Construction of Pantai 2 Sewage Treatment PlantFederal Territory of Kuala Lumpur (Design & Build)Presentation by BEWG (M) Sdn. Bhd.28 April 2014Monthly Progress Meeting No. 24Period : 27/03/2014 26/04/2014Kementerian Tenaga, Teknologi Hijau dan AirJabatan Perkhidmatan PembetunganKeTTHA / JPP / RMK10 / 11 / K2

JABATANPERKHIDMATANPEMBETUNGAN1Project Background1OwnerKementerian Tenaga, Teknologi Hijau Dan Air2Implementing AgencyJabatan Perkhidmatan Pembetungan3Project Management ConsultantKumpulan Ikhtisas Projek (M) Sdn. Bhd. MECIP (M) Sdn. Bhd. JV4Design & Build ContractorBEWG (M) Sdn. Bhd. (novated by BEWG Ltd. on 20 December 2011)5Design Capacity1.423 Million PE6Site Area17.264 hectare7Contract CostRM 983,246,360.008Contract Start Date28 July 20119O&M End Date27 July 201710Completion of STP & Facility (CSC-2 & CSC-3)27 January 201611Count Down (as of 28-04-2014) 274 days to 27 January 201512Count Down (as of 28-04-2014) 639 days to 27 January 20162Kerajaan Malaysia Kementerian Tenaga, Teknologi Hijau dan Air Jabatan Perkhidmatan Pembetungan BEWG (M) Sdn. Bhd. M&E SMHB Sdn. Bhd. Planner SS Planning & Consult TIA Runding TrafikMZK Sdn. Bhd. Project Management Consulting Agreement Project Management Process Design BEWGHQ BEWG LimitedNovationAgreementMajor Stakeholders QS Perunding NFL Sdn. Bhd. C&S, Geotechnical Engineering and EnvironmentalConsultants Sdn. Bhd. Dilapidation P-CON BuildingSurveyorsSdn. Bhd. Landscape PTA Design Sdn. Bhd. EIA ASMA Environmental Consultancy Sdn. Bhd. Comm. PlanSilver KreatifSdn. Bhd. Contractual relationships Functional relationship Licensed Surveyor GeoDatum SurveyQuality Professional &Excellent Sdn.Bhd.HAZOP ERMSub-Consultant SMEDRIC ArchitectKuek Wee Chien ArchitectKumpulan IkhtisasProjek (M) Sdn Bhd MECIP (M) Sdn Bhd JV GBI FacilitatorPrudenergy Sdn BhdMajor Stakeholders Functional & Contractual RelationshipDESIGN & BUILD CONTRACTORBEWG (M) Sdn. Bhd.CHIEF RESIDENT ENGINEEREECCLIENTMinistry of Energy, Green Technology & WaterSMHBKWCAPMCKI-MECIP JV CM - PMCKI-MECIP JVDESIGN & BUILD CONTRACTORBEWG (M) Sdn. Bhd.Site OperationPNFLOWNERGovernment of MalaysiaIMPLEMENTATION AGENCYSewerage Services DepartmentPTABEWG Ltd.Site NovationAgreementHQOther ConsultantsContractualrelationshipFunctionalrelationshipBEWG (M) Site Organization ChartBoard of DirectorsAdmin ManagerJi Yi (Sisley)Construction cum Planning ManagerAn RuizhiProject ManagerLuo Xue Geng (George)QA/QC Mgr / Asst. MgrNg Chin Hui (Fay)Ding Jiang BoSuhaimi MuhamadSchedulerLee Chia WaiCosting ExecTan Jia ChinWei WeiHew Kean WeiCommunication ManagerIntan PuteriAhmad ZaimCivil EngineerMegat ZulhilmiDeng Hui (Eric)Yap Koon Fah (Jeff) Liew Jo HannUmmu Balqis JohariProcurement ManagerWang Wei Meng (Sunny)Automation EngineerPeng YenboElectrical EngineerWang LiangZawawiContract ManagerNew Keat Teong (Vincent) Costing ManagerZhang JingHSSE OfficerSiti HafizahHSS SupervisorAlexanderAswadChief Technical OfficerMohd Subuki FadzilSr. Construction ManagerWoo Wan NinHSSE ManagerShah RizamDeputy Project ManagerYeung Kai HoiSr. Project AssistantTang Man Shing (Eric)Project AssistantWang Xue (William)Logistic ExecutiveAi Si Wei (Sylvia) Mechanical Engineer Zhang Yong ZaiZhang Su Peng(Rick)Wang WenLim Chang Hooi Technical ManagerToo Heng Yuen (Jeffrey) Environmental OfficerChoong Kok KuenProcess EngrLow Thong SoonChoong Kok KuenQA Executive Chow Kim WaiAdmin ExecutiveYan YijieLi Rong (Lily)5EEC Board of DirectorsDirector In ChargeIr. Yeow Yew Yuen /Ir. Lim Kim Oum( C&S Design Signatory )Project ManagerIr. Tan Eng Kew

Deputy Project ManagerIr. S. JeyaratnamAdvisorsIr. Hj. Abdullah IbrahimIr. Henry E. ChelvanayagamStructural

Ir. Choo Seng KitRosnah AwangLim Mew ChangGeotechnical, Foundation &Earthwork

Ir. Tang Tin SengIr. Leong Shian LoongNurul Hizza M. AzmiSewage TreatmentProcess Environmental, Solid Waste

Ir. S. SivarajahNorazlina AbdullahElectrical &Mechanical

Ir. Ismail Abu AhmadAzahari OsmanAbd. Mulok MohdInfrastructure

EarthworksNoreiney

RoadsIr. Chan Nai Thim

Stormwater DrainageIr. Tan Meng LuckRahayu Abdullah

Water SupplyIr. Rafidah HaronCLIENTGovernment of Malaysia,Ministry of Energy, Green Technology & Water,Sewerage Services DepartmentDESIGN & BUILD CONTRACTORBEWG (M) Sdn. Bhd.Admin Staff

Secretary Norhanem Zainal

Document Control Rozita Che BrahimSite Supervision

CREIr. Tan Kah Kian(Alex)Design Team Organization ChartEngineering and Environmental Consultants Sdn Bhd( C&S and Geotechnical Consultant )6SMHB Board of DirectorsProject DirectorIr. Pritam Singh( Electrical Design Signatory )Project ManagerIr. Chang Yit Wah( Mechanical Design Signatory )

AdvisorsMechanical

Sundara Morthi

Ahmad Faiz

Mohd HelmiElectrical

Meyappan

MathanrajProcess

Loo Ai Choo

Moghan Muniandy

Low Chen FooCLIENTGovernment of Malaysia,Ministry of Energy, Green Technology & Water,Sewerage Services DepartmentSite SupervisionElectrical

RE (Manimaran)Design Team Organization ChartSMHB Sdn Bhd (Mechanical & Electrical Consultant)DESIGN & BUILD CONTRACTORBEWG (M) Sdn. Bhd. Instrumentation /Scada

Meyappan

Site SupervisionMechanical

RE (William)

ARE (Mohd Helmi)

SiteOfficeConsultant Site SupervisionOrganization ChartCHIEF RESIDENT ENGINEERIr. Tan Kah Kian (Alex)Admin StaffSecretaryDoc. Control ClerkYusnaniResident Eng 1Geotechnical / CivilTBNResident Engineer 2Civil & StructuresWan ShakizanResident Eng (M)William HooiSr. Site QSJael QeokAsst Contract ExecFarah NajlaaAsst Contract ExecNuratiqahResident ArchitectTBNIOWLee Lin Teck (Max)IOWTBNResidentLandscape Architect TBNIOWTBNIOWTBNARE (M)Mohd HelmiIOW (M) 1AzmanIOW (M) 2Poh Kim SoonIOW (M) 3TBNResident Eng (E)ManimaranARE (E)Mohd KashfulIOW (E) 1BaharudinIOW (E) 2NarayananIOW (E) 3TBNARE (C&S)Muhammad ShafiqIOW (C&S) 1Mohd YusryIOW (C&S) 2Abdul HadiIOW (C&S) 3Mohd AffendiDraughtspersonNorlelaARE (C&S)SaharizalIOW (C&S) 1Akmal MohammadIOW (C&S) 2Chin Co SingIOW (C&S) 3TBNIOW (C&S) 4TBNARE (M&E P1 Pump Station)ZahrulIOW (M&E) 1Nek MustafaIOW (M&E) 2ZainalIOW (Build & Infra) 1AzmiIOW (Build & Infra) 2TBNXX New team memberTo check back new IOW (E) SMHB8CONSTRUCTION MANAGER

Ir. NUZOR B. SALLEHSITE CLERKNUR AINKU FATIHAHQS

ISMAIL B. AlwiJABATAN PERKHIDMATAN PEMBETUNGAN

TECHNICIAN 1MOHD SHAMSUL AZLAN B. AHMADCIVIL & STRUCTURE

Engr. DAHARI B. IDRISSITE MECHANICAL & ELECTRICAL

Engr. HAMZAH B. HAMIDEngr. MOHD NOR MAIZATULIOW (C&S) 1AHMAD HISYAMUDDINPROCESSLIQUID/SOLID LINE

T B NIOW (M&E)Engr. WAN MOHD NAZLANIOW (PROCESS)T B NKumpulan Ikhtisas Projek (M) Sdn. Bhd. MECIP (M) Sdn. Bhd. JV- Site Organization ChartIOW (C&S) 2SYAFFIQ UZZAIRIE B. ABD WAHABXX New team memberOverviewProgress

- Progress Summary, Project CPM Status, - Look Ahead Activities in May, June & July 2014 - P1PS Upgrading Work Schedule - Financial & Physical S-Curve - AIP StatusStatus of Enabling Work / Authorities ApprovalDesign / Engineering Procurement / Sub-ContractingConstruction Activities / Management - QA / QC - HSS - Environmental - Communication Areas of ConcernMatters Arising from Previous Meeting1010Progress Summary23rd March 201426th April 2014Scheduled%Actual%Scheduled%Actual%Variance%Financial Progress 60.2253.4162.0855.71-6.37Physical Progress 63.1255.2865.4458.12-7.32Project CPM Status64 days delayed58 days delayedTime Consumed, weeks (%)139 weeks (59.15 %)144 weeks (61.22 %)Countdown(as of 28th April 2014)639 days to 27 Jan 2016Progress SummaryWeek NoCut Off DateFinancialProgressCPM StatusSchedule, (%)Actual, (%)Variance, (%)Schedule, (%)Actual, (%)Variance, (%)13923 Mar 201460.2253.41-6.8163.1255.28-7.84Delay: 64 Days14030 Mar 201461.0653.65-7.4164.2155.30-8.91Delay: 65 Days14106 Apr 201461.8054.76-7.0465.1656.53-8.63Delay: 62 Days14213 Apr 201461.9054.91-6.9965.2657.21-8.05Delay 60 Days14320 Apr 201462.0055.07-6.9365.3657.43-7.93Delay: 58 Days14426 Apr 201462.0855.71-6.3765.4458.12-7.32Delay: 58 DaysProject CPM StatusDaysUpdate from Ms LeeMs Lee26-Apr-1413Look Ahead Activities in April June 2014

14P1PS Upgrading Work Schedule

To add Roof slabTarget date:15 may 2014Schedule:33%Actual: 28%15Financial S-CurveSchedule62.08(as of 26/04/14)Actual55.71(as of 26/04/14)MonthSep-12Oct-12Nov-12Dec-12Jan-13Feb-13Mar-13Apr-13May-13Jun-13Jul-13Aug-13Sep-13Oct-13Nov-13Dec-13Jan-14Feb-14Mar-14Apr-14% Schedule13.16%14.45%18.97%21.42%22.68%23.31%24.12%26.55%28.49%30.65%32.85%35.59%37.83%42.04%46.21%50.80%54.09%57.49%61.18%62.08%% Actual13.16%14.45%18.97%21.42%22.68%23.31%24.12%26.55%29.43%31.72%33.99%36.02%37.99%41.51%45.52%49.80%51.13%52.19%53.65%55.71%16Physical S-CurveActual58.12%(as of 26/04/14)Schedule65.44%(as of 26/04/14)MonthSep-12Oct-12Nov-12Dec-12Jan-13Feb-13Mar-13Apr-13May-13Jun-13Jul-13Aug-13Sep-13Oct-13Nov-13Dec-13Jan-14Feb-14Mar-1426/04/14% Schedule11.57%13.01%14.24%15.93%17.23%18.00%20.26%21.67%23.85%26.36%29.00%32.36%35.18%40.37%45.46%50.65%55.00%59.55%64.37%65.44%% Actual11.57%13.01%14.24%15.93%17.23%18.00%20.26%21.67%25.46%28.39%31.07%33.65%36.31%41.01%45.17%50.04%52.05%53.57%55.30%58.12%17Application for Interim Payment (Work done up to 31/03/2012)AIP No.AIP Submission DateSite Valuation DateTotal Certified Amount (RM) Cumulative Certified Amount (RM)Amount of Payment Received (RM)Cumulative Payment Received (RM)2525 / 09 / 201325 / 09 / 201319,371,500373,540,48019,371,500373,540,4802628 / 10 / 201328 / 10 / 201334,565,800408,106,28034,565,800408,106,2802726 / 11 / 201326 / 11 / 201339,456,100447,562,38039,456,100447,562,3802816 / 12 / 201316 / 12 / 201313,649,300461,211,68013,649,300461,211,6802927 / 12 / 201327 / 12 / 201328,405,800489,617,48028,405,800489,617,4803023 / 01 / 201423 / 01 / 201413,140,900502,758,38013,140,900502,758,3803124 / 02 / 201424 / 02 / 201410,391,300513,149,68010,391,300513,149,6803224 / 03 / 201424 / 03 / 201414,439,600527,589,28014,439,600527,589,2803323 / 04 / 201423 / 04 / 2014????????Status of Authorities ApprovalItemAuthorityStatusRemarkDiversion of Existing Drain from P1STPJPS / DBKLCompletedDBKL approval obtain

MSMA for Landscaped Park Retention PondDBKLOngoing- Proposal submitted to DBKL (discussion between EEC & SMHB and DBKL on-going)Revised Development Order Layout PlanDBKLOngoing- Proposal submitted to DBKL by KWCA. Pending Signature (in-progress) from PTG1.8m dia. Effluent Pipe DBKLOngoing- Design submitted to DBKL1919M&E PROCUREMENT

Procurement / Sub-Contracting- Equipment2013 Delivery and Inspection Status

ItemEquipmentSupplier / BrandStatusArrived Date1Mixers (Liquid Line )WiloArrived and Site Inspection Finished14-Jun-20132CompressorNeurosArrived and Site Inspection Finished28-Sep-20133Pump (Liquid Line )FlygtArrived and Site Inspection Finished28-Oct-20134Chain ScraperPolychemArrived and Site Inspection Finished13-Nov-20135Vortex Grit ChamberXylemArrived and Site Inspection Finished15-Nov-20136Sludge DecanterAndritzArrived and Site Inspection Finished9-Dec-20137P1 STP Pumps/Penstock/ScreenEbara/Esareka/JeffconArrived and Site Inspection Finished23-Dec-20138Rotary Fine ScreenHuberArrived and Site Inspection Finished29-Dec-2013Procurement / Sub-Contracting- Equipment

2014 Delivery Target

ItemEquipmentSupplier / BrandStatusArrived Date1UV SystemXylem/WedecoAwarded15th November20142CCTV SystemTBIIn EvaluationDecember 20143Ventilation Equipment EltafantechAwarded31st July 20144Hoisting Equipment ExcelliftAwarded31st July 20145Electrical Equipment (Transformer and Switchboard)PowerwellAwarded31st October 20146Diesel Genset TBIIn Evaluation31st March 20157InstrumentE+HAwarded31st August 20148ValvesSCIAwarded15th August 20149Sludge DigestionPURACAwarded10th September 201410Odour Control SystemNishiharaAwarded15th August 201411-12Solar Panel & Waste water Source Heat PumpJin DadiAwarded1st Feb-Apr 201513Effluent Reuse SystemFilcoreAwarded31st December 201414Biogas EngineGE JenbacherAwardedMarch 2015Postponed the date both FAT and delivery time of biogas genset until to Q1 2015;Add a column for FAT schedule, and add word done for NISHIHARA technical schedule;Recover Belt Thickener (Harbar) FAT

22Procurement / Sub-Contracting- EquipmentTBI = To be Informed

2014 FAT Schedule

ItemEquipmentSupplier / BrandCountryProposed DateStatusRemarks1Belt ThickenerHaibarChina26-30 May 2014Confirmed with manufactory2DiffuserJagerChina2-6 June 2014Confirmed with manufactory3ADG MixerStamoSweden9-11 June 2014Confirmed with manufactory4Heat ExchangerLackebySweden12-13 June 2014Confirmed with manufactory5Biogas EngineGE JenbacherAustria19-23 Jan 2015Depends on Shop drawing approval6Wastewater Source Heat Pump SystemJin DadiChina10 -15 Aug 2014Depends on Shop drawing approval7TransformerHuapengChinaTBI (Oct 2014)Depends on Shop drawing approval8Standby GensetTBIUK/MalaysiaTBI(2015)Depends on Shop drawing approval9Odour SystemNishiharaChina21-23 Apr 2014Done*Technical Visit Postponed the date both FAT and delivery time of biogas genset until to Q1 2015;Add a column for FAT schedule, and add word done for NISHIHARA technical schedule;Recover Belt Thickener (Harbar) FAT

CONSTRUCTION

Construction- Underground StructureAAOPRE-TREATMENTCLARIFIER

Construction- Aboveground StructureANAEROBIC DIGESTERUNDERPASS AT LEVEL 21 SOUTH SIDESLUDGE THICKENING STATION

ADMINISTRATION BUILDINGCONSUMER SUB-STATION 33kV/11kVConstruction- Aboveground StructureTNB Substation- CompletedConstruction- P1PS UPGRADING

PUMP PLINTH

SCREEN INSTALLATION

PENSTOCK INSTALLATIONACTIVITIES / MANAGEMENTQuality Assurance & Quality Control (QA/QC)Health, Safety & Security (HSS)EnvironmentalCommunication PlanQUALITY ASSURANCE & QUALITY CONTROL

QA/QC- Quality Control ActivitiesItemDescription Of TestFrom 1st 22nd April 2014Cumulative Total Of Tests Carried Out (No.)RemarkTests Carried Out (No.)Tests Passed (No.)Tests Failed (No.)1Concrete Cube Comp. Test @ 7-days48348309687Passed100.00%0.00%2Concrete Cube Comp. Test @ 28-days43843809279Passed100.00%0.00%ItemDescription Of TestFrom 1st 31st Mac 2014Cumulative Total Of Tests Carried Out (No.)RemarkTests Carried Out (No.)Tests Passed (No.)Tests Failed (No.)1Water Permeability @ 56-days39390626Passed100.00%0.00%Summary of Concrete Cube TestWater Permeability Test31Tensile Test

Item Sample Tests carried Out (No.)Remark1T10--2T12--3T16--4T20--5T25--6T32--7T40--Number of NCRsreceivedNumber of NCRs closed Number of NCRs To Be Closed 8278 (95%)4 (5%)NCR

Site Directive

Number of Site Directive ReceivedNumber of Site Directive Replied Number of Site Directive To Be Replied 178175 (99%)3 (1%)QA/QC- Quality Control ActivitiesWork Method Statements

Total Number of Submission (up to today)Number of ApprovedNumber of WMS waiting for answerNumber of WMS rejected

16013092132QA/QC- Quality Control ActivitiesList of NCR (Open)No.Ref No.Date receivedDescriptionRemarkStatus1P2/NCR/CRE/2029-Aug-12suitable material over unsuitable material C pondNo yet closeHOLD batching plantProjected to close on August 20142P2/NCR/CRE/2230-Aug-12suitable material over unsuitable material D pondNo yet closeHOLD sediment basinProjected to close on August 20143P2/NCR/RE/7310-Dec-13Anaerobic Digester Tank Slab - Finish concrete undulating, wall kicker surface smooth & not levelWMS123-r1 approvedHOLD scaffoldingProjected to close on May 20144P2/SMHB/NCR/14/00112-Feb-14Tower Crane Electrical InspectionWork in progressrectification in progressProjected to finish by this week33QA/QC- IFC Drawing (Statistic)No.Submitted byCategoryNo. Of DrawingDrawing Submitted To PMCDrawings Approved by PMC as IFCRev. 0Rev. ARev. BRev. CRev. DRev. ERev. FRev. GRev. H1EECTemporary Treatment Facilities41413742EXCEL CABINSite Office3333SMHBSite Office8884EECNew Temporary Sub Station33215EECGeotechnical4343118149000016EECEarthwork222215167EEC/SMHB/KWCAPUSAT MAKLUMAT5558EECPERMANENT PLANT (STRUCTURE)52552540994159SMHBPERMANENT PLANT (MECHANICAL)2672671387347610SMHBPERMANENT PLANT (ELECTRICAL)2622622556111SMHBPERMANENT PLANT - FIRE FIGHTING11117412SMHBPERMANENT PLANT - FIRE ALARM SYSTEM16161613SMHBPERMANENT PLANT (IRRIGATION22214SMHBPERMANENT PLANT (SCADA-CCTV-39393915EECPERMANENT PLANT (WATER SUPPLY)554116EECPERMANENT PLANT (SEWER 14141417EECPERMANENT PLANT (R&D)36363618EECTECHNICAL BUILDING545451319EECTNB SSU (ARCHITECTURE)885320EECTNB SSU (STRUCTURE)262622421SMHBTNB SSU (MECHANICAL)666QA/QC- IFC Drawing (Statistic)Update from RaziNo.Submitted byCategoryNo. Of DrawingDrawing Submitted To PMCDrawings Approved by PMC as IFCRev. 0Rev. ARev. BRev. CRev. DRev. ERev. FRev. GRev. H22SMHBTNB SSU (ELECTRICAL)55523EECCONSUMER 33Kv/11Kv SUBSTATION8824224EECCONSUMER 33Kv/11Kv SUBSTATION2121810325SMHBCONSUMER 33kV/11kV SUBSTATION44426SMHBCONSUMER 33kV/11kV SUBSTATION55527KWCAADMIN BUILDING (ARCHITECTURE)48483494128PTAADMIN BUILDING550529EECADMIN BUILDING (STRUCTURE)50502021930SMHBADMIN BUILDING (MECHANICAL)27277101031SMHBADMIN BUILDING (ELECTRICAL)232321232KWCACOMMUNITY CENTER 2828234133EECCOMMUNITY CENTER (STRUCTURE)484847134SMHBCOMMUNITY CENTER 14148635EECCHANGING ROOM (STRUCTURE)17171736SMHBCHANGING ROOM (MECHANICAL)66637EECGUARD HOUSE (ARCHITECTURE)22238EECGUARD HOUSE (STRUCTURE)88839SMHBGUARD HOUSE (MECHANICAL)55540EECREFUSE CHAMBER (STRUCTURE)11141EECSETTING OUT PLAN664242B&LTOWER CRANE11143CS RUNDINGSTORE FOR EQUIPMENT22244EECUPGRADING P1PS (MECHANICAL &)242423145EECUPGRADING P1PS (ELECTRICAL)121212TOTAL1766HEALTH, SAFETY & SECURITYHealth, Safety & SecuritySITE VISIT BY DBKLSafety & Health Walkabout on 01/04/2014

Site Inspection by Department of HealthHealth, Safety & SecurityHOUSE KEEPINGPreventive actions taken to prevent Dengue

Health, Safety & SecuritySAFETY AWARENESS & PROMOTIONSTalk by Department of Health Topic : Dengue Prevention Date : 17/04/2014 (Thursday)

Health, Safety & SecuritySAFETY AWARENESS & PROMOTIONS- Toolbox Talk

Health, Safety & SecuritySAFETY AWARENESS & PROMOTIONSTraining : Next Scheduled TrainingNOPROPOSED TRAINING / TALKPROPOSED DATE1TYPHOID VACCINATION PROGRAMME08/05/20142PLANNING & MANAGING OSH FOR CONSTRUCTION ACTIVITIES21 - 22/05/20143CIDB GREEN CARD COURSE24/05/2014Health, Safety & SecurityHEALTH & WELFARE Anti Viral Programme

Health, Safety & SecurityHEALTH & WELFARE Anti Viral Programme MONTH 2014 ACTIVITYWEEK1WEEK2WEEK3WEEK4WEEK5AREA JANUARYFOGGING05 Jan (P2)12 Jan (P1&WC)19 Jan (P2)26 Jan (P1&WC)04 Jan11 Jan19 Jan25 JanLARVACIDING07 Jan22 Jan07 Jan21 Jan FEBRUARYFOGGING02 Feb (P2)09 Feb (WC)16 Feb (P2)23 Feb (P1&WC)02 Feb09 Feb16 Feb23 FebLARVACIDING06 Feb 21 Feb 06 Feb21 Feb MARCHFOGGING02 Mar (P2)09 Mar (P1&WC)16 Mar (P2)23 Mar (P1&WC)24 Mar (P1, P2&WC)02 Mar09 Mar23 MarLARVACIDING06 Mar24 Mar06 Mar23 Mar APRILFOGGING06 Apr (P1&WC)11 Apr (P2)20 Apr (P1&WC)27 Apr (P2)06 Apr11 Apr20 Apr27 AprLARVACIDING11 Apr29 Apr11 AprScheduleActual - FoggingP1 & P2 STP Site Office, Workers Camp, Clarifier AreaP1 & P2 STP Site Office, Workers Camp, Clarifier AreaP1 & P2 STP Site Office, Workers Camp, Clarifier AreaP1 & P2 STP Site Office, Workers Camp, Clarifier AreaActual - LarvacidingHealth, Safety & SecurityHSSE STATISTIC Manhours StatisticCATEGORYMARCHCut off Date01 - 31/03/2014APRILCut off Date01 - 26/04/2014CUMMULATIVEACCIDENT 1 (08/03/2014)04LOST TIME INJURY (LTI)002(1st LTI - 14/06/2012)(2nd LTI 07/11/2013) MEDICAL TREATMENT CASES1 (08/03/2014)04FIRST AID CASES000PROPERTY / EQUIPMENT DAMAGE005DANGEROUS OCCURRENCE / NEAR MISS1 (08/03/2014)05TOTAL MANHOURS ACHIEVED SINCE LAST(LTI)328,110(1,374,900 until 31/03/2014)263,21001/04/2014 - 26/04/20141,638,11008/11/2013 26/04/2014TOTAL DAYS WORK31(144 days until 31/03/2014)2617008/11/2013 - 26/04/2014(511 days until 07/11/2013)(275 days until 14/06/2012)AVERAGE WORKER PER DAY1058101296408/11/2013 - 26/04/2014TOTAL MANHOURS ACHIEVED328,110263,2103,620,112until 26/04/2014(3,356,902 until 31/03/2014)TARGET 2,000,000 HOURS WITHOUT LTI** ON MAY 201444Health, Safety & SecurityHSSE STATISTIC CIDB RegisterCOMPANYTOTAL WORKERSWORKERS WITH CIDB%BEWG AND CONSULTANTS7777100BCEGI3096521LOYAL ENGINEERING51118336CSCEC481225VISI RAHMAT16425WARISAN HARMONI421331MEGAMIX11218NSA MAJU431535TOTAL WORKERS AS AT 26/04/2014105737135Health, Safety & SecurityHSSE STATISTIC Workers PopulationNATIONALITYMONTHMARCH (23/03/2014)APRIL (26/04/2014) MALAYSIAN143146 INDONESIAN223195 BANGLADESHI446384 VIETNAMESE2121 NEPALESE55 MYANMAR146144 PAKISTANI5050 INDIA66 CHINA106106 TOTAL11461057ENVIRONMENTALGeneral Layout Plan of Sampling Point

Environmental Components of MonitoringMonitoring ComponentRemarksAir Quality-TSPComplyOdourComplyNoise LevelSlightly higher than baselineVibration LevelComplyRiver Water QualityWater quality is within NWQS class IVTTF Effluent Comply, all parameters are within DOE Environmental Quality (Sewerage) Regulation 2009Groundwater QualityComply, all parameters are within DOE Environmental Quality (Sewerage) Regulation 2009Environmental- Odour Monitoring Result

Environmental- Noise & Vibration Monitoring Result

Mostly within EIA Approval Conditions: 60dB(A) during day time and 50 dB(A) during night time

Environmental- Effluent & Influent Monitoring Result

Environmental- Effluent & Influent Monitoring Result

EnvironmentalGround Water Monitoring Result

Environmental- River Quality Monitoring Result

COMMUNICATION ACTIVITIES

NoEvent1Project Documentation Log Sheet2Yasin & Tahlil Recital with PPR Sri Cempaka3University of Malaya (Quantity Surveying) Visit to P2STP

4Gotong Royong Activity with PPR Kg.Limau3Complaint Handling Log Sheet

4Buku Ilmiah 5Future Activities6Construction (Site Overview Pictures)Communication Plan - ActivitiesCommunication Plan - Project Documentation Log Sheet

April 2014NoShooting DateLocation / VenueEvent / Description125.04.2014

On SiteEstablish site from PPR230.04.2014

On SiteEstablish site from PPR

ItemActivities DetailsCategoryCommunity EngagementDate3rd April 2014Time7.30 pm 9.30 pmLocationSurau PPR Sri CempakaCommunication Plan - Yassin & Tahlil Recital with PPR Sri Cempaka

ItemActivities DetailsCategoryProject BriefingDate16th April 2014Time10.00 am - 12.30 pmLocationP2STP SiteCommunication Plan - University of Malaya(Quantity Surveying) Student Visit to P2STP

ItemActivities DetailsCategoryCommunity EngagementDate20th April 2014Time8.00 am - 1.00 pmLocationPPR Kg.LimauCommunication Plan - Gotong Royong Activity with PPR Kg.Limau

Communication Plan - Activities (March 2014 Complaint Handling Log Sheet)

April 2014No. Date of Complaints / Feedback ReceivedName & Address of ComplainantComplaint MattersAction TakenRemarks

No Complaint

--

--Communication Plan - Activities 6 month (Sept 2013 March 2014) Complaint handling Log SheetCommunication Plan- Buku Ilmiah Table of ContentChapter No & TitleReport Contributors1Project BackgroundEEC2Project PlanningBEWG, ASMA3Regulatory FrameworkPMC4Tender & Award of ContractsBEWG, PMC, PNFL5Preliminary EngineeringBEWG6Detailed DesignEEC, BEWG, SMHB, KWCA, PTA, HSSE7ConstructionBEWG, ASMA8Testing, Commissioning & Proving TestBEWG9Transfer of TechnologyBEWG10Project ControlsBEWG11Operation & MaintenanceBEWG12Communications ManagementSK13Challenges & Lessons LearnedALL14Appendices Milestone Dates & Progress PhotographsBEWGCommunication Plan-Buku Ilmiah ( Work schedule )Work scheduleTimelineContent CollectionJan - Jun 20141st DraftJul - Aug 20141st RevisionSep - Oct 2014Editing & RewritingNov - Jan 2015GraphicsFeb - Mar 2015Final Client ReviewApr - May 2015Printing & DistributionJun - Jul 2015- Buku Ilmiah ( Content Collection status for Feb & Mar14 )Chapter No & TitleReportContributorsCollection Status 6. Detailed Design6.7.1 Architecture( Design Intentions & Constraints, Design Proposals, Selection of Building Materials & Color Scheme )KWCA 6.7.2 Landscape( Design Criteria & Need Statement, Site / Earth work, Soft Scaping, Water Features, landscaping )PTA3. Regulatory Framework3.1 Implementation Structure3.2 Implementing Agency3.3 Regulatory ApprovalsPMCApril*TBC To be confirmed

Communication Plan - Future Activities NoActivitiesEventLocationDate1Project DocumentationVideo recording for DocumentaryP2STPFebruary 2014 till completion2Project DocumentationBuku Ilmiah CompilationP2STPFebruary 2014 till completion4Project BriefingTechnical Visit from Master Builders Association MalaysiaP2STP20.05.2014

5Project BriefingVisit from Universiti Kebangsaaan Malaysia (Faculty of Civil Engineering)P2STP24.05.20145Community EngagementYassin & Tahlil Recital with PPR Pantai Ria Surau PPR Pantai RiaMay 20146Media Crisis Management WorkshopMedia training for selected representatives from JPP, PMC & BEWG.*TBC7 & 8 May 2014Or 28 & 29 May 2014Construction- Site Overview

MARCH 2014

APRIL 2014Construction- Site Overview

MARCH 2014

APRIL 2014Thank YouTerima KasihFor more information about the Project, please visit our website @www.pantai2stp.com.my

Construction of Pantai 2 Sewage Treatment PlantFederal Territory of Kuala Lumpur (Design & Build)Dibentangkan oleh KI-MECIP JVMonthly Site Progress Meeting no. 24 28 April 2014Kementerian Tenaga, Teknologi Hijau dan AirJabatan Perkhidmatan Pembetungan

7172No.Matters of ConcernResponse by BEWG1.CPM delay of 58 days as of 20-04-2014. BEWG to reduce CPM delay about 4 to 5 days per month in order to achieve CSC-1 on 27-07-2015BEWG has reduced the delay by 6 days from 64 days on 23 March 2014 to 58 days on 20 April 2014.2.To display 2014 Revised Cashflow Chart at P2STP Conference RoomRevised Cashflow has been discussed on 25 April 2014.Revised Cashflow chart is displayed at P2STP Conference Room3.Shortage of water for concrete productionBEWG using the Balancing Tank A to store the water for concrete production4.TNB-SSU; Official taking over letter from TNB

Accepted by TNB on 7 March 201473No.Matters of ConcernResponse by BEWG5Pantai 1 Pump Station Upgrading Works to be completed by 30th April 2014Penstocks, mechanical screens and gate valves installation will be completed on 30 April 2014Pump will be installed after IWK clean the wet wellElectrical works by December 20146.Master Work Program; BEWG to expand WBS activities for M&E installation workAs per discussed, on 25 April 2014Work been separated to Zone A & Zone B which the commissioning for Zone A on 27 Jan 2015Q & A Session