1. INTRODUCTION
The Standard Practice and Standard Content are part of the NOSS document which is produced together with the Training Manual and Internship Manual to complete the whole NOSS.
This is a review NOSS for the Industrial Automation Engineering Support Service under the Machinery & Equipment sector. This document only covers competency standard for Level 2. This NOSS illustrates a structured set of activities that are essential to reach competencies for this particular occupation as well as facilitating interested individuals to embark on a career in this industry.
The development of this NOSS is to attract industry and training sectors towards a flexible, dynamic and responsive skills accreditation systems to meet the industrial needs. This NOSS shall be used as a guide to keep current training programs up to date and abreast with Industrial Automation Engineering science and technology.
Industrial automation is a discipline that comprises of knowledge, skills and attitude from various engineering fields, which include mechatronics, electronic, electrical, mechanical, chemical, metallurgy, computer, software and communication engineering. In today’s competitive free market environment the dependency on human strength and capability alone does not position the industrialists ahead of their competitors. Entrepreneurs are under tremendous pressure when customers required higher quantity of products within shorter period of time, but putting lower price as one of the conditions. The uncertainty on the demand for labour supply in terms of quality and quantity, and the insecure social environment are two of the major issues faced in the course of strengthening the organization’s production or services capacity. This major syndrome that has haunted the entrepreneurs since the 80s has successfully been reduced to a more comfortable level with the establishment of industrial automation systems. With the automation system, many industries previously depended highly on labourers have opted for the automation system and managed to stabilize their productions. Thus, at the same time, the difficulty in obtaining workforces in dangerous, difficult and dirty sectors or known as 3D sector could now be overcome. The establishment of industrial automation system has stabilized the productions that previously depended upon the volatile human labors. With the automation system, the ability in maintaining the production standards due to the elimination of exhaustion and emotional factors in the systems itself is higher. It has been proven to date that demands on the products of industrial automation has increased and the usage of automation system in the industry becomes a necessity and undisputed. In brief industrial automation is a way of industrial life today and in the future. It is hard to imagine industrial societies lives without industrial automation as it covers just about any productions and services including the production of food, equipment, hardware, mining, construction, shipping, aeronautical, agriculture, medical, aerospace, defense and weaponry. Continuous effort in the
2
creations of new areas in science and technology and existing system modifications pursuits are nonstop and limitless.
The Industrial Automation Engineering Support Service personnel are the technicians who are responsible for the industrial automation engineering support service functions in organizations. The role of the incumbent is to ensure the administration and execution of the support service functions is well-organized in order to achieve the departmental objectives and organizational mission and vision as a whole. It is the requirement for the incumbent to have the industrial automation related engineering skills, knowledge and attitude.
2. OCCUPATIONAL STRUCTURE
This NOSS provides the employers and employees the information on Industrial Automation Engineering Support Service functions and working environment. It underlines the career path and employment development for this profession.
2.1 OCCUPATIONAL AREA Industrial automation technology utilized in various industries such as manufacturing, engineering services, water supply engineering, construction, oil & gas, mining, security & defence, building services, transportation, maritime, hospitality, sea port & air port Services, Bio-Medical & Health services, agriculture etc. In general it can be divided into Industrial automation engineering and Industrial automation production or operation (Application). Although it had been utilized by various industries, the concept, application, development system and nature or work are similar. For this NOSS development and training, focus will solely be given to Industrial Automation Engineering Support Service Level 2. The Industrial Automation Engineering Support Service Level 2 support Industrial Automation Engineering function in the organization. Figure 1.1 illustrates the hierarchy and career path for those involved in the industry.
The development of this NOSS at Level 2 (Refer Figure 1.1 Occupational Framework matrix for Industrial Automation & Mechatronic Sub-sector and Figure 1.2 Occupational Area Structure (OAS) Chart for Industrial Automation Engineering is essential so that the sub sector of the industry will have complete standards and guidelines to be used.
2.2 PRE-REQUISITE
The pre-requisite for Sijil Kemahiran Malaysia (SKM) Industrial Automation Engineering Support Service Level 2 program is the ability to read, write and basic arithmetic.
3
Figure 1.1 Occupational Structure Chart for Industrial Automation & Mechatronic Sub-Sector
SECTOR MACHINERY & EQUIPMENT
SUB-SECTOR INDUSTRIAL AUTOMATION & MECHATRONIC
JOB AREA INDUSTRIAL AUTOMATION ENGINEERING
4
LEVEL INDUSTRIAL AUTOMATION ENGINEERING
5 Industrial Automation Engineering Management
4 Industrial Automation Engineering Administration
3 Industrial Automation Engineering Supervision
2 Industrial Automation Engineering Support Service
1
Figure 1.2 Occupational Area Structure (OAS) Chart for Industrial Automation Engineering
SECTOR MACHINERY & EQUIPMENT
SUB-SECTOR INDUSTRIAL AUTOMATION & MECHATRONIC
JOB AREA INDUSTRIAL AUTOMATION ENGINEERING
5
3. DESCRIPTION OF COMPETENCY LEVEL
The NOSS is produced for various occupational areas. For certification candidates must
be assessed and trained at certain levels to substantiate competencies. Below is the
guideline for each NOSS Level as defined by the Department of Skills Development,
Ministry of Human Resources, Malaysia.
Malaysia Skills Certificate Level 1: Competent in performing a range of varied
(Operation and Production Level) work activities, most of which are routine and
predictable.
Malaysia Skills Certificate Level 2: Competent in performing a significant range
(Operation and Production Level) of varied work activities, performed in a variety of
contexts. Some of the activities are non-routine
and required individual responsibility and
autonomy.
Malaysia Skills Certificate Level 3: Competent in performing a broad range of
(Supervisory Level) varied work activities, performed in a variety of
contexts, most of which are complex and non-
routine. There is considerable responsibility and
autonomy and control or guidance of others is
often required.
Malaysia Skills Diploma Level 4: Competent in performing a broad range of
(Executive Level) complex technical or professional work activities
performed in a wide variety of contexts and with
a substantial degree of personal responsibility
and autonomy. Responsibility for the work of
others and allocation of resources is often
present.
Malaysia Skills Advanced Diploma Competent in applying a significant range of
Level 5: (Managerial Level) fundamental principles and complex techniques
across a wide and often unpredictable variety of
contexts. Very substantial personal autonomy
and often significant responsibility for the work of
others and for the allocation of substantial
resources features strongly, as do personal
accountabilities for analysis, diagnosis, planning,
execution and evaluation.
6
4. MALAYSIAN SKILL CERTIFICATION
Candidates after being assessed, verified and fulfilled the Malaysian Skill Certification requirements shall be awarded with Sijil Kemahiran Malaysia (SKM) for Level 1, 2 and 3, and Diploma Kemahiran Malaysia (DKM) and Diploma Lanjutan Kemahiran Malaysia (DLKM) for Level 4 and 5 respectively.
This NOSS outlines the competency units, competency profile and curriculum of competency units in the Industrial Automation Engineering Support Service Level 2 working environment. . It has been analyzed, produced and documented by selected industrial panel of experts as per the industrial requirements. The industry requires for the competency units, competency profile and curriculum of competency units are outlined using high skills standards and consistencies throughout the assessment process. These were done by laying down a precise framework when conducting the assessment of competency units, competency profile and curriculum of competency units. The training and assessment of Industrial Automation Engineering Support Service Level 2 must be performed in accordance with JPK policy and in adherence to relevance business policy and legislations.
5. JOB COMPETENCIES The industrial automation engineering personnel bear responsibilities that are very challenging in their profession. This is among the professions demanded higher abilities and competencies in various integrated fields and functions. Incumbents normally faced significant resource constraint in their effort to manage the rapid acceleration of technological changes, and at the same time trying to keep reliability and smooth operating of factory machineries and instruments or service project. Thus making them seem to be the champion in the operational systems they are in. 5.1 In general the Industrial Automation Engineering Support Service incumbent is
required to acquire the following competencies recognized by the Malaysian Skills Certificate:
Industrial automation engineering drafting
Industrial automation computer aided design & drafting
Industrial automation fabrication and sub-assembling
Industrial automation installation
Industrial automation systems maintenance
5.2 There is no elective competency for this NOSS.
6. WORKING CONDITIONS
Incumbents in this field work in various environments that include the workshop and plant environment; in implementing the Industrial Automation Engineering Support Service functions. They will be in the factory or worksite environment that is exposed to installation, maintenance and recovery works following where the equipment and automation system are fitted and needed
7
The incumbent for this position belongs to the front line support group of the organisation. In addition to the competencies state at Para 5, incumbent is required to possess the following skills and qualities in order to be effective:
Self Discipline
Interpersonal skills
Technical skills
Informative
Creative
imaginative
Proactive Similar to other organization members, Industrial Automation Engineering Support Service incumbent must uphold the goals and vision of the organisation. This requires the incumbent to have knowledge of the business of the organisation. Industrial Automation Engineering Support Service incumbent is also required to meet clients, visit the production floor, construction sites, the areas of maintenance and or targeted project in order to get information, check and investigate manufacturing and or service operational cases. This will expose the incumbent to unforeseen circumstances. Industrial Automation Engineering Support Service incumbent must be geared to face various job situations.
7. EMPLOYMENT PROSPECTS Individual who hunts for a challenging career with higher rate of employability is suitable to venture into this field. The incumbent ought to be creative, imaginative and proactive in utilizing industrial automation technology to support solving industrial problems. Given that the industrial automation affects the whole operations, incumbents should be responsible and committed in their jobs. From the career point of view, incumbents in this field always face new challenges, which urged them to continue to explore new experience and knowledge at work placed and share experience with peers and colleague from other organization when facing fresh unique problem from time to time. These factors increase the mind's activeness and stop the occurrence of career exhaustion. Incumbents become relevant and preferable with their constants involvement in this area
The demands for Industrial Automation Engineering Support Service incumbents remain high and will continue to be so in line with the economic growth. It covers sectors in engineering services, manufacturing, infrastructure, transportation, water supply, oil & gas, agriculture, medical, marine, construction etc. The demands became the impeller factor for its development through the SKM certification. The Government’s effort to steadily strengthen our country’s growing economy under the economic transformation programme forms a guarantee and promising future for Malaysia citizen. And the benefits are enjoyed by most workforce and businessmen in Malaysia. The industry growth rate continues to leap and the trend is predicted to stay positive for the upcoming five to ten years. This economic growth is directly proportional with the high demand of skilled workers and professional workers including for to Industrial Automation Engineering Support Service personnel . This development further enlivened with the increase of foreign investors’ entry. Foreign investors bring in vast and high-tech investments. These factors have urged the
8
growth of high skilled, semi and professional workers such as the Industrial Automation Engineering Support Service incumbents. Individuals who have endeavoured into this area have promising future and wider career path should they work hard, honestly, and apply competencies as part of their lives culture.
The incumbents shall be able to further their training and enhance their skills by following higher level SKM programs or similar programs by other recognized professional bodies and higher learning institution within and outside of the country.
8. SOURCES OF ADDITIONAL INFORMATION
Local
Kementerian Sumber Manusia Malaysia Aras 6-9 Blok D3, Kompleks D, Pusat Pentadbiran Kerajaan Persekutuan, 62530 Putrajaya
Centre for Artificial Intelligence and Robotics (CAIRO) Universiti Teknologi Malaysia 81310 UTM Skudai Johor Malaysia
Malaysia Automation Technology Association Wisma FMM, No. 3, Persiaran Dagang, PJU 9 Bandar Sri Damansara 52200 Kuala Lumpur Tel: 603-6286 7200 Fax: 603-6277 6714
Board of Engineers Malaysia Tingkat 17 Ibu Pejabat JKR Jalan Sultan Salahuddin 50580 Kuala Lumpur Tel: +603-2692 5017
German-Malaysian Institute, Automation and Mechatronics Technology Section, Industrial Electronics Department. Jalan Ilmiah, Taman Universiti, 43000 Kajang, Selangor DE. Malaysia. Tel: 603-89219000 Fax: 603-89219007 Web: www.gmi.edu.my
The Institution of Engineers, Malaysia Bangunan Ingenieur, Lot 60/62, Jalan 52/4, Peti Surat 223 (Jalan Sultan), 46720 Petaling Jaya, Selangor Darul Ehsan Tel : 603 - 79684001/2 Fax : 603 - 79577678 Email : [email protected] Website : www.iem.org.my
National Industrial Experts and Technologists Council (NIETEC) 18, Jalan Desa Satu, Tmn Universiti, 43000 Kajang, Selangor DE Malaysia. www.nietec.com.my
9
International
International Labor Organization
4 route des Morillons , CH-1211 Genève 22 Switzerland
Switchboard: +41 (0) 22 799 6111 Fax: +41 (0) 22 798 8685
Website: http://www.ilo.org E-mail: [email protected]
BARA (British Automation and Robot Association) New Progress House
34 Stafford Road, Wallington, Surrey SM6 9AA T: 020 8773 8111, F: 020 8773 0022, E: [email protected]
IHS Global Headquarters 321 Inverness Drive South Englewood, Colorado 80112
BSI Group (British Standard) 389 Chiswick High Road London, W4 4AL United Kingdom Fax +44 20 8996 7001
ASTM International, 100 Barr Harbor Drive, PO Box C700, West Conshohocken, PA, 19428-2959 USA
9. APPROVAL DATE
The National Skills Development Board (MPKK), Ministry of Human Resources has agreed and endorsed this Standard on 30 December 2013
10. ACKNOWLEDGEMENT
10.1 This Standard has been circulated to the respective industry for two weeks for validation and feedback. The list of companies that have received the draft are as follows;
i) German-Malaysian Institute, Automation Mechatronics Technology Section, Industrial Electronics Department, Jalan Ilmiah, Taman Universiti, 43000 Kajang, Selangor DE. Malaysia. Web: www.gmi.edu.my
ii) National Industrial Experts and Technologists Council (NIETEC)
10
18, Jln Desa Satu, Tmn Universiti, Sg.Tangkas, 43000 Kajang, Selangor DE.
iii) Perusahan Otomobil Nasional Sdn Bhd. HICOM Industrial Estate, Batu 3 PO Box 7100 40918 Shah Alam Selangor Darul Ehsan
iv) PERODUA Engine Manufacturing Sdn Bhd. Sg Choh, Locked Bag 226 48009 Rawang, Selangor Darul Ehsan
v) Panasonic Appliances Foundry Malaysia Sdn Bhd, Lot 9 & 10, Tangga Batu Industrial Estate, 76400 Tg. Kling Melaka.
vi) OHRM Consult Sdn Bhd.
22-4-1 Diamond Square, Jln 4/50 Off Jln Gombak, 53000, Kuala Lumpur.
10.2 To meet the development process requirement, this standard has been presented to and reviewed by the following members of the Standard Technical Evaluation Committee on 24 July 2013 to ensure the suitability and accuracy of its contents:
i. MR. MR. ZAINUL AZHAN BIN AHMAD BASHIR
ii. MR. ISMAIL BIN IBRAHIM
iii. MR. FAKHRUL ANWAR BIN KAMBALI The committee concluded that the standard content is in accordance with the industry practice and fulfils the latest practice of Industrial Automation.
10.4 The Director General of DSD would like to extend his gratitude to the organisations and individuals who have been involved in developing this standard.
11
11. NOSS DEVELOPMENT COMMITTEE MEMBERS
INDUSTRIAL AUTOMATION ENGINEERING SUPPORT SERVICE LEVEL 2
PANEL
1. EN. SYED NIZAM BIN SYED IDRIS Head of Section German-Malaysian Institute, Kajang, Selangor
2. EN. MOHD ZAMRI BIN ABDULLAH Engineer Principal Empayar Klana Sdn Bhd.
3. EN. KAMARUL HAFIZ BIN MAHPOT
Principal Consultant - Rich Learning Sdn Bhd, Sri Kembangan, Selangor,
4. EN. ZALALUDIN BIN SLAMAT Pengurus Teknikal – Pembangunan Sapura Technical Centre S/Bhd
5. EN. ABD RAHIM BIN MANSOR Director Zasra Technology Sdn Bhd, Shah Alam.
6. EN. MOHD NAZRI BIN RAIS Line Operation Engineer F&N Beverages Sdn.Bhd. – Shah Alam
7. EN. JA'AFAR BIN ABDUL Asst Manager Kuari PATI Sdn Bhd, Kuala Lumpur.
8. EN. HAFIZ CHAI ABDULLAH Senior Manager ROHAS-EUCO Industries Berhad
9 EN. TAJUL ARIFFIN BIN ABD KARIM
SR. Executive Onkyo Asia Electronics (M) Sdn. Bhd
10 EN. SHAHRUDDIN BIN MOHAMED Manager Canon Opto (M) Sdn Bhd
11 EN.AHMAD ZAZLEY BIN MAT NASIR
Technical Executive RAPIDKL Sdn Bhd.
FACILITATOR
1. DR.MARZUKI BIN UJUD President OHRM Consult Sdn Bhd, Kuala Lumpur.
CO-FACILITATOR
1. PN. ROSITAH BINTI YAHAYA
Senior Consultant OHRM Consult Sdn Bhd, Kuala Lumpur
2. HAZIQ ASYRAF BIN MARZUKI Director - Legitimate Project Management Sdn Bhd. Kajang, Selangor DE.
12
12. GLOSSARY
Balloon: Balloon is used to itemize parts in an assembly to identify the parts and sub assemblies in communicating the design to others. Balloon contain parts list item number. Balloon guide users to identify parts and its location in the assembly drawing.
Coaching: is a powerful alliance designed to forward and enhance the lifelong process of human learning, effectiveness and fulfilment. It is a method of directing, instructing and training a person or group of people, with the aim to achieve some goal or develop specific skills.
Code of Conduct for Industrial Harmony: Areas for co-operation and Agreed Industrial Relations Practices. The Code to be observe. Failure to comply with any part of it may cause the award to be against you.
Conflict: A process that begins when one party perceives that another party has negatively affected, or is about to negatively affect , something that the first party cares about. Counseling: is a conversational process that can be instrumental in the development of skills that help employees effectively confront and cope with uncertainties and conflicts. Critical Incidents Method: a techniques that requires written records to be kept of highly favorable and highly unfavorable actions that occur in an employee’s work.
Culture: the set of values, guiding beliefs, understandings, and ways of thinking that is shared by members of an organization and is taught to new memebers as correct.
Employee referral program: is an internal recruitment method employed by organizations to identify potential candidates from their existing employee’s social networks. This scheme encourages a company's existing employees to select and recruit the suitable candidates from their social networks. As a reward, the employer typically pays the referring employee a referral bonus.
Employment pass: is type of work pass granted to foreign professionals with suitable qualifications and experience.
Exempt staff or exempt employee is an employee who falls outside of the definition of employee by the Employment Act 1955. Exempt employees are most often found in managerial, supervisory, professional, administrative, and functional leadership roles.
Expatriate: An expatriate (in abbreviated form, expat) is someone who has chosen to live in a country other than the one in which he or she legally resides.
PROOF READER
1.
Cik NUR KIASATINA BINTI MARZUKI B.Arch.Sc(Hons) IIUM, B.Architecture (Hons) IIUM, Cert.G.Translation ITNM. Cert.Japanese Lang. (UM), Arabic Lang.(IIUM).
Project Director/ Architect OHRM Consult Sdn Bhd., Kuala Lumpur.
13
External equity: A condition which exists when pay for employees performing jobs in a firm that is comparable to that of similar jobs in other firms.
Grievance: means any discontentment or dissatisfaction in an employee arising out of anything related to the enterprise where he/she is working. It arises when an employee feels that something has happened or is going to happen which is unfair, unjust or inequitable.
Industrial Action: Any form of coordinated action in an industrial dispute by employees, with or without the support of a trade union, that seeks to force employers to agree to their demands relating to wages, terms of employment, working conditions etc
Internal equity: A condition which exists when employees performing jobs for a company are paid according to their job’s relative value within that organization.
Job Bidding: A technique that permits individuals in the organization who believe that they possess the required qualifications to apply for the posted job.
Job analysis: The systematic process of determining the duties and skills required for performing jobs in an organization.
Job Posting: A procedure for communication to company employees the fact that job openings exist.
Job Description: A document that provides information regarding the tasks and responsibilities of the job.
Job Specification: The minimum acceptable qualifications that a person should possess to perform a job.
Key Performance Indicator: A Key Performance Indicator (KPI) is a critical measurement of the performance of essential tasks, operations, or processes. A KPI will usually unambiguously reveal conditions or performance that is outside the norm and that signals a need for managerial intervention
Laser cutting is an intensely concentrated beam of light which can be reduced to a tiny
point of very high temperature and controlled in a way which means that complex and
very exact shapes can be cut out of the metal. Often, the laser will be controlled by a
computer which has the pattern required programmed into it. The accuracy and focus of
the laser beam results in a very clean cut and a top rate finish.
Logistics: The procurement, maintenance, distribution, and replacement of personnel and material.
Objective: is a goal characterized by a comparatively short time span and specific, measurable achievements,
Organization Design: Is a formal, guided process for integrating the people, information and technology of an organization. It is used to match the form of the organization as closely as possible to the purpose(s) the organization seeks to achieve. Through the design process, organizations act to improve the probability that the collective efforts of members will be successful.
14
Performance Appraisal: A system that provides a periodic review and evaluation of an individual’s job performance.
Performance Dashboard; Performance dashboard is a management tool to gauge performance and progress toward business goals. Dashboards can be designed and produced to address a wide range of objectives, from monitoring the viability of a global organization's business strategy, to keeping a check on a department's ability to achieve service-level targets. Performance Gaps . The difference between the objectives established in the goal-formulation process and the result likely to be achieved if the existing strategy is continued.
Plasma Cutting is a metal cutting technique. A plasma torch pumps either oxygen or an inert gas out of the nozzle at high speed whilst simultaneously sending an electrical arc through the gas, thus creating plasma which is hot enough to melt the metal whilst also moving quickly enough to blow any molten. Situational analysis A situational analysis defines and interprets the state of the environment of a person or organization. A situational analysis describes an organization's competitive position, operating and financial condition and general state of internal and external affairs.
Standard Costing system: is a tool for planning budgets, managing and controlling costs, and evaluating cost management performance. At the end of the accounting period, the actual amounts and costs of direct material used and the actual amounts and pay rates of direct labour utilized are compared to the previously set standards. Comparing the actual costs to the standard costs and examining the variances between them allows managers to look for ways to improve cost control, cost management, and operational efficiency. Strategy: the current set of plans, decisions and objectives that have been adopted to achieve the organization’s goals. Turning: is a process via which the sharp point of a cutting tool is applied to the metals surface as it is rapidly spun by a device such as a lathe, thus removing the top layer of metal to a pre-determined size.
15
COMPETENCY PROFILE CHART (CPC)
COMPETENCY COMPETENCY UNIT
SECTOR MACHINERY & EQUIPMENT
SUB-SECTOR INDUSTRIAL AUTOMATION & MECHATRONIC
JOB AREA INDUSTRIAL AUTOMATION ENGINEERING
NOSS TITLE INDUSTRIAL AUTOMATION ENGINEERING SUPPORT SERVICE
JOB LEVEL TWO (2) JOB AREA CODE MC-091-2:2013
CORE
INDUSTRIAL AUTOMATION
ENGINEERING DRAFTING
INDUSTRIAL AUTOMATION
FABRICATION AND SUB-ASSEMBLING
INDUSTRIAL AUTOMATION COMPUTER
AIDED DESIGN AND DRAFTING
INDUSTRIAL AUTOMATION INSTALLATION
MC – XXX-01
MC – XXX-02
MC – XXX-03
MC – XXX-04
INDUSTRIAL AUTOMATION SYSTEMS
MAINTENANCE
MC – XXX-05
16
COMPETENCY PROFILE (CP)
Sub Sector INDUSTRIAL AUTOMATION & MECHATRONIC
Job Area INDUSTRIAL AUTOMATION ENGINEERING
NOSS Title INDUSTRIAL AUTOMATION ENGINEERING SUPPORT SERVICE
Level TWO (2)
CU Title CU Code CU Descriptor CU Work Activities Performance Criteria
1. Industrial
automation engineering drafting
MC-XXX-01 Industrial automation engineering drafting is the competency of composing plans that are visually communicated on how some things function or has to be constructed. Industrial automation engineering drafting should be done using accurate information as it is used as the visual communication media of interested parties and in job context, social, business and or legislation. The Industrial automation engineering drafting is in compliance with conventions, accepted and understood by the general locally and international. It is compulsory to produce
1. Perform Industrial
Automation Engineering Sketching
1.1 Engineering Drawing Sketching
instruction examined, Instruction source, instruction authority, instruction objective checked, Instruction content studied, imposed condition, instruction authority, instruction validity checked, engineering Drawing Sketching instruction accepted.
1.2 Pre- sketching requirements preparation performed, sketching requirement information obtained, engineering drawing sketching objectives, engineering drawing sketching time frame determined, Site exploration, In-situ measurements conducted, sketching concepts & orientation studied, sample visualization, client interview conducted, sketching
17
Industrial automation engineering drafting using accurate information as inaccurate information may cause deflection in ideology, end products specification and construction that are detrimental and costly. The person who is competent in Industrial automation engineering drafting will be able to perform Industrial Automation Engineering Sketching, perform two dimensions Industrial Automation Engineering drawing development, develop three dimensional Industrial Automation Engineering drawing, prepare Drawing Bill of Materials and perform Industrial Automation Engineering Drawing Filing. An effective industrial automation engineering drafter should be able to produce clean and precise technical drawing of an existing or non-existing object and or any parts of it, sectional views, detail
resources requirements gathered, engineering sketching tools, equipment and materials obtained, engineering drawing sketching requirements summary generated.
1.3 Engineering drawing sketching carried out, customer requirements & specification, product/object specification, actual sample visualisation obtained, actual object visualisation conducted, engineering drawing sketching site visit and exploration conducted, non-exist object sketching information gathering carried out, sketching Object orientation conducted, sketching view angle selected, engineering drawing sketching resources obtained, engineering drawing sketching techniques applied, engineering drawing sketching procedure followed, engineering drawing sketching detail provided, engineering drawing sketching check & confirmation conducted, engineering drawing sketching record prepared.
1.4 Engineering drawing sketching record updated, engineering drawing sketching record format utilized, engineering drawing sketching record contents provided, engineering drawing sketching recording techniques applied, engineering drawing sketching
18
assemblies and or sub-assemblies, hidden parts, its layout, in two and or three dimension, using symbols and methodology that complied with the specified standards, at a clear view angle, using a suitable accurate scale, drawn in an accurate dimensions, providing objects information as required and or specified, with the end product could be confidently referred to and become an understandable and effective communication media by any parties in accordance with organizational requirements. The outcome of this CU is to meet occupational skills standard which incorporate the skills, knowledge and attitude to be delivered systematically.
2. Perform two dimension Industrial Automation engineering drawing development
recording procedure followed, engineering drawing sketching record generated.
2.1 Two dimension engineering drawing
principles studied, two dimension engineering drawing produced, Engineering Drawing instruction Obtain engineering drawing requirements examined, Engineering Drawing Scale and dimension determined, plan elevation, side & end elevation produced, Engineering Drawing dimensions, Engineering Drawing detail, Engineering Drawing title block prepared, Engineering drawing submission carried out.
2.2 Two Dimension Sectional Drawing produced, sectional Drawing instruction, two dimension sectional drawing requirements obtained, sectional view cutting line determined, sectional view produced, sectional view detail, two dimension sectional Drawing title block prepared, Two dimension sectional drawing submission carried out.
2.3 Engineering drawing record updated, engineering drawing record format utilized, engineering drawing record contents provided, engineering drawing recording
19
3. Develop three dimensional Industrial Automation engineering drawing
techniques applied, engineering drawing recording procedure followed, engineering drawing record generated.
3.1 Three dimensional engineering
drawing development instruction examined, Instruction source, instruction authority and instruction objective checked, Instruction content studied, Imposed condition, Instruction authority and instruction validity checked and three dimensional engineering drawing instruction accepted.
3.2 Isometric Drawing principles studied, Engineering Drawing
instruction examined, isometric drawing requirements obtained, isometric drawing Scale and dimension determined, isometric drawing produced, Isometric Drawing detail, Isometric Drawing title block prepared, Isometric drawing submission carried out.
3.3 Orthographic drawing principles studied, orthographic Drawing
instruction examined, orthographic drawing requirements obtained, orthographic drawing Scale and dimension determined, orthographic view drawing produced,
orthographic drawing detail and
orthographic drawing title block prepared, orthographic drawing
20
4. Prepare Industrial Automation Drawing Bill of Materials
plan generated. Orthographic
drawing submission carried out. 3.4 Engineering drawing record
updated, engineering drawing record format utilized, engineering drawing record contents provided, and engineering drawing recording techniques applied, engineering drawing recording procedure followed.
4.1 Drawing Bill of Materials instruction
examined, instruction source, instruction authority, instruction validity, instruction requirements checked, job objectives defined, Drawing Bill of Materials job time frame determined, Drawing Bill of Materials instruction accepted.
4.2 Drawing Bill of Materials requirements obtained, drawing bill of materials principles examined, targeted object specification obtained, instruments, tools, board and materials prepared, required materials information list obtained, prescribed materials list scrutinized, required materials quantified, required part detail & specification obtained, required parts quantified, drawing bill of materials requirements checked.
4.3 Component part balloon created, type of part balloon, component part balloon purposes determined,
21
5. Perform Industrial Automation Engineering Drawing Filing
component part number provided. 4.4 Bill of Materials table created, Bill of
Materials table purposes, type of Bill of Materials table items and specification determined, Bill of Materials table created, part list table contents (Part name, quantity, part materials and size) inserted, Bill of Materials table content checked, updated drawing produced.
4.5 Updated drawing filed, Engineering drawing physical filing systems. Engineering drawing digital filing systems examined, engineering drawing filing carried out, engineering drawing record updated.
5.1 Engineering Drawing filing
instruction examined, instruction source, instruction contents, instruction authority, instruction validity checked, instruction acceptance recorded.
5.2 Engineering Drawing Filing requirements prepared, drawing filing objectives observed, type of filing (Physical /electronic) identified, drawing filing tools, equipments and materials, drawing filing indexing procedure, drawing filing procedure, Drawing filing record, drawing indexing register obtained.
5.3 Drawing indexing performed,
22
drawing indexing procedure identified, drawing indexing register examined, last series recorded, drawing revision identification number checked, drawing indexing detailing format utilized, unique new drawing index, revised drawing version number assigned, drawing date of birth inserted, drawing index printed, drawing index register, Drawing index record updated.
5.4 Physical drawing filing carried out, drawing filing objectives determined, physical drawing filing procedure followed, drawing title and coding, drawing classification, type of drawing filing determined, physical filing storage location identified, drawing security regulations, data security regulations checked, drawing storage section, drawing tray number determined, accurate drawing filing record prepared, physical drawing movement record updated.
5.5 Digital drawing filing carried out, electronic drawing filing procedure followed, drawing title and coding, drawing classification, type of drawing filing determined, digital filing storage location identified, digital drawing security regulations checked, data security regulations observed, digital drawing storage section determined, digital drawing
23
drive/tape/disc address assigned, drawing file saved, digital drawing filing record , digital drawing file movement record updated.
5.6 Engineering Drawing filing retrieve/ issuance performed, Engineering Drawing issuance instruction examined, issuance instruction authority, instruction validity checked, instruction acceptance recorded, Drawing title, drawing index and coding, drawing classification, drawing security level, drawing file location traced, storage media obtained, digital drawing file retrieved, date of drawing issuance determined, issuance and recipient detail recorded, drawing movement, Drawing record book updated.
2. Industrial
Automation computer aided design & drafting
MC-XXX-02
Industrial Automation computer aided design and drafting is a competency of creating, producing, storing and preparing design variations of a Industrial automation engineering drafting electronically in two or three dimensions so that they can be viewed, printed, or programmed directly into automated operation and or manufacturing systems. It is compulsory to produce
1. Obtain CAD
software and requirements
1.1 Computer Aided Design & Drafting
(CADD) Application systems requisition instruction examined, instruction official source identified, instruction direction recognized, instruction requirements scrutinized and instruction authority checked in accordance with organizational requirements.
1.2 CADD Application product availability checked.
1.3 CADD Application systems product requisition generated in accordance with organizational purchasing
24
Industrial automation engineering design & drawing using accurate information as inaccurate information may cause deflection in ideology, products output and construction that are detrimental and costly. The person who is competent in Industrial automation computer aided design and drafting application will be able to obtain Computer Aided Design & Drafting (CADD) application systems and requirements, Install CADD Application systems, Develop CADD Two Dimension Industrial Automation Drawing, Develop CADD Three Dimension Industrial automation Drawing, Develop CADD assembly drawing, Develop CADD 3D Assembly Drawing and Prepare CADD operation report. An effective Industrial Automation Computer Aided Design & Drafting (CADD) operator should be able to produce clean and precise mechanical drawing of an
2. Install CADD Application systems
procedure and requirements. 1.4 CADD Software specification
checked. 1.5 CADD software and requirements
delivery inspection conducted , CADD items & quantity, Software contents & serviceability, product licensing, hardware items, type & quantity and Product's manual checked in accordance with organizational purchasing policy and procedure.
1.6 Delivery receipt confirmed in accordance with organizational purchasing policy and procedure.
2.1 CADD application systems software
installation instruction and requirements examined in accordance with organizational requirements.
2.2 CADD application systems hardware installation instruction, manual and requirements examined in accordance with manufacturer's specification.
2.3 CADD application systems Installation requirements examined, installation tools , equipments and materials identified, hardware & software installation requirements scrutinized and licensing requirements studied in accordance with organizational requirements.
2.4 CADD application systems
25
existing or non-existing object and or any parts of it, sectional views, detail assemblies and or sub-assemblies, hidden parts, its layout, in two and or three dimension, using symbols and methodology that complied with the specified standards, at a clear view angle, using a suitable accurate scale, drawn in an accurate dimensions, providing objects information as required and or specified, using a specified computer aided design and drafting software, neatly and clearly printed or plotted, with the end product could be confidently referred and become an understandable and effective communication media by any parties in accordance with organizational requirements The outcome of this CU is to meet occupational skills standard which incorporate the skills, knowledge and attitude to be delivered systematically.
3. Develop CADD Two Dimension Industrial Automation Drawing
installation planned, CADD installation objectives, CADD installation time frame, CADD installation tools, equipments and materials determined in accordance with organizational requirements.
2.5 CADD application systems Installation performed, installation tools, equipments and materials obtained, CADD Hardware Installation and CADD Software Installation carried out in accordance with hardware manufacturer’s manual and CADD producer’s requirements.
2.6 CADD application systems Installation evaluated, installation performance parameters determined, CADD installation evaluation techniques applied and evaluation procedure followed in accordance with organizational requirements.
2.7 CADD application systems installation record prepared in accordance with organizational requirements.
3.1 Industrial Automation Drawing
instruction examined , instruction source, instruction authority, instruction validity, instruction requirements checked, job objectives defined, Industrial Automation Drawing instruction accepted.
3.2 CADD Industrial Automation drawing requirements , Industrial Automation
26
drawing sketches and drawing information, CADD Industrial Automation drawing tools and equipments obtained and Industrial Automation drawing requirements gathered.
3.3 Industrial Automation Drawing CADD Scale and dimension determined, two dimension drawing requirements examined, paper formats and units selected, drawing dimension style selected, standard line layers and thickness set, drawing base length checked and Drawing scale determined.
3.4 CADD plan elevation determined, lines based on standard line layers and thickness produced, construction line, object line, hidden line produced, drawing symbols provided.
3.5 CADD side & end elevation produced, projection line generated, intersection points determined, object line produced and projection line cleared.
3.6 CADD Industrial Automation Drawing dimensions prepared, dimension detail obtained, information accuracy checked, dimension line produced, dimension detail, dimension detail and dimension style consistencies checked.
3.7 CADD Industrial Automation Drawing detail prepared, drawing detail obtained, font/lettering size selected, information accuracy, detail spelling,
27
Industrial Automation drawing detail inserted, detail spelling and font consistencies checked.
3.8 CADD Industrial Automation Drawing title block prepared, Industrial Automation title block detail obtained, information accuracy checked, font/lettering size selected, title block format utilized, title block detail inserted, drawing title and identification number provided, signatories line and arrangements provided and detail spelling and font consistencies checked.
3.9 CADD Industrial Automation Drawing generated, plotter requirements installed, paper in plotter / printer prepared, page setup manager set, plotter / printer, paper size, plot scale, plot style table for pen assignments, drawing orientation and drawing scale determined, Industrial Automation Drawing plotted and plotting outcome checked.
3.10 Industrial Automation drawing submission and drawing final checking carried out, information accuracy checked, drawing submission check list attached, drawing folded, drawing submitted, file and Industrial Automation drawing log book updated.
28
4. Develop CADD
Three Dimension Industrial automation Drawing
4.1 Industrial Automation Drawing
instruction examined , instruction source, instruction authority, instruction validity, instruction requirements checked, job objectives defined, Industrial Automation Drawing instruction accepted.
4.2 CADD Industrial Automation drawing requirements , Industrial Automation drawing sketches and drawing information, CADD Industrial Automation drawing tools and equipments obtained and Industrial Automation drawing requirements gathered.
4.3 Industrial Automation Drawing CADD Scale and dimension determined, three dimension drawing requirements examined, paper formats and units selected, standard line layers & thickness set, drawing base length checked, drawing scale, three angles of dimension, thickness of structures, 3D Object (cube, cone, cylinder, sphere, geometry, etc.), 3D construction method (Boolean, Object Compose, Extrude, Loft, Bending, FFD, NURB, etc.) determined and Industrial Automation Drawing CADD Scale and dimension factors summarised.
4.4 CADD plan elevation, polylines based on standard line layers & thickness, construction line (using 2D spline
29
shape), object line, curve line, circle shape, triangle shape, rectangle shape, hidden line, dimension line, centre line, section line, dummy object produced, drawing symbols provided and CADD plan elevation (2D shape sketch) checked.
4.5 CADD side & end elevation (3D transforming) produced, extrude and revolved method applied, three dimension object created, Bending method applied (object reformation), Boolean method applied ( to attachment multiple object), NURB method applied (to construct surface of objects), CADD side & end elevation (3D transforming) checked.
4.6 3D Object Editing and Refining carried out, polygon using and object edited, Bending method and FFD method applied, and edited & refined 3D Object checked and recorded.
4.7 Object colouring conducted, object selected, Material Editor Panel opened, colour ( from palette) selected, selected object colour applied, object colouring process result checked.
4.8 3D Object Texture &Material Mapping carried out, object materials (steel, wood, aluminium, glass, sandy, shining, rubber, plastic, etc) determined, Material Editor Panel open, material from library selected, self design materials produced, object
30
material produced, object material named & saved, material object applied ( to 3D object), and 3D Object Texture & Material Mapping outcome checked.
4.9 Rendering conducted, rendering perspective angle determined, rendering object determined, Rendering Panel opened, rendering method selected, rendering process conducted, rendering result previewed.
4.10 CADD 3D process final Output previewed, perspective rendering angle determined, rendering object selected, Rendering Panel opened, rendering method selected, rendered object saving location selected, object format type selected (still image, video, draft, sequence, movie, etc ) , format document (jpg, png, avi, mov, swf, tif, targa, flv, gift) selected and CADD 3D process final Output previewed.
4.11 3D Camera Handling performed, view of visual determined, camera type selected, camera produced, camera position edited, camera distance edited, camera zooming carried out, camera view perspective rendering carried out , checked and recorded.
4.12 CADD Industrial Automation Drawing dimensions prepared, dimension detail obtained, information
31
accuracy checked, dimension line produced, dimension detail checked, dimension detail and dimension style consistencies checked.
4.13 CADD Industrial Automation Drawing detail prepared, drawing detail obtained, information accuracy checked, font/lettering size selected, drawing detail inserted, detail spelling, Industrial Automation drawing detail and detail spelling and font consistencies checked.
4.14 CADD Industrial Automation Drawing title block prepared, Industrial Automation title block detail obtained, information accuracy checked, font/lettering size selected, title block format used, title block detail inserted, Drawing title and identification number provided, signatories line and arrangements provided, detail spelling and font consistencies checked.
4.15 3D CADD Industrial Automation Drawing generated, plotter requirements installed, paper in plotter / printer loaded, page setup conducted, plotter / printer, paper size, plot scale plot style table for pen assignments, drawing orientation and drawing scale determined, Industrial Automation Drawing plotted, plotted drawing checked.
4.16 Industrial Automation drawing submission carried out, drawing final
32
5. Develop CADD assembly drawing
checking conducted, information accuracy checked, drawing submission check list attached, drawing folded/rolled and Industrial Automation drawing log book updated.
5.1 Assembly Drawing instruction,
instruction source, instruction authority, instruction validity and instruction requirements checked, job objectives defined, Industrial Automation Drawing instruction accepted.
5.2 CADD Assembly drawing requirements, Industrial Automation drawing sketches & drawing information, CADD Industrial Automation drawing tools & equipments obtained, Industrial Automation drawing requirements gathered.
5.3 Assembly drawing requirements prepared, targeted 2D drawing file and Assembly drawing specification obtained, Assembly drawing tools, equipment, instruments and materials gathered, layer (by different colour and line) produced, assembly component development or Import assembly component implemented, layer changed (for assembling), component reference point produced,
5.4 Assembly drawing produced, main drawing obtained, component
33
6. Develop CADD 3D Industrial Automation Assembly Drawing
assembled, layer locked, Assembly symbol (such as. welding, GD&T) provided, cutting plane (sectioning) produced, multi sectioning area view, object material and hatching process produced, and line accuracy checked.
5.5 Assembly drawing detail prepared, drawing detail obtained, information accuracy checked, font/lettering size selected, balloon and bill of material provided, Bill of material information completed, scale drawing produced and drawing detail indicated, drawing detail inserted, detail spelling, Industrial Automation drawing detail, and detail spelling and font consistencies checked.
5.6 Industrial Automation drawing submission and assembly drawing final checking carried out, assembly drawing detail accuracy checked, drawing submission check list attached, drawing folded and
Industrial Automation drawing log book updated.
6.1 Three D Assembly Drawing instruction examined, instruction source, instruction authority, instruction validity and instruction requirements checked, job objectives defined, Industrial Automation Drawing instruction accepted.
6.2 CADD 3D Assembly drawing
34
requirements and Industrial Automation drawing sketches, drawing information, CADD Industrial Automation drawing tools and equipments obtained, Industrial Automation drawing requirements gathered.
6.3 CADD 3D Assembly drawing requirements prepared, targeted 3D drawing file, Assembly drawing specification obtained, Assembly drawing tools, equipment, instruments and materials obtained, individual / parts drawing produced and new assembly lay out produced.
6.4 3D Assembly drawing produced, main drawing obtained, first component positioned, component added, component inserted, image moved & and rotated, component mated, alignment process conducted, mating concentric and coincident performed, assembly motion performed, hiding and transparency initiated, component properties checked, assembly image analyzed, compute mass properties calculation, interference detection checking performed, value of dimension changed, physical simulation conducted, exploded assemblies performed, explode line sketched, animating explode view performed.
6.5. CADD 3D Assembly Drawing Detail
35
7. Prepare CADD operation report.
prepared, drawing detail obtained, information accuracy checked, multi view orientation performed, balloon provided, bill of material provided, font/lettering size selected, bill of material information completed, scale drawing produced, detail drawing produced and indicated cutting plate ( sectioning) produced, assembly symbol produced (eg. welding, GD&T and etc), detail spelling checked, Industrial Automation drawing detail checked, detail spelling and font consistencies checked.
6.6. CADD 3D Industrial Automation drawing submission carried out, assembly drawing final checking conducted, assembly drawing detail accuracy checked, drawing submission check list attached, drawing Folded/rolled, Industrial Automation drawing log book updated.
7.1 CADD application performance record
examined. 7.2 CADD operation report planning
conducted, CADD operational critical area identified, report parameters indicated, organizational requirements scrutinized.
7.3 CADD operation report performed, CADD reporting format utilized, report subjects covered, report contents elaborated and CADD operation
36
report generated in accordance with organizational requirements.
7.4 CADD operation report implementation evaluated.
7.5 CADD operation report feedback obtained.
3. Industrial automation fabrication and sub-assembling
MC-XXX-03
Industrial automation fabrication and sub-assembling is a competency of constructing by making, combining and or assembling pieces into a finished product or sub-assemblies product or component. Industrial Automation Fabrication involve cutting, bolting bending, folding, soldering , welding, , brazing, rivetting , wiring, moulding, stamping, electronics components installation, usually pieces of metal to form the desired finished product, sub-assembled products or components. It is important someone directly involved with Industrial automation fabrication and sub- assembling support service to give high commitment and
1. Examine Industrial
Automation Fabrication instruction
2. Prepare Industrial Automation Fabrication & Sub Assembling requirements
3. Perform Industrial Automation Fabrication
1.1 Instruction source, instruction
authority, instruction validity, instruction content checked.
1.2 Industrial fabrication instruction accepted
1.3 Industrial fabrication instruction recorded.
2.1 Industrial Automation Fabrication &
Sub Assembling drawing and Industrial Automation Fabrication & Sub Assembling specification obtained.
2.2 Industrial Automation Fabrication & Sub Assembling parameters and Industrial Automation Fabrication & Sub Assembling time frames determined.
2.3 Industrial Automation Fabrication & Sub Assembling tools, equipment and material, and Industrial Automation Fabrication & Sub Assembling standard operating procedures obtained.
3.1 Industrial Automation Fabrication &
Sub Assembling drawings examined,
37
cooperation because end result of their work are the combination of inter dependable sub-assemblies that form one industrial automation system Failure in any part of the functions will affect function whole system. The person who is competent in Industrial automation computer aided design & drafting will be able to examine Industrial Automation Fabrication instruction, prepare Industrial Automation Fabrication & Sub Assembling requirements, perform Industrial Automation Fabrication & Sub assembling implementation, perform Industrial Automation Fabrication & Sub- Assembling Testing, perform Industrial Automation Fabrication & Sub Assembling product packaging and Perform Industrial Automation Fabrication & Sub Assembling product delivery preparation.
& Sub Assembling implementation
4. Perform Industrial
Automation Fabrication & Sub Assembling Testing
plan drawing, elevation drawing, sectional drawing, assembly drawing, drawing detail, Bill of Materials, Schematic plan, component layout plan studied.
3.2 Industrial Automation Fabrication & Sub Assembling specifications examined.
3.3 Cutting process, plasma Cutting, bend sawing, disc Cutting, laser cutting (Advance tech) and water Jet cutting (Advance Tech) conducted, machining process, joining process, Sheet metal joining, Soldering, Welding, Bolt & Nut joining, Riveting and Brazing conducted, moulding process arrangement, Sand moulding, Plastics moulding, Injection moulding, Gravity moulding, High pressure moulding and Low pressure moulding arrangement conducted, wiring process, Soldering connection, Crimping, Interconnecting cables, Cable termination, Wiring, Cable tagging and Grounding conducted, printed circuit board assembling, component Soldering, connector terminating and copper route printing conducted, and component sub assembling carried out.
4.1 Component wiring test, printed circuit
board assembling test, component sub assembling test, joining test conducted.
38
An effective industrial automation systems fabrication technician should be able to perform industrial automation fabrication process until the industrial automation systems fabrication components, assemblies and sub-assemblies are formed and ready for installation as specified by the organization. Fabrication works should be implemented neatly, accurately, functional and safe according to specifications with cost optimization, low scrap value, optimum labor utilization and within a given time frame. The administrator’s performance shall be measured based on the said requirements that are translated into the prescribed objectives and organization requirements.
5. Perform Industrial
Automation Fabrication & Sub Assembling product packaging
4.2 Industrial Automation Fabrication & Sub Assembling Testing record prepared, Industrial Automation Fabrication & Sub Assembling Testing record form, Industrial Automation Fabrication & Sub Assembling Testing result, Industrial Automation Fabrication & Sub Assembling Testing remarks prescribed.
4.3 Industrial Automation Fabrication & Sub Assembling product inspection carried out.
4.4 Industrial Automation Fabrication & Sub Assembling product inspection logbook updated.
5.1 Industrial Automation Fabrication &
Sub Assembling product packaging requirement prepared, Packaging procedure, packaging technique, packaging safety, packaging material, product packaging identification system obtained.
5.2 Industrial Automation Fabrication & Sub Assembling product pre packaging inspection, Industrial Automation Fabrication & Sub Assembling packaging process, and Industrial Automation Fabrication & Sub Assembling Product Labelling
5.3 Industrial Automation Fabrication & Sub Assembling product packaging recorded.
39
The outcome of this CU is to meet occupational skills standard which incorporate the skills, knowledge and attitude to be delivered systematically.
6. Perform Industrial Automation Fabrication & Sub Assembling product delivery preparation.
6.1 Industrial Automation Syst. Fabrication product sub-assembly listing prepared.
6.2 Industrial Automation Syst. Fabrication product tagging prepared
6.3 Industrial Automation Syst. Fabrication product documentation prepared
6.4 Industrial Automation Syst. Fabrication & sub-assembly product documentation and drawing attached.
6.5 Industrial Automation Syst. Fabrication& sub-assembly log book updated.
4. Industrial
automation installation
MC-XXX-04
Industrial automation installation is the competency that supports the management fixing and placing the industrial automation systems or any part of the systems to order and effectively functioning as required by the client. The support services incumbent is required to work hand in hand to complete the interrelated sets of jobs. Any malfunction at any sub-systems means the whole system’s failure. The person who is
1. Examine Industrial Automation System installation Instruction
2. Prepare Industrial
Automation System installation Requirements
1.1 Source of instruction, instruction
authority, instruction validity, and instruction content checked.
1.2 Industrial Automation System installation instructions accepted.
1.3 Industrial Automation System installation instructions recorded.
2.1 Industrial Automation System
installation objective observed 2.2 Industrial Automation System
installation specification, and Industrial Automation System installation Standard operation procedure obtained.
2.3 Prescribed installation plan examined.
2.4 Industrial Automation System
40
competent in Industrial automation installation will be able to examine Industrial Automation System installation instruction, prepare Industrial Automation System installation requirements, perform Industrial Automation System installation implementation, perform Industrial Automation System trial run, perform Industrial Automation System trial run record submission. An effective industrial automation installation technician should be able to perform industrial automation installation process using allocated resources that are most economical according to the specified methodology and techniques as instructed in order to achieve the function objective in the safest atmosphere and cost optimization according to set schedule. Customer acceptance to the industrial automation installation that is perfect, functional and on time according to the agreed
3. Perform Industrial Automation System installation implementation
installation checklist obtained, Industrial Automation System installation tools, equipments and machineries, Industrial Automation System installation record systems, Corrective Action Requisition Procedure, and Corrective Installation Record Systems obtained.
3.1 Industrial Automation System
installation specification, Installation on program specification, and corrective Installation Systems specification examined.
3.2 Installation standard operating procedure followed.
3.3 Installation implementation technique applied.
3.4 Mechanical part installation program, part Assembling, part Greasing, part Lubricating, part Joining, part Aligning, part Levelling, part Gap setting, part Limit setting carried out.
3.5 Electrical part installation program, part Power Supply Termination, part Wiring, part insulating, part Grounding, part calibration, part terminal connection, and part communication connection carried out.
3.6 Pneumatic / hydraulic part installation Program, part air supply connection tubing, part connect power
41
specification and organization requirements is the best outcome.
The outcome of this CU is to meet occupational skills standard which incorporated of the skills, knowledge and attitude to be delivered systematically.
.
4. Perform Industrial Automation System trial run
pack supply, part Cylinder stroke adjustment, and part Limit switch alignment carried out.
3.7 Industrial Automation System installation implementation recorded.
4.1 Industrial Automation System trial
run instruction, Industrial Automation System trial run requirement, Industrial Automation System trial run procedure, and Industrial Automation System trial run tools, equipment and machineries obtained.
4.2 Mechanical performance trial run conducted, alignment, vibration level, run out, back lash and mechanical part Motion checked.
4.3 Electrical functionality trial test conducted, motor movement, motor direction, sensor functionality and controller functionality tested.
4.4 Pneumatic and hydraulic functionality test, instrument functionality test and Industrial Automation System trial run conducted, sequential, functionality ensured, cycle time, safety system functionality checked, and durability test conducted.
4.5 Corrective Action Request Order performed, Corrective Action Request job sheet received, Corrective Action Request order performed, Corrective Action Request feedback obtained, Corrective Action Request Report
42
5. Perform Industrial Automation System trial run record submission
closed. 4.6 Industrial Automation System trial
run result compiled.
5.1 Industrial Automation System trial run
record prepared, Industrial Automation System trial run record form, Industrial Automation System trial run result, Industrial Automation System trial run remarks prescribed.
5.2 Industrial Automation System trial run record generated.
5.3 Industrial Automation System trial run record submitted.
5. Industrial
automation systems maintenance
MC-XXX-04
Industrial Automation Systems maintenance is the competency of restoring or retaining industrial automation systems, equipments, machineries, components, and or any related devices to the specified efficiency level to achieve the optimum economic capacity and longer life. The malfunction of the Industrial Automation System maintenance support service’s function will directly increase the operation idle time and the operation cost.
1. Examine Industrial
Automation System maintenance Instruction
2. Prepare Industrial Automation System maintenance Requirements
1.1 Source of instruction, instruction
authority, instruction validity, instruction content checked.
1.2 Industrial automation system maintenance instruction accepted.
1.3 Industrial automation system maintenance instruction recorded.
2.1 Industrial Automation System
maintenance objective observed 2.2 Industrial Automation System
maintenance specification, Industrial Automation System maintenance Standard operation procedure obtained.
2.3 Prescribed Industrial Automation System Total Preventive Maintenance (TPM) plan examined
2.4 Industrial Automation System TPM wear and tear spare part list,
43
The person who is competent in Industrial automation systems maintenance will be able to examine Industrial Automation System maintenance Instruction, prepare Industrial Automation System maintenance Requirements, perform Industrial Automation System maintenance implementation, Perform Industrial Automation System maintenance testing and Perform Industrial Automation System maintenance test record submission An effective industrial automation systems maintenance technician should be able to perform industrial automation maintenance functions and ensure the operations of industrial automation runs well with breakdowns, operation idle time and the stoppage interferences records are within permitted level with maintenance cost
3. Perform Industrial Automation System maintenance implementation
Industrial Automation System TPM Check list, Industrial Automation System TPM maintenance tools, equipments and machineries, Industrial Automation TPM record systems obtained.
2.5 Corrective Maintenance Standard Operating Procedure gathered.
2.6 Corrective Action Requisition Procedure obtained.
2.7 Corrective Action frequency analysis obtained.
2.8 Corrective Maintenance Record Systems obtained.
3.1 Industrial Automation System
maintenance specification examined, TPM Program specification, Corrective Maintenance Systems specification examined, TPM standard operating procedure followed, TPM implementation technique applied.
3.2 Mechanical part TPM program carried out, Greasing, Aligning, Tightening, Replacing, Trouble shooting, and Backlash setting carried out.
3.3 Electrical part TPM program carried out, Winding, Continuity, Insulation, Voltage level, Current leakage, Grounding checking, Calibration, and Trouble shooting carried out.
3.4 Pneumatic / hydraulic part TPM Program carried out, Leaking,
44
optimization. The technician is also responsible to achieve his individual and team performance objectives and contribute toward the highest achievement of the operation in accordance with the organization requirements. The outcome of this CU is to meet occupational skills standard which incorporate the skills, knowledge and attitude to be delivered systematically.
.
4. Perform Industrial Automation System maintenance testing
5. Perform Industrial Automation System maintenance test record submission
Pressure, Blocking, Oil level carried out.
3.5 Instrument TPM Program carried out, Calibration, Continuity, Voltage level, Current leakage, Trouble shooting carried out.
3.6 Corrective Action Request Order performed, Corrective Action Request job sheet received, Corrective Action Request order performed, Corrective Action Request feedback obtained, Corrective Action Request Report closed, Corrective Action Request Logbook updated.
3.7 Industrial Automation System maintenance implementation recorded.
4.1 Mechanical test, electrical test,
pneumatic and hydraulic test, instrument test conducted.
4.5 Industrial Automation System maintenance periodical systems test result compiled.
5.1 Industrial Automation System
maintenance test record prepared, Industrial Automation System maintenance testing record form, Industrial Automation System maintenance testing result, Industrial Automation System maintenance testing remarks prescribed,
5.2 Industrial Automation System maintenance test certificate/result
45
attachment provided. 5.3 Industrial Automation System
maintenance test record submitted.
46
CURRICULUM OF COMPETENCY UNIT (CoCU)
Sub Sector INDUSTRIAL AUTOMATION & MECHATRONIC
Job Area INDUSTRIAL AUTOMATION ENGINEERING
NOSS Title INDUSTRIAL AUTOMATION ENGINEERING SUPPORT SERVICE
Competency Unit Title INDUSTRIAL AUTOMATION ENGINEERING DRAFTING
Learning Outcomes The person who is competent in this CU shall be able to produce clean and precise technical drawing of an existing or non-existing object and or any parts of it, sectional views, detail assemblies and or sub-assemblies, hidden parts, its layout, in two and or three dimension, using symbols and methodology that complied with the specified standards, at a clear view angle, using a suitable accurate scale, drawn in an accurate dimensions, providing objects information as required and or specified, with the end product could be confidently referred to and become an understandable and effective communication media by any parties in accordance with organizational requirements.
. Upon completion of this competency unit, trainees will be able to :
Perform Industrial Automation Engineering Sketching
Perform two dimension engineering drawing development
Develop three dimensional engineering drawing
Prepare Drawing Bill of Materials
Perform Engineering Drawing Filing
Competency Unit ID MC-XXX-1 Level 2 Training Duration 110 Hours Credit Hours 11
Work Activities Related Knowledge Related Skills Attitude/Safety/ Environmental
Training Hours
Delivery Mode
Assessment Criteria
1. Perform Industrial Automation Engineering
i. Industrial Automation
Engineering Sketching Sketching instruction detail
Lecture
Industrial Automation Engineering
47
Work Activities Related Knowledge Related Skills Attitude/Safety/ Environmental
Training Hours
Delivery Mode
Assessment Criteria
Sketching Instruction source
Instruction authority
Instruction objective.
Instruction content
Imposed condition
Instruction authority.
Instruction validity
Engineering Drawing Sketching instruction acceptance.
ii. Pre-sketching
requirements preparation
Sketching requirement information.
Engineering drawing sketching objectives determinants.
Engineering drawing sketching time frame determinant.
Site exploration
In-situ measurements
Sketching concepts & orientation studies.
Sample visualization
Client interview
Sketching resources requirements
Engineering sketching
Sketching Sketching instruction interpreted, Instruction source, instruction authority, instruction objective confirmed, Instruction content interpreted, imposed condition, instruction authority, instruction validity confirmed, engineering Drawing Sketching instruction acceptance acknowledged.
Pre- sketching requirements preparation executed, sketching requirement information spelled, engineering
48
Work Activities Related Knowledge Related Skills Attitude/Safety/ Environmental
Training Hours
Delivery Mode
Assessment Criteria
tools, equipment and materials.
Engineering drawing sketching requirements summary.
iii. Industrial Automation
Engineering Sketching sketching activities
Customer requirements & specification
Product/object specification
Actual sample visualisation
Actual object visualisation.
Engineering drawing sketching site visit and exploration.
Non-exist object sketching information gathering.
Sketching Object orientation
Sketching view angle selection.
Engineering drawing sketching resources
Engineering drawing
drawing sketching objectives, engineering drawing sketching time frame ascertained, Site exploration, In-situ measurements executed, sketching concepts & orientation interpreted, sample visualization, client interview executed, sketching resources requirements listed, engineering sketching tools, equipment and materials listed, engineering drawing sketching requirements summary produced.
Industrial Automation Engineering
49
Work Activities Related Knowledge Related Skills Attitude/Safety/ Environmental
Training Hours
Delivery Mode
Assessment Criteria
sketching techniques application.
Engineering drawing sketching procedure
Engineering drawing sketching detail provision.
Engineering drawing sketching check & confirmation
Engineering drawing sketching record preparation
iv. Industrial Automation Engineering Sketching sketching record update.
Utilize Industrial Automation Engineering Sketching sketching record format
Provide Industrial Automation Engineering Sketching sketching record contents.
Apply Industrial Automation Engineering Sketching sketching recording techniques
Follow Industrial
Sketching sketching executed, customer requirements & specification, product/object specification, actual sample visualisation displayed, actual object visualisation executed, engineering drawing sketching site visit and exploration executed, non-exist object sketching information gathering executed, sketching Object orientation executed, sketching view angle ascertained, engineering drawing sketching resources displayed,
50
Work Activities Related Knowledge Related Skills Attitude/Safety/ Environmental
Training Hours
Delivery Mode
Assessment Criteria
Automation Engineering Sketching sketching recording procedure
v. Industrial Automation Engineering Sketching sketching record generation.
Industrial Automation Engineering Sketching sketching techniques used, Industrial Automation Engineering Sketching sketching procedure completed, Industrial Automation Engineering Sketching sketching detail spelled, Industrial Automation Engineering sketching check & confirmation executed, Industrial Automation Engineering Sketching sketching record produced.
Industrial
i. Examine Industrial
Automation Engineering Sketching Sketching instruction
ii. Perform Pre- sketching requirements preparation.
iii. Carry out Industrial Automation Engineering Sketching sketching
iv. Update engineering drawing sketching record.
v. Generate Industrial Automation Engineering Sketching sketching record
.
Practical
51
Work Activities Related Knowledge Related Skills Attitude/Safety/ Environmental
Training Hours
Delivery Mode
Assessment Criteria
Attitude:
i. Detail in examining
engineering Drawing Sketching instruction
ii. Objective focused in performing Pre- sketching requirements preparation.
iii. Informative in carrying out engineering drawing sketching
iv. Accurate in updating engineering drawing sketching record.
Safety:
i. Ensure data safety.
ii. Ensure safe work methodology.
iii. Ensure electrical safety on all electrically powered equipment.
Automation Engineering Sketching sketching record produced, Industrial Automation Engineering Sketching sketching record format used, Industrial Automation Engineering Sketching sketching record contents produced, Industrial Automation Engineering Sketching sketching recording techniques used, Industrial Automation Engineering Sketching sketching recording procedure completed,
52
Work Activities Related Knowledge Related Skills Attitude/Safety/ Environmental
Training Hours
Delivery Mode
Assessment Criteria
iv. Enforce safety & health rules and regulations
v. Ensure safe working condition.
vi. Promote good safety & health practice at workplace.
Environment:
i. Ensure energy saver office equipments.
ii. Reduce energy wastage.
iii. Practice paperless office.
Practice recycle policy.
Industrial Automation Engineering Sketching sketching record produced.
2. Perform two dimension engineering drawing development
i. Two dimension
engineering drawing development procedure
Instruction
Requirements
Scale and dimension.
Plan elevation
Side & end elevation.
Dimensions
Two dimension
engineering drawing produced, Engineering Drawing instruction produced, engineering drawing requirements listed, Engineering
53
Work Activities Related Knowledge Related Skills Attitude/Safety/ Environmental
Training Hours
Delivery Mode
Assessment Criteria
Drawing detail
Drawing title block.
Drawing submission ii. Two dimension sectional
drawing development procedure
iii. Two dimension sectional drawing requirements
iv. View cutting line v. Sectional view
development. vi. Sectional view detail
vii. Two dimension sectional drawing methodology
viii. Engineering drawing record documentation requirement
ix. Engineering drawing record format
x. Engineering drawing record contents.
xi. Engineering drawing recording procedure
xii. Engineering drawing record generation.
Drawing Scale and dimension ascertained, plan elevation, side & end elevation produced, Engineering Drawing dimensions, Engineering Drawing detail, Engineering Drawing title block produced, Engineering drawing submission executed.
Two Dimension Sectional Drawing produced, sectional Drawing instruction, two dimension sectional drawing requirements listed, sectional view cutting line ascertained, sectional view produced, sectional view
i. Develop two
dimension engineering drawing
ii. Develop Two
Dimension Sectional
54
Work Activities Related Knowledge Related Skills Attitude/Safety/ Environmental
Training Hours
Delivery Mode
Assessment Criteria
Drawing iii. Carry out two
dimension sectional drawing submission
iv. Update engineering
drawing record.
detail, two dimension sectional Drawing title block produced,
Two dimension sectional drawing submission executed.
Engineering drawing record produced, engineering drawing record format used, engineering drawing record contents produced, engineering drawing recording techniques used, engineering drawing recording procedure completed, engineering drawing record produced.
Attitude:
i. Precise in developing two dimension engineering drawing
ii. Precise in developing Two Dimension Sectional Drawing
iii. Timely in carrying out two dimension sectional drawing submission
iv. Accurate in updating engineering
drawing record. Safety:
i. Ensure data safety.
ii. Ensure safe work methodology.
55
Work Activities Related Knowledge Related Skills Attitude/Safety/ Environmental
Training Hours
Delivery Mode
Assessment Criteria
iii. Ensure electrical safety on all electrically powered equipment.
iv. Enforce safety & health rules and regulations
v. Ensure safe working condition.
vi. Promote good safety & health practice at workplace.
Environment:
i. Ensure energy saver office equipments.
ii. Reduce energy wastage.
iii. Practice paperless office.
iv. Practice recycle policy.
v.
3. Develop three dimensional Industrial Automation
i. Three dimensional
engineering drawing development instruction verification
Lecture Three dimensional
engineering drawing development
56
Work Activities Related Knowledge Related Skills Attitude/Safety/ Environmental
Training Hours
Delivery Mode
Assessment Criteria
engineering drawing
ii. Isometric drawing philosophy.
iii. Isometric Drawing specification
iv. Isometric development methodology.
v. Isometric drawing requirements
vi. Isometric drawing Scale and dimension.
vii. Isometric Drawing detail viii. Isometric Drawing title
block. ix. Orthographic drawing
philosophy x. Orthographic drawing
requirements xi. Orthographic drawing
Scale and dimension. xii. Orthographic view
drawing development. xiii. Orthographic Drawing
detail.
xiv. Orthographic drawing title block.
instruction interpreted, Instruction source, instruction authority and instruction objective confirmed, Instruction content interpreted, Imposed condition, Instruction authority and instruction validity confirmed and three dimensional engineering drawing instruction acceptance signed..
Isometric Drawing principles interpreted, Engineering Drawing instruction interpreted, isometric drawing requirements listed, isometric drawing Scale and dimension ascertained,
i. Examine three
dimensional engineering drawing development instruction
ii. Develop Isometric Drawing
Practical.
57
Work Activities Related Knowledge Related Skills Attitude/Safety/ Environmental
Training Hours
Delivery Mode
Assessment Criteria
iii. Develop
orthographic drawing
iv. Carry out orthographic drawing submission
v. Update engineering
drawing record.
isometric drawing produced, Isometric Drawing detail, Isometric Drawing title block produced, Isometric drawing submission executed.
Orthographic drawing principles interpreted, orthographic Drawing instruction interpretedd, orthographic drawing requirements listed, orthographic drawing Scale and dimension ascertained, orthographic view drawing produced, orthographic drawing detail and orthographic drawing title block produced, orthographic drawing plan produced.
Attitude:
i. Detail in examining three dimensional engineering drawing development instruction
ii. Objective focused in developing Isometric Drawing
iii. Objective focused in developing orthographic drawing
iv. Timely in carrying out two dimension sectional drawing submission
v. Accurate in updating engineering
58
Work Activities Related Knowledge Related Skills Attitude/Safety/ Environmental
Training Hours
Delivery Mode
Assessment Criteria
drawing record. Safety:
i. Ensure data safety.
ii. Ensure safe work methodology.
iii. Ensure electrical safety on all electrically powered equipment.
iv. Enforce safety & health rules and regulations
v. Ensure safe working condition.
vi. Promote good safety & health practice at workplace.
Environment:
i. Ensure energy saver office equipments.
ii. Reduce energy wastage.
iii. Practice paperless office.
iv. Practice recycle
Orthographic drawing submission executed.
Engineering drawing record updated, engineering drawing record format used, engineering drawing record contents provided, and engineering drawing recording techniques used, engineering drawing recording procedure followed
59
Work Activities Related Knowledge Related Skills Attitude/Safety/ Environmental
Training Hours
Delivery Mode
Assessment Criteria
policy.
4. Prepare Drawing Bill of Materials
i. Drawing Bill of Materials
instruction specification ii. Drawing Bill of Materials
requirements sources iii. Drawing bill of materials
principles. iv. Targeted object
specification v. Required materials
information list. vi. Prescribed materials list. vii. Required materials
quantification. viii. Required part detail &
specification ix. Required parts
quantification. x. Drawing bill of materials
requirements check. xi. Component part balloon
specification xii. Component part balloon
purposes. xiii. Part list table contents
(Part name, quantity, part materials and size)
xiv. Bill of Materials table specification
xv. Updated drawing filing.
Lecture
Drawing Bill of Materials instruction interpreted, instruction source, instruction authority, instruction validity, instruction requirements confirmed, job objectives interpreted, Drawing Bill of Materials job time frame determined, Drawing Bill of Materials instruction acceptance acknowledged.
Drawing Bill of Materials requirements listed, drawing bill of materials principles interpreted, targeted object
60
Work Activities Related Knowledge Related Skills Attitude/Safety/ Environmental
Training Hours
Delivery Mode
Assessment Criteria
i. Examine Drawing Bill of Materials instruction
ii. Obtain Drawing Bill of Materials requirements
iii. Create component part balloon
iv. Create Bill of Materials table.
v. File updated drawing
Practical. specification listed, instruments, tools, board and materials listed, required materials information list displayed, prescribed materials list confirmed, required materials counted, required part detail & specification listed, required parts counted, drawing bill of materials requirements confirmed.
Component part balloon created, type of part balloon, component part balloon purposes ascertained, component part number displayed.
Bill of Materials table produced, Bill of Materials table purposes, type of
Attitude: i. Detail in examining
Drawing Bill of Materials instruction
ii. Meticulous in obtaining Drawing Bill of Materials requirements
iii. Creative in creating component part balloon
iv. Accurate in creating Bill of Materials table.
v. Systematic in filing
61
Work Activities Related Knowledge Related Skills Attitude/Safety/ Environmental
Training Hours
Delivery Mode
Assessment Criteria
up updated drawing
Safety:
i. Ensure data safety.
ii. Ensure safe work methodology.
iii. Ensure electrical safety on all electrically powered equipment.
iv. Enforce safety & health rules and regulations
v. Ensure safe working condition.
vi. Promote good safety & health practice at workplace.
Environment:
i. Ensure energy saver office equipments.
ii. Reduce energy wastage.
iii. Practice paperless office.
iv. Practice recycle
Bill of Materials table items and specification ascertained, part list table contents (Part name, quantity, part materials and size) displayed, Bill of Materials table content confirmed, updated drawing produced.
Updated drawing filed, Engineering drawing physical filing systems. Engineering drawing digital filing systems interpreted, engineering drawing filing executed, engineering drawing record produced.
62
Work Activities Related Knowledge Related Skills Attitude/Safety/ Environmental
Training Hours
Delivery Mode
Assessment Criteria
policy.
5. Perform Engineering Drawing Filing
i. Engineering Drawing filing
instruction requirement ii. Engineering Drawing Filing
requirements iii. Drawing filing objectives. iv. Type of filing (Physical
/electronic) v. Drawing filing tools,
equipments and materials. vi. Drawing filing indexing
procedure. vii. Drawing filing procedure. viii. Drawing filing record ix. Drawing indexing register x. Drawing indexing
procedure xi. Drawing indexing register. xii. Drawing revision
identification number xiii. Drawing indexing detailing
format. xiv. Revised drawing version
number xv. Drawing date of birth. xvi. Drawing indexing method xvii. Physical drawing filing
requirement xviii. Physical drawing filing
procedure xix. Drawing title and coding
Lecture
Engineering Drawing filing instruction interpreted, instruction source, instruction contents, instruction authority, instruction validity confirmed, instruction acceptance acknowledged..
Engineering Drawing Filing requirements produced, drawing filing objectives achieved, type of filing (Physical /electronic) ascertained, drawing filing tools, equipments and materials, drawing filing indexing procedure,
63
Work Activities Related Knowledge Related Skills Attitude/Safety/ Environmental
Training Hours
Delivery Mode
Assessment Criteria
xx. Drawing classification xxi. Type of drawing filing xxii. Physical filing storage
location identification. xxiii. Drawing security
regulations xxiv. Data security regulations. xxv. Drawing storage section
determinant. xxvi. Drawing filing record
accuracy. xxvii. Physical drawing
movement record update. xxviii. Digital drawing filing
requirement xxix. Electronic drawing filing
procedure xxx. Drawing title and coding. xxxi. Drawing classification. xxxii. Type of drawing filing. xxxiii. Digital filing storage
location xxxiv. Digital drawing security
regulations xxxv. Data security regulations. xxxvi. Digital drawing storage
section. xxxvii. Digital drawing
drive/tape/disc address. xxxviii. Drawing file saving. xxxix. Digital drawing file
movement record update.
drawing filing procedure, Drawing filing record, drawing indexing register listed.
Drawing indexing performed, drawing indexing procedure ascertained, drawing indexing register interpreted, last series recorded, drawing revision identification number confirmed, drawing indexing detailing format used, unique new drawing index, revised drawing version number printed, drawing date of birth printed, drawing index printed, drawing index register, Drawing index record
64
Work Activities Related Knowledge Related Skills Attitude/Safety/ Environmental
Training Hours
Delivery Mode
Assessment Criteria
xl. Engineering Drawing filing retrieve/ issuance condition
produced.
Physical drawing filing carried out, drawing filing objectives ascertained, physical drawing filing procedure completed, drawing title and coding, drawing classification, type of drawing filing ascertained, physical filing storage location ascertained, drawing security regulations, data security regulations confirmed, drawing storage section, drawing tray number ascertained, accurate drawing filing record produced, physical drawing movement record produced.
Digital drawing
i. Examine
Engineering Drawing filing instruction
ii. Prepare Engineering Drawing Filing requirements
iii. Perform drawing indexing
iv. Carry out physical drawing filing
v. Carry out digital drawing filing
vi. Perform Engineering Drawing filing retrieve/ issuance
Practical
Attitude: i. Detail in examining
Engineering Drawing filing instruction
ii. Detail in preparing Engineering Drawing Filing
65
Work Activities Related Knowledge Related Skills Attitude/Safety/ Environmental
Training Hours
Delivery Mode
Assessment Criteria
requirements iii. Accurate in
performing drawing indexing
iv. Systematic in carrying out physical drawing filing
v. Systematic in carrying out digital drawing filing
vi. Meticulous in performing Engineering Drawing filing retrieve/ issuance
Safety:
i. Ensure data safety.
ii. Ensure safe work methodology.
iii. Ensure electrical safety on all electrically powered equipment.
iv. Enforce safety & health rules and regulations
v. Ensure safe working condition.
filing carried out, electronic drawing filing procedure completed, drawing title and coding, drawing classification, type of drawing filing ascertained, digital filing storage location ascertained, digital drawing security regulations confirmed, data security regulations complied, digital drawing storage section ascertained, digital drawing drive/tape/disc address printed, drawing file saved, digital drawing filing record , digital drawing file movement record produced.
Engineering Drawing filing
66
Work Activities Related Knowledge Related Skills Attitude/Safety/ Environmental
Training Hours
Delivery Mode
Assessment Criteria
vi. Promote good safety & health practice at workplace.
Environment:
i. Ensure energy saver office equipments.
ii. Reduce energy wastage.
iii. Practice paperless office. Practice recycle policy
retrieve/ issuance executed, Engineering Drawing issuance instruction interpreted, issuance instruction authority, instruction validity confirmed, instruction acceptance acknowledged, Drawing title, drawing index and coding, drawing classification, drawing security level, drawing file location traced, storage media listed, digital drawing file retrieved, date of drawing issuance ascertained, issuance and recipient detail recorded, drawing movement, Drawing record
67
Work Activities Related Knowledge Related Skills Attitude/Safety/ Environmental
Training Hours
Delivery Mode
Assessment Criteria
book record produced.
Employability Skills
Core Abilities Social Skills
01.01 Identify and gather information 01.02 Document information, procedures or processes 01.03 Utilize basic IT applications 01.04 Analyse information 01.05 Utilize the Internet to locate and gather information 01.06 Utilize word processor to process information 02.01 Interpret and follow manuals, instructions and SOP’s 02.02 Follow telephone/ telecommunication procedures 02.03 Communicate clearly 02.04 Prepare brief reports and checklists using standard forms 02.05 Read/interpret flowcharts and pictorial information 02.06 Write memos and letters 02.07 Utilize Local Area Network (LAN)/Intranet to exchange information 02.08 Prepare pictorial and graphic information 03.01 Apply cultural requirements to the workplace 03.02 Demonstrate integrity and apply ethical practices 03.03 Accept responsibility for own work and work area 03.04 Seek and act constructively upon feedback about performance 03.05 Demonstrate safety skills 03.06 Respond appropriately to people and situations
1. Communication skills 2. Conceptual skills 3. Interpersonal skills 4. Learning skills 5. Leadership skills 6. Multitasking and prioritizing 7. Self-discipline 8. Teamwork
68
03.07 Resolve interpersonal conflicts 03.08 Develop and maintain a cooperation within work group 04.01 Organize own work activities 04.02 Set and revise own objectives and goals 04.03 Organize and maintain own workplace 04.04 Apply problem solving strategies 04.05 Demonstrate initiative and flexibility 06.01 Understand systems 06.02 Comply with and follow chain of command 06.03 Identify and highlight problems 06.04 Adapt competencies to new situations/systems 06.05 Analyse technical systems 06.06 Monitor and correct performance of systems
Tools, Equipment and Materials (TEM)
Items Ratio (TEM: Trainee)
1. Computer Set with words processing & graphic application. 2. LCD Projector or any other projector with white screen 3. Drawing board 4. Measuring Instrument
1:25 1:25 1:1 1:1
REFERENCES
1. Frederick E. Giesecke, Alva E. Mitchell, Henry C. Spencer, Ivan L. Hill , John Thomas Dygdon ,James E. Novak , Shawna E. Lockhart ,
Prentice Hall; 13 edition (May 23, 2008), Technical Drawing (13th Edition), ISBN: 978-0135135273 2. Frederick E. Giesecke, Peachpit Press 1992, Principles of Technical Drawing, ISBN: 978-0023437359 3. John S. Rooke, IndyPublish.com, 2008, Textbook of Mechanical Drawing: Being an Explanation of the Principles of Geometry and
Orthographic Projection, the Helix, and Toothed Gearing, ISBN: 9781437165753
69
4. Frederick E. Giesecke (Author), Ivan L. Hill (Author), Henry C. Spencer (Author), Alva E. Mitchell (Author), John Thomas Dygdon (Author), James E. Novak (Author), Shawna E. Lockhart (Author), Marla Goodman , Peachpit Press, 14 Ed, 2011, Technical Drawing with Engineering Graphics, ISBN: 978-0135090497
70
CURRICULUM OF COMPETENCY UNIT (CoCU)
Sub Sector INDUSTRIAL AUTOMATION & MECHATRONIC
Job Area INDUSTRIAL AUTOMATION ENGINEERING
NOSS Title INDUSTRIAL AUTOMATION ENGINEERING SUPPORT SERVICE
Competency Unit Title COMPUTER AIDED DESIGN & DRAFTING
Learning Outcome The person who is competent in this CU shall be able to produce clean and precise mechanical drawing of an existing or non-existing object and or any parts of it, sectional views, detail assemblies and or sub-assemblies, hidden parts, its layout, in two and or three dimension, using symbols and methodology that complied with the specified standards, at a clear view angle, using a suitable accurate scale, drawn in an accurate dimensions, providing objects information as required and or specified, using a specified computer aided design and drafting software, neatly and clearly printed or plotted, with the end product could be confidently referred and become an understandable and effective communication media by any parties in accordance with organizational requirements. Upon completion of this competency unit, trainees will be able to :
1. Obtain CAD software and requirements 2. Perform CADD Application systems installation 3. Develop CADD Two Dimensional Industrial Automation Drawing
4. Develop CADD Industrial Automation Three Dimensional Drawing 5. Develop CADD Industrial Automation assembly Drawing 6. Develop CADD Three Dimensional Industrial Automation Assembly Drawing 7. Prepare CADD operation report.
Competency Unit ID MC-XXX-2 Level 2 Training Duration 120 Hours Credit Hours 12
Work Activities Related Knowledge Related Skills Attitude/Safety/
Environmental
Training Hours
Delivery Mode
Assessment Criteria
71
Work Activities Related Knowledge Related Skills Attitude/Safety/
Environmental
Training Hours
Delivery Mode
Assessment Criteria
1. Obtain
CADD software and requirements
i. CADD Application
requisition concept & requirements.
ii. CADD Application product availability
iii. Source of CADD software iv. Type of CADD Software v. CADD Software
specification vi. CADD software and
requirements delivery inspection.
vii. CADD Delivery receipt.
Lecture
CADD Application systems requisition instruction & requirements interpreted so that instruction official source declared, instruction direction officiated, instruction requirements listed and instruction authority confirmed.
CADD Application product availability confirmed.
CADD Application systems product requisition produced.
CADD Software specification confirmed.
CADD software and requirements delivery inspection executed so that CADD items & quantity, Software
i. Examine CADD application systems requisition instruction & requirements.
ii. Check CADD Application product availability.
iii. Check CADD Software specification
iv. Generate CADD Application systems product requisition.
v. Conduct CADD software and
Practical
72
Work Activities Related Knowledge Related Skills Attitude/Safety/
Environmental
Training Hours
Delivery Mode
Assessment Criteria
requirements delivery inspection.
vi. Check delivery receipt.
contents & serviceability, product licensing, hardware items, type & quantity and product's manual confirmed in accordance with organizational purchasing policy and procedure. Confirmed Delivery receipt collected in accordance with organizational purchasing policy and procedure.
Attitude:
i. Thorough in examining CADD Application instruction & requirements.
ii. Informative in checking CADD Application product availability.
iii. Detail in checking CADD Software specification
iv. Accurate in generating CADD Application systems product requisition.
v. Meticulous in checking CADD software and requirements delivery.
vi. Confidence in confirming delivery receipt.
73
Work Activities Related Knowledge Related Skills Attitude/Safety/
Environmental
Training Hours
Delivery Mode
Assessment Criteria
Safety:
i. Ensure data safety.
ii. Ensure safe work methodology.
iii. Ensure electrical safety on all electrically powered equipment.
iv. Enforce safety & health rules and regulations
v. Ensure safe working condition.
vi. Promote good safety & health practice at workplace.
Environment:
i. Ensure energy saver office equipments.
ii. Reduce energy wastage.
iii. Practice paperless office.
74
Work Activities Related Knowledge Related Skills Attitude/Safety/
Environmental
Training Hours
Delivery Mode
Assessment Criteria
iv. Practice recycle policy.
2.Perform
CADD Application systems installation
i. CAD software Installation
instruction and requirements.
Hardware requirements
Software requirements
Licensing requirements ii. CAD installation planning
CAD installation objectives.
CAD installation time frame
CAD installation tools, equipments & materials.
iii. CAD Installation • Installation Tools ,
equipments and materials.
• Hardware Installation • Software Installation
iv. CAD Installation evaluation • Installation performance
parameters • Evaluation techniques • Evaluation procedure.
v. CAD installation record • Hardware Installation • Software Installation
Lecture CAD Software
installation instruction and requirements interpreted.
CAD hardware installation instruction, manual and requirements interpreted.
CAD Installation requirements interpreted so that installation tools , equipments and materials listed, hardware & software installation requirements ascertained and licensing requirements understood.
CAD installation planning executed so that CAD installation objectives,
75
Work Activities Related Knowledge Related Skills Attitude/Safety/
Environmental
Training Hours
Delivery Mode
Assessment Criteria
i. Examine CAD
Software installation instruction and requirements.
ii. Examine CAD hardware installation manual and requirements.
iii. Examine CAD Installation requirements.
iv. Plan CAD installation
v. Perform CAD Installation
vi. Evaluate CAD Installation
vii. Accurate in preparing CAD installation record
Practical installation time frame, installation tools, equipments and materials ascertained.
CAD Installation executed so that installation tools , equipments and materials acquired, CAD Hardware Installation and CAD Software Installation executed in accordance with hardware manufacturer's manual and CAD producers requirements.
CAD Installation passed so that installation performance parameters ascertained, CAD installation evaluation techniques used and evaluation procedure
Attitude:
i. Detail in examining CAD Software installation instruction and requirements.
ii. Detail in examining CAD hardware installation manual
76
Work Activities Related Knowledge Related Skills Attitude/Safety/
Environmental
Training Hours
Delivery Mode
Assessment Criteria
and requirements. iii. Detail in examining
CAD Installation requirements.
iv. Objective focused in planning CAD installation
v. Meticulous in performing CAD Installation
vi. Accurate in preparing CAD installation record
Safety:
i. Ensure data safety.
ii. Ensure safe work methodology.
iii. Ensure electrical safety on all electrically powered equipment.
iv. Enforce safety & health rules and regulations
v. Ensure safe working condition.
vi. Promote good safety & health
completed in accordance with organizational requirements.
CAD installation record produced in accordance with organizational requirement.
77
Work Activities Related Knowledge Related Skills Attitude/Safety/
Environmental
Training Hours
Delivery Mode
Assessment Criteria
practice at workplace.
Environment:
i. Ensure energy saver office equipments.
ii. Reduce energy wastage.
iii. Practice paperless office.
iv. Practice recycle policy.
3. Develop
CADD Two Dimensional Industrial Automation Drawing
i. Examine CADD Two Dimensional Industrial Automation Drawing instruction
instruction source
instruction authority
instruction validity
instruction requirements
Assignment objectives ii. CADD Industrial Automation drawing requirements
Industrial Automation drawing sketches and drawing information
CADD Industrial Automation drawing tools and
Lecture
CADD Two Dimensional Industrial Automation Drawing instruction interpreted , instruction source, instruction authority, instruction validity, instruction requirements confirmed, job objectives understood, Industrial Automation Drawing instruction
78
Work Activities Related Knowledge Related Skills Attitude/Safety/
Environmental
Training Hours
Delivery Mode
Assessment Criteria
equipments.
Industrial Automation drawing requirements
iii CADD Two Dimensional Industrial Automation Drawing Scale and dimension.
Two dimension drawing requirements
Paper formats and units
Drawing dimension style
Standard line layers and thickness
Drawing base length
Drawing scale.
iv. Develop CADD plan elevation development
Lines based on standard line layers and thickness
Construction line
Object line
Hidden line
Drawing symbols
v. CADD side & end elevation development
Generate Projection line
Determine intersection points
Develop object line
acceptance signed.
CADD Two Dimensional Industrial Automation Drawing requirement, Industrial Automation drawing sketches and drawing information, CADD Industrial Automation drawing tools and equipments listed and Industrial Automation drawing requirements collected.
Industrial Automation Drawing CADD Scale and dimension ascertained, two dimension drawing requirements listed, paper
79
Work Activities Related Knowledge Related Skills Attitude/Safety/
Environmental
Training Hours
Delivery Mode
Assessment Criteria
Clear projection line. vi. CADD Industrial
Automation Drawing dimensions preparation
Dimension detail.
Information accuracy
Dimension line
Dimension detail.
Dimension detail and dimension style consistencies.
vii. CADD Industrial
Automation Drawing detail preparation
Drawing detail.
Information accuracy
Font/lettering size
Drawing detail
Detail spelling
Industrial Automation drawing detail.
Detail spelling and font consistencies.
8. CADD Industrial
Automation Drawing title block preparation
Industrial Automation title block detail.
formats and units ascertained, drawing dimension style ascertained, standard line layers and thickness set, drawing base length confirmed and Drawing scale ascertained.
CADD plan elevation ascertained, lines based on standard line layers and thickness produced, construction line, object line, hidden line produced, drawing symbols produced.
CADD side & end elevation produced, projection line generated, intersection points ascertained, object line produced and
80
Work Activities Related Knowledge Related Skills Attitude/Safety/
Environmental
Training Hours
Delivery Mode
Assessment Criteria
Information accuracy
Font/lettering size
Title block format
Title block detail
Drawing title and identification number.
Signatories line and arrangements.
Detail spelling and font consistencies.
9. Generate CADD Industrial Automation Drawing
Plotter requirements
Paper in plotter / printer
Page setup manager
Plotter / printer features
Paper size
Plotting scale
Plotting style table for pen assignments
Drawing orientation
Drawing scale
Plot / print Industrial Automation Drawing
Plotting outcome checking 10. Industrial Automation drawing submission process
Information accuracy checking
projection line removed.
CADD Industrial Automation Drawing dimensions printed, dimension detail listed, information accuracy confirmed, dimension line produced, dimension detail, dimension detail and dimension style consistencies confirmed.
CADD Industrial Automation Drawing detail printed, drawing detail listed, font/lettering size ascertained, information accuracy, detail spelling, Industrial Automation drawing detail printed, detail
81
Work Activities Related Knowledge Related Skills Attitude/Safety/
Environmental
Training Hours
Delivery Mode
Assessment Criteria
Drawing submission check list
Drawing folding method
Industrial Automation drawing log book.
Industrial Automation Drawing digital filing.
spelling and font consistencies confirmed.
CADD Industrial Automation Drawing title block produced, Industrial Automation title block detail printed, information accuracy confirmed, font/lettering size ascertained, title block format used, title block detail printed, drawing title and identification number printed, signatories line and arrangements allocated and detail spelling and font consistencies confirmed.
CADD Industrial Automation Drawing produced, plotter
i. Examine Industrial Automation Drawing instruction
ii. Obtain CADD Industrial Automation drawing requirements
iii. Determine Industrial Automation Drawing CADD Scale and dimension.
iv. Develop CADD plan elevation
v. Develop CADD side & end elevation
vi. 6.Prepare CADD Industrial Automation Drawing dimensions
vii. Prepare CADD Industrial
Practical
82
Work Activities Related Knowledge Related Skills Attitude/Safety/
Environmental
Training Hours
Delivery Mode
Assessment Criteria
Automation Drawing detail
viii. Prepare CADD Industrial Automation Drawing title block
ix. Generate CADD Industrial Automation Drawing
x. Carry out Industrial Automation drawing submission
requirements ready, paper in plotter / printer loaded, page setup manager set, plotter / printer, paper size, plot scale, plot style table for pen assignments, drawing orientation and drawing scale determined, Industrial Automation Drawing plotted and plotting outcome confirmed.
Industrial Automation drawing submission and drawing final checking executed, information accuracy confirmed, drawing submission check list disclosed, drawing folded, drawing submitted,
Attitude:
i. Detail in examining Industrial Automation Drawing instruction
ii. Detail in obtaining CADD Industrial Automation drawing requirements
iii. Accurate in determining Industrial Automation Drawing CADD Scale and dimension.
iv. Precise in
83
Work Activities Related Knowledge Related Skills Attitude/Safety/
Environmental
Training Hours
Delivery Mode
Assessment Criteria
developing CADD plan elevation
v. Precise in developing CADD side & end elevation
vi. Accurate in preparing CADD Industrial Automation Drawing dimensions
vii. Accurate in preparing CADD Industrial Automation Drawing detail
viii. Accurate in preparing CADD Industrial Automation Drawing title block
ix. Accurate in generating CADD Industrial Automation Drawing
x. Confidence in carrying out CADD Industrial Automation drawing
file digitally stored and Industrial Automation drawing log book update produced.
84
Work Activities Related Knowledge Related Skills Attitude/Safety/
Environmental
Training Hours
Delivery Mode
Assessment Criteria
submission
Safety:
i. Ensure data safety.
ii. Ensure safe work methodology.
iii. Ensure electrical safety on all electrically powered equipment.
iv. Enforce safety & health rules and regulations
v. Ensure safe working condition.
vi. Promote good safety & health practice at workplace.
Environment:
i. Ensure energy saver office equipments.
ii. Reduce energy wastage.
iii. Practice paperless office.
iv. Practice recycle
85
Work Activities Related Knowledge Related Skills Attitude/Safety/
Environmental
Training Hours
Delivery Mode
Assessment Criteria
policy.
4. Develop
CADD Industrial Automation Three Dimensional Drawing
i. CADD Industrial Automation
Three Dimensional Drawing instruction
ii. CADD Industrial Automation drawing requirements
Industrial Automation drawing sketches and drawing information
CADD Industrial Automation drawing tools and equipments.
Industrial Automation drawing requirements
iii. CADD Industrial
Automation Three Dimensional Drawing Scale and dimension.
three dimension drawing requirements
paper formats and units
standard line layers & thickness setting
drawing base length
Drawing scale.
three angles of dimension
thickness of structures
3D Object (cube, cone,
Lecture
CADD Industrial Automation Three Dimensional Drawing instruction
interpreted , instruction source, instruction authority, instruction validity, instruction requirements confirmed, job objectives explained, Industrial Automation Drawing instruction acceptance signed.
CADD Industrial Automation Three Dimensional Drawing instruction requirement, Industrial Automation drawing sketches and drawing information, CADD
86
Work Activities Related Knowledge Related Skills Attitude/Safety/
Environmental
Training Hours
Delivery Mode
Assessment Criteria
cylinder, sphere, geometry, etc.)
3D construction method (Boolean, Object Compose, Extrude, Loft, Bending, FFD, NURB, etc.)
iv. CADD plan elevation (2D
shape sketch)
polylines based on standard line layers and thickness
construction line using 2D spline shape
object line
curve line
circle shape
triangle shape
rectangle shape
hidden line
dummy object
drawing symbols
CADD plan elevation (2D shape sketch)
v. CADD side & end elevation (3D transforming) development
Extrude method application
Industrial Automation drawing tools and equipments displayed and Industrial Automation drawing requirements listed.
CADD Industrial Automation Three Dimensional Drawing Scale and dimension ascertained, three dimension drawing requirements interpreted, paper formats and units ascertained, standard line layers & thickness set, drawing base length confirmed, drawing scale, three angles of dimension, thickness of structures, 3D
87
Work Activities Related Knowledge Related Skills Attitude/Safety/
Environmental
Training Hours
Delivery Mode
Assessment Criteria
three dimension of objects (polygon) development
Bending method application
Boolean method to attachment multiple object
NURB method to construct surface of objects
CADD side & end elevation (3D transforming) checking
vi. 3D Object Editing and Refining
polygon editing
object editing using Bending method
object editing using FFD method
vii. Object Colouring
3D object
Material Editor Panel opening
colour from palette selection
colour to selected object application
object colouring process result checking
Object (cube, cone, cylinder, sphere, geometry, etc.), 3D construction method (Boolean, Object Compose, Extrude, Loft, Bending, FFD, NURB, etc.) ascertained and Industrial Automation Drawing CADD Scale and dimension factors summarised.
CADD plan elevation, polylines based on standard line layers & thickness, construction line (using 2D spline shape), object line, curve line, circle shape, triangle shape, rectangle shape, hidden line, Dimension line,
88
Work Activities Related Knowledge Related Skills Attitude/Safety/
Environmental
Training Hours
Delivery Mode
Assessment Criteria
viii. 3D Object Texture &Material Mapping
object materials (steel, wood, aluminium, glass, sandy, shining, rubber, plastic, etc)
material selection from library
Self design material development
object material development
material object naming
material object to 3D object application
3D Object Texture &Material Mapping outcome checking
ix. Rendering process
rendering perspective angle
rendering object
Rendering Panel opening
rendering method selection
rendering process performance
rendering result preview
centre line, section line, dummy object produced, drawing symbols drawn and CADD plan elevation (2D shape sketch) confirmed.
CADD side & end elevation (3D transforming) produced, extrude method and revolved method used, three dimension object produced, Bending method applied (object reformation), Boolean method used ( to attachment multiple object), NURB method used (to construct surface of objects), CADD side & end elevation (3D transforming)
89
Work Activities Related Knowledge Related Skills Attitude/Safety/
Environmental
Training Hours
Delivery Mode
Assessment Criteria
x. CADD 3D process final Output preview
perspective angle to rendering
Rendering Panel opening
rendering method selection
location to save rendered object selection
object format type (still image, video, draft, sequence, movie, etc) selection.
format document (jpg, png, avi, mov, swf, tif, targa, flv, gift) selection
rendering development xi. 3D Camera view
perspective rendering implementation.
view of visual
type of camera
camera development
position of camera
distance of camera
camera zooming
camera view perspective rendering implementation
xii. CADD Industrial
confirmed.
3D Object Editing and Refining executed, polygon using and object refined, Bending method and FFD method applied, and refined & refined 3D Object confirmed and record produced.
Object colouring executed, object ascertained, Material Editor Panel opened, colour (from palette) ascertained, selected object colour used, object colouring process result confirmed.
3D Object Texture &Material Mapping executed, object materials (steel,
90
Work Activities Related Knowledge Related Skills Attitude/Safety/
Environmental
Training Hours
Delivery Mode
Assessment Criteria
Automation Drawing dimensions
Dimension detail compilation.
Information accuracy check.
Dimension line development
Dimension detail check.
Dimension detail and dimension style consistencies check.
xiii. CADD Industrial Automation Drawing detail preparation.
Drawing detail compilation.
Information accuracy check
Font/lettering size selection
Drawing detail insertion.
Detail spelling check
Industrial Automation drawing detail check..
Detail spelling and font consistencies check
xiv. CADD Industrial
Automation Drawing title
wood, aluminium, glass, sandy, shining, rubber, plastic, etc) ascertained, Material Editor Panel open, material from library ascertained, self design materials produced, object material produced, object material named & saved, material object used (to 3D object), and 3D Object Texture & Material Mapping outcome confirmed.
Rendering executed, rendering perspective angle ascertained, rendering object ascertained, Rendering Panel
91
Work Activities Related Knowledge Related Skills Attitude/Safety/
Environmental
Training Hours
Delivery Mode
Assessment Criteria
block
Industrial Automation title block detail.
Information accuracy check
Font/lettering size selection.
Title block format utilization
Title block insertion
Drawing title and identification number provision.
Signatories line and arrangements provision.
Detail spelling and font consistencies check.
xv. 3D CADD Industrial
Automation Drawing generation
Plotter requirements installation
Paper in plotter / printer preparation.
Page setup manager
Plotter / printer selection
Paper size selection
Plot scale selection
Plot style table for pen assignments
ready, rendering method ascertained, rendering process executed, rendering result previewed.
CADD 3D process final Output previewed, perspective rendering angle ascertained, rendering object ascertained, Rendering Panel opened, rendering method ascertained, rendered object saving location ascertained, object format type ascertained (still image, video, draft, sequence, movie, etc ) , format document (jpg, png, avi, mov, swf, tif, targa, flv, gift)
92
Work Activities Related Knowledge Related Skills Attitude/Safety/
Environmental
Training Hours
Delivery Mode
Assessment Criteria
Drawing orientation
Drawing scale selection
Plot / print Industrial Automation Drawing
Plotting outcome xvi. Industrial Automation
drawing submission
Drawing final checking
Information accuracy checking
Attach drawing submission check list
Fold/roll drawing i. Industrial Automation
drawing log book update.
ascertained and CADD 3D process final Output previewed.
3D Camera Handling performed, view of visual ascertained, camera type ascertained, camera produced, camera position edited, camera distance edited, camera zooming executed, camera view perspective rendering executed , confirmed and record produced.
CADD Industrial Automation Drawing dimensions prepared, dimension detail obtained, information accuracy checked, dimension line
i. Examine Industrial
Automation Drawing instruction
ii.Develop CADD plan elevation (2D shape sketch)
iii. Carry out 3D Object Editing and Refining
ix. Conduct Rendering xiii. . Prepare CADD Industrial Automation Drawing detail xv. Generate 3D CADD Industrial Automation
Practical
93
Work Activities Related Knowledge Related Skills Attitude/Safety/
Environmental
Training Hours
Delivery Mode
Assessment Criteria
Drawing xvi. Carry out Industrial Automation drawing submission
produced, dimension detail, dimension detail and dimension style consistencies checked.
CADD Industrial Automation Drawing dimensions prepared, dimension detail obtained, information accuracy checked, dimension line produced, dimension detail, dimension detail and dimension style consistencies checked.
CADD Industrial Automation Drawing title block produced, Industrial Automation title block detail obtained,
Attitude:
i. Thorough in examining Industrial Automation Drawing instruction
ii. Resourceful in obtaining CADD Industrial Automation drawing requirements
iii. Objective focused in determining Industrial Automation Drawing CADD Scale and dimension.
iv. Careful in preparing CADD Industrial Automation Drawing
94
Work Activities Related Knowledge Related Skills Attitude/Safety/
Environmental
Training Hours
Delivery Mode
Assessment Criteria
dimensions v. Meticulous in
preparing CADD Industrial Automation Drawing detail
vi. Detailed in preparing CADD Industrial Automation Drawing title
vii. Meticulous in generating 3D CADD Industrial Automation Drawing
viii. Punctual in carrying out Industrial Automation drawing submission
Safety:
i. Ensure data safety.
ii. Ensure safe work methodology.
iii. Ensure electrical safety on all electrically
information accuracy confirmed, font/lettering size selected, title block format used, title block detail inserted, Drawing title and identification number provided, signatories line and arrangements provided, detail spelling and font consistencies confirmed.
3D CADD Industrial Automation Drawing produced, plotter requirements usabled, paper in plotter / printer loaded, page setup executed, plotter / printer, paper size, plot scale plot style table for pen assignments,
95
Work Activities Related Knowledge Related Skills Attitude/Safety/
Environmental
Training Hours
Delivery Mode
Assessment Criteria
powered equipment.
iv. Enforce safety & health rules and regulations
v. Ensure safe working condition.
vi. Promote good safety & health practice at workplace.
Environment:
i. Ensure energy saver office equipments.
ii. Reduce energy wastage.
iii. Practice paperless office.
iv. Practice recycle policy.
drawing orientation and drawing scale determined, Industrial Automation Drawing plotted, plotted drawing confirmed.
Industrial Automation drawing submission executed, drawing final checking executed, information accuracy confirmed, drawing submission check list attached, drawing folded/rolled and Industrial Automation drawing log book updated.
CADD Industrial Automation Drawing detail produced, drawing
96
Work Activities Related Knowledge Related Skills Attitude/Safety/
Environmental
Training Hours
Delivery Mode
Assessment Criteria
detail obtained, information accuracy, font/lettering size confirmed, drawing detail inserted,
Detail spelling
Check Industrial Automation drawing detail. Detail spelling and font consistencies.
5. Develop CADD Industrial Automation assembly Drawing
i. CADD Industrial
Automation assembly Drawing concept and application.
ii. Assembly drawing principles
iii. Assembly drawing purposes
iv. Assembly Drawing instruction
v. CADD Industrial Automation assembly Drawing requirements
Obtain Industrial Automation drawing sketches and drawing information
Obtain CADD Industrial
Lecture CADD Industrial Automation assembly Drawing
instruction, instruction source, instruction authority, instruction validity and instruction requirements interpreted, job objectives understood, Industrial Automation Drawing instruction signed.
CADD Industrial
97
Work Activities Related Knowledge Related Skills Attitude/Safety/
Environmental
Training Hours
Delivery Mode
Assessment Criteria
Automation drawing tools and equipments.
Gather Industrial Automation drawing requirements
vi. CADD Industrial
Automation assembly Drawing requirements preparation
Targeted 2D drawing file.
Assembly drawing specification
Assembly drawing tools, equipment, instruments and materials.
Layer (by different colour and line).
Assembly component development/ Import assembly component
Part layer changes (for assembling).
Component reference point development
vii. CADD Industrial
Automation assembly Drawing development
Main drawing preparation
Component assembling
Automation assembly Drawing
requirements, Industrial Automation drawing sketches & drawing information, CADD Industrial Automation drawing tools & equipments received, Industrial Automation drawing requirements listed.
Assembly drawing requirements produced, targeted 2D drawing file and Assembly drawing specification received, Assembly drawing tools, equipment, instruments and materials listed, layer (by different colour and line) created, assembly
98
Work Activities Related Knowledge Related Skills Attitude/Safety/
Environmental
Training Hours
Delivery Mode
Assessment Criteria
assemble & dissemble layer Locking systems
Develop assembly symbol (such as. welding, GD&T).
Develop cutting plane ( sectioning )
Develop multi sectioning area view
Develop object material
Conduct hatching process.
Check line accuracy
viii. Prepare CADD Industrial Automation assembly Drawing detail
Obtain drawing detail.
Check information accuracy
Select font/lettering size
Balloon creation
Bill of material provision
Bill of material information.
Scale drawing development
Drawing detail indication & development.
Detail spelling checking
Font consistencies
component development or Import assembly component executed, layer changed (for assembling), component reference point displayed.,
Assembly drawing produced, main drawing received, component assembled, layer locked, Assembly symbol (such as. welding, GD&T) printed, cutting plane (sectioning) produced,
multi sectioning area view produced, object material and hatching process executed, and line accuracy interpreted.
99
Work Activities Related Knowledge Related Skills Attitude/Safety/
Environmental
Training Hours
Delivery Mode
Assessment Criteria
checking
ix. Industrial Automation drawing submission implementation
Assembly drawing final checking
Assembly drawing detail accuracy checking
Drawing submission check list
Industrial Automation drawing log book update.
Assembly drawing detail produced, drawing detail received, information accuracy interpreted, font/lettering size selected, balloon and bill of material drawn, Bill of material information completed, scale drawing produced and drawing detail printed, drawing detail inserted, detail spelling, Industrial Automation drawing detail, and detail font consistencies interpreted.
Industrial Automation drawing submission and
i. Examine Assembly
Drawing instruction ii. Obtain CADD
Assembly drawing requirements
iii. Prepare Assembly drawing requirements
iv. Develop Assembly drawing
v. Prepare Assembly drawing detail
vi. Carry out Industrial Automation drawing submission
Practical
100
Work Activities Related Knowledge Related Skills Attitude/Safety/
Environmental
Training Hours
Delivery Mode
Assessment Criteria
Attitude:
i. Detail in examining Assembly Drawing instruction
ii. Detail in obtaining CADD Assembly drawing requirements
iii. Objective focused in preparing Assembly drawing requirements
iv. Accurate in developing Assembly drawing
v. Thorough in preparing Assembly drawing
detail. vi. Confidence in
carrying out Industrial Automation drawing submission
Safety:
i. Ensure data safety.
ii. Ensure safe work methodology.
assembly drawing final checking executed, assembly drawing detail accuracy interpreted, drawing submission check list attached, drawing folded and
Industrial Automation drawing log book updated.
101
Work Activities Related Knowledge Related Skills Attitude/Safety/
Environmental
Training Hours
Delivery Mode
Assessment Criteria
iii. Ensure electrical safety on all electrically powered equipment.
iv. Enforce safety & health rules and regulations
v. Ensure safe working condition.
vi. Promote good safety & health practice at workplace.
Environment:
i. Ensure energy saver office equipments.
ii. Reduce energy wastage.
iii. Practice paperless office.
iv. Practice recycle policy.
6. Develop CADD Three
i. CADD Three Dimensional Industrial Automation Assembly Drawing instruction
CADD Three Dimensional Industrial
102
Work Activities Related Knowledge Related Skills Attitude/Safety/
Environmental
Training Hours
Delivery Mode
Assessment Criteria
Dimensional Industrial Automation Assembly Drawing
Instruction source
Instruction authority
Instruction validity
ii. CADD Three Dimensional Industrial Automation Assembly Drawing requirements
Industrial Automation drawing sketches and drawing information
CADD Industrial Automation drawing tools and equipments.
iii. 3D Assembly drawing requirements preparation.
Targeted 3D drawing file.
Assembly drawing specification
Assembly drawing tools, equipment, instruments and materials gathering.
Individual / parts drawing development
New assembly lay out creation.
iv. CADD Three Dimensional Industrial Automation Assembly Drawing
Automation Assembly Drawing instruction interpreted, instruction source, instruction authority, instruction validity and instruction requirements confirmed, job objectives ascertained, Industrial Automation Drawing instruction signed.
CADD Three Dimensional Industrial Automation Assembly Drawing requirements and Industrial Automation drawing sketches, drawing information, CADD Industrial Automation
103
Work Activities Related Knowledge Related Skills Attitude/Safety/
Environmental
Training Hours
Delivery Mode
Assessment Criteria
development
Main drawing
First component positioning
Adding component
Insert component
Moving and rotating
Mating component
Component Alignment
Mating concentric and coincident performance
Assembly motion performance
Hiding and transparency
Component properties
Assembly analysis
Mass properties calculation
Interference detection checking
Value of dimension change
Physical simulation performance
Exploded assemblies
Exploded line sketch
Animating explode view v. CADD 3D Assembly Drawing Detail preparation
Drawing detail gathering
Information accuracy check
Multi view orientation
drawing tools and equipments listed, Industrial Automation drawing requirements listed.
CADD Three Dimensional Industrial Automation Assembly Drawing ready, targeted 3D drawing file, Assembly drawing specification listed, Assembly drawing tools, equipment, instruments and materials listed, individual / parts drawing produced and new assembly lay out produced.
3D Assembly drawing produced, main drawing listed, first component
104
Work Activities Related Knowledge Related Skills Attitude/Safety/
Environmental
Training Hours
Delivery Mode
Assessment Criteria
Balloon provision.
Bill of material provision.
Font/lettering size selection.
Bill of material complete information
Scale drawing development
Detail drawing development and indication
Cutting plate ( sectioning) development.
Assembly symbol provision (such as welding, GD&T and etc)
Detail spelling checking
Industrial Automation drawing detail checking.
Detail spelling and font consistencies checking.
vi. Carry out CADD 3D Industrial Automation drawing submission
Assembly drawing final checking
Assembly drawing detail accuracy checking
Drawing submission check list attachment.
Fold/roll drawing Industrial Automation drawing log
book update.
displayed, component increased, component displayed, image Moved & and rotated, component mated, alignment process executed, Mating concentric and coincident executed, Assembly motion executed, Hiding and transparency executed, Component properties confirmed, assembly image interpreted, compute Mass properties calculation, interference detection checking executed, value of dimension changed, physical simulation
105
Work Activities Related Knowledge Related Skills Attitude/Safety/
Environmental
Training Hours
Delivery Mode
Assessment Criteria
executed, exploded assemblies executed, explode line sketched, animating explode view executed,
1.5. CADD 3D Assembly Drawing Detail prepared, drawing detail listed, information accuracy confirmed, multi view orientation executed, balloon displayed, bill of material provided, font/lettering size selected, bill of material information completed, scale drawing produced, detail drawing produced and indicated cutting plate ( sectioning) produced, assembly symbol produced (eg.
i. Examine 3D Assembly Drawing instruction
ii. Obtain 3D CADD Assembly drawing requirement
iii. Prepare 3D Assembly drawing requirements
iv. Develop 3D Assembly drawing v. Prepare CADD 3D Assembly Drawing Detail vi. Carry out CADD 3D Industrial Automation drawing submission vii. Update Industrial Automation drawing log
book.
Attitude:
i. Detail in examining 3D Assembly Drawing instruction
106
Work Activities Related Knowledge Related Skills Attitude/Safety/
Environmental
Training Hours
Delivery Mode
Assessment Criteria
ii. Objective focused in obtaining 3D CADD Assembly drawing requirements
iii. Thorough in preparing 3D Assembly drawing requirements
iv. Objective focused in developing 3D Assembly drawing v. Thorough in preparing CADD 3D Assembly Drawing Detail vi. Confidence in carry out CADD 3D Industrial Automation drawing submission
Safety:
i. Ensure data safety.
ii. Ensure safe work methodology.
iii. Ensure electrical safety on all electrically powered equipment.
welding, GD&T and etc), detail spelling confirmed, Industrial Automation drawing detail confirmed, detail spelling and font consistencies confirmed.
CADD 3D Industrial Automation drawing submission executed, assembly drawing final checking executed, assembly drawing detail accuracy confirmed, drawing submission check list attached, drawing Folded/rolled, Industrial Automation drawing log book updated.
107
Work Activities Related Knowledge Related Skills Attitude/Safety/
Environmental
Training Hours
Delivery Mode
Assessment Criteria
iv. Enforce safety & health rules and regulations
v. Ensure safe working condition.
vi. Promote good safety & health practice at workplace.
Environment:
i. Ensure energy saver office equipments.
ii. Reduce energy wastage.
iii. Practice paperless office.
Prepare CAD operation report.
i. CAD application
performance report concept & requirements.
ii. CAD operation report planning
Operational Critical area identification.
Report parameters.
Organizational requirements.
iii. CAD operation report implementation.
CAD application performance report concept & requirements interpreted.
CAD operation report planning executed so that CAD operational critical area and report parameters ascertained, organizational
108
Work Activities Related Knowledge Related Skills Attitude/Safety/
Environmental
Training Hours
Delivery Mode
Assessment Criteria
Report format
Report subjects
Report contents.
Report generation. iv. CAD operation report
implementation evaluation v. CAD operation report
feedback.
requirements listed.
CAD operation report drafted so that CADD reporting format used, report subjects outlined, report contents printed and CADD operation report produced.
CAD operation report implementation graded.
CAD operation report feedback interpreted.
i. Examine CAD application performance report concept & requirements.
ii. Plan CAD operation report
iii. Perform CAD operation report
iv. Evaluate CAD operation report implementation.
v. Obtain CAD operation report feedback.
Attitude:
i. Thorough in examining CAD application
109
Work Activities Related Knowledge Related Skills Attitude/Safety/
Environmental
Training Hours
Delivery Mode
Assessment Criteria
performance report concept & requirements.
ii. Objective focused in Plan CAD operation report
iii. Factual in preparing CAD operation report
iv. Factual in evaluating CAD operation report implementation.
v. Diplomacy in obtaining CAD operation report feedback.
Safety:
i. Ensure data safety.
ii. Ensure safe work methodology.
iii. Ensure electrical safety on all electrically powered equipment.
iv. Enforce safety & health rules and regulations
110
Work Activities Related Knowledge Related Skills Attitude/Safety/
Environmental
Training Hours
Delivery Mode
Assessment Criteria
v. Ensure safe working condition.
vi. Promote good safety & health practice at workplace.
Environment:
i. Ensure energy saver office equipments.
ii. Reduce energy wastage.
iii. Practice paperless office.
Employability Skills
Core Abilities Social Skills
01.01 Identify and gather information 01.02 Document information, procedures or processes 01.03 Utilize basic IT applications 01.04 Analyse information 01.05 Utilize the Internet to locate and gather information 01.06 Utilize word processor to process information 02.01 Interpret and follow manuals, instructions and SOP’s
1. Communication skills 2. Conceptual skills 3. Interpersonal skills 4. Learning skills 5. Leadership skills 6. Multitasking and prioritizing 7. Self-discipline 8. Teamwork
111
02.02 Follow telephone/ telecommunication procedures 02.03 Communicate clearly 02.04 Prepare brief reports and checklists using standard forms 02.05 Read/interpret flowcharts and pictorial information 02.06 Write memos and letters 02.07 Utilize Local Area Network (LAN)/Intranet to exchange information 02.08 Prepare pictorial and graphic information 03.01 Apply cultural requirements to the workplace 03.02 Demonstrate integrity and apply ethical practices 03.03 Accept responsibility for own work and work area 03.04 Seek and act constructively upon feedback about performance 03.05 Demonstrate safety skills 03.06 Respond appropriately to people and situations 03.07 Resolve interpersonal conflicts 03.08 Develop and maintain a cooperation within work group 04.01 Organize own work activities 04.02 Set and revise own objectives and goals 04.03 Organize and maintain own workplace 04.04 Apply problem solving strategies 04.05 Demonstrate initiative and flexibility 06.01 Understand systems 06.02 Comply with and follow chain of command 06.03 Identify and highlight problems 06.04 Adapt competencies to new situations/systems 06.05 Analyse technical systems 06.06 Monitor and correct performance of systems
Tools, Equipment and Materials (TEM)
Items Ratio (TEM: Trainee)
1. LCD Projector or other type of projector with white screen. 2. Computer Set with words processing & CADD application
1:25 1:25
112
software. 3. Printer or Plotter 4. Stationery
1:25 As required.
REFERENCES
1. Thomas French , Jay Helsel, Glencoe/McGraw-Hill; 13 edition (February 13, 2002), Mechanical Drawing: Board and CAD
Techniques, Student Edition, ISBN: 978-0078251009 2. Terry Wohlers McGraw Hill Professional 2012 Applying AutoCAD® 2013, ISBN: 9780073375519 3. Randy Shih , SDC Publications; Pap/Cdr edition (April 27, 2012), AutoCAD 2013 Tutorial - First Level: 2D Fundamentals, ISBN:
978-1585037162 4. Shawna Lockhart , SDC Publications (May 23, 2012), Tutorial Guide to AutoCAD 2013, ISBN: 978-1585037216 5. Elise Moss, SDC Publications (April 13, 2012), Autodesk AutoCAD 2013 Fundamentals, ISBN: 978-1585037148 6. Terence M. Shumaker , David A. Madsen , David P. Madsen, Goodheart-Willcox Co; 18 Ed. 2010 AutoCAD and Its Applications
Basics 2011, ISBN:978-1605253282 7. Novak, Henry C. Spencer, John T. Dygdon, McGraw-Hill/Glencoe; 6 Ed. 1994 Basic Technical Drawing: Student Text 8. Michael Netzley & Graig Snow, Prentice Hall 1st. Ed. 2001, Guide to Report Writing ISBN 978-0130417718 9. John Bowden, Writing a Report- How to Accurate in preparing, Write & Present Really Effective, ISBN 978-1845284701
113
CURRICULUM OF COMPETENCY UNIT (CoCU)
Sub Sector INDUSTRIAL AUTOMATION & MECHATRONIC
Job Area INDUSTRIAL AUTOMATION ENGINEERING
NOSS Title INDUSTRIAL AUTOMATION ENGINEERING SUPPORT SERVICE
Competency Unit Title INDUSTRIAL AUTOMATION FABRICATION AND SUB-ASSEMBLING
Learning Outcome The person who is competent in this CU shall be able to perform industrial automation fabrication process until the industrial automation systems fabrication components, assemblies and sub-assemblies are formed and ready for installation as specified by the organization. Fabrication works should be implemented neatly, accurately, functional and safe according to specifications with cost optimization, low scrap value, optimum labor utilization and within a given time frame. The administrator’s performance shall be measured based on the said requirements that are translated into the prescribed objectives and organization requirements. Upon completion of this competency unit, trainees will be able to:
Examine Industrial Automation Fabrication instruction
Prepare Industrial Automation Fabrication & Sub Assembling requirements
Perform Industrial Automation Fabrication & Sub Assembling implementation
Perform Industrial Automation Fabrication & Sub Assembling Testing
Perform Industrial Automation Fabrication & Sub Assembling product packaging
Perform Industrial Automation Fabrication & Sub Assembling product delivery preparation.
Competency Unit ID MC-XXX-3 Level 2 Training Duration 90Hours Credit Hours 9
Work Activities Related Knowledge Related Skills Attitude/Safety/
Environmental
Training Hours
Delivery Mode
Assessment Criteria
1. Examine
i. Industrial Automation
Lecture
114
Work Activities Related Knowledge Related Skills Attitude/Safety/
Environmental
Training Hours
Delivery Mode
Assessment Criteria
Industrial Automation Fabrication instruction
Fabrication Official instruction source,
ii. Industrial Automation Fabrication Official Instruction authority
iii. Instruction validity requirement
iv. Industrial Automation Fabrication Instruction content
v. Industrial fabrication instruction requirement
Instruction source confirmed.
Instruction authority confirmed.
instruction validity
Instruction content confirmed.
Industrial automation fabrication instruction acceptance signed.
Industrial automation fabrication instruction record produced.
i. Check Instruction source
ii. Check instruction authority
iii. Check instruction validity
iv. Check instruction content
v. Accept industrial automation fabrication instruction
vi. Record industrial automation fabrication instruction
Practical
Attitude:
115
Work Activities Related Knowledge Related Skills Attitude/Safety/
Environmental
Training Hours
Delivery Mode
Assessment Criteria
i. Detail in checking Instruction source
ii. Detail in checking instruction authority
iii. Detail in checking instruction validity
iv. Detail in checking instruction content
v. Confidence in accepting industrial automation fabrication instruction
vi. Accurate in recording industrial automation fabrication instruction
Environment:
i. Ensure energy saver office equipments.
ii. Reduce energy wastage.
iii. Practice paperless office.
2. Prepare
Industrial Automation Fabrication & Sub Assembling
i. Industrial Automation
Fabrication & Sub Assembling drawing
ii. Industrial Automation Fabrication & Sub Assembling specification
Lecture
Industrial Automation Fabrication & Sub Assembling
116
Work Activities Related Knowledge Related Skills Attitude/Safety/
Environmental
Training Hours
Delivery Mode
Assessment Criteria
requirements iii. Industrial Automation Fabrication & Sub Assembling parameters
iv. Industrial Automation Fabrication & Sub Assembling time frames
v. Industrial Automation Fabrication & Sub Assembling tools
vi. Industrial Automation Fabrication & Sub Assembling equipment
vii. Industrial Automation Fabrication & Sub Assembling material
viii. Industrial Automation Fabrication & Sub Assembling standard operating procedures
drawing and Industrial Automation Fabrication & Sub Assembling specification displayed..
Industrial Automation Fabrication & Sub Assembling parameters and Industrial Automation Fabrication & Sub Assembling time frames ascertained.
Industrial Automation Fabrication & Sub Assembling tools, equipment and material, and
i. Obtain Industrial Automation Fabrication & Sub Assembling drawing
ii. Obtain Industrial Automation Fabrication & Sub Assembling specification
iii. Determine Industrial Automation
Practical
117
Work Activities Related Knowledge Related Skills Attitude/Safety/
Environmental
Training Hours
Delivery Mode
Assessment Criteria
Fabrication & Sub Assembling parameters
iv. Determine Industrial Automation Fabrication & Sub Assembling time frames
v. Obtain Industrial Automation Fabrication & Sub Assembling tools, equipment, and material
vi. Obtain Industrial Automation Fabrication & Sub Assembling standard operating procedures
Industrial Automation Fabrication & Sub Assembling standard operating procedures displayed.
Attitude: i. Resourceful in
obtaining Industrial Automation Fabrication & Sub Assembling drawing
ii. Resourceful in obtaining Industrial Automation Fabrication & Sub Assembling
118
Work Activities Related Knowledge Related Skills Attitude/Safety/
Environmental
Training Hours
Delivery Mode
Assessment Criteria
specification iii. Detail in determining
Industrial Automation Fabrication & Sub Assembling parameters
iv. Reasonable in determining Industrial Automation Fabrication & Sub Assembling time frames
v. Resourceful in obtaining Industrial Automation Fabrication & Sub Assembling tools, equipment, and material
vi. Resourceful in obtaining Industrial Automation Fabrication & Sub Assembling standard operating procedures
Safety:
i. Ensure data safety. ii. Ensure safe work
methodology. iii. Ensure electrical safety
on all electrically powered equipment.
119
Work Activities Related Knowledge Related Skills Attitude/Safety/
Environmental
Training Hours
Delivery Mode
Assessment Criteria
iv. Enforce safety & health rules and regulations
v. Ensure safe working condition.
vi. Promote good safety & health practice at workplace.
Environment:
i. Ensure energy saver office equipments.
ii. Reduce energy wastage.
iii. Practice paperless office.
3. Perform
Industrial Automation Fabrication & Sub Assembling implementation
i. Industrial Automation
Fabrication & Sub Assembling drawings inspection
ii. Plan drawing detail. iii. Elevation drawing detail. iv. Sectional drawing detail. v. Assembly drawing detail. vi. Bill of Materials
requirement vii. Schematic plan
requirement viii. Component layout plan
Lecture
Industrial Automation Fabrication & Sub Assembling drawings interpreted, plan drawing, elevation drawing, sectional drawing, assembly
120
Work Activities Related Knowledge Related Skills Attitude/Safety/
Environmental
Training Hours
Delivery Mode
Assessment Criteria
requirement ix. Industrial Automation
Fabrication & Sub Assembling specifications standard
x. Cutting process technique
xi. Machining process technique
xii. Joining process technique
xiii. Moulding process arrangement
xiv. Wiring process xv. Printed circuit board
concept & assembling xvi. Component sub
assembling process
drawing, drawing detail, Bill of Materials, Schematic plan, component layout plan understood.
Industrial Automation Fabrication & Sub Assembling specifications interpreted.
Cutting process, plasma Cutting, bend sawing, disc Cutting, laser cutting (Advance tech) and water Jet cutting (Advance Tech) executed.
Machining
i. Examine Industrial Automation Fabrication & Sub Assembling drawings
ii. Examine Industrial Automation Fabrication & Sub Assembling specifications
iii. Carry out cutting process
Practical
121
Work Activities Related Knowledge Related Skills Attitude/Safety/
Environmental
Training Hours
Delivery Mode
Assessment Criteria
iv. Carry out machining process
v. Carry out joining process
vi. Carry out moulding process arrangement
vii. Carry out wiring process
viii. Carry out printed circuit board assembling
ix. Carry out component sub assembling
process, joining process, Sheet metal joining, Soldering, Welding, Bolt & Nut joining, Riveting and Brazing executed.
Moulding process arrangement, Sand moulding, Plastics moulding, Injection moulding, Gravity moulding, High pressure moulding and Low pressure moulding arrangement executed.
Wiring process,
Attitude:
i. Detail in examining Industrial Automation Fabrication & Sub Assembling drawings
ii. Detail in examining Industrial Automation Fabrication & Sub Assembling specifications
iii. Objective focused in carrying out cutting process
iv. Objective focused in carrying out machining
122
Work Activities Related Knowledge Related Skills Attitude/Safety/
Environmental
Training Hours
Delivery Mode
Assessment Criteria
process v. Objective focused in
carrying out joining process
vi. Objective focused in carrying out moulding process arrangement
vii. Objective focused in carrying out wiring process
viii. Objective focused in carrying out printed circuit board assembling
ix. Objective focused in carrying out component sub assembling
Safety:
i. Ensure data safety. ii. Ensure safe work
methodology. iii. Ensure electrical safety
on all electrically powered equipment.
iv. Enforce safety & health rules and regulations
v. Ensure safe working
Soldering connection, Crimping, Interconnecting cables, Cable termination, Wiring, Cable tagging and Grounding executed.
Printed circuit board assembling, component Soldering, connector terminating and copper route printing executed.
Component sub assembling executed.
123
Work Activities Related Knowledge Related Skills Attitude/Safety/
Environmental
Training Hours
Delivery Mode
Assessment Criteria
condition. vi. Promote good safety &
health practice at workplace.
Environment:
i. Ensure energy saver office equipments.
ii. Reduce energy wastage.
iii. Practice paperless office.
4. Perform
Industrial Automation Fabrication & Sub Assembling Testing
i. Component wiring test
process ii. Printed circuit board
assembling test procedure iii. Component sub
assembling test process iv. Joining test procedure v. Industrial Automation
Fabrication & Sub Assembling Testing record technique
vi. Industrial Automation Fabrication & Sub Assembling Testing record form requirement
vii. Industrial Automation Fabrication & Sub Assembling Testing result
Component wiring test, Continuity testing, Harness test / cable test, Pull test, Dielectric strength test executed.
printed circuit board assembling test, Continuity
124
Work Activities Related Knowledge Related Skills Attitude/Safety/
Environmental
Training Hours
Delivery Mode
Assessment Criteria
requirement viii. Industrial Automation
Fabrication & Sub Assembling Testing remarks requirement
ix. Industrial Automation Fabrication & Sub Assembling product inspection process
test, Open loop test, Power-off test, In-circuit test and Functional test executed.
component sub assembling test, joining test, Load test, Push test, Pull test, Bend test and Leak test executed.
Industrial Automation Fabrication & Sub Assembling Testing record produced, Industrial Automation Fabrication
i. Conduct component
wiring test ii. Conduct printed
circuit board assembling test
iii. Conduct component sub assembling test
iv. Conduct joining test v. Prepare Industrial
Automation Fabrication & Sub Assembling Testing record
vi. Utilize prescribed Industrial Automation Fabrication & Sub Assembling Testing record form
vii. Determine Industrial Automation
125
Work Activities Related Knowledge Related Skills Attitude/Safety/
Environmental
Training Hours
Delivery Mode
Assessment Criteria
Fabrication & Sub Assembling Testing result
viii. Prescribe Industrial Automation Fabrication & Sub Assembling Testing remarks
ix. Carry out Industrial x. xi. xii. xiii. xiv. xv. xvi. xvii. xviii. xix. xx. Automation
Fabrication & Sub Assembling product inspection
xxi. Update Industrial Automation Fabrication & Sub Assembling product inspection logbook.
& Sub Assembling prescribed Testing record form utilized, Industrial Automation Fabrication & Sub Assembling Testing result ascertained, Industrial Automation Fabrication & Sub Assembling Testing remarks interpreted.
Industrial Automation Fabrication & Sub Assembling product inspection executed.
Industrial
126
Work Activities Related Knowledge Related Skills Attitude/Safety/
Environmental
Training Hours
Delivery Mode
Assessment Criteria
Automation Fabrication & Sub Assembling product inspection logbook record produced.
Attitude:
i. Objective focused in conducting component wiring test
ii. Objective focused in conducting printed circuit board assembling test
iii. Objective focused in conducting component sub assembling test
iv. Objective focused in conducting joining test
v. Accurate in preparing Industrial Automation Fabrication & Sub Assembling Testing record
vi. Specific in utilizing prescribed Industrial Automation Fabrication & Sub Assembling Testing record form
vii. Precise in prescribing Industrial Automation
127
Work Activities Related Knowledge Related Skills Attitude/Safety/
Environmental
Training Hours
Delivery Mode
Assessment Criteria
Fabrication & Sub Assembling Testing result
viii. Precise in prescribing Industrial Automation Fabrication & Sub Assembling Testing remarks
ix. Detail in carrying out Industrial Automation Fabrication & Sub Assembling product inspection
x. Accurate in updating Industrial Automation Fabrication & Sub Assembling product inspection logbook.
Safety:
i. Ensure data safety. ii. Ensure safe work
methodology. iii. Ensure electrical safety
on all electrically powered equipment.
iv. Enforce safety & health rules and regulations
v. Ensure safe working condition.
128
Work Activities Related Knowledge Related Skills Attitude/Safety/
Environmental
Training Hours
Delivery Mode
Assessment Criteria
vi. Promote good safety & health practice at workplace.
Environment:
i. Ensure energy saver office equipments.
ii. Reduce energy wastage.
iii. Practice paperless office.
5. Perform
Industrial Automation Fabrication & Sub Assembling product packaging
i. Industrial Automation
Fabrication & Sub Assembling product packaging official requirement
ii. Packaging procedure iii. Packaging technique iv. Packaging safety source v. Packaging material source vi. Product packaging
identification system process
vii. Industrial Automation Fabrication & Sub Assembling product pre packaging inspection procedure
viii. Industrial Automation
Industrial Automation Fabrication & Sub Assembling product packaging requirement listed, Packaging procedure, packaging technique, packaging safety, packaging material, product
129
Work Activities Related Knowledge Related Skills Attitude/Safety/
Environmental
Training Hours
Delivery Mode
Assessment Criteria
Fabrication & Sub Assembling packing process
ix. Industrial Automation Fabrication & Sub Assembling Product Labelling process
x. Industrial Automation Fabrication & Sub Assembling product packaging documentation method
xi. Industrial Automation Fabrication & Sub Assembling packing
packaging identification system listed.
Industrial Automation Fabrication & Sub Assembling product pre packaging inspection, Industrial Automation Fabrication & Sub Assembling packing process, and Industrial Automation Fabrication & Sub Assembling Product Labelling executed.
Industrial Automation Fabrication & Sub
i. Prepare Industrial Automation Fabrication & Sub Assembling product packaging requirement
ii. Obtain Packaging procedure
iii. Obtain packaging technique
iv. Obtain packaging safety
v. Obtain packaging material
vi. Obtain product
130
Work Activities Related Knowledge Related Skills Attitude/Safety/
Environmental
Training Hours
Delivery Mode
Assessment Criteria
packaging identification system
vii. Carry out Industrial Automation Fabrication & Sub Assembling product pre packaging inspection
viii. Carry out Industrial Automation Fabrication & Sub Assembling packing process
ix. Carry out Industrial Automation Fabrication & Sub Assembling Product Labelling
x. Record Industrial Automation Fabrication & Sub Assembling product packaging
Assembling product packaging record produced.
Attitude: i. Detail in preparing
Industrial Automation Fabrication & Sub Assembling product packaging requirement
ii. Resourceful in
131
Work Activities Related Knowledge Related Skills Attitude/Safety/
Environmental
Training Hours
Delivery Mode
Assessment Criteria
obtaining Packaging procedure
iii. Resourceful in obtaining packaging technique
iv. Resourceful in obtaining packaging safety
v. Resourceful in obtaining packaging material
vi. Resourceful in obtaining product packaging identification system
vii. Detail in carrying out Industrial Automation Fabrication & Sub Assembling product pre packaging inspection
viii. Objective focused in carrying out Industrial Automation Fabrication & Sub Assembling packing process
ix. Accurate in carrying out Industrial Automation Fabrication & Sub Assembling Product Labelling
x. Accurate in recording
132
Work Activities Related Knowledge Related Skills Attitude/Safety/
Environmental
Training Hours
Delivery Mode
Assessment Criteria
Industrial Automation Fabrication & Sub Assembling product packaging
Safety:
i. Ensure data safety. ii. Ensure safe work
methodology. iii. Ensure electrical safety
on all electrically powered equipment.
iv. Enforce safety & health rules and regulations
v. Ensure safe working condition.
vi. Promote good safety & health practice at workplace.
Environment:
i. Ensure energy saver office equipments.
ii. Reduce energy wastage.
iii. Practice paperless office.
133
Work Activities Related Knowledge Related Skills Attitude/Safety/
Environmental
Training Hours
Delivery Mode
Assessment Criteria
6. Perform Industrial Automation Fabrication & Sub Assembling product delivery
preparation.
i. Industrial Automation Syst.
Fabrication product sub-assembly listing.
ii. Industrial Automation Syst. Fabrication product tagging.
iii. Industrial Automation Syst. Fabrication product documentation
iv. Industrial Automation Syst. Fabrication & sub-assembly product documentation and drawing.
v. viii. Industrial Automation Syst. Fabrication & sub-assembly record.
Lecture Industrial Automation Syst. Fabrication product sub-assembly listing executed.
Industrial Automation Syst. Fabrication product tagging executed.
Industrial Automation Syst. Fabrication product documentation executed.
Industrial Automation Syst. Fabrication & sub-assembly product documentation and
i. Prepare Industrial Automation Syst. Fabrication product sub-assembly listing.
ii. Prepare Industrial Automation Syst. Fabrication product tagging.
iii. Prepare Industrial Automation Syst. Fabrication product documentation
iv. Attach Industrial
Practical
134
Work Activities Related Knowledge Related Skills Attitude/Safety/
Environmental
Training Hours
Delivery Mode
Assessment Criteria
Automation Syst. Fabrication& sub-assembly product documentation and drawing.
viii. Update Industrial Automation Syst. Fabrication& sub-assembly log book.
drawing produced.
Industrial Automation Syst. Fabrication& sub-assembly log book record produced.
Attitude:
i. Detail in preparing Industrial Automation Syst. Fabrication product sub-assembly listing.
ii. Accurate in preparing Industrial Automation Syst. Fabrication product tagging.
iii. Detail in preparing Industrial Automation Syst. Fabrication product documentation
iv. Accurate in attaching Industrial Automation Syst. Fabrication& sub-assembly product documentation and drawing.
viii. Accurate in updating
135
Work Activities Related Knowledge Related Skills Attitude/Safety/
Environmental
Training Hours
Delivery Mode
Assessment Criteria
Industrial Automation Syst. Fabrication& sub-assembly log book.
Safety:
i. Ensure data safety. ii. Ensure safe work
methodology. iii. Ensure electrical safety
on all electrically powered equipment.
iv. Enforce safety & health rules and regulations
v. Ensure safe working condition.
vi. Promote good safety & health practice at workplace.
Environment:
i. Ensure energy saver office equipments.
ii. Reduce energy wastage.
iii. Practice paperless office.
136
Employability Skills
Core Abilities Social Skills
01.01 Identify and gather information 01.02 Document information, procedures or processes 01.03 Utilize basic IT applications 01.04 Analyse information 01.05 Utilize the Internet to locate and gather information 01.06 Utilize word processor to process information 02.01 Interpret and follow manuals, instructions and SOP’s 02.02 Follow telephone/ telecommunication procedures 02.03 Communicate clearly 02.04 Prepare brief reports and checklists using standard forms 02.05 Read/interpret flowcharts and pictorial information 02.06 Write memos and letters 02.07 Utilize Local Area Network (LAN)/Intranet to exchange information 02.08 Prepare pictorial and graphic information 03.01 Apply cultural requirements to the workplace 03.02 Demonstrate integrity and apply ethical practices 03.03 Accept responsibility for own work and work area 03.04 Seek and act constructively upon feedback about performance 03.05 Demonstrate safety skills 03.06 Respond appropriately to people and situations 03.07 Resolve interpersonal conflicts 03.08 Develop and maintain a cooperation within work group 04.01 Organize own work activities 04.02 Set and revise own objectives and goals 04.03 Organize and maintain own workplace 04.04 Apply problem solving strategies 04.05 Demonstrate initiative and flexibility 06.01 Understand systems
1. Communication skills 2. Conceptual skills 3. Interpersonal skills 4. Learning skills 5. Leadership skills 6. Multitasking and prioritizing 7. Self-discipline 8. Teamwork
137
06.02 Comply with and follow chain of command 06.03 Identify and highlight problems 06.04 Adapt competencies to new situations/systems 06.05 Analyse technical systems 06.06 Monitor and correct performance of systems
Tools, Equipment and Materials (TEM)
Items Ratio (TEM: Trainee)
1. LCD Projector or other type of projector with white screen. 2. Computer Set with words processing & Graphic software.
1:25 1:1
REFERENCES
1. Denise Robitaille, Paton Press LLC, 2005, Document Control: A simple Guide To Managing Documentation, ISBN: 1-932828-03-6
2. Mike Jones, 2012, First Steps in Documentation for the Small Business - Book 4 Business Operations, ISBN: 9781476270340 3. Jeffrey Robert Stewart, Glencoe, 1995 Professional Records Management, ISBN: 9780028010281 4. Michael Netzley & Graig Snow, Prentice Hall 1st. Ed. 2001, Guide to Report Writing ISBN 978-0130417718 5. John Bowden, Writing a Report- How to Accurate in preparing, Write & Present Really Effective, ISBN 978-1845284701
138
CURRICULUM OF COMPETENCY UNIT (CoCU)
Sub Sector INDUSTRIAL AUTOMATION & MECHATRONIC
Job Area INDUSTRIAL AUTOMATION ENGINEERING
NOSS Title INDUSTRIAL AUTOMATION ENGINEERING SUPPORT SERVICE
Competency Unit Title INDUSTRIAL AUTOMATION INSTALLATION SUPPORT SERVICE
Learning Outcome The person who is competent in this CU shall be able to perform industrial automation installation process using allocated resources that are most economical according to the specified methodology and techniques as instructed in order to achieve the function objective in the safest atmosphere and cost optimization according to set schedule. Customer acceptance to the industrial automation installation that is perfect, functional and on time according to the agreed specification and organization requirements is the best outcome. Upon completion of this competency unit, trainees will be able to
Examine Industrial Automation System installation Instruction
Prepare Industrial Automation System installation Requirements
Perform Industrial Automation System installation implementation
Perform Industrial Automation System trial run
Perform Industrial Automation System trial run record submission
Competency Unit ID MC-XXX-4 Level 2 Training Duration 90 Hours Credit Hours 9
Work Activities Related Knowledge Related Skills Attitude/Safety/
Environmental
Training Hours
Delivery Mode
Assessment Criteria
1. Examine
Industrial Automation
i. Official instruction
source, ii. Official Instruction
Lecture Source of
instruction, instruction
139
Work Activities Related Knowledge Related Skills Attitude/Safety/
Environmental
Training Hours
Delivery Mode
Assessment Criteria
System installation Instruction
authority iii. Instruction validity
requirement iv. Instruction content
confirmation v. Industrial Automation
System installation instruction requirement
authority, instruction validity, and instruction content confirmed.
Industrial Automation System installation instruction acceptance signed.
Industrial Automation System installation instruction record produced.
i. Check source of
instruction ii. Check instruction
authority iii. Check instruction
validity iv. Check instruction
content v. Accept Industrial
Automation System installation instruction
vi. Record Industrial Automation System installation instruction
Practical
Attitude:
i. Detail in checking source of instruction
ii. Detail in checking instruction authority
iii. Detail in checking
140
Work Activities Related Knowledge Related Skills Attitude/Safety/
Environmental
Training Hours
Delivery Mode
Assessment Criteria
instruction validity iv. Detail in checking
instruction content v. Confidence in
accepting Industrial Automation System installation instruction
vi. Accurate in recording Industrial Automation System installation instruction
Safety:
i. Ensure data safety. ii. Ensure safe work
methodology. iii. Ensure electrical safety
on all electrically powered equipment.
iv. Enforce safety & health rules and regulations
v. Ensure safe working condition.
vi. Promote good safety & health practice at workplace.
Environment:
i. Ensure energy saver office equipments.
141
Work Activities Related Knowledge Related Skills Attitude/Safety/
Environmental
Training Hours
Delivery Mode
Assessment Criteria
ii. Reduce energy wastage.
iii. Practice paperless office.
2. Prepare
Industrial Automation System installation Requirements
i. Industrial Automation
System installation objective
ii. Industrial Automation System installation specification acquiring process
iii. Industrial Automation System installation Standard operation procedure
iv. prescribed installation plan requirement
v. Official Industrial Automation System installation checklist
vi. Industrial Automation System installation tools, equipments and machineries resource.
vii. Industrial Automation System installation record systems resource.
viii. Corrective Action Requisition Procedure resource.
Lecture Industrial
Automation System installation objective achieved.
Industrial Automation System installation specification produced, and Industrial Automation System installation Standard operation procedure produced.
Prescribed installation plan interpreted.
Industrial
142
Work Activities Related Knowledge Related Skills Attitude/Safety/
Environmental
Training Hours
Delivery Mode
Assessment Criteria
ix. Corrective Installation Record Systems resource.
Automation System installation checklist displayed, Industrial Automation System installation tools, equipments and machineries, Industrial Automation System installation record systems, Corrective Action Requisition Procedure, and Corrective Installation Record Systems displayed.
i. Observe Industrial
Automation System installation objective.
ii. Obtain Industrial Automation System installation specification
iii. Obtain Industrial Automation System installation Standard operation procedure
iv. Examine prescribed installation plan
v. Obtain Industrial Automation System installation checklist
vi. Obtain Industrial Automation System installation tools, equipments and machineries
vii. Obtain Industrial Automation System installation record systems.
viii. Obtain Corrective Action Requisition
Practical
143
Work Activities Related Knowledge Related Skills Attitude/Safety/
Environmental
Training Hours
Delivery Mode
Assessment Criteria
Procedure.
ix. Obtain Corrective Installation Record Systems.
Attitude:
i. Focus in observing Industrial Automation System installation objective.
ii. Resourceful in obtaining Industrial Automation System installation specification
iii. Resourceful in obtaining Industrial Automation System installation Standard operation procedure
iv. Thorough in examining prescribed installation plan
v. Resourceful in obtaining Industrial Automation System installation checklist
vi. Resourceful in obtaining Industrial Automation System installation tools, equipments and
144
Work Activities Related Knowledge Related Skills Attitude/Safety/
Environmental
Training Hours
Delivery Mode
Assessment Criteria
machineries vii. Resourceful in
obtaining Industrial Automation System installation record systems.
viii. Resourceful in obtaining Corrective Action Requisition Procedure.
ix. Resourceful in obtaining Corrective Installation Record Systems.
Safety:
i. Ensure data safety. ii. Ensure safe work
methodology. iii. Ensure electrical safety
on all electrically powered equipment.
iv. Enforce safety & health rules and regulations
v. Ensure safe working condition.
vi. Promote good safety & health practice at workplace.
145
Work Activities Related Knowledge Related Skills Attitude/Safety/
Environmental
Training Hours
Delivery Mode
Assessment Criteria
Environment:
i. Ensure energy saver office equipments.
ii. Reduce energy wastage.
iii. Practice paperless office.
3. Perform Industrial Automation System installation implementation
i. Industrial Automation System installation specification inspection list.
ii. Installation Program specification requirement
iii. Certified Corrective Installation Systems specification
iv. Installation standard operating procedure
v. installation implementation technique application
vi. Certified Mechanical part installation program
vii. Part Assembling technique
viii. Part Greasing technique ix. Part Lubricating technique x. Part Joining technique xi. Part Aligning technique xii. Part Levelling technique xiii. Part Gap setting
Industrial Automation System installation specification, Installation on program specification, and corrective Installation Systems specification interpreted.
Installation standard operating procedure completed.
Installation implementation technique used.
146
Work Activities Related Knowledge Related Skills Attitude/Safety/
Environmental
Training Hours
Delivery Mode
Assessment Criteria
technique xiv. Part Limit setting
technique xv. Certified Electrical part
installation program xvi. Part Power Supply
Termination requirement xvii. Part Wiring method xviii. Part Insulating method xix. Part Calibration method xx. Part Terminal Connection
method xxi. Part Communication
connection method xxii. Certified Pneumatic /
hydraulic part installation Program
xxiii. Part air supply connection tubing requirement
xxiv. Part Connect power pack supply requirement
xxv. Part Cylinder stroke adjustment requirement
xxvi. Part Limit switch alignment requirement Industrial Automation System installation implementation record documentation
Mechanical part installation program, part Assembling, part Greasing, part Lubricating, part Joining, part Aligning, part Levelling, part Gap setting, part Limit setting executed.
Electrical part installation program, part Power Supply Termination, part Wiring, part Insulating , part Grounding, part
i. Examine Industrial
Automation System installation
147
Work Activities Related Knowledge Related Skills Attitude/Safety/
Environmental
Training Hours
Delivery Mode
Assessment Criteria
specification
Installation Program specification
Corrective Installation Systems specification.
ii. Follow installation standard operating procedure.
iii. Apply installation implementation techniques.
iv. Carry out mechanical part installation program
v. Carry out electrical part installation program
vi. Carry out pneumatic / hydraulic part installation Program
vii. Record Industrial Automation System installation implementation
Calibration, part Terminal Connection, and part Communication Connection executed.
Pneumatic / hydraulic part installation Program, part air supply connection tubing, part Connect power pack supply, part Cylinder stroke adjustment, and part Limit switch alignment executed.
Industrial Automation System installation
Attitude: i. Thorough in examining
Industrial Automation
148
Work Activities Related Knowledge Related Skills Attitude/Safety/
Environmental
Training Hours
Delivery Mode
Assessment Criteria
System installation specification
ii. Faithful in following installation standard operating procedure.
iii. Creative in applying installation implementation technique.
iv. Objective focused in carrying out mechanical part installation program
v. Objective focused in carrying out electrical part installation program
vi. Objective focused in carrying out pneumatic and or hydraulic part installation Program
vii. Accurate in recording Industrial Automation System installation implementation
Safety:
i. Ensure data safety. ii. Ensure safe work
methodology. iii. Ensure electrical
implementation record
produced.
149
Work Activities Related Knowledge Related Skills Attitude/Safety/
Environmental
Training Hours
Delivery Mode
Assessment Criteria
safety on all electrically powered equipment.
iv. Enforce safety & health rules and regulations
v. Ensure safe working condition.
vi. Promote good safety & health practice at workplace.
Environment:
i. Ensure energy saver office equipments.
ii. Reduce energy wastage.
iii. Practice paperless office.
4. Perform Industrial Automation System trial run
i. Industrial Automation System trial run official instruction
ii. Industrial Automation System trial run requirement list
iii. Industrial Automation System trial run procedure
iv. Industrial Automation System trial run tools, equipment and machineries requirement
Industrial Automation System trial run instruction, Industrial Automation System trial run requirement, Industrial
150
Work Activities Related Knowledge Related Skills Attitude/Safety/
Environmental
Training Hours
Delivery Mode
Assessment Criteria
v. Mechanical performance trial run specification
vi. Alignment requirement vii. Vibration level
requirement viii. Run out requirement ix. Back lash requirement x. Mechanical part motion
requirement xi. Electrical functionality trial
test procedure xii. Motor movement requisite xiii. Motor direction requisite xiv. Sensor functionality
requisite xv. Controller functionality
requisite xvi. Pneumatic and hydraulic
functionality test requisite xvii. Instrument functionality
test requisite xviii. Industrial Automation
System trial run requisite xix. Sequential specification xx. Functionality assessment
list xxi. Official Cycle time xxii. Safety system
functionality xxiii. Durability test method xxiv. Corrective Action Request
Order form.
Automation System trial run procedure, and Industrial Automation System trial run tools, equipment and machineries displayed.
Mechanical performance trial run executed, alignment, vibration level, run out, back lash and mechanical part Motion confirmed.
Electrical functionality trial test executed, motor movement,
151
Work Activities Related Knowledge Related Skills Attitude/Safety/
Environmental
Training Hours
Delivery Mode
Assessment Criteria
xxv. Corrective Action job sheet request instruction
xxvi. Corrective Action Request order process
xxvii. Corrective Action request feedback assessment
xxviii. Corrective Action Request Report documentation
xxix. Industrial Automation System trial run result compilation method
motor direction, sensor functionality and controller functionality confirmed.
Pneumatic and hydraulic functionality test, instrument functionality test and Industrial Automation System trial run executed, sequential, functionality worked, cycle time, safety system functionality confirmed, and durability test executed.
i. Obtain Industrial Automation System trial run instruction.
ii. Obtain Industrial Automation System trial run requirement
iii. Obtain Industrial Automation System trial run procedure
iv.Obtain Industrial Automation System trial run tools, equipment and machineries
v.Conduct mechanical performance trial run
vi.Conduct electrical functionality trial test
152
Work Activities Related Knowledge Related Skills Attitude/Safety/
Environmental
Training Hours
Delivery Mode
Assessment Criteria
vii. Conduct pneumatic
and hydraulic functionality test
viii. Conduct instrument functionality test
ix .Conduct Industrial Automation System trial run
x. Perform Corrective Action Request Order.
xi. Compile Industrial Automation System trial run result.
Corrective Action Request Order executed, Corrective Action Request job sheet recorded, Corrective Action Request order executed, Corrective Action Request feedback reported, Corrective Action Request Report answered.
Industrial Automation System trial run result listed.
Attitude:
i. Resourceful in obtaining Industrial Automation System trial run instruction
ii. Resourceful in obtaining Industrial Automation System trial run requirement
iii. Resourceful in obtaining Industrial Automation System trial run procedure
iv. Resourceful in obtaining Industrial Automation System
153
Work Activities Related Knowledge Related Skills Attitude/Safety/
Environmental
Training Hours
Delivery Mode
Assessment Criteria
trial run tools, equipment and machineries
v. Objective focused in conducting mechanical performance trial run
vi. Objective focused in conducting electrical functionality trial test
vii. Objective focused in conducting pneumatic and hydraulic functionality test
viii. Objective focused in conducting instrument functionality test
ix. Objective focused in conducting Industrial Automation System trial run
x. Objective focused in performing Corrective Action Request Order.
Safety:
i. Ensure data safety. ii. Ensure safe work
methodology. iii. Ensure electrical
safety on all electrically powered
154
Work Activities Related Knowledge Related Skills Attitude/Safety/
Environmental
Training Hours
Delivery Mode
Assessment Criteria
equipment. iv. Enforce safety &
health rules and regulations
v. Ensure safe working condition.
vi. Promote good safety & health practice at workplace.
Environment:
iv. Ensure energy saver office equipments.
v. Reduce energy wastage.
vi. Practice paperless office.
vii.
5. Perform Industrial Automation System trial run record submission
i. Industrial Automation System trial run record requirement
ii. Industrial Automation System trial run record form
iii. Industrial Automation System trial run result
Industrial Automation System trial run remarks
iv. Industrial Automation System trial run record
Industrial Automation System trial run record produced, Industrial Automation System trial run record form, Industrial Automation
155
Work Activities Related Knowledge Related Skills Attitude/Safety/
Environmental
Training Hours
Delivery Mode
Assessment Criteria
allocation System trial run result, Industrial Automation System trial run remarks interpreted.
Industrial Automation System trial run record produced
Industrial Automation System trial run record registered.
i. Prepare Industrial
Automation System trial run record
ii. Generate Industrial Automation System trial run record
iii. Submit Industrial Automation System trial run record
Attitude: ii. Timely in preparing
Industrial Automation System trial run record
ii. Accurate in generating Industrial Automation System trial run record
iii. Confidence in submitting Industrial Automation System trial run record
Safety:
i. Ensure data safety. ii. Ensure safe work
methodology. iii. Ensure electrical
safety on all electrically powered
156
Work Activities Related Knowledge Related Skills Attitude/Safety/
Environmental
Training Hours
Delivery Mode
Assessment Criteria
equipment. iv. Enforce safety &
health rules and regulations
v. Ensure safe working condition.
vi. Promote good safety & health practice at workplace.
Environment:
viii. Ensure energy saver office equipments.
ix. Reduce energy wastage.
x. Practice paperless office.
Employability Skills
Core Abilities Social Skills
01.01 Identify and gather information 01.02 Document information, procedures or processes 01.03 Utilize basic IT applications 01.04 Analyse information 01.05 Utilize the Internet to locate and gather information 01.06 Utilize word processor to process information 02.01 Interpret and follow manuals, instructions and SOP’s
1. Communication skills 2. Conceptual skills 3. Interpersonal skills 4. Learning skills 5. Leadership skills 6. Multitasking and prioritizing 7. Self-discipline 8. Teamwork
157
02.02 Follow telephone/ telecommunication procedures 02.03 Communicate clearly 02.04 Prepare brief reports and checklists using standard forms 02.05 Read/interpret flowcharts and pictorial information 02.06 Write memos and letters 02.07 Utilize Local Area Network (LAN)/Intranet to exchange information 02.08 Prepare pictorial and graphic information 03.01 Apply cultural requirements to the workplace 03.02 Demonstrate integrity and apply ethical practices 03.03 Accept responsibility for own work and work area 03.04 Seek and act constructively upon feedback about performance 03.05 Demonstrate safety skills 03.06 Respond appropriately to people and situations 03.07 Resolve interpersonal conflicts 03.08 Develop and maintain a cooperation within work group 04.01 Organize own work activities 04.02 Set and revise own objectives and goals 04.03 Organize and maintain own workplace 04.04 Apply problem solving strategies 04.05 Demonstrate initiative and flexibility 06.01 Understand systems 06.02 Comply with and follow chain of command 06.03 Identify and highlight problems 06.04 Adapt competencies to new situations/systems 06.05 Analyse technical systems 06.06 Monitor and correct performance of systems
Tools, Equipment and Materials (TEM)
Items Ratio (TEM: Trainee)
1. LCD Projector or other type of projector with white screen.
1:25
158
2. Computer Set with words processing & Graphic software. 3. Stationery
1:1 As required
REFERENCES
1. Denise Robitaille, Paton Press LLC, 2005, Document Control: A simple Guide To Managing Documentation, ISBN: 1-932828-03-6
2. Mike Jones, 2012, First Steps in Documentation for the Small Business - Book 4 Business Operations, ISBN: 9781476270340 3. Jeffrey Robert Stewart, Glencoe, 1995 Professional Records Management, ISBN: 9780028010281 4. Michael Netzley & Graig Snow, Prentice Hall 1st. Ed. 2001, Guide to Report Writing ISBN 978-0130417718 5. John Bowden, Writing a Report- How to Accurate in preparing, Write & Present Really Effective, ISBN 978-1845284701
159
CURRICULUM OF COMPETENCY UNIT (CoCU)
Sub Sector INDUSTRIAL AUTOMATION & MECHATRONIC
Job Area INDUSTRIAL AUTOMATION ENGINEERING
NOSS Title INDUSTRIAL AUTOMATION ENGINEERING SUPPORT SERVICE
Competency Unit Title INDUSTRIAL AUTOMATION SYSTEM MAINTENANCE
Learning Outcome The person who is competent in this CU shall be able to perform industrial automation maintenance functions and ensure the operations of industrial automation runs well with breakdowns, operation idle time and the stoppage interferences records are within permitted level with maintenance cost optimization. The technician is also responsible to achieve his individual and team performance objectives and contribute toward the highest achievement of the operation in accordance with the organization requirements. Upon completion of this competency unit, trainees will be able to:
Examine Industrial Automation System maintenance Instruction
Prepare Industrial Automation System maintenance Requirements
Perform Industrial Automation System maintenance implementation
Perform Industrial Automation System maintenance testing
Perform Industrial Automation System maintenance test record submission
Competency Unit ID MC-XXX-5 Level 2 Training Duration 90 Hours Credit Hours 9
Work Activities Related Knowledge Related Skills Attitude/Safety/
Environmental
Training Hours
Delivery Mode
Assessment Criteria
1. Examine
Industrial
i. Official source of
instruction
Lecture Source of
instruction,
160
Work Activities Related Knowledge Related Skills Attitude/Safety/
Environmental
Training Hours
Delivery Mode
Assessment Criteria
Automation System maintenance Instruction
ii. Official instruction authority
iii. Instruction validity requirement
iv. Instruction content specification
v. Industrial automation system maintenance instruction acceptance requirement
vi. Industrial automation system maintenance instruction recording method
instruction authority, instruction validity, instruction content confirmed.
Industrial automation system maintenance instruction acceptance signed.
Industrial automation system maintenance instruction record produced.
i. Check source of instruction
ii. Check instruction authority
iii. Check instruction validity
iv. Check instruction content
v. Accept industrial automation system maintenance instruction
vi. Record industrial automation system maintenance instruction
Practical
161
Work Activities Related Knowledge Related Skills Attitude/Safety/
Environmental
Training Hours
Delivery Mode
Assessment Criteria
Attitude:
i. Factual in checking source of instruction
ii. Factual in checking instruction authority
iii. Factual in checking instruction validity
iv. Detailed in checking instruction content
v. Confidence in accepting industrial automation system maintenance instruction
vi. Accurate in recording industrial automation system maintenance instruction
Safety:
i. Ensure data safety. ii. Ensure safe work
methodology. iii. Ensure electrical safety
on all electrically powered equipment.
iv. Enforce safety & health rules and regulations
v. Ensure safe working condition.
162
Work Activities Related Knowledge Related Skills Attitude/Safety/
Environmental
Training Hours
Delivery Mode
Assessment Criteria
vi. Promote good safety & health practice at workplace.
Environment:
i. Ensure energy saver office equipments.
ii. Reduce energy wastage.
iii. Practice paperless office.
2. Prepare
Industrial Automation System maintenance Requirements
i. Industrial Automation
System maintenance objective
ii. Industrial Automation System maintenance specification
iii. Industrial Automation System maintenance Standard operation procedure Industrial Automation System Total Preventive Maintenance (TPM) plan prescription
iv. Industrial Automation System TPM wear and tear spare part list sources
v. Industrial Automation
Lecture Industrial
Automation System maintenance objective achieved.
Industrial Automation System maintenance specification, Industrial Automation System maintenance Standard operation
163
Work Activities Related Knowledge Related Skills Attitude/Safety/
Environmental
Training Hours
Delivery Mode
Assessment Criteria
System TPM Check list sources
vi. Industrial Automation System TPM maintenance tools, equipments and machineries sources
vii. Industrial Automation TPM record systems resource.
viii. Corrective Maintenance Standard Operating Procedure
ix. Corrective Action Requisition Procedure.
x. Corrective Action frequency analysis source.
xi. Corrective Maintenance Record Systems source.
procedure displayed.
Prescribed Industrial Automation System Total Preventive Maintenance (TPM) plan interpreted.
Industrial Automation System TPM wear and tear spare part list, Industrial Automation System TPM Check list, Industrial Automation System TPM maintenance tools, equipments and machineries, Industrial Automation TPM record
i. Observe Industrial
Automation System maintenance objective.
ii. Obtain Industrial Automation System maintenance specification
iii. Obtain Industrial Automation System maintenance Standard operation procedure
iv. Examine prescribed
Practical
164
Work Activities Related Knowledge Related Skills Attitude/Safety/
Environmental
Training Hours
Delivery Mode
Assessment Criteria
Industrial Automation System Total Preventive Maintenance (TPM) plan
v. Obtain Industrial Automation System TPM wear and tear spare part list
vi. Obtain Industrial Automation System TPM Check list
vii. Obtain Industrial Automation System TPM maintenance tools, equipments and machineries
viii. Obtain Industrial Automation TPM record systems.
ix. Gather Corrective Maintenance Standard Operating Procedure
x. Obtain Corrective Action Requisition Procedure.
xi. Obtain Corrective Action frequency analysis data.
xii. Obtain Corrective Maintenance
systems listed.
Corrective Maintenance Standard Operating Procedure displayed.
Corrective Action Requisition Procedure displayed.
Corrective Action frequency analysis data displayed.
Corrective Maintenance Record Systems displayed.
165
Work Activities Related Knowledge Related Skills Attitude/Safety/
Environmental
Training Hours
Delivery Mode
Assessment Criteria
Record Systems.
Attitude: i. Focus in observing
Industrial Automation System maintenance objective.
ii. Resourceful in obtaining Industrial Automation System maintenance specification
iii. Resourceful in obtaining Industrial Automation System maintenance Standard operation procedure
iv. Thorough in examining prescribed Industrial Automation System Total Preventive Maintenance (TPM) plan
v. Resourceful in obtaining Industrial Automation System TPM wear and tear spare part list
vi. Resourceful in obtaining Industrial Automation System TPM Check list
166
Work Activities Related Knowledge Related Skills Attitude/Safety/
Environmental
Training Hours
Delivery Mode
Assessment Criteria
vii. Resourceful in obtaining Industrial Automation System TPM maintenance tools, equipments and machineries
viii. Resourceful in obtaining Industrial Automation TPM record systems.
ix. Resourceful in gathering Corrective Maintenance Standard Operating Procedure
x. Resourceful in obtaining Corrective Action Requisition Procedure.
xi. Resourceful in obtaining Corrective Action frequency analysis.
xii. Resourceful in obtaining Corrective Maintenance Record Systems.
Safety:
i. Ensure data safety. ii. Ensure safe work
methodology.
167
Work Activities Related Knowledge Related Skills Attitude/Safety/
Environmental
Training Hours
Delivery Mode
Assessment Criteria
iii. Ensure electrical safety on all electrically powered equipment.
iv. Enforce safety & health rules and regulations
v. Ensure safe working condition.
vi. Promote good safety & health practice at workplace.
Environment:
iv. Ensure energy saver office equipments.
v. Reduce energy wastage.
vi. Practice paperless office.
3. Perform
Industrial Automation System maintenance implementation
i. Industrial Automation
System maintenance specification
ii. Corrective Maintenance Systems specification
iii. TPM Program specification
iv. TPM standard operating procedure
v. TPM implementation
Lecture
Industrial Automation System maintenance specification interpreted, TPM Program specification,
168
Work Activities Related Knowledge Related Skills Attitude/Safety/
Environmental
Training Hours
Delivery Mode
Assessment Criteria
technique application vi. Mechanical part TPM
administration vii. Greasing requirement viii. Oiling requirement ix. Aligning method x. Tightening process xi. Replacing requirement xii. Trouble shooting
process xiii. Backlash setting xiv. Electrical part TPM
program administration xv. Winding process xvi. Continuity process xvii. Insulation process xviii. Voltage level
requirement xix. Current leakage xx. Grounding checking xxi. Calibration xxii. Trouble shooting
process xxiii. pneumatic / hydraulic
part TPM Program administration
xxiv. Leaking xxv. Pressure measurement xxvi. Blocking requirement xxvii. Oil Level xxviii. Instrument TPM
Program administration
Corrective Maintenance Systems specification interpreted, TPM standard operating procedure completed, TPM implementation technique used
Mechanical part TPM program executed, Greasing, Aligning, Tightening, Replacing, Trouble shooting, Backlash setting executed.
Electrical part TPM program executed,
169
Work Activities Related Knowledge Related Skills Attitude/Safety/
Environmental
Training Hours
Delivery Mode
Assessment Criteria
xxix. Calibration xxx. Continuity process xxxi. Voltage Levelling xxxii. Current leakage xxxiii. Trouble shooting
process xxxiv. Corrective Action
Request instruction xxxv. Corrective Action job
sheet work instruction xxxvi. Corrective Action
Request feedback xxxvii. Corrective Action
Request Report finishing
xxxviii. Corrective Action Request Logbook updating requirement
xxxix. Industrial Automation System maintenance implementation record production
Winding, Continuity, Insulation, Voltage level, Current leakage, Grounding checking, Calibration, Trouble shooting executed.
Pneumatic / hydraulic part TPM Program executed, Leaking, Pressure, Blocking, Oil level executed.
Instrument TPM Program executed, Calibration, Continuity, Voltage level, Current leakage,
i. Examine Industrial Automation System maintenance specification
Corrective Maintenance Systems
Practical
170
Work Activities Related Knowledge Related Skills Attitude/Safety/
Environmental
Training Hours
Delivery Mode
Assessment Criteria
specification. ii. Follow TPM
standard operating procedure.
iii. Apply TPM implementation technique.
iv. Carry out mechanical part TPM program
v. Carry out electrical part TPM program
vi. Carry out pneumatic / hydraulic part TPM Program
vii. Carry out instrument TPM Program
viii. Perform Corrective Action Request Order.
ix. Record Industrial Automation System maintenance implementation
Trouble shooting executed.
Corrective Action Request Order executed, Corrective Action Request job sheet registered, Corrective Action Request order executed, Corrective Action Request feedback produced, Corrective Action Request Report settled, Corrective Action Request Logbook
Attitude:
i. Thorough in examining Industrial Automation System maintenance
171
Work Activities Related Knowledge Related Skills Attitude/Safety/
Environmental
Training Hours
Delivery Mode
Assessment Criteria
specification ii. Faithful in following
TPM standard operating procedure.
iii. Creative in applying TPM implementation technique.
iv. Objective focused in carrying out mechanical part TPM program
v. Thorough in carrying out electrical part TPM program
vi. Objective focused in carrying pneumatic / hydraulic part TPM Program
vii. Objective focused in carrying instrument TPM Program
viii. Thorough in performing Corrective Action Request Order.
ix. Accurate in recording Industrial Automation System maintenance implementation
Safety:
i. Ensure data safety.
record produced.
Industrial Automation System maintenance implementation record produced.
172
Work Activities Related Knowledge Related Skills Attitude/Safety/
Environmental
Training Hours
Delivery Mode
Assessment Criteria
ii. Ensure safe work methodology.
iii. Ensure electrical safety on all electrically powered equipment.
iv. Enforce safety & health rules and regulations
v. Ensure safe working condition.
vi. Promote good safety & health practice at workplace.
Environment:
i. Ensure energy saver office equipments.
ii. Reduce energy wastage.
iii. Practice paperless office.
4. Perform
Industrial Automation System maintenance testing
i. Conduct mechanical test ii. Conduct electrical test iii. Conduct pneumatic and
hydraulic test iv. Conduct instrument test
v. Compile Industrial Automation System maintenance periodical systems test result.
Mechanical test executed
Electrical test executed
Pneumatic and hydraulic test executed
Instrument test executed
173
Work Activities Related Knowledge Related Skills Attitude/Safety/
Environmental
Training Hours
Delivery Mode
Assessment Criteria
i. Conduct
mechanical test ii. Conduct electrical
test iii. Conduct pneumatic
and hydraulic test iv. Conduct instrument
test v. Compile Industrial
Automation System maintenance periodical systems test result.
Industrial Automation System maintenance periodical systems test result binded.
Attitude: i. Meticulous in
conducting mechanical test
ii. Meticulous in conducting electrical test
iii. Meticulous in conducting pneumatic and hydraulic test
iv. Meticulous in conducting instrument test
v. Systematic in compiling Industrial Automation System maintenance periodical systems test
174
Work Activities Related Knowledge Related Skills Attitude/Safety/
Environmental
Training Hours
Delivery Mode
Assessment Criteria
result.
Safety:
i. Ensure data safety. ii. Ensure safe work
methodology. iii. Ensure electrical safety
on all electrically powered equipment.
iv. Enforce safety & health rules and regulations
v. Ensure safe working condition.
vi. Promote good safety & health practice at workplace.
Environment:
i. Ensure energy saver office equipments.
ii. Reduce energy wastage.
iii. Practice paperless office.
5. Perform
Industrial Automation System maintenanc
i.Industrial Automation System maintenance test record requirement
ii. Industrial Automation System maintenance
Industrial Automation System maintenance test record
175
Work Activities Related Knowledge Related Skills Attitude/Safety/
Environmental
Training Hours
Delivery Mode
Assessment Criteria
e test record submission
testing record form prescription
iii.Industrial Automation System maintenance testing result
iv.Industrial Automation System maintenance testing remarks
v. Industrial Automation System maintenance test certificate/result attachment procedure
vi.Industrial Automation System maintenance test record submission requirement
prepared, Industrial Automation System maintenance testing record form, Industrial Automation System maintenance testing result, Industrial Automation System maintenance testing remarks prescribed,
Industrial Automation System maintenance test certificate/result attachment provided.
Industrial Automation System
vii. i. Prepare Industrial
Automation System maintenance test record
Prescribe Industrial Automation System maintenance testing record form
Prescribe Industrial Automation System maintenance testing result
Prescribe Industrial Automation System
176
Work Activities Related Knowledge Related Skills Attitude/Safety/
Environmental
Training Hours
Delivery Mode
Assessment Criteria
maintenance testing remarks
ii. Provide Industrial Automation System maintenance test certificate/result attachment.
iii. Submit Industrial Automation System maintenance test record
maintenance test record submitted.
Attitude: i. Meticulous in preparing
Industrial Automation System maintenance test record
ii. Systematic in providing Industrial Automation System maintenance test certificate/result attachment.
iii. Confidence in submitting Industrial Automation System maintenance test record
Safety:
i. Ensure data safety. ii. Ensure safe work
177
Work Activities Related Knowledge Related Skills Attitude/Safety/
Environmental
Training Hours
Delivery Mode
Assessment Criteria
methodology. iii. Ensure electrical safety
on all electrically powered equipment.
iv. Enforce safety & health rules and regulations
v. Ensure safe working condition.
vi. Promote good safety & health practice at workplace.
Environment:
i. Ensure energy saver office equipments.
ii. Reduce energy wastage. Practice paperless office.
Employability Skills
Core Abilities Social Skills
01.01 Identify and gather information 01.02 Document information, procedures or processes 01.03 Utilize basic IT applications 01.04 Analyse information
1. Communication skills 2. Conceptual skills 3. Interpersonal skills 4. Learning skills 5. Leadership skills
178
01.05 Utilize the Internet to locate and gather information 01.06 Utilize word processor to process information 02.01 Interpret and follow manuals, instructions and SOP’s 02.02 Follow telephone/ telecommunication procedures 02.03 Communicate clearly 02.04 Prepare brief reports and checklists using standard forms 02.05 Read/interpret flowcharts and pictorial information 02.06 Write memos and letters 02.07 Utilize Local Area Network (LAN)/Intranet to exchange information 02.08 Prepare pictorial and graphic information 03.01 Apply cultural requirements to the workplace 03.02 Demonstrate integrity and apply ethical practices 03.03 Accept responsibility for own work and work area 03.04 Seek and act constructively upon feedback about performance 03.05 Demonstrate safety skills 03.06 Respond appropriately to people and situations 03.07 Resolve interpersonal conflicts 03.08 Develop and maintain a cooperation within work group 04.01 Organize own work activities 04.02 Set and revise own objectives and goals 04.03 Organize and maintain own workplace 04.04 Apply problem solving strategies 04.05 Demonstrate initiative and flexibility 06.01 Understand systems 06.02 Comply with and follow chain of command 06.03 Identify and highlight problems 06.04 Adapt competencies to new situations/systems 06.05 Analyse technical systems 06.06 Monitor and correct performance of systems
6. Multitasking and prioritizing 7. Self-discipline 8. Teamwork
179
Tools, Equipment and Materials (TEM)
Items Ratio (TEM: Trainee)
1. LCD Projector or other type of projector with white screen. 2. Computer Set with words processing & CADD software. 3. Individual maintenance Tools Set. 4. Sample Total Preventive Maintenance program checklist 5. Industrial Automation Systems model or sample 6. Personal Safety Attire
1:25 1:1 1:1 1:1 As required As required
REFERENCES
1. Thomas French , Jay Helsel, Glencoe/McGraw-Hill; 13 edition (February 13, 2002), Mechanical Drawing: Board and CAD
Techniques, Student Edition, ISBN: 978-0078251009
2. Terry Wohlers McGraw Hill Professional 2012 Applying AutoCAD® 2013, ISBN: 9780073375519
3. Randy Shih , SDC Publications; Pap/Cdr edition (April 27, 2012), AutoCAD 2013 Tutorial - First Level: 2D Fundamentals, ISBN: 978-1585037162
4. Shawna Lockhart , SDC Publications (May 23, 2012), Tutorial Guide to AutoCAD 2013, ISBN: 978-1585037216
5. Elise Moss, SDC Publications (April 13, 2012), Autodesk AutoCAD 2013 Fundamentals, ISBN: 978-1585037148
6. Terence M. Shumaker , David A. Madsen , David P. Madsen, Goodheart-Willcox Co; 18 Ed. 2010 AutoCAD and Its Applications Basics 2011, ISBN:978-1605253282
7. Novak, Henry C. Spencer, John T. Dygdon, McGraw-Hill/Glencoe; 6 Ed. 1994 Basic Technical Drawing: Student Text 8. Michael Netzley & Graig Snow, Prentice Hall 1st. Ed. 2001, Guide to Report Writing ISBN 978-0130417718 9. John Bowden, Writing a Report- How to Accurate in preparing, Write & Present Really Effective, ISBN 978-1845284701