warta kerajaan persekutuan - energy commission...p.u. (a) 321 13 (3) the fee payable for processing...
TRANSCRIPT
2 Disember 2014 2 December 2014
P.U. (A) 321
WARTA KERAJAAN PERSEKUTUAN
FEDERAL GOVERNMENT GAZETTE
PERATURAN-PERATURAN BEKALAN GAS (PINDAAN) 2014
GAS SUPPLY (AMENDMENT) REGULATIONS 2014
DISIARKAN OLEH/ PUBLISHED BY
JABATAN PEGUAM NEGARA/ ATTORNEY GENERAL’S CHAMBERS
P.U. (A) 321
2
AKTA BEKALAN GAS 1993
PERATURAN-PERATURAN BEKALAN GAS (PINDAAN) 2014 PADA menjalankan kuasa yang diberikan oleh seksyen 39 Akta Bekalan Gas 1993 [Akta 501],
Menteri membuat peraturan-peraturan yang berikut:
Nama dan permulaan kuat kuasa
1. (1) Peraturan-peraturan ini bolehlah dinamakan Peraturan-Peraturan
Bekalan Gas (Pindaan) 2014.
(2) Peraturan-Peraturan ini mula berkuat kuasa pada 1 Januari 2016.
Pindaan am
2. Peraturan-Peraturan Bekalan Gas 1997 [P.U. (A) 287/1997], yang disebut
"Peraturan-Peraturan ibu" dalam Peraturan–Peraturan ini, dipinda—
(a) dengan menggantikan perkataan “Ketua Pengarah” di mana-mana jua
terdapat dengan perkataan “Suruhanjaya”; dan
(b) dalam teks bahasa kebangsaan, dengan menggantikan perkataan “fee”
di mana-mana jua terdapat dengan perkataan “fi”.
Pindaan peraturan 15
3. Peraturan 15 Peraturan-Peraturan ibu dipinda—
(a) dalam subperaturan (1), dengan menggantikan perkataan “pada” dengan
perkataan “pada mana-mana”;
(b) dalam subperaturan (1), dengan menggantikan perkataan “atau
sambungan gas” dengan perkataan “, pepasangan gas tambahan atau
sambungan pepasangan gas”; dan
P.U. (A) 321
3
(c) dengan memasukkan selepas subperaturan (3) subperaturan yang
berikut:
“(4) Semua terma dan syarat kelulusan untuk memasang hendaklah
dipatuhi oleh—
(a) pemunya pepasangan itu;
(b) orang kompeten yang dilantik untuk memberi nasihat
mengenai kerja pada pepasangan itu, setakat skop kerjanya;
dan
(c) Kontraktor Gas yang berdaftar dengan Suruhanjaya, yang
menjalankan kerja-kerja pada pepasangan,
seperti yang terkandung dalam suatu kelulusan untuk memasang yang
dikeluarkan oleh Suruhanjaya menurut subperaturan (3).
(5) Fi yang kena dibayar untuk memproses permohonan dan
pengeluaran kelulusan untuk memasang adalah sebagaimana yang
ditetapkan dalam Bahagian I Jadual Ketiga.”.
Pindaan peraturan 16
4. Peraturan 16 Peraturan-Peraturan ibu dipinda—
(a) dengan menomborkan semula peraturan 16 sebagai subperaturan 16(1);
(b) dalam subperaturan (1), dengan memasukkan selepas perkataan
“pepasangan gas” perkataan “, pepasangan gas tambahan atau sambungan
pepasangan gas”; dan
(c) dengan memasukkan selepas subperaturan (1) subperaturan yang
berikut:
P.U. (A) 321
4
“(2) Suruhanjaya boleh meluluskan permohonan itu jika ia berpuas hati
bahawa pemohon itu telah memenuhi kehendak Peraturan-Peraturan ini
dan seterusnya mengeluarkan kelulusan untuk mengendali,
yang mengandungi apa-apa terma dan syarat yang difikirkan patut oleh
Suruhanjaya.
(3) Fi yang kena dibayar untuk memproses permohonan dan
pengeluaran kelulusan untuk mengendali adalah sebagaimana yang
ditetapkan dalam Bahagian I Jadual Ketiga.”.
Pindaan peraturan 94
5. Peraturan 94 Peraturan-Peraturan ibu dipinda dengan menggantikan perkataan
“Fee” dengan perkataan “Fi bagi memproses permohonan untuk peperiksaan dan fi”.
Peraturan baru 114A
6. Peraturan-Peraturan ibu dipinda dengan memasukkan selepas peraturan 114
peraturan yang berikut:
114A. (1) Jika Perakuan Pendaftaran Kontraktor Gas yang
dikeluarkan oleh Suruhanjaya hilang, dicuri, termusnah,
lusuh, atau rosak, suatu Perakuan gantian boleh dikeluarkan
oleh Suruhanjaya apabila suatu akuan berkanun bahawa
salinan asal Perakuan tersebut telah hilang, dicuri ataupun
termusnah dikemukakan oleh pemegang atau apabila salinan
asal Perakuan yang lusuh atau rosak itu diserah balik.
(2) Fi bagi perakuan gantian yang dikeluarkan di bawah
subperaturan (1) adalah sebagaimana yang ditetapkan dalam
Bahagian II Jadual Ketiga.”.
“Penggantian
Perakuan
Pendaftaran
Kontraktor
Gas.
P.U. (A) 321
5
Pindaan peraturan 118
7. Peraturan 118 Peraturan-Peraturan ibu dipinda—
(a) dengan menomborkan semula peraturan 118 sebagai subperaturan
118(1); dan
(b) dengan memasukkan selepas subperaturan (1) subperaturan yang
berikut:
“(2) Jika Perakuan Kelulusan yang dikeluarkan oleh Suruhanjaya hilang,
dicuri, termusnah, lusuh, atau rosak, suatu Perakuan gantian boleh
dikeluarkan oleh Suruhanjaya apabila suatu akuan berkanun bahawa
salinan asal Perakuan telah hilang, dicuri atau termusnah dikemukakan oleh
pemegang ataupun apabila salinan asal Perakuan yang lusuh atau rosak itu
diserah balik.
(3) Fi bagi perakuan gantian yang dikeluarkan di bawah subperaturan
(2) adalah sebagaimana yang ditetapkan dalam Bahagian II Jadual Ketiga.”.
Pindaan Jadual Ketiga
8. Peraturan-Peraturan ibu dipinda dengan menggantikan Jadual Ketiga dengan
Jadual yang berikut:
P.U. (A) 321
6
“JADUAL KETIGA
(Peraturan 6, 9, Subperaturan 15(5) dan 16(3), Peraturan 24, Subperaturan 88(2) dan 89(2), Peraturan 94, Perenggan 100(e), Subperaturan 101(1) dan 102(2), Peraturan 111, Subperaturan 114A(2), 115(6), 118(1) dan 118(3)).
KERAJAN MALAYSIA
AKTA BEKALAN GAS 1993
FI
BAHAGIAN I
1. Fi bagi lesen penggunaan gas (Peraturan 6)
Fi hendaklah berdasarkan isipadu gas yang dibekalkan dalam MMBTU, mengikut
rekod tahun sebelumnya. Fi yang dikenakan ialah 1.1 sen/MMBTU.
(MMBTU = Million British Thermal Unit)
2. Fi bagi lesen gas persendirian (Peraturan 9)
Fi hendaklah berdasarkan kelas pepasangan gas seperti yang berikut:
RM setahun
(a) Pepasangan gas Kelas I 300.00
(b) Pepasangan gas Kelas II 200.00
(c) Pepasangan gas Kelas III 100.00
3. Fi bagi kelulusan untuk memasang dan kelulusan untuk mengendali pepasangan gas
(Subperaturan 15(5) dan 16(3))
RM/Perakuan
(a) Memproses dan mengeluarkan kelulusan untuk memasang 200.00
(b) Memproses dan mengeluarkan kelulusan untuk mengendali 100.00
P.U. (A) 321
7
4. Fi bagi pemeriksaan dan ujian pepasangan (Peraturan 24)
(a) Pemeriksaan RM
i. Pepasangan gas Kelas I 300.00
ii. Pepasangan gas Kelas II 200.00
iii. Pepasangan gas Kelas III 100.00
iv. Pepasangan gas tambahan 100.00
(b) Ujian kebocoran
i. Pepasangan gas Kelas I 300.00
ii. Pepasangan gas Kelas II 200.00
iii. Pepasangan gas Kelas III 100.00
iv. Pepasangan gas tambahan 100.00
(c) Ujian Holiday 100.00
BAHAGIAN II
1. Fi bagi Perakuan Kekompetenan gantian (Subperaturan 88(2))
RM
(a) Jurutera Gas 150.00
(b) Penyelia Kejuruteraan Gas 100.00
(c) Jurugegas Gas 50.00
2. Fi bagi pendaftaran dan pembaharuan pendaftaran bagi orang kompeten
(Subperaturan 89(2))
RM setahun
(a) Jurutera Gas 150.00
(b) Penyelia Kejuruteraan Gas 100.00
(c) Jurugegas Gas 50.00
P.U. (A) 321
8
3. Fi bagi peperiksaan (Peraturan 94)
RM
(a) Fi pemprosesan peperiksaan 20.00
(b) Peperiksaan bagi Perakuan Kekompetenan sebagai
Jurutera Gas
150.00
(c) Peperiksaan bagi Perakuan Kekompetenan sebagai
Penyelia Kejuruteraan Gas
100.00
(d) Peperiksaan bagi Perakuan Kekompetenan sebagai
Jurugegas Gas
50.00
4. Fi bagi memotong suatu sekatan dan pengendorsan suatu Perakuan Kekompetenan
(Perenggan 100(e))
RM
(a) Jurutera Gas 150.00
(b) Penyelia Kejuruteraan Gas 100.00
(c) Jurugegas Gas 50.00
5. Fi bagi Perakuan Kekompetenan sementara bagi orang asing (Subperaturan 101(1))
RM setahun
(a) Jurutera Gas 150.00
(b) Penyelia Kejuruteraan Gas 100.00
(c) Jurugegas Gas 50.00
6. Fi bagi pengendorsan Perakuan Kekompetenan yang setaraf (Subperaturan 102(2))
RM
(a) Jurutera Gas 150.00
(b) Penyelia Kejuruteraan Gas 100.00
(c) Jurugegas Gas 50.00
P.U. (A) 321
9
7. Fi bagi Perakuan Pendaftaran sebagai Kontraktor Gas (Peraturan 111 dan
Subperaturan 115(6))
Fi pengeluaran
RM
Fi pembaharuan setahun
RM (a) Kelas A 3000.00 2000.00
(b) Kelas B 2000.00 1000.00
(c) Kelas C 1000.00 700.00
(d) Kelas D 500.00 300.00
8. 8. Fi bagi pengeluaran dan pembaharuan Perakuan Kelulusan untuk
mengilang, memasang atau mengimport gegasan gas, perkakas gas atau
kelengkapan gas (Subperaturan 118(1))
Fi pengeluaran RM
Fi pembaharuan setahun
RM (a) Pengilang/Pemasang
500.00 250.00
(b) Pengimport 800.00 400.00
9. Fi bagi pengeluaran dan pembaharuan Perakuan Kelulusan bagi penjualan atau
penggunaan mana-mana gegasan gas, kelengkapan gas atau perkakas gas
(Subperaturan 118(1))
Fi pengeluaran
RM
Fi pembaharuan
setahun
RM
(a) Gegasan gas 100.00 100.00
(b) Kelengkapan gas 200.00 200.00
(c) Perkakas gas 110.00 110.00
1 10. Fi bagi perakuan gantian selain daripada perakuan kekompetenan
(Subperaturan 114A (2) dan subperaturan 118(3))
RM
(a) Pendaftaran Kontraktor Gas 35.00
(b) Perakuan Kelulusan 35.00
P.U. (A) 321
10
Dibuat 17 November 2014 [UPE(S)25/16/68 Sj 1 Jld.5; PN(PU2)528/II]
DATO’ SRI MOHD. NAJIB BIN TUN HAJI ABDUL RAZAK Perdana Menteri
P.U. (A) 321
11
GAS SUPPLY ACT 1993
GAS SUPPLY (AMENDMENT) REGULATIONS 2014 IN exercise of the powers conferred by section 39 of the Gas Supply Act 1993 [Act 501],
the Minister makes the following regulations:
Citation and commencement
1. (1) These regulations may be cited as the Gas Supply (Amendment)
Regulations 2014.
(2) These Regulations come into operation on 1 January 2016.
General Amendment
2. The Gas Supply Regulations 1997 [P.U. (A) 287/1997], which are referred to as
the “principal Regulations” in these Regulations, are amended—
(a) by substituting for the words “Director General” the words “the
Commission”, wherever appearing; and
(b) in the national language text, by substituting for the word “fee” the word
“fi”, wherever appearing.
Amendment of regulation 15
3. Regulation 15 of the principal Regulations is amended─
(a) in subregulation (1), by substituting for the word “a” before the word
“new” the word “any”;
(b) in subregulation (1), by substituting for the words “or gas extension” the
words “, additional gas installation or extension of gas installation”; and
P.U. (A) 321
12
(c) by inserting after subregulation (3) the following subregulations:
“(4) All the terms and conditions of the approval to install shall be
complied with by—
(a) the owner of the installation;
(b) the competent person engaged to advice on the work on the
installation, to the extent of his scope of work; and
(c) the Gas Contractor registered with the Commission, carrying
out the work on the installation,
as contained in an approval to install issued by the Commission pursuant to
subregulation (3).
(5) The fee payable for processing the application for and the issuance of
the approval to install is as prescribed in Part I of the Third Schedule.”.
Amendment of Regulation 16
4. Regulation 16 of the principal Regulations is amended—
(a) by renumbering regulation 16 as subregulation 16(1);
(b) in subregulation (1), by inserting after the word “installation” the words “,
additional gas installation or extension of gas installation”; and
(c) by inserting after subregulation (1) the following subregulations:
“(2) The Commission may approve the application if it is satisfied that
the applicant has fulfilled the requirements of these Regulations and
subsequently issue an approval to operate, containing such terms and
conditions as it deems fit.
P.U. (A) 321
13
(3) The fee payable for processing the application for and the issuance of
the approval to operate is as prescribed in Part I of the Third Schedule.”.
Amendment of Regulation 94
5. Regulation 94 of the principal Regulations is amended by substituting for the
word “The” the words “The processing fee for an application for examination and the”.
New Regulation 114A
6. The principal Regulations are amended by inserting after regulation 114 the
following regulation:
114A. (1) If a Certificate of Registration of a Gas Contractor
issued by the Commission is lost, stolen, destroyed, mutilated,
or defaced, a replacement of the Certificate may be issued by
the Commission on production of a statutory declaration by
the holder that the original Certificate has been lost, stolen or
destroyed or upon surrender of the mutilated or defaced
original Certificate.
(2) The fee for the replacement certificate issued under
subregulation (1) is as prescribed in Part II of the Third
Schedule.”.
Amendment of Regulation 118
7. Regulation 118 of the principal Regulations is amended—
(a) by renumbering regulation 118 as subregulation 118(1); and
(b) by inserting after subregulation (1) the following subregulations:
“(2) If a Certificate of Approval issued by the Commission is lost, stolen,
destroyed, mutilated, or defaced, a replacement of the Certificate may be
“Replacement of
Certificate of
Registration of
Gas Contractor.
P.U. (A) 321
14
issued by the Commission on production of a statutory declaration by the
holder that the original Certificate has been lost, stolen or destroyed or
upon surrender of the mutilated or defaced original Certificate.
(3) The fee for the replacement certificate issued under subregulation
(2) is as prescribed in Part II of the Third Schedule.”.
Amendment of the Third Schedule
8. The principal Regulations are amended by substituting for the Third Schedule
the following Schedule:
“THIRD SCHEDULE
(Regulations 6, 9, Subregulations 15(5) and 16(3), Regulation 24, Subregulations 88(2) and 89(2), Regulation 94, Paragraph 100(e), Subregulations 101(1) and 102(2), Regulation 111, Subregulations 114A(2), 115(6), 118(1) and 118(3)).
GOVERNMENT OF MALAYSIA
GAS SUPPLY ACT 1993
FEE
PART I
1. Fee for gas utility licence (Regulation 6)
The fee shall be based on the volume of gas supplied in MMBTU, in accordance
with the previous year's record. The unit of fee charged shall be 1.1 sen/MMBTU.
(MMBTU = Million British Thermal Unit)
2. Fee for private gas licence (Regulation 9)
The fee shall be based on the class of gas installation as follows:
RM per year
(a) Class I gas installation 300.00
(b) Class II gas installation 200.00
(c) Class III gas installation 100.00
P.U. (A) 321
15
3. Fee for approval to install and approval to operate for gas installation
(Subregulations 15(5) and 16(3))
RM/Certificate
(a) Processing and issuance of approval to install 200.00
(b) Processing and issuance of approval to operate 100.00
4. Fee for inspection and tests of installation (Regulation 24)
(a) Inspection RM
i. Class I gas installation 300.00
ii. Class II gas installation 200.00
iii. Class III gas installation 100.00
iv. Additional gas installation 100.00
(b) Leak Test
i. Class I gas installation 300.00
ii. Class II gas installation 200.00
iii. Class III gas installation 100.00
iv. Additional gas installation 100.00
(c) Holiday Test 100.00
PART II
1. Fee for replacement of Certificate of Competency (Subregulation 88(2))
RM
(a) Gas Engineer 150.00
(b) Gas Engineering Supervisor 100.00
(c) Gas Fitter 50.00
P.U. (A) 321
16
2. Fee for registration and renewal of registration for competent person
(Subregulation 89(2))
RM per year
(a) Gas Engineer 150.00
(b) Gas Engineering Supervisor 100.00
(c) Gas Fitter 50.00
3. Fee for examinations (Regulation 94)
RM
(a) Examination processing fee 20.00
(b) Examination for a Certificate of Competency as a
Gas Engineer
150.00
(c) Examination for a Certificate of Competency as a
Gas Engineering Supervisor
100.00
(d) Examination for a Certificate of Competency as a
Gas Fitter
50.00
4. Fee for removal of a restriction and endorsement of a Certificate of Competency
(Paragraph 100(e))
RM
(a) Gas Engineer 150.00
(b) Gas Engineering Supervisor 100.00
(c) Gas Fitter 50.00
5. Fee for temporary Certificate of Competency for a foreign person
(Subregulation 101(1))
RM per year
(a) Gas Engineer 150.00
(b) Gas Engineering Supervisor 100.00
(c) Gas Fitter 50.00
P.U. (A) 321
17
6. Fee for endorsement of equivalent Certificate of Competency
(Subregulation 102(2))
RM
(a) Gas Engineer 150.00
(b) Gas Engineering Supervisor 100.00
(c) Gas Fitter 50.00
7. Fee for Certificate of Registration as Gas Contractor (Regulation 111 and
Subregulation 115(6))
Issuance fee
RM
Renewal per year
RM (a) Class A 3000.00 2000.00
(b) Class B 2000.00 1000.00
(c) Class C 1000.00 700.00
(d) Class D 500.00 300.00
8. Fee for issuance and renewal of Certificate of Approval to assemble, manufacture
or import any gas fitting, gas appliance or gas equipment (Subregulation 118(1))
Issuance fee
RM
Renewal per year
RM (a) Manufacturer/Assembler
500.00 250.00
(b) Importer 800.00 400.00
9. Fee for issuance and renewal of Certificate of Approval for sale or use of
any gas fitting, gas equipment or gas appliance (Subregulation 118(1))
Issuance fee
RM
Renewal
per year
RM
(a) Gas fitting 100.00 100.00
(b) Gas equipment 200.00 200.00
(c) Gas appliance 110.00 110.00
P.U. (A) 321
18
10. Fee for replacement of certificate other than certificate of competency
(Subregulation 114A(2) and Subregulation 118(3))
RM
(a) Registration of Gas Contractor 35.00
(b) Certificate of Approval 35.00
Made 17 November 2014 [UPE(S)25/16/68 Sj 1 Jld.5; PN(PU2)528/II]
DATO’ SRI MOHD. NAJIB BIN TUN HAJI ABDUL RAZAK
Prime Minister