRM) atau di balai polis yang

berhampiran. Kegagalan berbuat demikian adalah merupakan satu kesalahan

di bawah Akta Pencegahan Rasuah 1997.

5.3 Tanpa prejudis kepada tindakan-tindakan lain, tindakan tatatertib terhadap

anggota perkhidmatan awam dan menyenaraihitamkan kontraktor atau

pembekal boleh diambil sekiranya pihak-pihak terlibat dengan kesalahan

rasuah di bawah Akta Pencegahan Rasuah.

5.4 Mana-mana kontraktor atau pembekal yang membuat tuntutan bayaran

berkaitan perolehan ini walaupun tiada kerja dibuat atau tiada barangan

dibekalkan mengikut spesifikasi yang ditetapkan atau tiada perkhidmatan

diberi dan mana-mana anggota perkhidmatan awam yang mengesahkan

tuntutan berkenaan adalah melakukan kesalahan di bawah Akta Pencegahan

Rasuah 1997.

Page 7: DOKUMEN SEBUTHARGA - pjk.edu.my · PDF fileBerjaya seperti di lampiran beserta dengan *Surat Setuju Terima/Borang Perjanjian Inden Kerja yang telah ditandatangani di mana ia ... SUB-SEWA

6. ‘INTEGRITY PACT’

6.1 Penyebutharga wajib mengemukakan surat akuan pembida seperti di lampiran

bersama-sama dengan Dokumen Sebutharga di mana ia berwaad untuk tidak

akan menawarkan atau memberi rasuah kepada mana-mana individu lain

sebagai sogokan untuk dipilih dalam tawaran tersebut. Wakil syarikat yang

menandatangani Surat Akuan Pembida hendaklah juga melampirkan Surat

Perwakilan Kuasa menandatangani bagi pihak Syarikat.

6.2 Surat Akuan Pembida tersebut adalah menjadi salah satu dokumen wajib

dalam penilaian sebutharga peringkat pertama. Sekiranya pembida gagal

mengemukakan Surat Akuan tersebut yang telah ditandatangani oleh pegawai

syarikat bertauliah, pembida tersebut akan dinilai sebagai gagal dalam

penilaian peringkat pertama ( gagal mengemukakan dokumen wajib ) dan

penilaian seterusnya tidak akan dilaksanakan.

6.3 Kontraktor yang Berjaya wajib mengemukakan Surat Akuan Pembida

Berjaya seperti di lampiran beserta dengan *Surat Setuju Terima/Borang

Perjanjian Inden Kerja yang telah ditandatangani di mana ia berwaad tidak

akan memberi rasuah sebagai ganjaran kerana mendapatkan kontrak. Wakil

Syarikat yang menandatangani Surat Akuan Pembida Berjaya hendaklah juga

melampirkan surat perwakilan kuasa menandatangani bagi pihak syarikat.

Surat Akuan ini akan menjadi sebahagian daripada Perjanjian Sebutharga.

Page 8: DOKUMEN SEBUTHARGA - pjk.edu.my · PDF fileBerjaya seperti di lampiran beserta dengan *Surat Setuju Terima/Borang Perjanjian Inden Kerja yang telah ditandatangani di mana ia ... SUB-SEWA

SYARAT-SYARAT SEBUTHARGA UNTUK KERJA

1. PEMERIKSAAN TAPAK BINA

Kontraktor adalah dinasihatkan untuk memeriksa dan meneliti Tapakbina dan

sekitarnya, bentuk dan jenis Tapak bina, takat dan jenis kerja, bahan dan barang yang

perlu bagi menyiapkan Kerja, cara-cara perhubungan dan laluan masuk ke Tapakbina

dan hendaklah mendapatkan sendiri segala maklumat yang perlu tentang risiko, luar

jangkaan dan segala hal-keadaan yang mempengaruhi dan menjejas Sebutharganya.

Sebarang tuntutan yang timbul akibat daripada kegagalan Kontraktor mematuhi

kehendak ini tidak akan dipertimbangkan.

2. INSURANS / BON PERLAKSANAAN

2.1 Kontraktor hendaklah atas nama bersama Kerajaan Malaysia dan Kontraktor

mengambil perkara-perkara seperti berikut:-

a) Bon Perlaksanaan sebanyak 5% daripada jumlah nilai Sebutharga, jika

nilai yang tawarkan melebihi Rm 50,000.00. (Kontraktor dibenarkan

membuat pilihan untuk mengemukakan Jaminan Bank atau Jaminan

Insurans atau memilih dikenakan Wang Jaminan Perlaksanaan).

b) Polisi Insuran Tanggungan Awam (iaitu insurans terhadap bencana

kepada orang dan kerosakan kepada harta), dan

c) Nombor-nombor pendaftaran di bawah Skim Keselamatan Sosial

Pekerja (PERKESO). bagi tempoh perlaksanaan kerja Inden ini.

2.2 Kontraktor hendaklah mengemukakan kepada Pegawai Inden semua polisi

insurans, Bon Perlaksanaan dan Nombor Kod Pendaftaran dengan PERKESO

yang tersebut di atas sebelum memulakan Kerja. Bagaimanapun untuk tujuan

memulakan Kerja sahaja Nota-nota Perlindungan dan resit-resit bayaran

premium adalah mencukupi. Sekiranya Kontraktor gagal mengemukakan

semua polisi Insurans selepas tempoh sah Nota-nota Perlindungan, tanpa

sebarang sebab yang munasabah, Pegawai Inden berhak mengambil tindakan

seperti di bawah Fasal 10 (d).

3. PERATURAN PERLAKSANAAN KERJA

Kerja-kerja yang dilaksanakan hendaklah mematuhi Spesifikasi, pelan-pelan, butir-

butir kerja dalam Ringkasan Sebutharga dan Syarat–syarat yang dinyatakan dalam

Dokumen Sebutharga ini dan arahan Pegawai Inden atau Wakilnya.

Page 9: DOKUMEN SEBUTHARGA - pjk.edu.my · PDF fileBerjaya seperti di lampiran beserta dengan *Surat Setuju Terima/Borang Perjanjian Inden Kerja yang telah ditandatangani di mana ia ... SUB-SEWA

4. KEGAGALAN KONTRAKTOR MEMULAKAN KERJA

Sekiranya Kontraktor gagal memulakan kerja selepas 7 hari dari tarikh akhir tempoh

mula kerja yang dinyatakan dalam Inden Kerja, tanpa sebab-sebab yang munasabah,

Inden Kerja akan dibatalkan oleh Pegawai Inden dan tindakan tatatertib akan diambil

terhadap Kontraktor.

5. SUB-SEWA DAN MENYERAHAK KERJA.

Kontraktor tidak dibenarkan mengsub-sewakan Kerja kepada kontraktor-kontraktor

lain. Kontraktor tidak boleh menyerahak apa-apa faedah di bawah Inden Kerja ini

tanpa terlebih dahulu mendapatkan persetujuan bertulis dari Pegawai Inden.

6. PENOLAKAN BAHAN, BARANG DAN KERJA OLEH PEGAWAI INDEN.

Pegawai Inden atau Wakilnya berhak menolak bahan, barang dan kerja-kerja yang

tidak menepati Spesifikasi. Bahan, barang dan kerja-kerja yang ditolak hendaklah

diganti dan sebarang kos tambahan yang terlibat hendaklah ditanggung oleh

Kontraktor sendiri.

7. RINGKASAN SEBUTHARGA

7.1 Ringkasan Sebutharga hendaklah menjadi sebahagian daripada Borang

Sebutharga ini dan hendaklah menjadi asas Jumlah Harga Sebutharga.

7.2 Harga–harga dalam Ringkasan Sebutharga hendaklah mengambil kira semua

kos termasuk kos pengangkutan, cukai, duti, bayaran dan caj-caj lain yang

perlu dan berkaitan bagi penyiapan Kerja dengan sempurnanya.

7.3 Tiada sebarang tuntutan akan dilayan bagi pelarasan harga akibat daripada

perubahan kos buruh, bahan–bahan dan semua duti dan cukai Kerajaan,

samada dalam tempoh sah Sebutharga atau dalam tempoh Kerja.

7.4 Harga–harga dalam Ringkasan Sebutharga yang dikemukakan oleh Kontraktor

hendaklah tertakluk kepada persetujuan sebelumnya daripada Pegawai Inden

tentang kemunasabahannya. Persetujuan sebelumnya itu dan apa–apa

pelarasan kemudiannya kepada harga–harga dalam Ringkasan Sebutharga

hendaklah dibuat sebelum Inden Kerja dikeluarkan.

7.5 Apa-apa perlarasan harga dalam Ringkasan Sebutharga menurut perenggan

(iv) tersebut di atas dan apa–apa kesilapan hisab dalam Ringkasan Sebutharga

hendaklah dilaras dan diperbetulkan sebelum Inden Kerja dikeluarkan. Jumlah

amaun yang dilaraskan hendaklah sama dengan amaun jumlah harga pukal

dalam Borang Sebutharga. Amaun jumlah harga pukal dalam Borang

Sebutharga hendaklah tetap tidak berubah.

Page 10: DOKUMEN SEBUTHARGA - pjk.edu.my · PDF fileBerjaya seperti di lampiran beserta dengan *Surat Setuju Terima/Borang Perjanjian Inden Kerja yang telah ditandatangani di mana ia ... SUB-SEWA

8. PERCANGGAHAN DALAM DOKUMEN SEBUTHARGA

Jika Kontraktor mendapati apa–apa percanggahan dalam Dokumen Sebutharga, dia

hendaklah merujuk kepada Pegawai Inden untuk mendapatkan keputusan.

9. BAYARAN BERPERINGKAT

Bagi Kerja yang bernilai melebihi RM25,000.00, satu kali bayaran berperingkat

dibenarkan setelah nilai Kerja-kerja yang disiapkan melebihi 50% dari nilai

Sebutharga tersebut.

10. KEGAGALAN KONTRAKTOR MENYIAPKAN KERJA DAN PENAMATAN

PER-LANTIKAN KONTRAKTOR

Pegawai Inden berhak membatalkan Inden Kerja sekiranya Kontraktor berada dalam

keadaan berikut dan setelah menerima surat amaran daripada Pegawai Inden.

a) Sekiranya Kontraktor masih gagal menyiapkan Kerja dalam tempoh masa

yang telah ditetapkan;

b) Kemajuan Kerja terlalu lembab tanpa apa–apa sebab yang munasabah;

c) Penggantungan perlaksanaan seluruh atau sebahagian Kerja, tanpa apa–apa

sebab yang munasabah;

d) Tidak mematuhi arahan Pegawai Inden tanpa apa–apa alasan yang munasabah;

dan

e) Apabila Kontraktor diisytiharkan bankrap oleh pihak yang sah.

11. KERJA PERUBAHAN

11.1 Pegawai Inden boleh menurut budi bicaranya mengeluarkan arahan–arahan

yang berkehendakkan sesuatu perubahan kerja dengan secara bertulis. Tiada

apa–apa perubahan yang dikeluarkan oleh Pegawai Inden atau yang disahkan

kemudian oleh Pegawai Inden boleh membatalkan Sebutharga ini.

11.2 Semua kerja perubahan dan/atau tambahan yang diluluskan oleh Pegawai

Inden akan diukur atau dinilai menggunakan kadar harga yang ada dalam

Senarai Kuantiti/Ringkasan Sebutharga. Jika tidak terdapat sebarang kadar

harga yang bersesuaian kadar harga yang dipersetujui oleh Pegawai Inden dan

kontraktor hendaklah digunakan.

12. PEMATUHAN KEPADA UNDANG–UNDANG OLEH KONTRAKTOR

Kontraktor hendaklah mematuhi segala kehendak Undang–Undang Kecil dan

Undang-undang Berkanun dalam Malaysia semasa perlaksanaan Kerja. Kontraktor

Page 11: DOKUMEN SEBUTHARGA - pjk.edu.my · PDF fileBerjaya seperti di lampiran beserta dengan *Surat Setuju Terima/Borang Perjanjian Inden Kerja yang telah ditandatangani di mana ia ... SUB-SEWA

tidak berhak menuntut sebarang kos dan bayaran tambahan kerana pematuhannya

dengan Syarat–syarat ini.

13. PERATURAN MEMBAYAR SELEPAS SIAP

Bayaran sepenuhnya hanya akan dibayar setelah Kontraktor menyiapkan Kerja

dengan sempurnanya dan mengembalikan Inden Kerja Asal.

14. TEMPOH TANGGUNGAN KECACATAN

Tempoh Tanggungan Kecacatan bagi Kerja yang bernilai di antara RM10,000.00

hingga RM200,000.00 adalah selama Enam (6) Bulan dari tarikh Kerja diperakukan

siap.

15. TARIKH TUTUP TAWARAN

Tarikh Tutup Sebutharga seperti yang dinyatakan dalam surat pelawaan sebutharga

pada atau sebelum 12.30 tengahari. Dokumen Sebutharga yang telah lengkap diisi

hendaklah dimasukkan ke dalam Peti Sebutharga di pejabat 20hb September 2015.

Page 12: DOKUMEN SEBUTHARGA - pjk.edu.my · PDF fileBerjaya seperti di lampiran beserta dengan *Surat Setuju Terima/Borang Perjanjian Inden Kerja yang telah ditandatangani di mana ia ... SUB-SEWA

BORANG SEBUTHARGA

SEBUTHARGA PJK(S)/SH/04/2015

PENGARAH

POLITEKNIK JELI KELANTAN

JALAN RAYA TIMUR-BARAT

17600 JELI

KELANTAN.

Tuan,

Sebutharga untuk KERJA-KERJA PENYENGGARAAN BERKALA BAGI SISTEM

PENYAMAN UDARA DAN PENGUDARAAN MEKANIKAL SERTA KERJA-

KERJA BERKAITAN DI POLITEKNIK JELI, KELANTAN. ( MULAI OKTOBER

2015 HINGGA OKTOBER 2016 )

Dibawah dan tertakluk kepada Arahan Kepada Pentender, Syarat-syarat Am Sebut Harga,

Spesifikasi Kerja dan Pelan-pelan, saya yang menandatangani di bawah ini adalah dengan ini

menawarkan untuk melaksana dan menyiapkan kerja tersebut bagi jumlah wang pukal

sebanyak :

Ringgit Malaysia : …………………………………………………………....

……………………………………………………..…. ( RM ..............................................)

2. Saya bersetuju menyiapkan kerja-kerja ini dalam masa ..…..... minggu dari tarikh

tempoh mula kerja seperti yang ditetapkan di bawah Fasal 2 Borang Inden Kerja.

Bertarikh pada ........... haribulan ............... 2015

(Tandatangan Kontraktor) (Tandatangan Saksi)

Nama Penuh : Nama Penuh :

No. K/P : No. K/P :

Alamat : Alamat :

Atas sifat:

(Meteri atau Cop Kontraktor)

Tarikh :

Page 13: DOKUMEN SEBUTHARGA - pjk.edu.my · PDF fileBerjaya seperti di lampiran beserta dengan *Surat Setuju Terima/Borang Perjanjian Inden Kerja yang telah ditandatangani di mana ia ... SUB-SEWA

SURAT AKUAN PEMBIDA

Bagi

KERJA-KERJA PENYENGGARAAN BERKALA BAGI SISTEM PENYAMAN

UDARA DAN PENGUDARAAN MEKANIKAL SERTA KERJA-KERJA

BERKAITAN DI POLITEKNIK JELI, KELANTAN.

( MULAI OKTOBER 2015 HINGGA OKTOBER 2016 )

NO. SEBUT HARGA:

PJK(S)/SH/04/2015

Saya, ___________________________________ nombor K.P. _________________ yang

mewakili __________________________________________________________ nombor

Pendaftaran ________________________ (MOF/PKK/CIDB/ROS/ROC/ROB) dengan ini

mengisytiharkan bahawa saya atau mana-mana individu yang mewakili syarikat ini tidak

akan menawar atau memberi rasuah kepada mana-mana individu dalam Politeknik Jeli

Kelantan (PJK) atau mana-mana individu lain, sebagai sogokan untuk dipilih dalam

sebutharga seperti di atas. Bersama-sama ini dilampirkan Surat Perwakilan Kuasa bagi saya

mewakili syarikat seperti tercatat di atas untuk membuat perisytiharan ini (jika berkaitan).

2. Sekiranya saya atau mana- mana individu yang mewakili syarikat ini didapati

bersalah menawar atau memberi rasuah kepada mana-mana individu dalam PJK atau mana-

mana individu lain sebagai sogokan untuk dipilih dalam sebutharga seperti di atas, maka saya

sebagai wakil syarikat bersetuju tindakan-tindakan berikut diambil :

2.1 penarikan balik tawaran kontrak bagi sebutharga di atas; atau

2.2 penamatan kontrak bagi sebutharga di atas; dan

2.3 lain-lain tindakan tatatertib mengikut Peraturan Perolehan Kerajaan.

3. Sekiranya terdapat mana-mana individu cuba meminta rasuah daripada saya atau

mana-mana individu yang berkaitan dengan syarikat ini sebagai sogokan untuk dipilih dalam

sebutharga seperti di atas, maka saya berjanji akan dengan segera melaporkan perbuatan

tersebut kepada pejabat Suruhanjaya Pencegahan Rasuah Malaysia (SPRM) atau balai polis

yang berhampiran.

Yang Benar,

................................

(Nama dan No. KP)

Cop Syarikat :

Page 14: DOKUMEN SEBUTHARGA - pjk.edu.my · PDF fileBerjaya seperti di lampiran beserta dengan *Surat Setuju Terima/Borang Perjanjian Inden Kerja yang telah ditandatangani di mana ia ... SUB-SEWA

SPESIFIKASI KERJA

Menyediakan satu ( 1 ) orang pekerja supaya berada di kawasan lokasi kerja sepanjang waktu pejabat KERAJAAN dan pada masa majlis rasmi berlangsung di Politeknik Jeli Kelantan termasuk hari cuti tanpa mengenakan sebarang caj bayaran, dan juga untuk 'on' dan 'off' sistem penyaman udara setiap hari (hari bekerja)

Memastikan semua pekerja memakai pakaian seragam sepanjang waktu bekerja dan menghormati peraturan Politeknik Jeli Kelantan

1.0 AM

Spesifikasi Kerja yang perlu dilaksanakan oleh Kontraktor adalah membekal bahan, perkakasan/peralatan/mesin, pekerja/buruh dan kelengkapan yang diperlukan bagi Kerja-kerja Penyenggaraan Berkala Bagi Sistem Penyaman Udara Dan Pengudaraan Mekanikal Serta Kerja-kerja Berkaitan Di Politeknik Jeli Kelantan.

Semua kerja yang perlu dilaksanakan hendaklah mengikut spesifikasi, amalan dan piawaian kejuruteraan yang baik.

2.0 MUTU KERJA DAN BAHAN

Kerja hendaklah dilaksanakan oleh pekerja mahir dalam pemeriksaan, penyenggaraan dan pembaikian Sistem Penyaman Udara dan Pengudaraan Mekanikal serta kerja-kerja berkaitan, dan dilaksanakan mengikut amalan kejuruteraan terbaik. Kerja dilaksanakan dengan gangguan minimum. Sekiranya perlu oleh Politeknik Jeli Kelantan, Kontraktor hendaklah meletakkan tanda ‘AMARAN’. Kontraktor hendaklah mengeluarkan sisa buangan kerja yang tidak diperlukan dari tapak. Bahan yang dibekalkan berkaitan dengan kerja ini hendaklah baru dan belum digunakan, dan hendaklah amnya mempunyai kualiti terbaik sepertimana jaminan pengeluar dan mematuhi Standard Malaysia atau setaraf.

3.0 PENYELIAAN

Kontraktor hendaklah menyediakan seorang Penyelia tetap dan diterima oleh Politeknik Jeli Kelantan. Penyelia hendaklah bertanggungjawab dan cekap dalam menyelia pemeriksaan, penyenggaraan dan pembaikian semua jenis Sistem Penyaman Udara dan Pengudaraan Mekanikal serta kerja-kerja berkaitan.

Page 15: DOKUMEN SEBUTHARGA - pjk.edu.my · PDF fileBerjaya seperti di lampiran beserta dengan *Surat Setuju Terima/Borang Perjanjian Inden Kerja yang telah ditandatangani di mana ia ... SUB-SEWA

Kontraktor hendaklah menyediakan pekerja-pekerja tetap yang mahir terutama dalam pemeriksaan, penyenggaraan dan pembaikian Sistem Penyaman Udara dan Pengudaraan Mekanikal serta kerja-kerja berkaitan.

4.0 SKOP KERJA

Kontraktor hendaklah memeriksa dan menyenggara Sistem Penyaman Udara dan Pengudaraan Mekanikal serta kerja-kerja berkaitan seperti yang dinyatakan dalam Lampiran A, B, C, D dan E. Kerja-kerja hendaklah dilaksanakan mengikut Jadual Penyenggaraan yang telah dipersetujui oleh Politeknik Jeli Kelantan. Kontraktor hendaklah memaklumkan Politeknik Jeli Kelantan apa-apa kerosakan/kecacatan pada mana-mana bahagian Sistem Penyaman Udara dan Pengudaraan Mekanikal serta kerja-kerja berkaitan yang diperhatikan semasa pemeriksaan dan penyenggaraan rutin, dan hendaklah membaiki kerosakan/kecacatan itu jika dikehendaki oleh Politeknik Jeli Kelantan.

Sekiranya berlaku kerosakan bangunan oleh kontraktor semasa perlaksanaan kerja, kontraktor hendaklah membaiki tanpa mengenakan bayaran kepada Politeknik Jeli Kelantan.

Kontraktor hendaklah menyediakan khidmat kerja kecemasan bagi memeriksa dan membaiki pada waktu kerja biasa dan juga diluar waktu kerja biasa jika dikehendaki berbuat demikian oleh Politeknik Jeli Kelantan.

5.0 PEMERIKSAAN DAN PENYENGGARAAN BERJADUAL

Kontraktor hendaklah memeriksa dan menyenggara mesin dan peralatan Sistem Penyaman Udara dan Pengudaraan Mekanikal serta kerja-kerja berkaitan di Politeknik Jeli Kelantan sekurang-kurang sebulan sekali, kecuali jika selainnya diarahkan oleh Politeknik Jeli Kelantan.

Kontraktor hendaklah melaksanakan pemeriksaan dan penyenggaraan bulanan Sistem Penyaman Udara dan Pengudaraan Mekanikal serta kerja-kerja berkaitan sepertimana diperincikan dalam Jadual Penyenggaraan.

6.0 BAHAN GUNA HABIS (CONSUMABLE)

Kontraktor hendaklah membekal bahan-bahan guna habis sepertimana berikut dan apabila dikehendaki:

(a) Minyak dan gris untuk pelinciran pemampat, galas (bearing) kipas, galas

(bearing) motor, pivot dan bahagian beroperasi yang lain. (b) Bahan pendingin yang diperlukan bagi menggantikan kehilangan

pendingin dalam sistem pendingin. (c) Elemen penapis guna habis.

Page 16: DOKUMEN SEBUTHARGA - pjk.edu.my · PDF fileBerjaya seperti di lampiran beserta dengan *Surat Setuju Terima/Borang Perjanjian Inden Kerja yang telah ditandatangani di mana ia ... SUB-SEWA

(d) Berus karbon yang diperlukan bagi menggantikan berus haus dalam motor elektrik

(e) Titik sentuh elektrik yang diperlukan bagi menggantikan Titik sentuh elektrik yang haus di suis gear, penghidup motor gear, kawalan elektrik gear dan geganti elektrik.

(f) Sisa kapas, sabun bahan pencuci dan bahan pencuci lain yang diperlukan bagi tujuan pembersihan.

Kos bahan-bahan guna habis ini tidak akan dikenakan bayaran secara berasingan oleh Kontraktor, tetapi hendaklah dimasukkan ke dalam kadar tetap bulanan yang telah disebuthargakan oleh Kontraktor bagi Sistem Penyaman Udara dan kerja-kerja berkaitan.

7.0 PEMBAIKAN

Kontraktor perlu memaklum kepada Politeknik Jeli Kelantan untuk sebarang kerosakan atau penggantian pada Sistem Penyaman Udara dan Pengudaraan Mekanikal serta kerja-kerja berkaitan.

Kontraktor hendaklah membaiki kerosakan d atas arahan Politeknik Jeli Kelantan. Kos pembaikan itu tidak boleh dimasukkan dalam sebutharga ini oleh Kontraktor hendaklah dikenakan bayaran secara berasingan oleh Kontraktor.

Politeknik Jeli Kelantan berhak untuk memanggil kontraktor lain bagi melaksanakan kerja-kerja pembaikian kerosakan tersebut.

Semua pembaikan hendaklah dijamin oleh Kontraktor terhadap kecacatan mutu kerja dan bahan-bahan untuk tempoh satu tahun berkuatkuasa dari tarikh pembaikian. Dalam tempoh jaminan, Kontraktor hendaklah membaiki kecacatan dalam pembaikan yang dijalankan tanpa sebarang caj tambahan kepada Politeknik Jeli Kelantan.

8.0 REKOD PEMERIKSAAN DAN PENYENGGARAAN

8.1 Kontraktor hendaklah menyediakan buku rekod pemeriksaan dan penyenggaraan bagi Sistem Penyaman Udara dan Pengudaraan Mekanikal serta kerja-kerja berkaitan yang diperiksa dan disenggara. Buku rekod ini hendaklah disimpan di Pejabat Unit Pembangunan Dan Senggaraan, dan semua butiran ringkas permeriksaan, penyenggaraan dan pembaikian yang dilaksanakan hendaklah dimasukkan oleh Kontraktor ke dalam buku ini bagi tujuan pemeriksaan. Turut disertakan alamat dan nombor telefon Kontraktor bagi memudahkan panggilan kecemasan.

8.2 Kontraktor hendaklah juga menyimpan rekod terperinci dalam dua salinan

bagi semua pemeriksaan, penyenggaraan dan pembaikian. Rekod ini hendaklah dalam bentuk Laporan Penyenggaraan / Pembaikian, dan

Page 17: DOKUMEN SEBUTHARGA - pjk.edu.my · PDF fileBerjaya seperti di lampiran beserta dengan *Surat Setuju Terima/Borang Perjanjian Inden Kerja yang telah ditandatangani di mana ia ... SUB-SEWA

hendaklah ditandatangan pengesahan oleh Politeknik Jeli Kelantan atau wakil setiap kali kerja oleh Kontraktor.

8.3 Kontraktor hendaklah mengemukakan satu salinan laporan bulanan

pemeriksaan dan penyenggaraan, yang diperakui dengan sewajarnya dan ditandatangani oleh Kontraktor, untuk Politeknik Jeli Kelantan. Laporan hendaklah dikemukakan tidak lebih daripada satu (1) minggu selepas pemeriksaan dan penyenggaraan dijalankan.

9.0 KADAR PEMERIKSAAN DAN PENYENGGARAAN

Kadar bagi pemeriksaan dan penyenggaraan Sistem Penyaman Udara dan Pengudaraan Mekanikal serta kerja-kerja berkaitan hendaklah sebagaimana yang dinyatakan di dalam Jadual Kadar Harga bagi Sebutharga ini. Kadar ini disebuthargakan oleh Kontraktor semasa menghantar dokumen sebutharga sebelum ini, dan boleh dipakai untuk tempoh SATU tahun bermula dari tarikh Surat Setuju Terima dan tempoh penyenggaraan. Kontraktor dikehendaki mengikat kontrak dengan Politeknik Jeli Kelantan untuk tempoh di atas berdasarkan Kontrak Piawai Bagi Servis dan Penyenggaraan Sistem Mekanikal dan Kelengkapan Sampingan.

10.0 BAYARAN

Bayaran bulanan hendaklah dibuat mengikut Kontrak ini, manakala bil pembayaran hendaklah disertakan dengan satu penyata lengkap dan disokong dengan satu salinan rekod laporan penyenggaraan/pembaikian sepertimana dikehendaki di bawah perenggan 8.0 Spesifikasi ini. Kegagalan kontraktor akan menyebabkan pembayaran tidak dapat dilakukan.

Page 18: DOKUMEN SEBUTHARGA - pjk.edu.my · PDF fileBerjaya seperti di lampiran beserta dengan *Surat Setuju Terima/Borang Perjanjian Inden Kerja yang telah ditandatangani di mana ia ... SUB-SEWA

Item Keterangan Kerja B 2B 3B 6B

A Chiller

1 check refrigerants and oil level x

2 check oil pressure x

3 check heaters x

4 check all hold down nuts and bolts x

5 check all controls, safety devices and switches x

6 inspect and clean the shell and tube of the condenser of each chiller units x

7 inspect and clean the cooler tubers x

8 touch up any rusty part of equipments x

B Cooling Tower

1 check for excessive noise/vibration for fan, gear box and motor x

2 check for motor terminal box x

3 check operation of float valves x

4 check tension of belt drive and wear x

5 check for tightness of bolts and nuts x

6 check for any water leakage x

7 check water temperature x

8 remove and clear clogged nozzles x

9 check for any rust forming x

10 drain water and clean water basin/sump x

11 lubricate fan bearings x

12 check valve operations x

C Water Pumps

1 check and rectify all seals, glands and pipelines for leaks x

2 check all pump and motor bearings, lubricate with grease and oil as necessary x

3 check coupling and alignment x

4 check strainer and clean as necessary x

5 check for water leakage, all hold-down bolts and nuts x

6 check running amps and operation relays x

7 check and note pump suction and discharge pressure x

8 check connection of flexible joints x

9 check flow switches and thermostats for correct operation x

10 open up pump to inspect for wear x

SPESIFIKASI TEKNIKAL

Page 19: DOKUMEN SEBUTHARGA - pjk.edu.my · PDF fileBerjaya seperti di lampiran beserta dengan *Surat Setuju Terima/Borang Perjanjian Inden Kerja yang telah ditandatangani di mana ia ... SUB-SEWA

Item Keterangan Kerja B 2B 3B 6B

D Air Handling Unit (AHU) / Fan Coil Unit (FCU)

1 check and clean all air filters x

2 check fan operation x

3 check tension of belt drive and alignment x

4 check motor bearings and lubricate if necessary x

5 check control dampers and oil leakage x

6 check cooling coils and pipe for leaks x

7 inspect & clean condensate pans, tray and drain x

8 check for tightness of screw, bolts and nuts x

9 check for any excessive/abnormal noise x

10 check for electrical control board x

11 check and clean strainer x

12 check diffuser & grille for cleanliness x

13 check operation of regulating valve x

14 check operations of thermostats x

15 check refrigerants/water connections x

16 check water piping connection soundness x

17 check anti-vibration mounting x

18 grease fan bearings x

E Ducted Blower (Chilled Water Fan Coil Unit)

1 check and clean air filters and coils x

2 check and clean fan blower x

3 check for chilled water leakage x

4 check for any excessive/abnormal noise and vibration x

5 check and tighten bolts and nuts x

6 check for condensate drain pan x

7 check strainer and clean x

8 check for operation of control and isolation valves x

9 check operations of thermostat x

10 check anti-vibration mount x

Page 20: DOKUMEN SEBUTHARGA - pjk.edu.my · PDF fileBerjaya seperti di lampiran beserta dengan *Surat Setuju Terima/Borang Perjanjian Inden Kerja yang telah ditandatangani di mana ia ... SUB-SEWA

Item Keterangan Kerja B 2B 3B 6B

F Compressor

1 check all seals, gaskets and pipe for leak x

2 check refrigerant and oil levels x

3 check oil pressures x

4 check crankcase heaters x

5 check compressor hold down bolt x

6 check all controls, safety devices and switches x

G Evaporator

1 check all air filters, and clean as necessary x

2 check all water coils, seals and pipelines for leaks and rectify as necessary x

3 purge air from all water coils. x

4 check all fan bearings and lubricate with grease as necessary. x

5 check the tension of all belt drives and adjust as necessary. x

6check the operation of all automatic water regulating valves, and clean, adjusts and lubricate

as necessary.x

7check the operation of all automatic multi-blade face and by-pass dampers and clean, adjust

and lubricate as necessary.x

8 clean all condensate pans, trays and drains. x

H Electrical Motor

1 inspect and clean carbon burshes x

2 check brushes tension x

3 check slip rings for smooth contact x

4 check and lubricate bearings x

5 check alignment and coupling x

6 check motor terminals and tightness x

I Electrical Switchgear

1 inspect contact finger and alignment x

2 clean and adjust contacts x

3 Inspect starter coil condition x

4 check tightness of starters connection x

5 check thermal overload and relays x

6 check cut-out fuses x

Page 21: DOKUMEN SEBUTHARGA - pjk.edu.my · PDF fileBerjaya seperti di lampiran beserta dengan *Surat Setuju Terima/Borang Perjanjian Inden Kerja yang telah ditandatangani di mana ia ... SUB-SEWA

Item Keterangan Kerja B 2B 3B 6B

J Purge Unit

1 check tension of belt drive if applicable x

2 check moisture indicator x

3 check purge unit operation x

K Pipe System

1 check pipework and valve glands for leaks and rectify as necessary x

2 check all valves x

3 clean all pipe support and correct any excessive vibration, aeration or noise x

4 clean all strainers x

L Other

1check the performance of the complete air-conditioning plant and adjust the air volume

control dampers as necessary.x

Nota :- B - Bulan

2B - 2 Bulan

3B - 3 Bulan

6B - 6 Bulan

Page 22: DOKUMEN SEBUTHARGA - pjk.edu.my · PDF fileBerjaya seperti di lampiran beserta dengan *Surat Setuju Terima/Borang Perjanjian Inden Kerja yang telah ditandatangani di mana ia ... SUB-SEWA

Projek :

No. Sebutharga : PJK(S)/SH/04/2015

Nota :

Kekerapan

(12 Bulan)

1.0

1.1

(a) pukal pukal pukal

( c) Insurans Tanggungan Awam pukal pukal pukal

(d) Insurans Kerja pukal pukal pukal

1.2

a) pukal pukal pukal

b) pukal 12 pukal

c) kad servis dan sampul kad pukal pukal pukal

JUMLAH DIBAWA KE RINGKASAN SEBUTHARGA

laporan kerja bulanan merangkumi borang

semakan kerja dan gambar kerja untuk

dikemukakan bersama-sama tuntutan

bayaran.

JADUAL SEBUTHARGA

KERJA-KERJA PENYENGGARAAN BERKALA BAGI SISTEM MEKANIKAL

SERTA KERJA-KERJA BERKAITAN DI POLITEKNIK JELI, KELANTAN.

(MULAI OKTOBER 2015 HINGGA OKTOBER 2016 )

Harga yang dimasukkan hendaklah bagi kerja-kerja membekal, memasang, menguji dan menyenggara

sistem mekanikal yang lengkap dan kerja-kerja berkaitan mengikut skop kerja dan spesifikasi dengan

dua belas (12) bulan penyenggaraan dan jaminan yang dinyatakan.

Pentender adalah dianggap telah melawat tapak bina dan sebarang tuntutan bayaran tambahan

berhubung dengan perkara di atas tidak akan dipertimbangkan.

BIL BUTIRAN-BUTIRAN KERJA Kuantiti Kadar

(RM)

Jumlah

(RM)

KERJA-KERJA PERMULAAN DAN SYARAT-

SYARAT AM

Menyediakan keperluan-keperluan sebagaimana

syarat-syarat Sebutharga.

Akta Keselamatan Sosial Pekerja 1969

(PERKESO)

Jadual Penyenggaraan lengkap untuk

diguna sepanjang tempoh kontrak

Kerja-kerja penyediaan dokumen sepertimana

berikut;

MS.1/4

Page 23: DOKUMEN SEBUTHARGA - pjk.edu.my · PDF fileBerjaya seperti di lampiran beserta dengan *Surat Setuju Terima/Borang Perjanjian Inden Kerja yang telah ditandatangani di mana ia ... SUB-SEWA

Kekerapan

(12 Bulan)

2.0 KERJA-KERJA PENYENGGARAAN BERKALA

2.1

2.2

( Rujuk Lampiran A )

a) Chiller 3 12

b) Cooling Tower 3 12

c) Water Tank 1 2

d) CWP Pump 4 12

4 12

pukal 12 pukal

9 6

h) Ducted Blower 17 4

i) Fan Coil Unit 81 4

2.3 Water-Cooled Package Unit Air Conditioning

( Rujuk Lampiran B )

a) Cooling Tower 4 12

b) Water Tank 1 2

c) CWP Pump 6 12

pukal 12 pukal

4 6

f) Ducted Blower 6 4

g) Fan Coil Unit 44 4

e) Air Handling Unit

JUMLAH DIBAWA KE RINGKASAN SEBUTHARGA

d) Chemical

BIL BUTIRAN-BUTIRAN KERJA Kuantiti Kadar

(RM)

Jumlah

(RM)

Memeriksa, menguji, menyenggara dan servis secara

berkala ke atas Sistem Penyaman Udara Dan

Pengudaraan Mekanikal di Politeknik Jeli Kelantan

sebagaimana Jadual Penyenggaraan yang diluluskan

oleh pihak Politeknik, termasuk menyediakan satu (

1 ) orang pekerja supaya berada di kawasan lokasi

kerja sepanjang waktu pejabat KERAJAAN dan

pada masa majlis rasmi berlangsung di Politeknik

Jeli Kelantan termasuk hari cuti (Rujuk Spesifikasi).

Chilled Water System (Building Automation

System - BAS)

e) CHWP Pump

f) Chemical

g) Air Handling Unit

MS.2/4

Page 24: DOKUMEN SEBUTHARGA - pjk.edu.my · PDF fileBerjaya seperti di lampiran beserta dengan *Surat Setuju Terima/Borang Perjanjian Inden Kerja yang telah ditandatangani di mana ia ... SUB-SEWA

Kekerapan

(12 Bulan)

..sambungan 2.0 Kerja-kerja Penyenggaraan Berkala…

2.4 Air-Cooled Split Unit Air Conditioning 6 12

( Rujuk Lampiran C )

2.5 Precision Air Conditioner 4 12

( Rujuk Lampiran C )

2.6 Cold Room 2 4

( Rujuk Lampiran C )

2.7 Split Unit Aircond 26 6

( Rujuk Lampiran D )

2.8 Exhaust Fan 93 2

( Rujuk Lampiran E )

JUMLAH DIBAWA KE RINGKASAN SEBUTHARGA

BIL BUTIRAN-BUTIRAN KERJA Kuantiti Kadar

(RM)

Jumlah

(RM)

MS.3/4

Page 25: DOKUMEN SEBUTHARGA - pjk.edu.my · PDF fileBerjaya seperti di lampiran beserta dengan *Surat Setuju Terima/Borang Perjanjian Inden Kerja yang telah ditandatangani di mana ia ... SUB-SEWA

Projek :

No. Sebutharga : PJK(S)/SH/04/2015

RINGKASAN SEBUTHARGA

1.0 KERJA-KERJA PERMULAAN DAN SYARAT-SYARAT AM MS.1/4

2.0 KERJA-KERJA PENYENGGARAAN BERKALA

Catatan:

Tarikh : ……………………. Tandatangan Pemborong : ……………………………………

Nama & Alamat : ……………………………………

……………………………………

……………………………………

……………………………………

Tarikh : ……………………. Tandatangan Saksi : ……………………………………

Nama & Alamat : ……………………………………

……………………………………

……………………………………

……………………………………

JUMLAH DIBAWA KE BORANG SEBUTHARGA

Jika ada butiran yang dikehendaki dalam Spesifikasi dan Skop Kerja tidak termasuk di dalam Ringkasan

Sebut Harga ini, harga butiran tersebut hendaklah disifatkan telah dimasukkan ke dalam salah satu

butiran dalam Ringkasan Sebut Harga.

MS.2/4 &

MS. 3/4

KERJA-KERJA PENYENGGARAAN BERKALA BAGI SISTEM MEKANIKAL

SERTA KERJA-KERJA BERKAITAN DI POLITEKNIK JELI, KELANTAN.

(MULAI OKTOBER 2015 HINGGA OKTOBER 2016 )

BIL BUTIRAN-BUTIRAN KERJAMUKA

SURAT

Jumlah

(RM)

MS.4/4

Page 26: DOKUMEN SEBUTHARGA - pjk.edu.my · PDF fileBerjaya seperti di lampiran beserta dengan *Surat Setuju Terima/Borang Perjanjian Inden Kerja yang telah ditandatangani di mana ia ... SUB-SEWA

9,000 13,000 18,000 25,000 30,000 40,000

BTU/HR BTU/HR BTU/HR BTU/HR BTU/HR BTU/HR

1 To replace new condenser fan motor

2 To rewind condenser fan motor

3 To replace new fan motor capacitor

4 To replace new compressor capacitor

5 To replace new blower fan motor

6 To rewind blower fan motor

7 To replace new DOL starter

8 To replace new overload DOL starter

9 To replace new autoruns starter

10 To replace new condenser fan blade

11 To renew evaporator fan blower wheel

12

13 To weld/repair piping & coil system

14

15 To replace new filter drier

16 To replace new starter switch

17

18 To weld/rebuilt body & repair

19 To replace new compressor

20

21 To replace new indoor unit

22 To replace new fan motor bearing

23

24 To replace new timer 60sec

25 To replace new timer 60min

JADUAL KADAR HARGA BAGI KERJA PEMBAIKIAN UTAMA DAN ALAT GANTI

To replace electric 3 point plug socket

(25 amp)

To replace new thermal expansion

valve/capillary tube

To replace new supporting bracket for

outdoor

To replace new outdoor unit c/w rubber

mounting

To reposition the complete split unit

system (inddor, outdoor, wiring, etc.)

HARGA

ITEMBIL.

Page 27: DOKUMEN SEBUTHARGA - pjk.edu.my · PDF fileBerjaya seperti di lampiran beserta dengan *Surat Setuju Terima/Borang Perjanjian Inden Kerja yang telah ditandatangani di mana ia ... SUB-SEWA

1 Permetre run of wiring and conduit used (above ground)

2 Permetre run of wiring and conduit used (underground)

3 Permetre run of PVC armoured cable (underground)

Permetre run of refrigerant piping c/w fittings used

a) 6 mm dia.

b) 10mm dia.

c) 12mm dia.

5 Permetre run trunking 4"x2'

6 Price per kilogram of general purpose grease

7 Price per kilogram of ball and roller bearing grease

8 Price per litre of general purpose lubricating oil

9 Price per litre of compressor oil

10 Price per litre of cleaning agent for condenser coil

11 Price per kilogram of refrigerant

a) R22

b) R410

c) R134a

12 Price per air filter used

13 Price per refrigerant filter used

14 Price per set of carbon brushes used

15 Price per compressor motor contactor

16 Price per compressor motor starter

17 Price per electrical fuse for compressor motor

18 Price per electrical fuse for pump motor

19 Price per electrical fuse for automatic temperature control and relay

20 Price per metre of V-belt used

Tandatangan Penyebutharga :

Nama & Alamat :

(Dengan Cop) :

Tarikh :

4

HARGABIL. ITEM

Page 28: DOKUMEN SEBUTHARGA - pjk.edu.my · PDF fileBerjaya seperti di lampiran beserta dengan *Surat Setuju Terima/Borang Perjanjian Inden Kerja yang telah ditandatangani di mana ia ... SUB-SEWA

JADUAL PERKHIDMATAN DAN PENYELENGGARAAN

Petender perlu mengemukakan maklumat berikut, menentukan keupayaan untuk menyiapkan kerja-kerja mengikut tarikh yang ditetapkan.

a) Tempoh Servis satu (1) unit sistem penyaman udara : ___________ Minit

b) Tempoh Servis semua unit sistem penyaman udara dalam 1 bulan : ___________ Hari

c) Ujian dan pentauliahan Tempoh peralatan yang diperlukan dalam 1 bulan : ___________ Hari

Jumlah ( item b & c ) :___________ Hari

Tarikh : Tandatangan

Penyebutharga :

Nama dan alamat :

(Dengan Cop)

Tarikh : Tandatangan Saksi :

Nama dan alamat :

Page 29: DOKUMEN SEBUTHARGA - pjk.edu.my · PDF fileBerjaya seperti di lampiran beserta dengan *Surat Setuju Terima/Borang Perjanjian Inden Kerja yang telah ditandatangani di mana ia ... SUB-SEWA

LAMPIRAN A

A. Chiller Plant Room

Description Make Model Capacity Qty.

Water Tank - - 60000 L 1

Cooling Tower Truwater TCS-300-1B 300 tonne 3

Chiller York YEWS200SA55D1 200 tonne 3

Condenser Water Pumpsets Calgon HES 125-320 2750 LPM @

30m/Head

4

Chilled Water Pumpsets Calgon HES 100-400 2000 LPM @

55m/Head

4

Exhaust Fan KDK 40KQT - 4

Supply Fan KDK 40KQT - 2

B. YORK Air Handling Unit

Block Location Unit No. ModelCapacity

(BTU/HR)Qty.

1A AHU Room AHU-1A-G-1 YSM 30 X 40 154030 1

1B AHU Room AHU-1B-G YSM 20 X 30 72150 1

1A AHU Room AHU-1A-1-1 YSM 20 X 50 161240 1

1B AHU Room AHU-1B-1-1 YSM 30 X 30 128730 1

1A AHU Room AHU-1A-2-1 YSM 30 X 50 162660 1

3 Lib AHU Room AHU-3-1-1 YSM 40 X 80 702370 1

3 JAB AHU Room AHU-3-1-2 YSM 50 X 60 641070 1

3 Lib AHU Room AHU-3-2-1 YSM 40 X 70 560940 1

3 JPA AHU Room AHU-3-2-2 YSM 40 X 60 402740 1

CHILLED WATER SYSTEM (BUILDING AUTOMATION SYSTEM - BAS)

Page 30: DOKUMEN SEBUTHARGA - pjk.edu.my · PDF fileBerjaya seperti di lampiran beserta dengan *Surat Setuju Terima/Borang Perjanjian Inden Kerja yang telah ditandatangani di mana ia ... SUB-SEWA

LAMPIRAN A

C. YORK Ducted Blower

Block Location Unit No. ModelCapacity

(BTU/HR)Qty.

Reception FC-1A-G-1 DB 40 144850 1

VIP Room FC-1A-1-1 DB 12 54305 1

Conference Room FC-1A-1-2 DB 30 108496 1

Work Area FC-1B-1-3 DB 20 75811 1

Work Area FC-1B-1-5 DB 16 58628 1

AHU Room FC-1B-2-1 DB 30 108496 1

AHU Room FC-1B-2-2 DB 16 72144 1

Coord. Work Area FC-1B-2-3 DB 16 72144 1

Coordinator Room FC-20-1-1&2 DB12 (6/12) 54305 2

Operation, Work

AreaFC-20-1-3 DB30 (6/12)

1396351

I.C. Room 1,2,4 & 5 FC-20-1-4 DB16 (4/12) 58628 1

Group Couns./Pantry FC-20-1-5 DB12 (6/12) 54305 1

D. YORK Ceiling Cassette Fan Coil

Block Location Unit No. ModelCapacity

(BTU/HR)Qty.

Seminar Room 1 FC-1B-G-3 YCK 50 AW 36500 1

Seminar Room 2 FC-1B-G-4 YCK 50 AW 36500 1

Meeting Room 2 FC-1B-G-5 YCK 20 AW 22500 1

Meeting Room 1 FC-1B-G-6 YCK 20 AW 22500 1

Waiting Area FC-1A-1-3 YCK 20 AW 22500 1

Meeting Room FC-1A-1-6 YCK 30 AW 30000 1

Director Room FC-1A-1-7 YCK 20 AW 22500 1

Head of Department FC-3-1-3 YCK 20 AW 22500 1

Meeting Room FC-3-1-5 YCK 20 AW 22500 1

Head of Department FC-3-1-11 YCK 20 AW 22500 1

Meeting Room FC-3-1-13 YCK 20 AW 22500 1

Head of Department FC-3-2-3 YCK 20 AW 22500 1

Meeting Room FC-3-2-4 YCK 20 AW 22500 1

Meeting Room FC-3-2-9 YCK 20 AW 25500 1

Head of Department FC-3-2-10 YCK 20 AW 22500 1

Head of Department FC-3-2-14 YCK 20 AW 22500 1

Meeting Room FC-3-2-15 YCK 25 AW 25500 1

3 Lib

1A

1B

20

1B

1A

3 JAB

3 Lib

3 JPA

3 JMSK

Page 31: DOKUMEN SEBUTHARGA - pjk.edu.my · PDF fileBerjaya seperti di lampiran beserta dengan *Surat Setuju Terima/Borang Perjanjian Inden Kerja yang telah ditandatangani di mana ia ... SUB-SEWA

LAMPIRAN A

E. YORK Wall Mounted Fan Coil

Block Location Unit No. ModelCapacity

(BTU/HR)Qty.

Audio Recording FC-1A-G-2 YWM 10 GW 9500 1

AV Control Room FC-1A-G-3 YWM 10 GW 9500 1

Shooting FC-1A-G-4 YWM 10 GW 9500 1

Control Room FC-1A-G-5 YWM 10 GW 9500 1

E-Learning FC-1A-G-6 YWM 15 GW 11000 1

Digital Desktop FC-1A-G-7 YWM 15 GW 11000 1

Video Editing 1 FC-1A-G-8 YWM 10 GW 9500 1

Video Editing 2 FC-1A-G-9 YWM 10 GW 9500 1

Animation FC-1A-G-10 YWM 10 GW 9500 1

Archive FC-1A-G-11 YWM 10 GW 9500 1

Media View FC-1A-G-12 YWM 10 GW 9500 1

1B Discussion Room 1-4 FC-1B-G-7 To 10 YWM 10 GW 9500 4

Deputy Director 2 FC-1A-1-4 YWM 10 GW 9500 1

Deputy Director 1 FC-1A-1-5 YWM 10 GW 9500 1

PA Room FC-1A-1-8 YWM 25 GW 18000 1

Head of Unit FC-1B-1-1 YWM 10 GW 9500 1

Head of Unit 2 FC-1B-1-2 YWM 10 GW 9500 1

Head of Centre FC-1B-1-4 YWM 25 GW 18000 1

Meeting Room FC-1A-2-1 YWM 25 GW 18000 1

Head Assistance FC-1A-2-2 YWM 15 GW 11000 1

Head of Unit FC-1A-2-3 YWM 15 GW 11000 1

Discussion Room FC-3-1-1 YWM 25 GW 18000 1

Head of Unit FC-3-1-2 YWM 15 GW 11000 1

Head of Unit FC-3-1-6 YWM 15 GW 11000 1

Discussion Room FC-3-1-7 YWM 25 GW 18000 1

Discussion Room FC-3-1-8 YWM 25 GW 18000 1

Head of Unit FC-3-1-9 & 10 YWM 15 GW 11000 2

Discussion Room FC-3-1-14 YWM 15 GW 11000 1

Discussion Room FC-3-2-1 YWM 25 GW 18000 1

Head of Unit FC-3-2-2 YWM 15 GW 11000 1

Discussion Room FC-3-2-5 YWM 25 GW 18000 1

Discussion Room FC-3-2-6 YWM 15 GW 11000 1

Head of Unit FC-3-2-7 & 8 YWM 15 GW 11000 2

Discussion Room FC-3-2-11 YWM 15 GW 11000 1

Head of Unit FC-3-2-12 & 13 YWM 15 GW 11000 2

1A

1A

1B

1A

3 JAB

3 Lib

3 JPA

3 JMSK

3 Lib

Page 32: DOKUMEN SEBUTHARGA - pjk.edu.my · PDF fileBerjaya seperti di lampiran beserta dengan *Surat Setuju Terima/Borang Perjanjian Inden Kerja yang telah ditandatangani di mana ia ... SUB-SEWA

LAMPIRAN A

F. YORK Ceiling Exposed Fan Coil

Block Location Unit No. ModelCapacity

(BTU/HR)Qty.

Training Computer FC-1B-G-1&2 YCE 20 DW 17700 2

Tech. Enable Room 1 FC-1B-G-11&12 YCE 30 DW 24600 2

Tech. Enable Room 2 FC-1B-G-13&14 YCE 30 DW 24600 2

G. YORK Ceiling Ducted Fan Coil

Block Location Unit No. ModelCapacity

(BTU/HR)Qty.

3 Ind. Tech. Lab FC-3-G-4 & 5 DB20 75811 2

3 Lib Reception FC-3-1-4 DB 16 58628 1

3 JAB Reception FC-3-1-12 DB 16 58628 1

H. YORK Ceiling Suspended Fan Coil

Block Location Unit No. ModelCapacity

(BTU/HR)Qty.

Office FC-20-G-1&6 YCE20DW 17700 2

Mini Market FC-20-G-2&3 YCE40DW 31200 2

Shop 1 & 2 FC-20-G-4&5 YCE25DW 20800 2

Unit Head 1 & 2 FC-20-1-6&7 YCE20DW 17700 2

Dept. Head Room FC-20-1-8 YCE20DW 17700 1

Couns. Room 1&2 FC-20-1-9&10 YCE20DW 17700 2

Group Counselling

RoomFC-20-1-11 YCE30DW

246001

Meeting Room FC-20-1-12 YCE50DW 45000 1

Note :- Block 1 - Administration & CISC

Block 3 - Common Facilities

Block 6 - JMSK Department Lab

Block 7 - Agrotech Department Lab

Block 20 - Student Center & Cafetaria

Block 30 - Fish Propagation

20

1B

Page 33: DOKUMEN SEBUTHARGA - pjk.edu.my · PDF fileBerjaya seperti di lampiran beserta dengan *Surat Setuju Terima/Borang Perjanjian Inden Kerja yang telah ditandatangani di mana ia ... SUB-SEWA

LAMPIRAN B

A. Water-cooled Block 3 Theatres

Description Make Model Capacity Qty.

Cooling Tower Truwater TCS-60-1B 60 tonne 2

Condenser Water Pumpsets Calgon HES 80-400 1100 LPM @

40m/Head

2

B. Water-cooled Blok 6

Description Make Model Capacity Qty.

Cooling Tower Truwater TCS-60-1B 60 tonne 1

Cooling Tower Truwater TCS-100-1B 100 tonne 1

Condenser Water Pumpsets Calgon HES 50-320 600 LPM @

30m/Head

2

Condenser Water Pumpsets Calgon HES 80-400 1100 LPM @

30m/Head

2

Cold Water Make Up Tank - - 16000 L 1

C. YORK Air Handling Unit

Block Location Unit No. ModelCapacity

(BTU/HR)Qty.

Mini Lecture Theatre AHU-3-G-1 To 3 EWM250 224800 3

Main Lecture Hall AHU-3-G-4 EWM400 367200 1

D. YORK Ducted Blower

Block Location Unit No. ModelCapacity

(BTU/HR)Qty.

Student Work Area 1 FCSU-6-1-2 To 4 EHW48 46800 3

Student Work Area 2 FCSU-6-1-5 To 7 EHW48 46800 3

WATER-COOLED PACKAGE UNIT AIR CONDITIONING

3

6

Page 34: DOKUMEN SEBUTHARGA - pjk.edu.my · PDF fileBerjaya seperti di lampiran beserta dengan *Surat Setuju Terima/Borang Perjanjian Inden Kerja yang telah ditandatangani di mana ia ... SUB-SEWA

LAMPIRAN B

E. YORK Wall Mounted Fan Coil

Block Location Unit No. ModelCapacity

(BTU/HR)Qty.

3 Preparation Area FC-3-G-1 To 3 YWM15G/WSS15A 14000 3

F. YORK Ceiling Suspended Fan Coil

Block Location Unit No. ModelCapacity

(BTU/HR)Qty.

Student Work Area 1 FCSU-6-G-1&2 YCE50CB/WSS50A 46000 2

Preparation 1 FCSU-6-G-3 YCE20CB/WSS20A 18900 1

Student Work Area 2 FCSU-6-G-4&5 YCE50CB/WSS50A 46000 2

Preparation 2 FCSU-6-G-6 YCE20CB/WSS20A 18900 1

Student Work Area 3 FCSU-6-G-7&8 YCE50CB/WSS50A 46000 2

Preparation 3 FCSU-6-G-9 YCE50CB/WSS20A 18900 1

Student Work Area 4 FCSU-6-G-10&11 YCE50CB/WSS50A 46000 2

Preparation 4 FCSU-6-G-12 YCE50CB/WSS20A 18900 1

Preparation 5 FCSU-6-G-13 YCE50CB/WSS20A 18900 1

Lab & Briefing Area FCSU-6-G-14 To 16YCE50CB/WSS50A 46000 2

Preparation 1 FCSU-6-1-1 YCE20CB/WSS20A 18900 1

Preparation 2 FCSU-6-1-8 YCE20CB/WSS20A 18900 1

Language Lab 3 FCSU-6-1-9 & 10 YCE50CB/WSS50A 46000 2

Preparation 4 FCSU-6-1-11 YCE20CB/WSS20A 18900 1

Language Lab 2 FCSU-6-1-12 & 13 YCE50CB/WSS50A 46000 2

Language Lab 1 FCSU-6-1-14 & 15 YCE50CB/WSS20A 46000 2

Preparation 3 FCSU-6-1-16 YCE20CB/WSS20A 18900 1

Agro Biotech Lab -

Analysis &

Apparatus

FSCU-7-1 YCE20CB/WSS20A

18900

1

Agro Biotech Lab -

Preparation RoomFSCU-7-2 YCE20CB/WSS20A

189001

Agro Biotech Lab -

Working AreaFSCU-7-3 YCE61CB/YWC60

564001

Agro Biotech Lab -

Working AreaFSCU-7-4 YCE50CB/YWC48

468001

Food Technology

Lab - Working AreaFSCU-7-5 & 6 YCE61CB/YWC60

564002

7

6

Page 35: DOKUMEN SEBUTHARGA - pjk.edu.my · PDF fileBerjaya seperti di lampiran beserta dengan *Surat Setuju Terima/Borang Perjanjian Inden Kerja yang telah ditandatangani di mana ia ... SUB-SEWA

LAMPIRAN B

..cont...M. YORK Ceiling Suspended Fan Coil

Block Location Unit No. ModelCapacity

(BTU/HR)Qty.

Food Technology

Lab - Preparation

Room

FSCU-7-7 YCE20CB/WSS20A

18900

1

Aqua Engineering

Lab - Calibration

Room

FSCU-7-8 YCE20CB/WSS20A

18900

1

Aqua Engineering

Lab - Preparation

Room

FSCU-7-9 YCE20CB/WSS20A

18900

1

Aqua Engineering

Lab - Working AreaFSCU-7-10 YCE61CB/YWC60

564001

Aqua Engineering

Lab - Working AreaFSCU-7-11 YCE50CB/YWC48

468001

Soil & Water Lab -

Working AreaFSCU-7-12 YCE61CB/YWC60

564001

Soil & Water Lab -

Working AreaFSCU-7-13 YCE50CB/YWC48

468001

Soil & Water Lab -

Preparation RoomFSCU-7-14 YCE20CB/WSS20A

189001

Soil & Water Lab -

Analysis RoomFSCU-7-15 YCE20CB/WSS20A

189001

Post Harverst

Workshop -

Preparation Room

FSCU-7-16 YCE20CB/WSS20A

18900

1

Note :- Block 1 - Administration & CISC

Block 3 - Common Facilities

Block 6 - JMSK Department Lab

Block 7 - Agrotech Department Lab

Block 20 - Student Center & Cafetaria

Block 30 - Fish Propagation

7

Page 36: DOKUMEN SEBUTHARGA - pjk.edu.my · PDF fileBerjaya seperti di lampiran beserta dengan *Surat Setuju Terima/Borang Perjanjian Inden Kerja yang telah ditandatangani di mana ia ... SUB-SEWA

LAMPIRAN C

YORK Air-Cooled Split Unit (Ceiling Exposed/Suspended)

Block Location Unit No. ModelCapacity

(BTU/HR)Qty.

MDF & PABX ACSU-1A-G-3 YSL 25 C/YCE 25 CB25000 1

Security ACSU-1A-G-1 & 2 YSL 18 C/YCE 20 CB18000 2

30 Briefing Room ACSU-30-1 To 3 YCE40CB/YSL40D 40000 3

DB Precision AC

Block Location Unit No. ModelCapacity

(BTU/HR)Qty.

1A Server Room ACSU-1A-G-4 & 5 DBAD 19/DBRC 20 246600 2

6 Network Server

Room & ICT / Tel

Core

PAC No 1 & 2 DBTAU-05/DBRC-06246600

2

Bizair Stand Alone Cooler/Blower

Block Location Unit No. ModelCapacity

(BTU/HR)Qty.

7 Post Harvest

Workshop - Cold

Room

FCSU-7-17 BEM-017

14100

1

30 Cold Room FCSU-30-4 BEL-014 14100 1

Note :- Block 1 - Administration & CISC

Block 3 - Common Facilities

Block 6 - JMSK Department Lab

Block 7 - Agrotech Department Lab

Block 20 - Student Center & Cafetaria

Block 30 - Fish Propagation

PRECISION AIR CONDITIONER

COLD ROOM

1A

AIR-COOLED SPLIT UNIT AIR CONDITIONING

Page 37: DOKUMEN SEBUTHARGA - pjk.edu.my · PDF fileBerjaya seperti di lampiran beserta dengan *Surat Setuju Terima/Borang Perjanjian Inden Kerja yang telah ditandatangani di mana ia ... SUB-SEWA

LAMPIRAN D

Block Location Model Capacity Qty.

ICT & Tel YORK 1hp 1

ICT & Tel YORK 1hp 1

ICT & Tel ACSON 1hp 1

Bilik PET ACSON 2hp 1

ICT & Tel ACSON 1hp 1

ICT & Tel YORK 1hp 1

ICT & Tel YORK 1hp 1

ICT & Tel ACSON 1hp 1

ICT & Tel ACSON 1hp 1

ICT & Tel ACSON 1hp 1

Bilik Kuliah 8 (Robot) ACSON 4hp 1

Bilik Kuliah 16 ACSON 4hp 1

Bilik Kuliah 17 ACSON 4hp 1

Bilik Kuliah 18 ACSON 4hp 1

Bilik Kuliah 19 ACSON 4hp 1

Bilik Kuliah 20 ACSON 4hp 1

Bilik Kuliah 1 (Gim) ACSON 4hp 1

Bilik Kuliah 21 (Galeri) ACSON 4hp 1

Core ACSON 1hp 1

ICT Core YORK 1hp 1

Bilik Audit ACSON 1hp 1

Ruang Kerja YORK 1hp 1

Ruang Kerja YORK 3hp 1

20 ICT & Tel ACSON 1hp 1

Pejabat UPS ACSON 1.5hp 2

19 Pejabat Pemandu YORK 1.5hp 2

Note :- Block 1 - Administration & CISC

Block 3 - Common Facilities

Block 6 - JMSK Department Lab

Block 7 - Agrotech Department Lab

Block 20 - Student Center & Cafetaria

Block 30 - Fish Propagation

Split Unit Biasa Aircond

6 JMSK

19

3

1A

1B

Page 38: DOKUMEN SEBUTHARGA - pjk.edu.my · PDF fileBerjaya seperti di lampiran beserta dengan *Surat Setuju Terima/Borang Perjanjian Inden Kerja yang telah ditandatangani di mana ia ... SUB-SEWA

LAMPIRAN E

A. KDK Ceiling Type Exhaust Fan

Block Location Unit No. ModelCapacity

(BTU/HR)Qty.

Agro Biotech Lab -

Chemical RoomEF-7-1 25TGQ7

-1

Soil & Water Lab -

Chemical RoomEF-7-5 25TGQ7

-1

20 Stall 1 - 6 KF-20-1 To 6 CSD 250 - 6

B. KDK Wall Mounted Exhaust Fan

Block Location Unit No. Model Capacity Qty.

ICT & Tel EF-1A-G-5 25AQM7 - 1

Toilets EF-1A-G-1 To 4 25AQM1 - 4

ICT & Tel EF-1B-G-4 25AQM7 - 1

Toilets EF-1A-G-1 To 2 25AQM7 - 2

ICT & Tel Room EF-1A-1-7 25AQM7 - 1

Toilets and Utility EF-1A-1-1,2,4&6 25AQM7 - 4

1B ICT & Tel Room EF-1B-1-3 25AQM7 - 1

ICT & Tel EF-1A-2-4 25AQM7 - 1

Utility EF-1A-2-1 25AQM7 - 1

Male Toilet 6 EF-1A-2-2 25AQM7 - 1

Female Toilet 6 EF-1A-2-3 25AQM7 - 1

ICT & Tel EF-1B-2-4 25AQM7 - 1

Female Toilet 7 EF-1B-2-1 25AQM7 - 1

Male Toilet 7 EF-1B-2-2 25AQM7 - 1

Utility EF-1B-2-3 25AQM7 - 1

3 Lib Toilets & Misc. EF-3-1-1 To 6 25AQM7 - 6

3 JAB Toilets & Misc. EF-3-1-7 To 11 25AQM7 - 5

3 Lib Toilets & Misc. EF-3-2-1 To 6 25AQM7 - 6

3 JMSK Toilets & Misc. EF-3-2-7 To 14 25AQM7 - 8

Toilets & Misc. EF-6-G-1 To 8 25AQM7 - 8

Locker & Misc. EF-6-1-1 To 2 25AQM7 - 2

7General Area - Male &

Female ToiletEF-7-2 & 3 25AQM7

-2

7General Area - Switch

RoomEF-7-4 25AQM7

-1

7Post Harvest Workshop

- Chemical RoomEF-7-6 25AQM7

-

1

7 Post Harvest Workshop EF-7-7 To 10 40KQT-

4

20 Toilets & Misc. EF-20-G-1 To 7 25AQM7 - 7

1A

1A

1B

6 JMSK

7

1A

1B

Page 39: DOKUMEN SEBUTHARGA - pjk.edu.my · PDF fileBerjaya seperti di lampiran beserta dengan *Surat Setuju Terima/Borang Perjanjian Inden Kerja yang telah ditandatangani di mana ia ... SUB-SEWA

C. KDK Glass Mounted Exhaust Fan

Block Location Unit No. Model Capacity Qty.

1B M/Toilet-3 EF-1B-G-3 20WUD - 1

1A Toilets and Utility EF-1A-1-3&5 20WUD - 2

1B Toilets and Utility EF-1B-1-1 To 2 20WUD - 2

3 Toiltes & Misc. EF-3-G-1 & 2 20WUD - 2

6 JMSK Toilets & Misc. EF-6-G-9 20WUD - 1

D. KDK Axial Flow Exhaust Fan

Block Location Unit No. Model Capacity Qty.

20 Toilet & Misc. EF-20-1-1 To 5 25AQM7 - 5

Note :- Block 1 - Administration & CISC

Block 3 - Common Facilities

Block 6 - JMSK Department Lab

Block 7 - Agrotech Department Lab

Block 20 - Student Center & Cafetaria

Block 30 - Fish Propagation

Page 40: DOKUMEN SEBUTHARGA - pjk.edu.my · PDF fileBerjaya seperti di lampiran beserta dengan *Surat Setuju Terima/Borang Perjanjian Inden Kerja yang telah ditandatangani di mana ia ... SUB-SEWA

MAKLUMAT LATAR BELAKANG, KEWANGAN

DAN PRESTASI KONTRAKTOR

Lampiran - Arahan-arahan yang perlu dimasukkan ke

dalam Arahan Kepada Pentender

Lampiran A - Surat Pengakuan Kebenaran

Maklumat dan Keesahan Dokumen

Yang Dikemukakan oleh Pentender

Lampiran B - Maklumat Am Latar

Belakang Pentender

Lampiran C - Data-data Kewangan

Lampiran D - Rekod Pengalaman Kerja

Lampiran E - Kakitangan Teknikal

Lampiran F - Senarai Kerja Kontrak Semasa

Lampiran G - Senarai loji dan Peralatan Utama

Lampiran H - Borang CA – Laporan Bank/

Institusi Kewangan Mengenai

Kedudukan Kewangan Pentender

Lampiran I - Borang FA – Laporan Penyelia Projek

Atas Prestasi Kerja (Bukan Projek

JKR) Semasa Pentender

Lampiran J - Borang FA1 – Laporan Jurutera Projek

Atas Prestasi Kerja Semasa Pentender

Page 41: DOKUMEN SEBUTHARGA - pjk.edu.my · PDF fileBerjaya seperti di lampiran beserta dengan *Surat Setuju Terima/Borang Perjanjian Inden Kerja yang telah ditandatangani di mana ia ... SUB-SEWA

Lampiran

ARAHAN-ARAHAN YANG PERLU DIMASUKKAN KE DALAM ARAHAN KEPADA

PENTENDER

A. Maklumat Latar Belakang. Kewangan Dan Prestasi Pentender.

1. Pentender-pentender hendaklah mengambil maklum bahawa penilaian Tender ini

akan mengambil kira dan mementingkan keupayaan pentender untuk melaksanakan

projek yang ditender, di samping kemunasabahan harga tender., Jesteru itu keupayaan

pentender - pentender akan dinilai semasa penilaian Tender. Penilaian ini akan dibuat

berasaskan kedudukan kewangan, pengalaman kerja, kakitangan teknikal, dan prestasi

kerja semasa pentender serta keempunyaan peralatan dan loji.

2. Untuk membolehkan Penilaian ini dibuat, Pentender - pentender adalah dikehendaki

mengemukakan dokumen dokumen seperti tersenarai di bawah ini bersama sama

tendernya.

(a) Salinan Akaun Syarikat yang telah disahkan dan diaudit oleh Juru Audit yang

bertauliah, bagi dua ( 2 ) tahun kewangan terakhir : (Bagi Syarikat Sdn. Bhd. sahaja).

(b) Salinan Penyata Bulanan Akaun Bank mengenai Wang Dalam Tangan Pentender bagi

tiga (3) bulan terakhir sebelum tarikh tutup tender.

(c) Laporan bank / institusi kewangan mengenai kedudukan kewangan pentender, atas

format seperti Borang CA, dalam satu sampul berlakri.

(d) Salinan Perakuan / Pengesahan siap kerja bagi setiap kerja yang telah disiapkan dan

disenaraikan di Borang D.

(e) Salinan Borang KWSP ' A ' bagi bulan caruman terakhir bagi setiap kakitangan

teknikal atau salinan perjanjian perkhidmatan professional yang diambil secara

kontrak yang disenaraikan di Borang E.

(f) Salinan sijil kelulusan / kelayakan setiap kakitangan teknikal kategori A dan b yang

disenaraikan di Borang E.

(g) Laporan Penyeliaan Projek mengenai prestasi semasa pretender, bagi setiap kerja

semasa yang bukan projek JKR yang disenaraikandi Borang F, atas format seperti

Borang FA, dalam satu sampul berlakri.

Dokumen-dokumen ini sangatlah penting untuk membolehkan penilaian keupayaan yang

sewajarnya dibuat ke atas pentender. Sekiranya pretender tidak atau gagal untuk

mengemukakan dokumen-dokumen ini, terutamanya dokumen-dokumen (a), (b) dan (g),

tender pretender akan ditolak dan tidak akan dipertimbangkan.

3. Sekiranya pentender gagal untuk mengemukakan salah satu atau sebahagian daripada

dokumen-dokumen (c), (d), (e) dan (f), maklumat dan data-data yang tidak dapat disemak

kerana ketiadaan atau ketidak-cukupan dokumen-dokumen tersebut adalah tidak sah dan

tidak boleh diambilkira dalam penilaian keupayaan pentender yang berkenaan melainkan

maklumat atau data-data tersebut membawa kesan negative terhadap nilai keupayaanya.

Ini bermakna kriteria-kriteria yang mana penilaiannya memerlukan maklumat atau data-

data ini, akan diambil sebagai kosong.

Page 42: DOKUMEN SEBUTHARGA - pjk.edu.my · PDF fileBerjaya seperti di lampiran beserta dengan *Surat Setuju Terima/Borang Perjanjian Inden Kerja yang telah ditandatangani di mana ia ... SUB-SEWA

4. Disamping mengemukakan dokumen dokumen yang tersebut diatas pentender

pentender dikehendaki melengkapkan borang borang berikut yang disertakan bersama

Dokumen Tender ini, dengan sempuma dan mengembalikannya bersama sama dengan

tender masing masing.

(a) Lampiran A - SURAT PENGAKUAN KEBENARAN MAKLUMAT

DAN KEESAHAN DOKUMEN YANG DIKEMUKAKAN

OLEH PENTENDER

(b) Lampiran B - MAKLUMAT AM LATAR BELAKANG

PENTENDER

(c) Lampiran C - DATA-DATA KEWANGAN PENTENDER

(d) Lampiran D - REKOD PENGALAMAN KERJA

(e) Lampiran E - KAKITANGAN TEKNIKAL

(f) Lampiran F - SENARAI KERJA KONTRAK SEMASA

(g) Lampiran G - KEEMPUNYAAN LOJI DAN PERALATAN

PENTENDER

Borang-borang ini hendaklah diisi dengan maklumat maklumat yang benar dan data data

yang tepat. Semua butiran perlu diisi dan jawapan yang jelas hendaklah diberikan

terhadap semua pertanyaan didalam borang borang di atas. Jika perlu helaian tambahan

boleh dilampirkan setiap helaian tambahan yang dilampirkan kepada borang borang lain

hendaklah ditandatangani oleh pentender.

5. Bagi pentender usahasama atau gabongan ( seperti yang dibenarkan oleh PKK ) antara

dua atau lebih Kontraktor setiap ahli gabongan hendaklah masing masing menyertakan

dokumen-dokumen yang tersebut diatas secara berasingan.

6. Semua maklumat dan dokumen dokumen yang tersebut di atas hendaklah dikemukakan

oleh pentender bersama sama tendemya sebelum tarikh mengemukakannya selepas itu.

Sebarang maklumat atau mana mana dokumen tersebut yang diterima selepas Tender

ditutup tidak akan diambil kira dalam penilaian keupayaan pentender.

7. Sekiranya pentender didapati memberi maklumat palsu atau sengaja menyorok (withhold)

atau tidak memberikan mana mana maklumat yang memberikan kesan negatif terhadap

keupayaannya, tendemya akan ditolak dan tindakan tatatertib akan diperakukan

terhadapnya.

B. Tempoh Siap Inginan*

1. Julat Tempoh Siap Inginan bagi projek ini antara …………… hingga …………. Minggu.

2. Pentender adalah dinasihatkan untuk menawarkan julat tempoh penyiapan kerja yang

dianggap sesuai dan munasabah baginya.

** Batalkan jika Tender berasaskan satu tempoh penyiapan yang ditetapkan oleh Jabatan.

Page 43: DOKUMEN SEBUTHARGA - pjk.edu.my · PDF fileBerjaya seperti di lampiran beserta dengan *Surat Setuju Terima/Borang Perjanjian Inden Kerja yang telah ditandatangani di mana ia ... SUB-SEWA

C. Kriteria Penilaian

1. Penilaian akan dibuat dalam dua (2) peringkat berdasarkan pra-syarat dan kriteria -kriteria

penilaian yang ditetapkan.

2. Penilaian Peringkat Pertama

2.1 Tender - tender yang diterima mestilah mematuhi beberapa pra-syarat sebelum boleh

dinilai diperingkat kedua. Pra syarat yang telah ditetapkan ialah:-

(i) Tender mestilah sempurna dimana pentender telah mematuhi syarat syarat

tender.

(ii) Tender telah disertai dengan dokumen-dokumen wajib yang telah ditetapkan

di perenggan A2 di atas.

(iii) Pentender mempunyai asset mudah cair tidak kurang daripada 3% dari

anggaran jabatan (kerja Pembina).

(iv) Pentender mestilah tidak mempunyai projek - projek yang mana prestasi

semasanya ridak memuaskan iaitu peratus (%) kemajuan sebenar melebihi

30% terkebelakang dari jadual atau sedang menghadapi tindakan penamatan

pengambilan kerjanya.

2.2 Hanya tender-tender yang memenuhi pra-syarat diatas sahaja yang akan dinilai di

peringkat kedua.

3. Penilaian Peringkat Kedua - Penentuan Tender Yang Paling Menguntungkan Untuk

Diperakukan

3.1 Penilaian akan dibuat berdasarkan kriteria - kriteria berikut:-

(i) Harga tender berbanding dengan anggaran Jabatan (kerja pembina).

(ii) Pengalaman Pentender menyiapkan projek dalam lima (5) tahun terbelakang.

(iii) Prestasi Kerja Semasa samada cemerlang atau memuaskan berdasarkan

laporan Pegawai Penguasa atau Pegawai Penyelia.

(iv) Kakitangan teknikal yang mencukupi untuk melaksanakan projek projek yang

ditender.

(v) Faktor faktor lain yang menyokong harga tendemya seperti pentender

mempunyai loji, kuari, kilang dan sebagainya.

3.2 Disamping itu kriteria-kriteria lain dalam menentukan tender yang akan diperakukan

adalah seperti berikut:

3.2.1 Tempoh Siap Kerja

Sekiranya tempoh siap tender terendah yang layak dipertimbangkan lebih

panjang dari had tertinggi julat Tempoh Siap Inginan (TSI) atau penengah

Tempoh-tempoh siap kerja yang ditawarkan (sekiranya TSI tidak ditetapkan)

Page 44: DOKUMEN SEBUTHARGA - pjk.edu.my · PDF fileBerjaya seperti di lampiran beserta dengan *Surat Setuju Terima/Borang Perjanjian Inden Kerja yang telah ditandatangani di mana ia ... SUB-SEWA

maka pelarasan ke atas harga tender akan dibuat untuk mengambilkira kesan

kelambatan penyiapan projek kepada kerajaan.

3.2.2 Beban Kerja Semasa

Pentender akan dipastikan tidak mempunyai beban kerja semasa yang terlalu

banyak yang dijangka akan dapat menjejaskan prestasinya.

Page 45: DOKUMEN SEBUTHARGA - pjk.edu.my · PDF fileBerjaya seperti di lampiran beserta dengan *Surat Setuju Terima/Borang Perjanjian Inden Kerja yang telah ditandatangani di mana ia ... SUB-SEWA

Lampiran A

SURAT PENGAKUAN KEBENARAN MAKLUMAT DAN KEESAHAN DOKUMEN YANG

DIKEMUKAKAN OLEH PENTENDER.

Nama Kontraktor : ……………………………………………….

Alamat : ……………………………………………….

……………………………………………….

Kepada,

(Pihak yang akan menilai tender)

Tuan,

Maklumat Latar Belakang, Kewangan dan Teknikal Pentender.

1. Kami telah membaca dengan teliti semua arahan arahan yang terkandung dalam Arahan

Kepada Pentender termasuk arahan arahan yang menghendakkan kami mengemukakan

maklumat maaklumat dan dokumen dokumen mengenai perkara diatas bersama sama

dokumen tender kami semasa mengemukakan Tender ini untuk membolehkan JKR menilai

keupayaan kami untuk melaksanakan kerja yang ditender, semasa penilaian Tender.

2. Kami faham dan mengambil maklum bahawa penilaian Tender ini akan mengambil kira dan

mementingkan keupayaan kami melaksanakan kerja yang ditender. Justeru itu tender kami

akan hanya dipertimbangkan untuk diperakukan kepada Lembaga Tender untuk disetuju

terima sekiranya kami didapati berupayaan untuk melaksanakan projek yang ditender,

mengikut penilaian JKR berasaskan maklumat maklumat dan dokumen dokumen yang kami

kemukakan.

3. Kami juga mengambil maklum bahawa kami dikehendaki mengemukakan semua maklumat

dan dokumen dokumen yang diminta bersama sama tender kami sebelum Tender ditutup dan

maklumat maklumat atau dokumen dokumen yang dikemukakan kemudian daripada itu tidak

akan diterima untuk diambil kira dalam penilaian keupayaan kami.

4. Kami mengaku bahawa maklumat maklumat dan data data yang kami berikan bersama sama

ini di Borang B,C,CA,D,E,F,FA dan dokumen dokumen yang kami sertakan bersamanya

setahu kami adalah semuanya benar dan sari pada semua segi dan telah mengambil maklum

dan sedar akan tindakan yang boleh diambil oleh Kerajaan terhadap kami dan / atau tender

kami, sekiranya mana mana maklumat, data data dan dokumen yang kami berikan itu didapati

tidak benar atau palsu.

5. Kami juga mengambil maklum dan sedar bahawa Tender kami akan ditolak (disqualified) dan

tidak akan dipertimbangkan sekiranya maklumat maklumat yang kami berikan tidak

mencukupi atau sekiranya kami gagal untuk memberkan bersama sama ini mana mana

maklumat dan / atau menyertakan mana mana dokumen dokumen penting yang sangat

diperlukan untuk membolehkan JKR menilai keupayaan kami, terutamanya dokumen

dokumen berhubung dengan kedudukan kewangan dan prestasi kerja semasa kami seperti

berikut:

(i) Salinan Akaun Syarikat yang telah disahkan dan diaudit oleh Juru Audit yang

bertauliah, bagi (2) tahun kewangan terakhir,

Page 46: DOKUMEN SEBUTHARGA - pjk.edu.my · PDF fileBerjaya seperti di lampiran beserta dengan *Surat Setuju Terima/Borang Perjanjian Inden Kerja yang telah ditandatangani di mana ia ... SUB-SEWA

(ii) Salinan Penyata Bulanan Akuan Bank mengenai Wang Dalam Tangan pentender bagi

tiga ( 3 ) bulan terakhir sebelum tarikh tutup Tender;

(ii) Laporan Penyelia Projek atas prestasi kerja semasa yang bukan projek JKR diatas

Borang FA dalam satu sampul berlakri bagi setiap kerja semasa yang sedang

dilaksanakan.

6. Kami dengan ini memberi kuasa kepada mana mana pegawai Kerajaan, jurutera jurutera

projek, bank dan kewangan lain, dan lain lain atau mana mana orang yang atau firma yang

berkenaan untuk memberikan maklumat maklumat yang dianggap perlu dan diminta oleh

JKR untuk menyemak makiumat maklumat yang kami berikan atau untuk mendapatkan

maklumat maklumat tambahan. Kami mengambil maklum bahawa pihak JKR juga boleh

merujuk apa apa maklumat yang kami kemukakan dengan mana mana pihak termasuk Jabatan

Hasil Dalam Negeri. Walaubagaimanapun, kami tetap bertanggungjawab diatas maklumat

maklumat dan dokumen dokumen yang kami berikan bersama sama ini.

Yang Benar,

(Tandatangan Pentender)

Nama Penuh : Tarikh :

Kad Pengenalan :

Atas Sifat :

yang diberi kuasa dengan sempumanya untuk

menandatangani Tender ini untuk dan bagi pihak

Meteri atau Cap Pentender

(Tandatangan Saksi)

Nama Penuh : Tarikh :

Kad Pengenalan :

Pekerjaan :

Alamat :

Page 47: DOKUMEN SEBUTHARGA - pjk.edu.my · PDF fileBerjaya seperti di lampiran beserta dengan *Surat Setuju Terima/Borang Perjanjian Inden Kerja yang telah ditandatangani di mana ia ... SUB-SEWA

Lampiran B

MAKLUMAT AM LATAR BELAKANG PENTENDER

Semua butir dilampirkan ini hendaklah diisi oleh Pentender dengan betul dan lengkap dan

dikembalikan bersama-sama dengan tendernya. Kegagalan berbuat demikian boleh mengakibatkan

tender ini ditolak atau/dan mengakibatkan tindakan tatatertib diambil keatas pentender berkenaan.

LATARBELAKANG PENTENDER

Bahagian A

1. Nama :

2. Alamat :

3. Kelas : Tajuk/Tajuk Kecil:

4. Tarikh didaftarkan :

5. Jika bertaraf Bumiputera, nyatakan :

Tarikh berkuatkuasa :

Tarikh tamat :

6. Bagi Syarikat Sdn. Bhd., nyatakan :

Modal dibenarkan :

Modal dibayar :

7. Ahli-ahli Lembaga Pengarah

Nama Jawatan Saham Modal

Dipegang

Page 48: DOKUMEN SEBUTHARGA - pjk.edu.my · PDF fileBerjaya seperti di lampiran beserta dengan *Surat Setuju Terima/Borang Perjanjian Inden Kerja yang telah ditandatangani di mana ia ... SUB-SEWA

8. Ahli-ahli Pengurusan

Nama Jawatan Kelulusan Akedemik/Iktisas

Page 49: DOKUMEN SEBUTHARGA - pjk.edu.my · PDF fileBerjaya seperti di lampiran beserta dengan *Surat Setuju Terima/Borang Perjanjian Inden Kerja yang telah ditandatangani di mana ia ... SUB-SEWA

Lampiran C

BORANG DATA-DATA KEWANGAN

A. Ringkasan harta dan liabiliti seperti yang ditunjukkan dalam Lembaran Imbangan (Balance

Sheet) yang diaudit bagi tahun kewangan terakhir.

Asset

(A)

Liabiliti

(B)

Nilai Kewangan

(Worth) (A - B)

Semasa:

Tetap :

Semasa:

Tetap :

Modal Pusingan :

Modal Tetap :

Jumlah : Jumlah : Net Woth:

B. Akaun Wang Di Tangan (Cash in Hand)

1. Nama dan Alamat Bank dimana akaun dibuka :

2. Nombor Akaun :

C. Kemudahan Kredit

1. Nama dan Alamat Bank dimana akaun dibuka :

2. Bentuk dan baki amaun yang boleh digunakan untuk projek pembinaan

(i) Overdraf atau Talian Kredit : RM

(ii) Overdraf bercagar : RM

(iii) Pinjaman Tetap yang akan/layak

diperolehi untuk projek : RM

(iv) ........................................ : RM

JUMLAH : RM

__________________________________________________________________________________

Peringatan Penting

* Sila sertakan salinan Akaun Syarikat bagi (2) tahun kewangan terakhir, yang disahkan dan

diaudit oleh Juru Audit bertauliah (Certified Accountant) atau sekiranya tiada, bagi tahun

kewangan setahun sebelumnya bagi menyokong data-data yang diberi Tender yang tidak

disertakan dengan Akaun ini akan ditolak.

** Sila Sertakan salinan penyata Bulanan Bank bagi tiga (3) bulan terakhir sebeelum tarikh tutu

Tender. Tender yang tidak disertakan dengan penyata akan ditolak.

*** Sila dapatkan dan sertakan Laporan sulit daripada pihak Bank/Institusi Kewangan atas format

seperti Borang CA, dalam satu sampul berlakri.

SULIT

Page 50: DOKUMEN SEBUTHARGA - pjk.edu.my · PDF fileBerjaya seperti di lampiran beserta dengan *Surat Setuju Terima/Borang Perjanjian Inden Kerja yang telah ditandatangani di mana ia ... SUB-SEWA

Lampiran D

REKOD PENGALAMAN KERJA

Senarai semua kerja yang disiapkan dalam 5 tahun lepas.

Bil. Nama Kontrak / Projek

Dan Skop Kerja+

Nilai Kontrak

(RM)

Nilai Pentender

Bertanggungja

wab*

Tempoh

Kontrak**

Tarikh

Milik

Tapak

Tarikh Siap Nama Dan Alamat

Pegawai Penguasa /

Jurutera Perunding

Nama Dan Alamat

Majikan Kontrak Sebenar

+ Salinan Perakuan / Pengesahan Siap Kerja bagi setiap kerja yang disenaraikan hendaklah disertakan.

* Hanya perlu diisi sekiranya pentender melaksanakan kerja sebagai ahli syarikat gabungan.

** Tempoh Kontrak hendaklah termasuk lanjutan masa yang diluluskan.

Page 51: DOKUMEN SEBUTHARGA - pjk.edu.my · PDF fileBerjaya seperti di lampiran beserta dengan *Surat Setuju Terima/Borang Perjanjian Inden Kerja yang telah ditandatangani di mana ia ... SUB-SEWA

Lampiran E

KAKITANGAN TEKNIKAL

Butir-butir kakitangan teknikal yang ada dalam penggajian pentender masa kini.

Bil. Nama dan No. K/Pengenalan

*

Kelulusan

Profesional /

Pendidikan**

Tahun

Kelulusan

Tarikh

Diambil

Bekerja

Jawatan Yang

Disandang / Tugas-

tugas Semasa

Pengalaman Lepas (Jawatan disandang,

nama projek dan majikan dan tempoh

bekerja dan sebagainya)

* Salinan Borang KWSP ‘A’ setiap pekerja bagi bulan caruman terakhir dan salinan perjanjian perkhidmatan ahli professional yang diambil

khidmat secara kontrak hendaklah disertakan.

** Sila sertakan salinan sijil kelulusan atau sijil keahlian Badan-badan professional.

Page 52: DOKUMEN SEBUTHARGA - pjk.edu.my · PDF fileBerjaya seperti di lampiran beserta dengan *Surat Setuju Terima/Borang Perjanjian Inden Kerja yang telah ditandatangani di mana ia ... SUB-SEWA

Lampiran F

SENARAI KERJA KONTRAK SEMASA

Senarai semua kerja di dalam tangan / sedang berjalan dan belum siap termasuk kontrak yang baru diaward.

Bil. Nama Kontrak / Projek

Dan Skop Kerja+

Nilai

Kontrak

(RM)

Nilai

Pentender

Bertanggungj

awab*

Tempoh

Kontrak**

Tarikh

Milik

Tapak

Tarikh

Siap

Kontrak

Kemajuan Kerja

Nama Dan Alamat

Jurutera Projek

Nama Dan Alamat

Majikan Ikut

Jadual

(%)

Sebenar

Dicapai

(%)

* Hanya perlu diisi sekiranya pentender melaksanakan kerja sebagai ahli syarikat gabungan.

** Tempoh Kontrak hendaklah termasuk lanjutan masa yang diluluskan.

+ Peringatan Penting:

Bagi setiap kerja semasa bukan projek JKR, sertakan (wajib) Laporan Penyelia Projek atau format seperti Borang FA, dalam satu sampul

berlakri. Tender yang tidak disertakan dengan laporan ini bagi setiap kerja semasa yang disenaraikan akan ditolak.

Page 53: DOKUMEN SEBUTHARGA - pjk.edu.my · PDF fileBerjaya seperti di lampiran beserta dengan *Surat Setuju Terima/Borang Perjanjian Inden Kerja yang telah ditandatangani di mana ia ... SUB-SEWA

Lampiran G

LAPORAN KEEMPUYAAN LOJI DAN PERALATAN PENTENDER

- Pentender hendaklah mengemukakan bukti dan dilengkapkan dengan gambar-gambar berkaitan dengan peralatan atau loji kepunyaannya bagi kerja-

kerja membaikpulih peralatan Mekanikal dalam format yang dinyatakan dibawah ini.

Bil. Jenis Modal, Buatan Dan

Keupayaan / Saiz

Tahun

Buatan

Bil. Setiap

Satu

Nilai Semasa

(RM)

Baki Umur

Bekerja

(Tahun)

Tempat Simpanan / Digunakan

Sekarang

Jenis Keupayaan (Nyatakan

Hak Milik Atau Dalam

Sewa/Beli)

A.

B.

Loji Pembinaan

Lori / Trak

(Pengangkutan Bahan Korekan

& Timbunan Sahaja)

* Salinan kad pengenalan dan/atau dokumen-dokumen lain bukti keempunyaan hakmilik pentender atau perjanjian sewabeli/sewapajak atas

setiap Loji dan Peralatan yang disenaraikan hendaklah disertakan.

Page 54: DOKUMEN SEBUTHARGA - pjk.edu.my · PDF fileBerjaya seperti di lampiran beserta dengan *Surat Setuju Terima/Borang Perjanjian Inden Kerja yang telah ditandatangani di mana ia ... SUB-SEWA

Lampiran H

BORANG CA - LAPORAN BANK/INSTITUSI KEWANGAN

MENGENAI KEDUDUKAN KEWANGAN PETENDER

(Borang ini hendaklah dilengkapkan oleh pihak bank atau institusi kewangan lain dan diserahkan

kepada petender dalam satu sampul berlakri untuk disertakan bersama-sama tendernya sekiranya

terdapat pentender mempunyai kemudahan kredit dengan Bank/Institusi Kewangan yang berkenaan)

Kepada,

(Pihak yang akan menilai tender)

Nama Pentender : .............................................................

Projek : Tender Untuk

…………………………………………………………………….…………

……

…………………………………………………………………………………

………….. ……………………………………………………………..

(A) Kemudahan Kredit yang boleh digunakan untuk pelaksanaan Projek :

Kemudahan Kredit yang diluluskan dan kemudian kredit tambahan minimum yang layak

diperolehi oleh pentender adalah seperti berikut :-

Bentuk Kemudahan Kredit Baki drp. Yang

Telah diluluskan

Tambahan

Minima Yang

Akan diluluskan

Jumlah

i

ii

iii

iv

v

Overdraf

Overdraf bercagar

Talian Kredit

Pinjaman Tetap yang

akan/layak diperolehi

untuk projek*

……………………...

RM

RM

RM

RM

RM

RM

RM

RM

RM

RM

RM

RM

RM

RM

RM

JUMLAH : RM RM RM

(*Jika Projek diawardkan kepada Pentender)

(B) ULASAN

Tandatangan untuk dan bagi pihak Bank : .......................................................................

Nama Bank : ........................................... Nama Pegawai : ...........................................

Materi Bank : ........................................... Jawatan : ...........................................

Tarikh : ...........................................

Page 55: DOKUMEN SEBUTHARGA - pjk.edu.my · PDF fileBerjaya seperti di lampiran beserta dengan *Surat Setuju Terima/Borang Perjanjian Inden Kerja yang telah ditandatangani di mana ia ... SUB-SEWA

Lampiran I

BORANG FA - LAPORAN PENYELIA PROJEK ATAS PRESTASI KERJA (BUKAN

PROJEK JKR) SEMASA PENTENDER

(Borang ini hendaklah dilengkapkan oleh Penyelia Projek atau Pembantu Kanannya yang mengawasi

projek dan diserahkan kepada Kontraktor dalam satu sampul berlakri untuk disertakan bersama sama

tendernya).

Kepada,

(Pihak yang akan menilai tender)

Nama Kontraktor :

Nama Projek Yang Dilaksanakan :

No. Kontrak :

Harga Kontrak (termasuk anggaran nilai kerja perubahan) : RM

Wang Kos Prima dan Peruntukan Sementara : RM

Nilai Kerja Pembina : RM

Tarikh Milik Tapak : Tempoh Kontrak : Minggu

Tarikh Penyiapan Asal :

Lanjutan Masa Yang Telah Diluluskan : Hari

Lanjutan Masa Seterusnya :

Yang difikirkan/dijangka layak diperakukan :

Hari

Atas sebab-sebab : (i)

(ii)

Kemajuan Kerja ( berdasarkan nilaian kerja yang telah dilaksanakan) :

Pencapaian sebenar : % Mengikut jadual : %

Tarikh Kerja dijangka akan dapat disiapkan :

Nilai Bahagian Kerja Yang Telah Siap : RM

Nilai Baki Kerja Yang Belum Siap : RM

Ulasan ulasan mengenai Prestasi Kontraktor :

(Nyatakan apa apa kepujian dan / atau kelemahan kontraktor dan juga apa apa tindakan / perakuan

yang diambil / dipertimbang berhubung dengan prestasi Kontraktor melaksanakan Kontrak).

(Tandatangan Pegawai Penguasa / Jurutera Projek / Wakilnya)

Nama :

Jawatan :

Tarikh :

Page 56: DOKUMEN SEBUTHARGA - pjk.edu.my · PDF fileBerjaya seperti di lampiran beserta dengan *Surat Setuju Terima/Borang Perjanjian Inden Kerja yang telah ditandatangani di mana ia ... SUB-SEWA

Lampiran J

BORANG FA1 - LAPORAN JURUTERA PROJEK ATAS PRESTASI KERJA SEMASA

PENTENDER

(Borang ini hendaklah dilengkapkan oleh Jurutera Projek atau Pembantu Kanannya yang mengawasi

projek apabila diminta berbuat demikian oleh Pegawai Penilaian dan hendaklah dihantar segera

dengan menggunakan mesin fax).

Kepada,

(Pihak yang akan menilai tender)

Nama Kontraktor :

Nama Projek Yang Dilaksanakan :

No. Kontrak :

Harga Kontrak (termasuk anggaran nilai kerja perubahan) : RM

Wang Kos Prima dan Peruntukan Sementara : RM

Nilai Kerja Pembina : RM

Tarikh Milik Tapak : Tempoh Kontrak : Minggu

Tarikh Penyiapan Asal :

Lanjutan Masa Yang Telah Diluluskan : Hari

Lanjutan Masa Seterusnya : Hari

Atas sebab-sebab : (i)

(ii)

Kemajuan Kerja ( berdasarkan nilaian kerja yang telah dilaksanakan) :

Pencapaian sebenar : % Mengikut jadual : %

Tarikh Kerja dijangka akan dapat disiapkan :

Nilai Bahagian Kerja Yang Telah Siap : RM

Nilai Baki Kerja Yang Belum Siap : RM

Ulasan ulasan mengenai Prestasi Kontraktor :

(Nyatakan apa apa kepujian dan / atau kelemahan kontraktor dan juga apa apa tindakan / perakuan

yang diambil / dipertimbang berhubung dengan prestasi Kontraktor melaksanakan Kontrak).

(Tandatangan Pegawai Penguasa / Jurutera Projek / Wakilnya)

Nama :

Jawatan :

Tarikh :