LAPORAN KEMAJUAN PROJEK NO.19

‘MAC 2009’

PROJEK ADTEC TAIPING

KEMENTERIAN SUMBER MANUSIA

JABATAN KERJA RAYA MALAYSIA

KAMALBINA SDN. BHD

PEMILIK

PEGARAH PROJEK

KONTRAKTOR R&B

ADTEC TAIPING

LOKASI PROJEK

BANGUNAN PENTADBIRAN

BENGKEL TEK. MAKLUMAT& JAMIN KUALITI

DEWAN BESAR

PUSAT SUMBER

DEWAN KULIAH

LOBI UTAMA

KAFETERIA

MIKRO ELEKTRONIK

KOMPOSIT PLASTIK

M&E PLANT ROOM

1

TNB SUB

STATION

SERAMIK

M&E PLANT ROOM

2

GARAJ KENDERAAN

ASRAMA LELAKIASRAMA PEREMPUAN

DEWANMAKAN

SURAU

KELAS F

KELAS G

KUARTERSB, C, C&D

PELAN TAPAK ADTEC TAIPING

KEMAJUAN KERJA FIZIKAL

JADUAL : 84.22%SEBENAR : 68.03%KESELURUHAN : -16.19%

TARIKH LAPORAN : 11 MAC 2009

KEMAJUAN KERJA KEWANGAN

JADUAL : 86.30%SEBENAR : 68.81%KESELURUHAN : -17.49% @ 136 HARI

(LEWAT )

TARIKH LAPORAN : 11 MAC 2009

Graf Kemajuan Kerja Keseluruhan Sehingga 11/3/2009

0.00

10.00

20.00

30.00

40.00

50.00

60.00

70.00

80.00

90.00

100.00

Bulan

Per

atu

s %

% Kem. Fizikal J adual % Kem. Fizikal Sebenar

% Kem. Kewangan J adual % Kem. Kewangan Sebenar

% Kem. Fizikal J adual 0.00 0.48 1.04 2.56 4.19 6.12 7.70 9.98 13.53 18.44 20.82 23.34 26.09 29.06 30.76 33.81 36.84 41.32 43.00 47.08 60.55 70.88 84.22 98.95 100.00

% Kem. Fizikal Sebenar 0.00 2.59 5.28 7.56 9.30 11.64 13.12 15.62 18.74 22.53 26.73 29.56 32.40 35.71 37.09 41.47 45.77 46.74 50.89 55.19 58.46 67.03 68.03

% Kem. Kewangan J adual 0.00 0.94 2.05 3.93 5.77 8.92 10.71 13.46 17.45 22.24 25.62 27.75 31.15 34.56 35.93 39.26 42.63 45.59 48.62 52.35 64.16 74.78 86.30 99.09 100.00

% Kem. Kewangan Sebenar 0.00 3.97 6.30 13.91 15.50 17.58 17.26 19.52 22.30 25.93 30.26 32.79 35.32 38.47 38.97 43.62 47.34 48.16 52.42 56.36 59.42 68.50 68.81

16-05-07 25-06-07 24-07-07 20-08-07 13-09-07 18-10-07 09-11-07 05-12-07 12-01-08 21-02-08 27-03-08 15-04-08 29-05-08 08-07-08 15-07-08 22-08-08 19-09-08 28-10-08 14-11-08 04-12-08 08-01-09 12-02-09 11-03-09 15-04-09 13-05-09

Actual Physical 68.03%

Actual Financial

68.81%

MONTH PLANNED ACTUAL AHEAD / DELAY

FEB 09’ 97.222% 65.52% - 31.70%

MAC 09’ 99.12% 74.17% - 24.95%

MECHANICAL PLANNED

ACTUAL

AIR COND 100.00% 50.00%

FIRE FIGHTING 100.00% 39.77%

KITCHEN EQUIP. NA NA

LPG INSTALL. NA NA

COMPRES. AIR NA NA

DUST CONTROL NA NA

PROCESS COOLING

NA NA

KEMAJUAN KERJA FIZIKAL - DEWAN BESAR

BANGUNAN

ELECTRICAL PLANNED ACTUAL

WIRING 100.00% 85.00%

SUBMAIN CABLE 100.00% 75.00%

DB 100.00% 0.00%

LUMINAIRE 100.00% 0.00%

MAIN S/BOARD 100.00% 0.00%

LPS NA NA

PA 100.00% 31.81%

SMATV 100.00% 25.00%

CCTV NA NA

ICT 100.00% 0.00%

DEWAN BESAR

DEWAN BESAR

MONTH PLANNED ACTUAL AHEAD / DELAY

FEB 09’ 82.83% 78.68% -4.15%

MAC 09’ 95.00% 89.22% -5,78%

MECHANICAL PLANNED

ACTUAL

AIR COND NA NA

FIRE FIGHTING NA NA

KITCHEN EQUIP. NA NA

LPG INSTALL. NA NA

COMPRES. AIR NA NA

DUST CONTROL NA NA

PROCESS COOLING

NA NA

KEMAJUAN KERJA FIZIKAL – LOBI

BANGUNAN

ELECTRICAL PLANNED ACTUAL

WIRING 100.00% 90.00%

SUBMAIN CABLE 100.00% 85.00%

DB 100.00% 0.00%

LUMINAIRE 100.00% 0.00%

MAIN S/BOARD NA NA

LPS NA NA

PA 100.00% 65.37%

SMATV NA NA

CCTV 100.00% 65.37%

ICT NA NA

LOBI UTAMA

MONTH PLANNED ACTUAL AHEAD / DELAY

FEB 09’ 83.03% 66.39% -16.64%

MAC 09’ 94.20% 74.34% -19.87%

MECHANICAL PLANNED

ACTUAL

AIR COND 62.86% 75.00%

FIRE FIGHTING 86.64% 3.87%

KITCHEN EQUIP. NA NA

LPG INSTALL. NA NA

COMPRES. AIR NA NA

DUST CONTROL NA NA

PROCESS COOLING

NA NA

KEMAJUAN KERJA FIZIKAL – DEWAN KULIAH UTAMABANGUNAN

ELECTRICAL PLANNED ACTUAL

WIRING 100.00% 90.00%

SUBMAIN CABLE 56.25% 75.00%

DB 100.00% 0.00%

LUMINAIRE 0.00% 50.00%

MAIN S/BOARD 100.00% 0.00%

LPS 100.00% 83.13%

PA 100.00% 28.96%

SMATV NA NA

CCTV NA NA

ICT 100.00% 0.00%

DEWAN KULIAH UTAMA

MONTH PLANNED ACTUAL AHEAD / DELAY

FEB 09’ 93.37% 84.41% -8.96%

MAC 09’ 96.79% 85.99% -10.80%

MECHANICAL PLANNED

ACTUAL

AIR COND 100.00% 75.00%

FIRE FIGHTING 79.40% 29.24%

KITCHEN EQUIP. NA NA

LPG INSTALL. NA NA

COMPRES. AIR NA NA

DUST CONTROL NA NA

PROCESS COOLING

NA NA

KEMAJUAN KERJA FIZIKAL – PUSAT SUMBER/PERPUSTAKAAN

BANGUNAN

ELECTRICAL PLANNED ACTUAL

WIRING 100.00% 90.00%

SUBMAIN CABLE 100.00% 85.00%

DB 100.00% 0.00%

LUMINAIRE 100.00% 75.00%

MAIN S/BOARD 100.00% 0.00%

LPS 100.00% 77.33%

PA 100.00% 41.75%

SMATV 100.00% 68.59%

CCTV NA NA

ICT 40.84% 0.00%

PUSAT SUMBER / PERPUSTAKAAN

MONTH PLANNED ACTUAL AHEAD / DELAY

FEB 09’ 91.35% 77.52% -13.83%

MAC 09’ 96.07% 83.49% -12.58%

MECHANICAL PLANNED

ACTUAL

AIR COND 95.68% 50.00%

FIRE FIGHTING 81.99% 40.30%

KITCHEN EQUIP. NA NA

LPG INSTALL. NA NA

COMPRES. AIR NA NA

DUST CONTROL NA NA

PROCESS COOLING

NA NA

KEMAJUAN KERJA FIZIKAL – PENTADBIRAN & PENGURUSAN SUMBERBANGUNAN

ELECTRICAL PLANNED ACTUAL

WIRING 100.00% 77.50%

SUBMAIN CABLE 100.00% 75.00%

DB 100.00% 0.00%

LUMINAIRE 100.00% 30.00%

MAIN S/BOARD 100.00% 0.00%

LPS 100.00% 72.59%

PA 100.00% 19.15%

SMATV 100.00% 62.46%

CCTV 99.86% 2.13%

ICT 82,62% 0.00%

BANGUNAN PENTADBIRAN & PENGURUSAN SUMBER

MONTH PLANNED ACTUAL AHEAD / DELAY

FEB 09’ 84.36% 89.11% -4.75%

MAC 09’ 94.82% 93.88% -0.95%

MECHANICAL PLANNED

ACTUAL

AIR COND 76.19% 0.00%

FIRE FIGHTING 14.60% 6.32%

KITCHEN EQUIP. 45.48% 0.00%

LPG INSTALL. NA NA

COMPRES. AIR NA NA

DUST CONTROL NA NA

PROCESS COOLING

NA NA

KEMAJUAN KERJA FIZIKAL - KAFETARIA

BANGUNAN

ELECTRICAL PLANNED ACTUAL

WIRING 100.00% 90.00%

SUBMAIN CABLE 100.00% 85.00%

DB 100.00% 0.00%

LUMINAIRE 100.00% 75.00%

MAIN S/BOARD NA NA

LPS 75.13% 66.47%

PA 100.00% 27.35%

SMATV 99.59% 60.35%

CCTV NA NA

ICT 100.00% 0.00%

KAFETERIA

MONTH PLANNED ACTUAL AHEAD / DELAY

FEB 09’ 85.84% 81.62% -4.22%

MAC 09’ 95.07% 84.50% -10.56%

MECHANICAL PLANNED

ACTUAL

AIR COND 57.23% 50.00%

FIRE FIGHTING 100.00% 15.93%

KITCHEN EQUIP. NA NA

LPG INSTALL. NA NA

COMPRES. AIR NA NA

DUST CONTROL NA NA

PROCESS COOLING

NA NA

KEMAJUAN KERJA FIZIKAL – BENGKEL TEKNOLOGI MAKLUMATBANGUNAN

ELECTRICAL PLANNED ACTUAL

WIRING 100.00% 90.00%

SUBMAIN CABLE 100.00% 90.00%

DB 100.00% 90.00%

LUMINAIRE 100.00% 50.00%

MAIN S/BOARD 100.00% 0.00%

LPS 100.00% 87.01%

PA 100.00% 42.43%

SMATV 100.00% 70.94%

CCTV 97.59% 33.71%

ICT 29.05% 0.00%

BENGKEL TEKNOLOGI MAKLUMAT

MONTH PLANNED ACTUAL AHEAD / DELAY

FEB 09’ 78.05% 86.03% 7.98%

MAC 09’ 88.52% 90.27% 1.75%

MECHANICAL PLANNED

ACTUAL

AIR COND 56.66% 75.00%

FIRE FIGHTING 49.72% 34.03%

KITCHEN EQUIP. NA NA

LPG INSTALL. NA NA

COMPRES. AIR 62.86% 75.00%

DUST CONTROL NA NA

PROCESS COOLING

35.30% 0.00%

KEMAJUAN KERJA FIZIKAL – BENGKEL KEJ. BAHAN TERMAJU (PLASTIK)BANGUNAN

ELECTRICAL PLANNED ACTUAL

WIRING 100.00% 90.00%

SUBMAIN CABLE 47.06% 85.00%

DB 0.00% 0.00%

LUMINAIRE 0.00% 75.00%

MAIN S/BOARD 0.00% 0.00%

LPS 86.70% 91.49%

PA 85.81% 56.22%

SMATV NA NA

CCTV 77.25% 49.69%

ICT 17.49% 1.34%

BENGKEL KEJ. BAHAN TERMAJU (PLASTIK)

MONTH PLANNED ACTUAL AHEAD / DELAY

FEB 09’ 79.39% 83.64% 4.25%

MAC 09’ 87.48% 91.18% 3.70%

MECHANICAL PLANNED

ACTUAL

AIR COND 62.87% 75.00%

FIRE FIGHTING 67.96% 32.95%

KITCHEN EQUIP. NA NA

LPG INSTALL. NA NA

COMPRES. AIR 68.57% 75.00%

DUST CONTROL 48.77% 23.77%

PROCESS COOLING

50.33% 0.00%

KEMAJUAN KERJA FIZIKAL – BENGKEL KEJ. BAHAN TERMAJU (KOMPOSIT)BANGUNAN

ELECTRICAL PLANNED ACTUAL

WIRING 100.00% 90.00%

SUBMAIN CABLE 58.22% 85.00%

DB 0.00% 0.00%

LUMINAIRE 35.71% 75.00%

MAIN S/BOARD 35.71% 0.00%

LPS 81.02% 82.52%

PA 83.73% 48.47%

SMATV NA NA

CCTV 92.94% 50.54%

ICT 15.86% 1.16%

BENGKEL KEJ. BAHAN TERMAJU (KOMPOSIT)

MONTH PLANNED ACTUAL AHEAD / DELAY

FEB 09’ 76.14% 79.96% 3.82%

MAC 09’ 81.17% 90.55% 9.38%

MECHANICAL PLANNED

ACTUAL

AIR COND 41.99% 75.00%

FIRE FIGHTING 43.45% 33.30%

KITCHEN EQUIP. NA NA

LPG INSTALL. NA NA

COMPRES. AIR 77.14% 75.00%

DUST CONTROL 16.46% 8.86%

PROCESS COOLING

41.29% 0.00%

KEMAJUAN KERJA FIZIKAL – BENGKEL KEJ. BAHAN TERMAJU (SERAMIK)BANGUNAN

ELECTRICAL PLANNED ACTUAL

WIRING 100.00% 90.00%

SUBMAIN CABLE 72.22% 85.00%

DB 0.00% 0.00%

LUMINAIRE 0.00% 75.00%

MAIN S/BOARD 0.00% 0.00%

LPS 76.32% 89.38%

PA 97.72% 49.95%

SMATV NA NA

CCTV 74.79% 57.16%

ICT 23.12% 1.58%

BENGKEL KEJ. BAHAN TERMAJU (SERAMIK)

MONTH PLANNED ACTUAL AHEAD / DELAY

FEB 09’ 80.11% 77.74% -2.37%

MAC 09’ 91.91% 83.93% -7.97%

MECHANICAL PLANNED

ACTUAL

AIR COND 53.50% 55.00%

FIRE FIGHTING 79.89% 14.81%

KITCHEN EQUIP. NA NA

LPG INSTALL. NA NA

COMPRES. AIR 100.00% 75.00%

DUST CONTROL 71.70% 19.13%

PROCESS COOLING

NA NA

KEMAJUAN KERJA FIZIKAL – BENGKEL KEJ. JAMINAN KUALITIBANGUNAN

ELECTRICAL PLANNED ACTUAL

WIRING 100.00% 82.50%

SUBMAIN CABLE 100.00% 90.00%

DB 100.00% 85.00%

LUMINAIRE 14.29% 45.00%

MAIN S/BOARD 100.00% 0.00%

LPS 91.41% 81.69%

PA 100.00% 33.28%

SMATV 98.53% 40.97%

CCTV 86.29% 40.48%

ICT 28.12% 0.00%

BENGKEL KEJ. JAMINAN KUALITI

MONTH PLANNED ACTUAL AHEAD / DELAY

FEB 09’ 79.37% 78.27% -1.10%

MAC 09’ 89.92% 87.86% -2.06%

MECHANICAL PLANNED

ACTUAL

AIR COND 58.27% 50.00%

FIRE FIGHTING 36.20% 11.16%

KITCHEN EQUIP. NA NA

LPG INSTALL. NA NA

COMPRES. AIR 94.29% 75.00%

DUST CONTROL NA NA

PROCESS COOLING

NA NA

KEMAJUAN KERJA FIZIKAL – BENGKEL MIKRO ELEKTRONIKBANGUNAN

ELECTRICAL PLANNED ACTUAL

WIRING 100.00% 90.00%

SUBMAIN CABLE 90.48% 85.00%

DB 0.00% 7.00%

LUMINAIRE 0.00% 45.00%

MAIN S/BOARD 0.00% 0.00%

LPS 83.20% 84.16%

PA 98.98% 39.69%

SMATV 80.65% 55.50%

CCTV 88.56% 52.62%

ICT 31.59% 0.00%

BENGKEL MIKRO ELEKTRONIK

MONTH PLANNED ACTUAL AHEAD / DELAY

FEB 09’ 90.43% 95.76% 5.33%

MAC 09’ 95.86% 96.63% 0.77%

MECHANICAL PLANNED

ACTUAL

AIR COND 100.00% 90.00%

FIRE FIGHTING NA NA

KITCHEN EQUIP. NA NA

LPG INSTALL. NA NA

COMPRES. AIR NA NA

DUST CONTROL NA NA

PROCESS COOLING

NA NA

KEMAJUAN KERJA FIZIKAL – KUATERS KELAS ‘B’

BANGUNAN

ELECTRICAL PLANNED ACTUAL

WIRING 100.00% 90.00%

SUBMAIN CABLE 100.00% 90.00%

DB 100.00% 90.00%

LUMINAIRE 100.00% 90.00%

MAIN S/BOARD 100.00% 0.00%

LPS 100.00% 90.40%

PA NA NA

SMATV 100.00% 32.27%

CCTV 100.00% 34.02%

ICT 100.00% 90.00%

KUARTERS KELAS ‘B’

MONTH PLANNED ACTUAL AHEAD / DELAY

FEB 09’ 88.42% 95.12% 6.70%

MAC 09’ 95.03% 96.71% 1.68%

MECHANICAL PLANNED

ACTUAL

AIR COND 100.00% 90.00%

FIRE FIGHTING NA NA

KITCHEN EQUIP. NA NA

LPG INSTALL. NA NA

COMPRES. AIR NA NA

DUST CONTROL NA NA

PROCESS COOLING

NA NA

KEMAJUAN KERJA FIZIKAL – KUATERS KELAS ‘C’

BANGUNAN

ELECTRICAL PLANNED ACTUAL

WIRING 100.00% 90.00%

SUBMAIN CABLE 100.00% 90.00%

DB 100.00% 90.00%

LUMINAIRE 100.00% 90.00%

MAIN S/BOARD 100.00% 0.00%

LPS 98.44% 90.63%

PA NA NA

SMATV 100.00% 24.75%

CCTV NA NA

ICT 100.00% 62.02%

KUARTERS KELAS ‘C’

MONTH PLANNED ACTUAL AHEAD / DELAY

FEB 09’ 84.31% 94.25% 9.94%

MAC 09’ 92.69% 96.33% 3.63%

MECHANICAL PLANNED

ACTUAL

AIR COND 100.00% 90.00%

FIRE FIGHTING NA NA

KITCHEN EQUIP. NA NA

LPG INSTALL. NA NA

COMPRES. AIR NA NA

DUST CONTROL NA NA

PROCESS COOLING

NA NA

KEMAJUAN KERJA FIZIKAL – KUATERS KELAS ‘C+D’BANGUNAN

ELECTRICAL PLANNED ACTUAL

WIRING 100.00% 90.00%

SUBMAIN CABLE 100.00% 90.00%

DB 100.00% 90.00%

LUMINAIRE 100.00% 90.00%

MAIN S/BOARD 100.00% 0.00%

LPS 100.00% 91.85%

PA NA NA

SMATV 100.00% 32.27%

CCTV NA NA

ICT 100.00% 90.00%

KUARTERS KELAS ‘C’ + ‘D’

MONTH PLANNED ACTUAL AHEAD / DELAY

FEB 09’ 77.45% 91.08% 13.63%

MAC 09’ 85.15% 94.13% 8.98%

MECHANICAL PLANNED

ACTUAL

AIR COND NA NA

FIRE FIGHTING NA NA

KITCHEN EQUIP. NA NA

LPG INSTALL. NA NA

COMPRES. AIR NA NA

DUST CONTROL NA NA

PROCESS COOLING

NA NA

KEMAJUAN KERJA FIZIKAL – KUATERS KELAS F ( 1 BLOK 4 TINGKAT & I BLOK 5 TINGKAT)BANGUNAN

ELECTRICAL PLANNED ACTUAL

WIRING 100.00% 90.00%

SUBMAIN CABLE 52.38% 90.00%

DB 0.00% 90.00%

LUMINAIRE 0.00% 90.00%

MAIN S/BOARD 0.00% 0.00%

LPS 100.00% 88.80%

PA NA NA

SMATV 100.00% 73.58%

CCTV NA NA

ICT 100.00% 65.58%

KUARTERS KELAS ‘F’ ( 4 TINGKAT )

KUARTERS KELAS ‘F’ ( 5 TINGKAT )

MONTH PLANNED ACTUAL AHEAD / DELAY

FEB 09’ 77.88% 92.63% 14.75%

MAC 09’ 86.68% 93.87% 7.19%

MECHANICAL PLANNED

ACTUAL

AIR COND NA NA

FIRE FIGHTING NA NA

KITCHEN EQUIP. NA NA

LPG INSTALL. NA NA

COMPRES. AIR NA NA

DUST CONTROL NA NA

PROCESS COOLING

NA NA

KEMAJUAN KERJA FIZIKAL – KUATERS KELAS G

(1 BLOK 4 TINGKAT & 1 BLOK 5 TINGKAT)BANGUNAN

ELECTRICAL PLANNED ACTUAL

WIRING 100.00% 90.00%

SUBMAIN CABLE 100.00% 90.00%

DB 44.44% 90.00%

LUMINAIRE 0.00% 90.00%

MAIN S/BOARD 26.67% 0.00%

LPS 100.00% 88.80%

PA NA NA

SMATV 100.00% 73.58%

CCTV NA NA

ICT 100.00% 69.85%

KUARTERS KELAS ‘G’ ( 5 TINGKAT )

KUARTERS KELAS ‘G’ ( 4 TINGKAT )

MONTH PLANNED ACTUAL AHEAD / DELAY

FEB 09’ 98.16% 94.87% -3.29%

MAC 09’ 98.39% 96.95% -1.44%

MECHANICAL PLANNED

ACTUAL

AIR COND 100.00% 75.00%

FIRE FIGHTING 100.00% 12.24%

KITCHEN EQUIP. 42.73% 0.00%

LPG INSTALL. NA NA

COMPRES. AIR NA NA

DUST CONTROL NA NA

PROCESS COOLING

NA NA

KEMAJUAN KERJA FIZIKAL – DEWAN MAKAN

BANGUNAN

ELECTRICAL PLANNED ACTUAL

WIRING 100.00% 90.00%

SUBMAIN CABLE 100.00% 85.00%

DB 100.00% 50.00%

LUMINAIRE 100.00% 75.00%

MAIN S/BOARD 100.00% 0.00%

LPS 100.00% 88.67%

PA 100.00% 51.18%

SMATV 100.00% 60.35%

CCTV NA NA

ICT 100.00% 0.00%

DEWAN MAKAN

MONTH PLANNED ACTUAL AHEAD / DELAY

FEB 09’ 86.42% 91.05% 4.63%

MAC 09’ 92.69% 95.69% 3.00%

MECHANICAL PLANNED

ACTUAL

AIR COND 100.00% 10.00%

FIRE FIGHTING 100.00% 29.58%

KITCHEN EQUIP. NA NA

LPG INSTALL. NA NA

COMPRES. AIR NA NA

DUST CONTROL NA NA

PROCESS COOLING

NA NA

KEMAJUAN KERJA FIZIKAL – ASRAMA LELAKI A & BBANGUNAN

ELECTRICAL PLANNED ACTUAL

WIRING 89.29% 86.25%

SUBMAIN CABLE 0.00% 85.00%

DB 0.00% 50.00%

LUMINAIRE 0.00% 75.00%

MAIN S/BOARD 0.00% 0.00%

LPS 93.12% 85.86%

PA 60.31% 54.28%

SMATV 60.53% 54.88%

CCTV 42.12% 31.69%

ICT 98.57% 78.12%

ASRAMA LELAKI A & B

MONTH PLANNED ACTUAL AHEAD / DELAY

FEB 09’ 81.04% 93.81% 12.77%

MAC 09’ 90.09% 96.91% 6.82%

MECHANICAL PLANNED

ACTUAL

AIR COND 17.86% 10.00%

FIRE FIGHTING 46.33% 20.18%

KITCHEN EQUIP. NA NA

LPG INSTALL. NA NA

COMPRES. AIR NA NA

DUST CONTROL NA NA

PROCESS COOLING

NA NA

KEMAJUAN KERJA FIZIKAL – ASRAMA PEREMPUAN C & DBANGUNAN

ELECTRICAL PLANNED ACTUAL

WIRING 100.00% 90.00%

SUBMAIN CABLE 100.00% 85.00%

DB 100.00% 50.00%

LUMINAIRE 100.00% 75.00%

MAIN S/BOARD 100.00% 0.00%

LPS 93.12% 85.86%

PA 60.31% 54.28%

SMATV 60.53% 54.88%

CCTV 42.12% 31.69%

ICT 98.57% 78.12%

ASRAMA PEREMPUAN C & D

MONTH PLANNED ACTUAL AHEAD / DELAY

FEB 09’ 77.94% 78.73% 0.79%

MAC 09’ 86.10% 84.06% -2.04%

MECHANICAL PLANNED

ACTUAL

AIR COND NA NA

FIRE FIGHTING 57.14% 0.00%

KITCHEN EQUIP. NA NA

LPG INSTALL. NA NA

COMPRES. AIR NA NA

DUST CONTROL NA NA

PROCESS COOLING

NA NA

KEMAJUAN KERJA FIZIKAL - SURAU

BANGUNAN

ELECTRICAL PLANNED ACTUAL

WIRING 100.00% 75.00%

SUBMAIN CABLE 41.67% 75.00%

DB NA NA

LUMINAIRE 0.00% 0.00%

MAIN S/BOARD 0.00% 0.00%

LPS 65.01% 81.70%

PA 87.81% 22.89%

SMATV NA NA

CCTV NA NA

ICT NA NA

SURAU

MONTH PLANNED ACTUAL AHEAD / DELAY

FEB 09’ 91.60% 87.62% 3.98%

MAC 09’ 99.03% 98.95% -0.45%

MECHANICAL PLANNED

ACTUAL

AIR COND NA NA

FIRE FIGHTING 0.00% 0.00%

KITCHEN EQUIP. NA NA

LPG INSTALL. NA NA

COMPRES. AIR NA NA

DUST CONTROL NA NA

PROCESS COOLING

NA NA

KEMAJUAN KERJA FIZIKAL - ASTAKA

BANGUNAN SOKONGAN

ELECTRICAL PLANNED ACTUAL

WIRING 100.00% 90.00%

SUBMAIN CABLE 100.00% 85.00%

DB 100.00% 0.00%

LUMINAIRE 100.00% 75.00%

MAIN S/BOARD 100.00% 0.00%

LPS 69.22% 37.93%

PA 100.00% 28.62%

SMATV NA NA

CCTV NA NA

ICT NA NA

BANGUNAN SOKONGAN

ASTAKA

MONTH PLANNED ACTUAL AHEAD / DELAY

MAC 09’ 91.00% 99.77% 8.77%

MECHANICAL PLANNED

ACTUAL

AIR COND 94.03% 77.59%

FIRE FIGHTING 79.72% 0.00%

KITCHEN EQUIP. NA NA

LPG INSTALL. 0.00% 0.00%

COMPRES. AIR NA NA

DUST CONTROL NA NA

PROCESS COOLING

NA NA

KEMAJUAN KERJA FIZIKAL – M&E PLANT ROOM

BANGUNAN SOKONGAN

ELECTRICAL PLANNED ACTUAL

WIRING 100.00% 90.00%

SUBMAIN CABLE 100.00% 75.00%

DB 100.00% 0.00%

LUMINAIRE 100.00% 75.00%

MAIN S/BOARD 100.00% 0.00%

LPS NA NA

PA NA NA

SMATV NA NA

CCTV NA NA

ICT NA NA

BANGUNAN SOKONGAN

M&E PLANT ROOM – PUSAT SUMBER

BANGUNAN SOKONGAN

M&E PLANT ROOM - BENGKEL

DECORATIVE FENCE

BANGUNAN SOKONGAN

GARAJ KENDERAAN

ELEVATED WATER TANK, PUMP HOUSE & SUCTION TANK

WAKAF

LALUAN BERBUMBUNG

OPEN PLAZA

KERJA INFRA – JALAN UTAMA

GELANGGANG PERMAINAN

M&E INSTALLATION

M&E INSTALLATION

M&E INSTALLATION

BENGKEL MIKROELEKTRONIK – CLEAN ROOM

BENGKEL MIKROELEKTRONIK – CLEAN ROOM

• SEKIAN TERIMA KASIH