LAPORAN KEMAJUAN MINGGUAN BIL.104
CADANGAN MENAIKTARAF DAN MEMBAIKPULIH BANGUNAN PARLIMEN MALAYSIA FASA 3B
C A W A N G A N K E R J A B A N G U N A N A M , I B U P E J A B A T J K R M A L A Y S I A
1
CADANGAN MENAIKTARAF DAN MEMBAIKPULIH BANGUNAN PARLIMEN FASA 3B
MAKLUMAT PROJEK
LOKASI : Tapak Parlimen, Kuala Lumpur KOMPONEN PROJEK :
• Blok Ahli Parlimen (MP)
• Dewan Serbaguna
• Link Bridge
• Gelanggang Tenis
• Pembesaran Pondok Pengawal
• Kerja-kerja Luar ➢ Service tunnel, Pintu & Pagar Berhias, Tapak Semaian & Pangkin Nurser, Jalan & Perparitan ➢ Pengalihan utiliti ➢ Force Main & Pump House
KOS PROJEK : RM 200,700,000.00 (ATDA)
KOS KONTRAK ASAL : RM 181,578,000.00
KOS KONTRAK SEMASA : RM 181,726,675.28
KAEDAH PELAKSANAAN : Konvensional JKR
KAEDAH PEROLEHAN : Tender Terbuka
KONTRAKTOR UTAMA : DKLS Construction Sdn Bhd
TEMPOH PEMBINAAN : 39 Bulan
TARIKH MILIK TAPAK : 28 September 2015
TARIKH SIAP ASAL : 27 Disember 2018
LANJUTAN MASA : TIADA
KEMAJUAN KERJA KESELURUHAN SEHINGGA 14 DISEMBER 2017*
KEMAJUAN % JADUAL % SEBENAR BEZA Hari Awal (+) /
Lewat (-)
FIZIKAL 23.0 26.0 3.0 +5
KEWANGAN 54,520,500
(30.0%) 51,549,637 (28.37%)
-2,970,863 (-1.63%)
(Berdasarkan Rujukan SKALA pada 14 Disember 2017 : 18 Hari Lewat)
STATUS KEWANGAN BERAKHIR 16 NOVEMBER 2017
Bayaran kepada Kontraktor RM 47,355,500.00 (26.0%)
Wang Jaminan Pelaksanaan : Belum Dilepaskan Wang Pendahuluan : RM 10,000,000.00
Bayaran Balik Wang Pendahuluan (Recoupment) : RM 4,194,108.04 Liquidated & Ascertained Damages (LAD) : RM 34,137.00 / hari
*Berdasarkan Recovery CPM Terkini (14/12/2017)
LAPORAN KEMAJUAN MINGGUAN BIL.104
CADANGAN MENAIKTARAF DAN MEMBAIKPULIH BANGUNAN PARLIMEN MALAYSIA FASA 3B
C A W A N G A N K E R J A B A N G U N A N A M , I B U P E J A B A T J K R M A L A Y S I A
2
KEMAJUAN KERJA SEMASA DI TAPAK SEHINGGA 14 DISEMBER 2017
ITEM WEIGHTAGE % PLANNING % ACTUAL %BEZA SEBAB-SEBAB KELEWATAN
PRELIMINARIES 5.66% 69.0 69.0 0
PILING WORKS 9.02% 100 100 0
BUILDING WORKS & INFRA STRUCTURE (36.67%)
BESMEN 3.57% 58.0 64.0 +6.0
BLOK MP 30.11% 30 39 +9.0
LINK BRIDGE 0.56% 0 0 0
DEWAN SERBAGUNA 2.15% 23.0 19.0 -4.0
TAPAK SEMAIAN 0.12% 32.0 32.0 0
TEMPAT LETAK BAS BERBUMBUNG
0.16% 0 0 0
INTERNAL SERVICES (PC SUMS) (32.98%)
Mechanical Works
AC System (PC Sums) 7.43% 2.0 2.0 0
Fire Fighting (PC Sums) 1.55% 3.0 2.0 -1.0
Lift System (PC Sums) 1.24% 0 0 0
BAS (PC Sums) 1.24% 0 0 0
Kitchen Equipments (PC Sums) 0.25% 5.0 0 -5.0
Electrical Works
Electrical Installation (PC Sums) 10.09% 8.0 7.0 -1.0
ELV (PC Sums) 8.29% 7.0 5.0 -2.0
ICT (PC Sums) 2.91% 14.0 7.0 -7.0
EXTERNAL WORKS (5.14%)
Site Preparation & Earthworks 0.57% 100 100 0
SI & Geotechnical I&M 0.19% 100 100 0
Roadworks 0.09% 0 0 0
Surface Water Drainage 0.82% 0 0 0
Permanent Water Reticulation 0.06% 0 0 0
Temporary Water Reticulation 0.12% 100 100 0
Sewerage 0.28% 24.0 24.0 0
Turfing 0.06% 0 0 0
Fencing & Gates 0.23% 0 0 0
Infra Works for Electrical 0.05% 0 0 0
Terowong Utiliti 0.08% 100 100 0
LAPORAN KEMAJUAN MINGGUAN BIL.104
CADANGAN MENAIKTARAF DAN MEMBAIKPULIH BANGUNAN PARLIMEN MALAYSIA FASA 3B
C A W A N G A N K E R J A B A N G U N A N A M , I B U P E J A B A T J K R M A L A Y S I A
3
KEMAJUAN KERJA SEMASA DI TAPAK SEHINGGA 14 DISEMBER 2017
ITEM WEIGHTAGE % PLANNING % ACTUAL %BEZA SEBAB-SEBAB KELEWATAN
RE Wall System 1.86% 90.0 90.0 0
Trench for Mechanical Pipes 0.09% 0 0 0
External Staircases 0.01% 0 0 0
OTHERS (10.53%)
Gelanggang Tenis G1 0.12% 0 0 0
Pondok Pengawal G2 0.19% 0 0 0
Built-in Furnitures 0.88% 0 0 0
Loose Furnitures 0.58% 0 0 0
Office Furnitures 1.46% 0 0 0
Landschapping Works 0.29% 0 0 0
Interior Design 2.04% 0 0 0
Acoustic Works 0.35% 0 0 0
Forensic Works 0.15% 100 100 0
Equipment at Gymnasium 0.09% 0 0 0
Equipment at Sauna Room 0.09% 0 0 0
Signages 0.26% 0 0 0
Energy Efficiency 0.23% 100 100 0
Rainwater Harvesting System 0.12% 0 0 0
Pump House & Force Main 1.75% 0 0 0
OSD Pond 1.17% 25.0 30.0 +5.0
Relocation of Services & Utility 0.18% 100 100 0
BWIC 0.58%
KESELURUHAN 100.00% 23.0% 26.0% +3.0%
LAPORAN KEMAJUAN MINGGUAN BIL.104
CADANGAN MENAIKTARAF DAN MEMBAIKPULIH BANGUNAN PARLIMEN MALAYSIA FASA 3B
C A W A N G A N K E R J A B A N G U N A N A M , I B U P E J A B A T J K R M A L A Y S I A
4
AKTIVITI SEMASA DI TAPAK
1. BlOK MP
• Kerja Struktur - Pembinaan Tangga 4 Aras 4, Tangga 1 Aras 4, Tangga 6 Aras 4, Tangga 5 Aras 4 - Pemasangan Hollow Core Slab Aras 3 dan Aras 4 - Topping Aras 3 - Pemasangan Steel Column & Beam Aras 3 & Aras 4 - Pemasangan Besi untuk rasuk Aras Bumbung - Pemasangan firecut Aras 2
• Kerja Arkitek - Brickwork Aras 1 - Pemasangan Door Frame Aras 2 - Floor rendering utk sample mockup Aras 1
• Kerja Mekanikal - Pemasangan Internal sanitary fitting di Aras 2 dan Aras 3 - Pemasangan fire fighting pipe Aras Basemen, Aras Tanah dan Aras 1
• Kerja Elektrikal - Pemasangan cable tray dan conduit Aras Basement, Aras Tanah, Aras 1, Aras 2, Aras 3
2. BLOK DEWAN SERBAGUNA
• Kerja Struktur – Pemasangan formwork & steel reinforcement untuk rasuk bumbung. 3. OSD No. 2
• Pemasangan heavy duty module
• Kerja konkrit outlet sump
• Pemasangan outlet culvert 4. RE Retaining Wall
• Kerja tanah di CH 280 – CH 326
LAPORAN KEMAJUAN MINGGUAN BIL.104
CADANGAN MENAIKTARAF DAN MEMBAIKPULIH BANGUNAN PARLIMEN MALAYSIA FASA 3B
C A W A N G A N K E R J A B A N G U N A N A M , I B U P E J A B A T J K R M A L A Y S I A
5
ISU-ISU/MASALAH SEMASA
1. LINK-BRIDGE
• Kerja-kerja tertangguh kerana memberi ruang untuk sesi dewan bersidang sehingga pertengahan bulan Disember 2017 kerana turut melibatkan kawasan Dewan Parlimen sediada. Kerja-kerja dijangka akan dimulakan pada bulan Januari 2018.
2. CENTRALIZED SEWERAGE SYSTEM (FORCE MAIN & RUMAH PAM)
• Kelulusan PDC 2 bagi rumah pam belum diperolehi.
3. PERUBAHAN SAIZ DAN SUSUNATUR BILIK MP
• Berdasarkan Mesyuarat Jawatankuasa Dewan yang diadakan pada 1 November 2017, mesyuarat bersetuju dengan perubahan saiz bilik 8m x 6m. Oleh yang demikian semua HODT sedang dalam proses membuat rekabentuk pindaan berdasarkan saiz bilik yang telah diputuskan.
4. BLOK MP – Concrete Gutter
• Lukisan pindaan masih belum dimuktamadkan kerana perubahan rekabentuk concrete gutter yang dikemukakan perlu ditambahbaik.