Lx = 630 cm Mutu Beton 300Ly = 445 cm f'c = 249 kg/cm2Ho = 405 cm 24.9 MpaH = 335 cm E = 23452.95290576 MPaq atap = 112 kg/m2 Fy (Baja Ulir) 400 Mpaq lantai = 295 kg/m2 Fy (Sengkang) 240 Mpa

Tebal Plat = 19.09091 cm= 0.2 m

Perhitungan Beban

Perhitungan Beban Mati Perhitungan Beban Hidup

Lantai 1 -9 Lantai 1-9

Berat Plat = 24 kN/m3 Beban accupa 2.95 kN/m2Beban Partisi = 2.5 kN/m2 Berat Tiap La 82.70325 kNBerat screed+kerami 1.6 kN/m2 Berat Tiap Lan 1240.54875 kNBerat Tiap Lantai ( 269.4553 kN

Plat = 134.568 kNPartisi = 90.03125 kNLain-Lain = 44.856 kN

Berat Tiap Lantai = 4041.829 kN/m2

Lantai 10 Lantai 10Berat Plat = 24 kN/m3 Beban accupa 1.12 kN/m2Berat plafond, elekt 0.5 kN/m2 Berat Atap (1 31.3992 kNBerat Atap (1 segm 148.5855 kN Berat Atap = 470.988 kN

Plat = 134.568 kNLain-Lain = 14.0175 kN

Berat Tiap Lantai = 2228.783 kN

Dimensi Balok dan Kolom

Penentuan Balok Penentuan KolomTinggi Balok = 45 - 52.5 cm Luas Kolom = 5795.96361Ukuran Balok = 40 x 50 Ukuran Kolom = 76.1312263

= 80

1kN = 100 kg

cm2cm

x 80

Perhitungan Beban Gempa

Berat Lantai 1 Berat Lantai 10Berat Balok = 989.28 kN Berat Balok 989.28 kN

Arah X = 604.8 kN Arah X = 604.8Arah Y = 384.48 kN Arah Y = 384.48

Berat Kolom = 2110.464 kN Berat Kolo 617.472 kNBerat Lantai = 4413.993 kN Berat Lanta2370.079 kN

Berat Lantai 2-9 Berat StrukturBerat Balok = 989.28 kN Lantai 1 = 7513.737 kN

Arah X = 604.8 kN Lantai 2-9 6638.217 kNArah Y = 384.48 kN Lantai 10 = 3976.831 kN

Berat Kolom = 1234.944 kNBerat Lantai = 4413.993 kN

Wilayah Gempa Palembang adalah zona 2Gedung di gunakan untuk perkantoranTanah LunakPercepatan Puncak di batuan Dasar = 0.1 gPercepatan Puncak Muka Tanah (Ao)= 0.2 gn = 10I = 1R = 8.5Am = 0.5ζ = 0.19Tc = 1 detik

Utara-SelatanT = 1.119462 detik (ASCE 7-10, 12.8-7)

T1 = 1.9 detikT yang dipakai = 1 detikAr = 0.5Cus = 0.446643

Timur-BaratT = 1.119462 detik (ASCE 7-10, 12.8-7)

T1 = 1.9 detikT yang dipakai = 1 detikAr = 0.5Ctb = 0.446643

Base ShearVus = 3394.293 kNVtb = 3394.293 kN

Gaya Lateral

Utara-Selatan Timur-BaratF1 = 87.37989 kN F1 = 87.37989 kNF2 = 141.0534 kN F2 = 141.0534 kNF3 = 204.9087 kN F3 = 204.9087 kNF4 = 268.764 kN F4 = 268.764 kNF5 = 332.6192 kN F5 = 332.6192 kNF6 = 396.4745 kN F6 = 396.4745 kNF7 = 460.3298 kN F7 = 460.3298 kNF8 = 524.185 kN F8 = 524.185 kNF9 = 588.0403 kN F9 = 588.0403 kNF10 = 390.5384 kN F10 = 390.5384 kN

ΣH / Lus = 2.561798 >>>>> tidak perlu ada beban horizontal terpusat sebesar 0,1 Vb di lantai tingkat paling atas (Kurang dari 3).

ΣH / Ltb = 0.904762 >>>>> tidak perlu ada beban horizontal terpusat sebesar 0,1 Vb di lantai tingkat paling atas (Kurang dari 3).

Gaya tiap jointUtara-Selatan ARAH Y Timur-Barat ARAH XF1 = 14.56332 kN F1 = 21.84497 kNF2 = 23.50891 kN F2 = 35.26336 kNF3 = 34.15145 kN F3 = 51.22717 kNF4 = 44.79399 kN F4 = 67.19099 kNF5 = 55.43654 kN F5 = 83.15481 kNF6 = 66.07908 kN F6 = 99.11863 kNF7 = 76.72163 kN F7 = 115.0824 kNF8 = 87.36417 kN F8 = 131.0463 kNF9 = 98.00672 kN F9 = 147.0101 kNF10 = 65.08973 kN F10 = 97.63459 kN

Berat Struktur per LantaiLantai Tinggi (m) Berat Lantai (kN) Wx.Hx

10 34.2 3976.8309 136007.69 30.85 6638.217375 204789

kN 8 27.5 6638.217375 182551kN 7 24.15 6638.217375 160312.9

6 20.8 6638.217375 138074.95 17.45 6638.217375 115836.94 14.1 6638.217375 93598.863 10.75 6638.217375 71360.842 7.4 6638.217375 49122.811 4.05 7513.737375 30430.64

Σ 64596.307275 1182086

tidak perlu ada beban horizontal terpusat sebesar 0,1 Vb di lantai tingkat paling atas (Kurang dari 3).

tidak perlu ada beban horizontal terpusat sebesar 0,1 Vb di lantai tingkat paling atas (Kurang dari 3).

Beban Mati Beban Hidup

Lantai 1-9 Lantai 1-9Beban Plat = 4.8 kN/m2 Beban accupancy 2.95Beban Partisi = 2.5 kN/m2 Total Beban = 2.95Berat screed+kera 1.6 kN/m2Beban q = 2.95 kN/m2Total Beban = 11.85 kN/m2

Lantai 10 Lantai 10Beban Plat = 4.8 kN/m2 Beban accupancy 1.12Berat plafond, ele 0.5 kN/m2 Total Beban = 1.12Beban q = 1.12 kN/m2Total Beban = 6.42 kN/m2

Beban Mati Beban HidupPinggir Tengah Pinggir Tengah

Lantai 1-9 37.3275 74.655 9.2925 18.585Lantai 10 20.223 40.446 3.528 7.056

Beban Hidup

kN/m2kN/m2

kN/m2kN/m2