PROSEDUR OSC 3.0 Bahagian Kawalan Pemajuan JABATAN KERAJAAN TEMPATAN KEMENTERIAN KESEJAHTERAAN BANDAR, PERUMAHAN DAN KERAJAAN TEMPATAN PENGALAMAN PELAKSANAAN PENGELUARAN SIJIL SIAP DAN PEMATUHAN (CCC) DI MBJB

Upload: tranduong

Post on 16-Apr-2018

331 views

Category:

Documents


12 download

TRANSCRIPT

Page 1: PROSEDUR OSC 3 - mpkk.gov.my · ccc (borang f) dan borang g1 – g21 p4 pemeriksaan interim proses 4 proses 5 p5 proses 6 kelulusan pelan pembinaan ccc . kebenaran merancang;

PROSEDUR OSC 3.0

Bahagian Kawalan Pemajuan

JABATAN KERAJAAN TEMPATAN

KEMENTERIAN KESEJAHTERAAN BANDAR, PERUMAHAN DAN KERAJAAN TEMPATAN

PENGALAMAN PELAKSANAAN PENGELUARAN SIJIL

SIAP DAN PEMATUHAN (CCC) DI

MBJB

Page 2: PROSEDUR OSC 3 - mpkk.gov.my · ccc (borang f) dan borang g1 – g21 p4 pemeriksaan interim proses 4 proses 5 p5 proses 6 kelulusan pelan pembinaan ccc . kebenaran merancang;

PROSEDUR 3.0

Pekeliling KPKT

9. SURAT ARAHAN 29 MEI 2014 – Pemakaian OSC 3.0 Kepada Pihak Berkuasa

Tempatan (PBT).

i. Pemakaian manual agensi dan manual pemohon OSC 3.0;

ii. Selaras dengan Pekeliling KSU KPKT Bil. 2, Bil. 3 dan Bil. 4 Tahun 2011.

SKOP

PERANAN

STRUKTUR TADBIR URUS

MODEL BAHARU OSC

Kelulusan Pelan Pemajuan Pelan Utiliti Permit pembinaan Notis Mula Kerja Pemeriksaan dan Pentauliahan Penyambungan Utiliti Deposit CCC

Menyelaras Dan Memantau Sehingga CCC

Comprehensive

MODEL SEDIA ADA

Kelulusan Pelan Pemajuan Deposit CCC

Menyelaras Sehingga Mesyuarat OSC

Fragmented

Page 3: PROSEDUR OSC 3 - mpkk.gov.my · ccc (borang f) dan borang g1 – g21 p4 pemeriksaan interim proses 4 proses 5 p5 proses 6 kelulusan pelan pembinaan ccc . kebenaran merancang;

PROSEDUR 3.0

0 - CCC

P2 P3

PEMBERITAHUAN MULA KERJA

PERTIMBANGAN PELAN-PELAN

PEMAJUAN

Proses 2 Proses 3

PENGUMPULAN DATA TEKNIKAL

P6

PEMERIKSAAN AKHIR

PERINGKAT I DAN

PERINGKAT II

P1

Proses 1

PENDEPOSITAN CCC (BORANG F)

DAN BORANG G1 –

G21

P4

PEMERIKSAAN INTERIM

Proses 4 Proses 5

P5

Proses 6

KELULUSAN PELAN PEMBINAAN CCC

Page 4: PROSEDUR OSC 3 - mpkk.gov.my · ccc (borang f) dan borang g1 – g21 p4 pemeriksaan interim proses 4 proses 5 p5 proses 6 kelulusan pelan pembinaan ccc . kebenaran merancang;

KEBENARAN MERANCANG; Commence, Undertake Or Carry Out

Any Development

PLANNING PERMISSION IS DEALING WITH ‘PEMAJUAN’

PROSEDUR 3.0

PROSES 2 – PERTIMBANGAN KELULUSAN PELAN PEMAJUAN

ACT 172

Page 5: PROSEDUR OSC 3 - mpkk.gov.my · ccc (borang f) dan borang g1 – g21 p4 pemeriksaan interim proses 4 proses 5 p5 proses 6 kelulusan pelan pembinaan ccc . kebenaran merancang;

PEMAJUAN

KERJA; • Bangunan • Kejuruteraan

• Perlombongan • Perindustrian

PERUBAHAN MATAN (guna tanah dan bangunan); • Secara fizikal

• Perubahan nyata/jelas • Berlanggaran/ tidak

selaras dengan RT

HAL TANAH; • Pecah sempadan • Cantuman tanah

• Implikasi terhadap perancangan

How is KM Dealing With The Development ?

LAND AND BUILDING USE

LAND AND BUILDING USE

LAND USE

LAND AND BUILDING USE ARE ‘PEMAJUAN’

ANY ‘PEMAJUAN’ NEED PLANNING PERMISSION

PROSEDUR 3.0

PROSES 2 – PERTIMBANGAN KELULUSAN PELAN PEMAJUAN

Page 6: PROSEDUR OSC 3 - mpkk.gov.my · ccc (borang f) dan borang g1 – g21 p4 pemeriksaan interim proses 4 proses 5 p5 proses 6 kelulusan pelan pembinaan ccc . kebenaran merancang;

PELAN BANGUNAN; Construction And CCC

BUILDING ERECTION/ CONSTRUCTION

NO BUILDING PLAN APPROVAL WITHOUT APPROVAL OF ROAD AND DRAINAGE PLAN

ACT 133

PROSEDUR 3.0

PROSES 2 – PERTIMBANGAN KELULUSAN PELAN PEMAJUAN

Page 7: PROSEDUR OSC 3 - mpkk.gov.my · ccc (borang f) dan borang g1 – g21 p4 pemeriksaan interim proses 4 proses 5 p5 proses 6 kelulusan pelan pembinaan ccc . kebenaran merancang;

PELAN KERJA TANAH; Construction And CCC

PROSEDUR 3.0

PROSES 2 – PERTIMBANGAN KELULUSAN PELAN PEMAJUAN

ACT 133

SIMULTENOUSLY SUBMISSION EARTH WORK AND BUILDING TO LOCAL AUTHORITY

EARTH WORK/ CONSTRUCTION

Page 8: PROSEDUR OSC 3 - mpkk.gov.my · ccc (borang f) dan borang g1 – g21 p4 pemeriksaan interim proses 4 proses 5 p5 proses 6 kelulusan pelan pembinaan ccc . kebenaran merancang;

PELAN JALAN DAN PARIT; Construction And CCC

PROSEDUR 3.0

PROSES 2 – PERTIMBANGAN KELULUSAN PELAN PEMAJUAN

ACT 133

ACT 172

ROAD CONSTRUCTION

Page 9: PROSEDUR OSC 3 - mpkk.gov.my · ccc (borang f) dan borang g1 – g21 p4 pemeriksaan interim proses 4 proses 5 p5 proses 6 kelulusan pelan pembinaan ccc . kebenaran merancang;

CCC

CONSTRUCTION PERMITS

HOW KM DEALING WITH THE DEVELOPMENT?

PROSEDUR 3.0

PROSES 2 – PERTIMBANGAN KELULUSAN PELAN PEMAJUAN

KEBENARAN MERANCANG

Page 10: PROSEDUR OSC 3 - mpkk.gov.my · ccc (borang f) dan borang g1 – g21 p4 pemeriksaan interim proses 4 proses 5 p5 proses 6 kelulusan pelan pembinaan ccc . kebenaran merancang;

PROSEDUR 3.0

PROSES 3 – PENDEPOSITAN BORANG B

NOTIFIKASI BORANG B

Page 11: PROSEDUR OSC 3 - mpkk.gov.my · ccc (borang f) dan borang g1 – g21 p4 pemeriksaan interim proses 4 proses 5 p5 proses 6 kelulusan pelan pembinaan ccc . kebenaran merancang;

PROSEDUR 3.0

PROSES 4 – 6 : PEMERIKSAAN INTERIM, AKHIR DAN CCC

1

• SUBSEKSYEN 70(22) – KUASA DAN TANGGUNGJAWAB PBT PASTIKAN PEMAJUAN MENEPATI PELAN LULUS;

• UKBS 25 (4) – KUASA PBT DAN PEGAWAI PBT BUAT PEMERIKSAAN MANA-MANA PERINGKAT PEMBINAAN BAGI MEMASTIKAN KEPATUHAN PELAN LULUS.

2

• SUBSEKSYEN 70(23) – PBT KELUARKAN NOTIS BERTULIS KEPADA PSP;

• BAGI MEMATUHI KETIDAKPATUHAN PELAN LULUS;

• MENAHAN PENGELUARAN CCC.

3 • UKBS 25 (5) HINGGA (13)

• TATACARA PELAKSANAAN ‘DUTY OF CARE’

DASAR PELAKSANAAN ’DUTY OF CARE’ PROJEK PEMBANGUNAN DI MAJLIS

BANDARAYA JOHOR BAHRU

Page 12: PROSEDUR OSC 3 - mpkk.gov.my · ccc (borang f) dan borang g1 – g21 p4 pemeriksaan interim proses 4 proses 5 p5 proses 6 kelulusan pelan pembinaan ccc . kebenaran merancang;

PROSEDUR 3.0

PROSES 4 – 6 : PEMERIKSAAN INTERIM, AKHIR DAN CCC

Page 13: PROSEDUR OSC 3 - mpkk.gov.my · ccc (borang f) dan borang g1 – g21 p4 pemeriksaan interim proses 4 proses 5 p5 proses 6 kelulusan pelan pembinaan ccc . kebenaran merancang;

PROSEDUR 3.0

PROSES 4 – 6 : PEMERIKSAAN INTERIM, AKHIR DAN CCC

CLEAR HEIGHT (MULTILEVEL CARPARK) TIDAK DAPAT DI

SEDIAKAN KERANA KEWUJUDAN DUCTING DAN MENYEBABKAN TLK

TIDAK BOLEH DI GUNAKAN

1.2 METER

Page 14: PROSEDUR OSC 3 - mpkk.gov.my · ccc (borang f) dan borang g1 – g21 p4 pemeriksaan interim proses 4 proses 5 p5 proses 6 kelulusan pelan pembinaan ccc . kebenaran merancang;

PROSEDUR 3.0

PROSES 4 – 6 : PEMERIKSAAN INTERIM, AKHIR DAN CCC

A 172

Page 15: PROSEDUR OSC 3 - mpkk.gov.my · ccc (borang f) dan borang g1 – g21 p4 pemeriksaan interim proses 4 proses 5 p5 proses 6 kelulusan pelan pembinaan ccc . kebenaran merancang;

PROSEDUR 3.0

PROSES 4 – 6 : PEMERIKSAAN INTERIM, AKHIR DAN CCC

1

• PINDAAN UKBS 25 TAHUN 1999;

• MEMASUKKAN PERUNTUKAN BARU – UKBS 25(A)

• BORANG F (PERAKUAN SIAP DAN PEMATUHAN)

2

• SEBELUM MAC 2007

• UKBS 25A – PERAKUAN SIAP DAN PEMATUHAN DIKELUARKAN OLEH PSP;

• TIADA ELEMEN BORANG G1 – G21.

3

• APRIL 2007- SEKARANG

• PINDAAN UKBS 25 (CCC MENGGANTIKAN CFO)

• UKBS 25A DIMANSUHKAN

• BORANG F (BERSERTA BORANG G1 - G21) DIKELUARKAN OLEH PSP;

• DIDEPOSIT KE PBT DAN LEMBAGA PROFESSIONAL BERKAITAN.

PENGELUARAN CCC UNTUK RUMAH BANGLO MILIKAN TUNGGAL

Page 16: PROSEDUR OSC 3 - mpkk.gov.my · ccc (borang f) dan borang g1 – g21 p4 pemeriksaan interim proses 4 proses 5 p5 proses 6 kelulusan pelan pembinaan ccc . kebenaran merancang;

PROSEDUR 3.0

PROSES 4 – 6 : PEMERIKSAAN INTERIM, AKHIR DAN CCC

PENGELUARAN CCC UNTUK RUMAH BANGLO MILIKAN TUNGGAL

Page 17: PROSEDUR OSC 3 - mpkk.gov.my · ccc (borang f) dan borang g1 – g21 p4 pemeriksaan interim proses 4 proses 5 p5 proses 6 kelulusan pelan pembinaan ccc . kebenaran merancang;

PROSEDUR 3.0

PROSES 4 – 6 : PEMERIKSAAN INTERIM, AKHIR DAN CCC

PENGELUARAN CCC UNTUK RUMAH BANGLO MILIKAN TUNGGAL

Page 18: PROSEDUR OSC 3 - mpkk.gov.my · ccc (borang f) dan borang g1 – g21 p4 pemeriksaan interim proses 4 proses 5 p5 proses 6 kelulusan pelan pembinaan ccc . kebenaran merancang;

PROSEDUR 3.0

PROSES 4 – 6 : PEMERIKSAAN INTERIM, AKHIR DAN CCC

BORANG C DAN D SERTA PELAN SETTING OUT PLAN

TIDAK DIWAJIBKAN SEBAGAIMANA CFO

CFO CCC

BORANG STATUS BORANG STATUS

BORANG C (NOTIS SIAP PANCANG TANDA)

WAJIB BORANG G2 (PEMANCANGAN TANDA)

TIDAK WAJIB

BORANG D (NOTIS SIAP TAPAK)

WAJIB BORANG G3 (ASAS TAPAK)

TIDAK WAJIB

Page 19: PROSEDUR OSC 3 - mpkk.gov.my · ccc (borang f) dan borang g1 – g21 p4 pemeriksaan interim proses 4 proses 5 p5 proses 6 kelulusan pelan pembinaan ccc . kebenaran merancang;

PROSEDUR 3.0

PROSES 4 – 6 : PEMERIKSAAN INTERIM, AKHIR DAN CCC

SETTING OUT TAPAK BERUBAH ? SETBACK BERUBAH ?

KOMPETENSI PSP UNTUK MEMASTIKAN PELAN KM DAN PB DI

PINDA SEGERA ?

BORANG C DAN D SERTA PELAN SETTING OUT PLAN

TIDAK DIWAJIBKAN SEBAGAIMANA CFO

Page 20: PROSEDUR OSC 3 - mpkk.gov.my · ccc (borang f) dan borang g1 – g21 p4 pemeriksaan interim proses 4 proses 5 p5 proses 6 kelulusan pelan pembinaan ccc . kebenaran merancang;

PROSEDUR 3.0

PROSES 4 – 6 : PEMERIKSAAN INTERIM, AKHIR DAN CCC

BORANG C DAN D SERTA PELAN SETTING OUT PLAN

TIDAK DIWAJIBKAN SEBAGAIMANA CFO

Page 21: PROSEDUR OSC 3 - mpkk.gov.my · ccc (borang f) dan borang g1 – g21 p4 pemeriksaan interim proses 4 proses 5 p5 proses 6 kelulusan pelan pembinaan ccc . kebenaran merancang;

PROSEDUR 3.0

PROSES 4 – 6 : PEMERIKSAAN INTERIM, AKHIR DAN CCC

PENGELUARAN F1 – CCC SEBAHAGIAN

(BAGI PEMBANGUNAN BERSTRATA)

21

FASA 1- PODIUM

FASA 2- BLOK 1

FASA 3 - BLOK 2

PODIUM

BLOK 1

BLOK 2

CONTOH PENGELUARAN CCC SEBAHAGIAN / BERFASA (DITANDAKAN PADA PELAN DAN DILULUSKAN TAJUKNYA DALAM PELAN BANGUNAN)

Page 22: PROSEDUR OSC 3 - mpkk.gov.my · ccc (borang f) dan borang g1 – g21 p4 pemeriksaan interim proses 4 proses 5 p5 proses 6 kelulusan pelan pembinaan ccc . kebenaran merancang;

PROSEDUR 3.0

PROSES 4 – 6 : PEMERIKSAAN INTERIM, AKHIR DAN CCC

PENGELUARAN F1 – CCC SEBAHAGIAN

(BAGI PEMBANGUNAN BERSTRATA)

22

Mengambil kira saiz pemajuan dan tertakluk kepada Akta Hakmilik Strata dan Akta Pengurusan Strata

Pengiraan tempat letak kenderaan yang mencukupi mengikut fasa

Penyediaan kemudahan sebagaimana garis panduan SPA / SNP

25% hakmilik strata dikeluarkan

Construction method – piling, tower cranes, tahap kebisingan

VP vs F1 ( bolehkah diserahkan kunci ?)

Page 23: PROSEDUR OSC 3 - mpkk.gov.my · ccc (borang f) dan borang g1 – g21 p4 pemeriksaan interim proses 4 proses 5 p5 proses 6 kelulusan pelan pembinaan ccc . kebenaran merancang;

PROSEDUR 3.0

PROSES 4 – 6 : PEMERIKSAAN INTERIM, AKHIR DAN CCC

PENGELUARAN F1 – CCC SEBAHAGIAN

(BAGI PEMBANGUNAN BERSTRATA)

Page 24: PROSEDUR OSC 3 - mpkk.gov.my · ccc (borang f) dan borang g1 – g21 p4 pemeriksaan interim proses 4 proses 5 p5 proses 6 kelulusan pelan pembinaan ccc . kebenaran merancang;

TERIMA KASIH