C 4006/UNIT 8/1ATURCARA KONTRAK DAN UKUR BINAAN 2 KAEDAH MEMBUAT PENGUKURAN KUANTITIUNIT 8CERUCUK KONKRIT BERTETULANG TUANG DULU (PRECAST RC PILE) DAN CERUCUK KAYU (TIMBER PILE)OBJEKTIFObjektif am: Memahami dan mengetahui kaedah pengukuran kuantiti bagi kerja cerucuk untuk bangunan kurang daripada 5 tingkat berdasarkan SMM 2. Objektif Khusus: Di akhir unit ini anda sepatutnya dapat:Membaca dan mentafsir lukisan kerja cerucuk. Menghubungkaitkan SMM2 dengan llukisan dan kuantiti kerjaTRANSCRIPT
KAEDAH MEMBUAT PENGUKURAN KUANTITI
C 4006/UNIT 8/ATURCARA KONTRAK DAN UKUR BINAAN 2
CERUCUK KONKRIT BERTETULANG TUANG DULU
(PRECAST RC PILE) DAN CERUCUK KAYU (TIMBER
PILE)
Objektif am:
Memahami dan mengetahui kaedah pengukuran kuantiti bagi kerja cerucuk untuk bangunan kurang daripada 5 tingkat berdasarkan SMM 2.
Objektif Khusus:
Di akhir unit ini anda sepatutnya dapat:-
Membaca dan mentafsir lukisan kerja cerucuk.
Menghubungkaitkan SMM2 dengan llukisan dan kuantiti kerja yang
diukur.
Menyenaraikan butiran kerja mengikut operasi kerja-kerja
berdasarkan lukisan kerja/pelan yang dibekalkan.
Mengukur kuantiti kerja cerucuk.
MOHD, SAFRI OMAR JKA, POLISAS
1
UNIT 8
OBJEKTIF
KAEDAH MEMBUAT PENGUKURAN KUANTITI
C 4006/UNIT 8/ATURCARA KONTRAK DAN UKUR BINAAN 2
Menulis keterangan kerja cerucuk.
8.0 Pengenalan
Tahukah anda apakah yang dimaksudkan dengan cerucuk?
8.1 Kategori Cerucuk Galas Beban
Terdapat berbagai jenis bahan yang boleh digunakan untuk pembuatan cerucuk galas beban iaitu;
Cerucuk konkrit pra tuang (precast)Cerucuk konkrit tuang di situ (insitu)Cerucuk kayuCerucuk bakauCerucuk keluli.
MOHD, SAFRI OMAR JKA, POLISAS
2
INPUT
Kaedah pengukuran CERUCUK
Cerucuk merupakan struktur binaan
bawah tanah yang menerima,
menanggung dan menyebarkan
beban bangunan dengan selamat
kepada tanah bawah.
Cerucuk merupakan struktur binaan
bawah tanah yang menerima,
menanggung dan menyebarkan
beban bangunan dengan selamat
kepada tanah bawah.
KAEDAH MEMBUAT PENGUKURAN KUANTITI
C 4006/UNIT 8/ATURCARA KONTRAK DAN UKUR BINAAN 2
Paras Tanah Tiang
Tetopi Cerucuk Cerucuk
Rajah 8.1 : Pandangan Keratan Kedudukan Cerucuk
8.2 Istilah-istilah Kerja Cerucuk
a. Lubang (point) - bilangan lubang tiang-tiang cerucuk pada suatu tetopi cerucuk (pile cap).
1 lubang 2 lubang 4 lubang
Rajah 5.2 : Kedudukan Lubang (Point) Cerucuk
b. Tetopi Cerucuk (pile caps) - papak konkrit yang dibina diatas tiang cerucuk. (rujuk rajah 8.1)
c. “Singly” / “Cluster” - ia merujuk kepada bilangan lubang pada tetopi cerucuk.
Singly - 1 lubang sahaja
MOHD, SAFRI OMAR JKA, POLISAS
3
KAEDAH MEMBUAT PENGUKURAN KUANTITI
C 4006/UNIT 8/ATURCARA KONTRAK DAN UKUR BINAAN 2
Cluster - melebihi 1 lubang
(i) Singly (ii) Cluster
Rajah 5.3 : Pelan Kategori Lubang Cerucuk Singly dan Cluster
d. Cerucuk permulaan (preliminary piles) – tiang cerucuk yang mula-mula sekali dibenam ke dalam tanah.
e. Cerucuk sambungan (extension piles) – tiang cerucuk yang dibenam selepas cerucuk permulaan. Cerucuk sambungan akan disambungkan kepada cerucuk permulaan .
Cerucuk Permulaan
Penyambung Cerucuk
Cerucuk Sambungan
Cerucuk Permulaan
Cerucuk Sambungan
MOHD, SAFRI OMAR JKA, POLISAS
4
KAEDAH MEMBUAT PENGUKURAN KUANTITI
C 4006/UNIT 8/ATURCARA KONTRAK DAN UKUR BINAAN 2
Rajah 5.4 : Posisi Cerucuk Permulaan Dan Cerucuk Sambungan
8.3 Penyenaraian Butiran Kerja
Sebelum mengukur kuantiti para pelajar adalah dinasihatkan supaya menyenaraikan semua butiran kerja yang terdapat di dalam pelan/lukisan kerja. Tujuan penyenaraian ini adalah untuk mengelakkan kemungkinan terdapat butiran kerja yang tidak diukur.
Bilangan butiran yang disenaraikan bergantung kepada pelan/lukisan kerja yang diberikan. Bagi tujuan penulisan modul ini hanya pengukuran cerucuk kayu sahaja yang akan diterangkan .
Apakah butiran kerja ceruck kayu yang perlu diukur berdasarkan kepada SMM 2 ?
MOHD, SAFRI OMAR JKA, POLISAS
5
Butiran kerja cerucuk kayu yang perlu diukur berdasarkan SMM 2 adalah seperti di dalam jadual 5.1 di bawah. (Sila perhatikan, quek...quek....quek...)
Butiran kerja cerucuk kayu yang perlu diukur berdasarkan SMM 2 adalah seperti di dalam jadual 5.1 di bawah. (Sila perhatikan, quek...quek....quek...)
KAEDAH MEMBUAT PENGUKURAN KUANTITI
C 4006/UNIT 8/ATURCARA KONTRAK DAN UKUR BINAAN 2
BIL. BUTIRAN KERJA UNIT UKURAN1 Mobilisation Of Piling Plant Item2 Supply Of Piles No.3 Driven Of Piles m4 Joint Of Piles No.5 Cutting Of Top Piles No6 Testing Of Piles Item
Jadual 8.1 Senarai Butiran Kerja (Taking off list)
Setiap butiran di atas hendaklah di tandakan silang/ pangkah ( ) dengan pen merah apabila butiran berkenaan telah diukur kuantitinya. Ini bagi mengelakkan butiran berkenaan diukur dua kali ataupun tidak diukur langsung.
MOHD, SAFRI OMAR JKA, POLISAS
6
KAEDAH MEMBUAT PENGUKURAN KUANTITI
C 4006/UNIT 8/ATURCARA KONTRAK DAN UKUR BINAAN 2
AKTIVITI 8a
ARAHAN
KAMI YAKIN ANDA MUNGKIN TELAH BEGITU BERMINAT UNTUK MENGUKUR KUANTITI. SEBELUM ITU ANDA PERLU MENGUJI KEFAHAMAN ANDA TERLEBIH DAHULU DENGAN MENJAWAB SOALAN-SOALAN MUDAH DI BAWAH.
PASTIKAN ANDA TIDAK MERUJUK KEPADA TEKS YANG DISEDIAKAN DI BAHAGIAN INPUT 8a.
INGAT…. JANGAN MERUJUK KEPADA INPUT 8a.
SELAMAT MENCUBA
MOHD, SAFRI OMAR JKA, POLISAS
7
KAEDAH MEMBUAT PENGUKURAN KUANTITI
C 4006/UNIT 8/ATURCARA KONTRAK DAN UKUR BINAAN 2
SOALAN
Isikan tempat-tempat kosong di dalam kumpulan awam di bawah dengan butiran kerja yang lazimnya terdapat di dalam kerja-kerja penanaman cerucuk kayu.
MOHD, SAFRI OMAR JKA, POLISAS
8
TIMBER PILE
KAEDAH MEMBUAT PENGUKURAN KUANTITI
C 4006/UNIT 8/ATURCARA KONTRAK DAN UKUR BINAAN 2
MAKLUMBALAS 8a
MOHD, SAFRI OMAR JKA, POLISAS
9
TIMBER PILES
Mobilisation Of Piling Plant
Supply Of Piles
Driven Of Piles
Cutting Of Top Piles
Testing Of Piles
KAEDAH MEMBUAT PENGUKURAN KUANTITI
C 4006/UNIT 8/ATURCARA KONTRAK DAN UKUR BINAAN 2
ADAKAH ANDA TELAH MENDAPAT JAWAPAN SEPERTI DI ATAS.
JIKA YA. SILA MAJU KE AKTIVITI SETERUSNYA.
INPUT 8b
8.4 Pengukuran Kuantitit Dan Penulisan Keterangan Kerja Cerucuk Kayu
F 2 F 1
MOHD, SAFRI OMAR JKA, POLISAS
10
F 1 F1
F2 F1
Tetopi Cerucuk Konkrit Gred 20
NOTA1. Konkrit untuk tetopi cerucuk ialah konkrit Gred 20
2. Tebal ‘lean concrete’ ialah 50mm tebal
3. Panjang cerucuk permulaan = 6.00M
4. Panjang cerucuk sambungan = 6.00M
5. Kedalaman penanaman cerucuk = 10.00M
6. Ujian cerucuk: beban ujian (50 tonne) = 2 x beban rekabentuk (25 tonne)
KAEDAH MEMBUAT PENGUKURAN KUANTITI
C 4006/UNIT 8/ATURCARA KONTRAK DAN UKUR BINAAN 2
Rajah 5.5 : Pelan Tatatur Tetopi Cerucuk
250 x 250mm tiang
150mm x 150mm Cerucuk Kayu Kempas Yang Diawet
Tetopi Cerucuk Jenis F1 Tetopi Cerucuk Jenis F2
MOHD, SAFRI OMAR JKA, POLISAS
11
150
mm
dal
am
500
mm
m
Pandangan Keratan
Cerucuk kayu
KAEDAH MEMBUAT PENGUKURAN KUANTITI
C 4006/UNIT 8/ATURCARA KONTRAK DAN UKUR BINAAN 2
Rajah 8.6 : Pandangan Keratan dan Pelan Tetopi Cerucuk
Sebelum kuantiti kerja cerucuk boleh diukur, adalah menjadi amalan untuk menyediakan ‘senarai butiran kerja’ terlebih dahulu.
Jadi, berdasarkan rajah 8.5 dan 8.6 senarai butiran kerja yang perlu dinyatakan adalah seperti berikut .
BIL BUTIRAN KERJA UNIT1 Mobilisation of piling plant Item2 Supply of piles No3 Driven of piles M4 Joint of piles No5 Cutting off top piles No6 Testing of piles Item
Setiap butiran di atas hendaklah di tandakan silang/ pangkah ( ) dengan pen merah apabila butiran berkenaan telah diukur kuantitinya. Ini bagi mengelakkan butiran berkenaan diukur dua kali ataupun tidak diukur langsung.
MOHD, SAFRI OMAR JKA, POLISAS
12
Pelan Tetopi Cerucuk
INGATKuantiti dan keterangan kerja hendaklah ditulis
di dalam borang dimensa.
KAEDAH MEMBUAT PENGUKURAN KUANTITI
C 4006/UNIT 8/ATURCARA KONTRAK DAN UKUR BINAAN 2
4 /
Item
Item
4
Mobilisation of Piling Plant
Allow for the provision of all necessary piling equipment , plant, tools and ancillary equipment and for their transportation to site, handling, assembling, erecting , dismantling and removal off the site after completion of the operation
Allow for the moving and handling piling equipment, plant , tools and ancillary equipment about the site as often and whenever necessary for the execution of the whole piling operation including any excavation and filling required for moving the plant , tools and ancillary equipment from different level of the site
Supply Of Preliminary Piles
Supply, deliver and unload on site 150mm x 150mm x 6.0m long preliminary tanalised kempas timber piles with 150mm x 150mm x 16 gauge galvanized anti-
CATATAN[rujukan kepada fasal-fasal di dalam SMM 2]
E.4.1(a) : an item shall be given for bringing to site and removing from site all plant required for this section of work.
E.4.1.(b) : An item shall be given for maintaining on site all plant required for this section of the work.
E.5.3 : …..item shall be given for :(a) The total number of piles stating the specified length. The size and weight of head and shoes shall be stated in the description
MOHD, SAFRI OMAR JKA, POLISAS
13
KAEDAH MEMBUAT PENGUKURAN KUANTITI
C 4006/UNIT 8/ATURCARA KONTRAK DAN UKUR BINAAN 2
4/4/
4/4/
4 /
4 /
4.00
10.00
4
4
splitting plate at both ends
Supply Of Extension Piles
Ditto extension piles ditto exceeding 3.00m
Driven Of Piles
Drive only vertical 150mm x 150mm tanalised kempas timber piles
Jointing Of Piles
Supply and fixed 160mm x 160mm x 450mm long rectangular mild steel piles sleeve extension joint fabricated with 5mm thick mild steel plate with and including 150mm x 150mm x 5mm thick mild steel diving plate cut to shape and welded mid-way in sleeve including shaving end of pile to fit into sleeve, painting steel work with two coats of bituminous paint inside and outside and apply two coats of approved timber preservative to all shaved surface of piles in joint
Cutting Off Top Piles
Cut off 150mm x 150mm tanalised kempas timber piles at required level including all appliances and apply two
E.5.7 : In the case of pile extensions, item shall be given for :
(b) The total length of pile extensions given in metres classified into the following ranges of pile length:
not exceeding 3.0mexceeding 3.0m
E.5.3 : The total driven depth given in metres
E.5.7 (a) : The total number of pile extensions
E.5.9 : The following shall be enumerated :(a) Cutting off tops ….
MOHD, SAFRI OMAR JKA, POLISAS
14
KAEDAH MEMBUAT PENGUKURAN KUANTITI
C 4006/UNIT 8/ATURCARA KONTRAK DAN UKUR BINAAN 2
coats of approved wood preservative to cut off head and clearing away debris
MOHD, SAFRI OMAR JKA, POLISAS
15
KAEDAH MEMBUAT PENGUKURAN KUANTITI
C 4006/UNIT 8/ATURCARA KONTRAK DAN UKUR BINAAN 2
Item
Testing Of Piles
Provide all equipment hydraulic jack, deflection gauges , kentledges, temporary staging etc. and test on piles size 150mm x 150mm to a vertical load 50 tonnes including all extra cost before commencing of the main piling works
E.7 : Item shall be given for test of pile stating the detail
MOHD, SAFRI OMAR JKA, POLISAS
16
KAEDAH MEMBUAT PENGUKURAN KUANTITI
C 4006/UNIT 8/ATURCARA KONTRAK DAN UKUR BINAAN 2
AKTIVITI 8b
ARAHAN
SELAMAT MENCUBA
SOALAN
Berdasarkan pelan pada Rajah 8.7 dan 8.8, sila ukur kuantiti cerucuk konkrit berkenaan.
MOHD, SAFRI OMAR JKA, POLISAS
17
BBAGI MENINGKATKAN DAYA KEFAHAMAN ANDA, SILA JAWAB SEMUA SOALAN DI BAWAH TANPA MERUJUK KEPADA TEKS YANG DISEDIAKAN DI BAHAGIAN INPUT.
KAEDAH MEMBUAT PENGUKURAN KUANTITI
C 4006/UNIT 8/ATURCARA KONTRAK DAN UKUR BINAAN 2
F1 F1
F1 F1
F2
NOTA
1. Campuran konkrit untuk tetopi cerucuk ialah 30/202. Penutup konkrit bagi :
- tetopi cerucuk = 75mm- tiang = 40mm
MOHD, SAFRI OMAR JKA, POLISAS
18
Kedudukan Tetopi Cerucuk Konkrit Gred 30
KAEDAH MEMBUAT PENGUKURAN KUANTITI
C 4006/UNIT 8/ATURCARA KONTRAK DAN UKUR BINAAN 2
3. Semua cerucuk konkrit bertetulang hendaklah bersaiz 300mm x 300mm4. Panjang sementara (provisional length) cerucuk hendaklah 18m5. Kedalaman cerucuk 15m6. Beban Kerja ialah 25 Tone7. Beban Ujian adalah 2 kali Beban Kerja
Rajah 8.7 : Pelan Tatatur Tetopi Cerucuk
600mm
F1
MOHD, SAFRI OMAR JKA, POLISAS
19
50mm Tebal Konkrit Alas
Cerucuk Konkrit 300mm x 300mm
1500mm
600mm
50mm Tebal Konkrit Alas
300mm x 300mm Cerucuk Konkrit
KAEDAH MEMBUAT PENGUKURAN KUANTITI
C 4006/UNIT 8/ATURCARA KONTRAK DAN UKUR BINAAN 2
F2
Rajah 5.8 : Pandangan Keratan F1 dan F2
8.7 MAKLUMBALAS
MOHD, SAFRI OMAR JKA, POLISAS
20
KAEDAH MEMBUAT PENGUKURAN KUANTITI
C 4006/UNIT 8/ATURCARA KONTRAK DAN UKUR BINAAN 2
9/
Item
Item
9
9
9.00
15.00
PILING WORKS (ALL PROVISIONAL)Mobilisation of Piling Plant
Allow for the provision of all necessary piling equipment , plant, tools and ancillary equipment and for their transportation to site, handling, assembling, erecting , dismantling and removal off the site after completion of the operation
Allow for the moving and handling piling equipment, plant , tools and ancillary equipment about the site as often and whenever necessary for the execution of the whole piling operation including any excavation and filling required for moving the plant , tools and ancillary equipment from different level of the site
Supply Of Preliminary Piles
Supply, deliver and unload on site 300mm x 300mm x 9.0m long preliminary precast concrete piles as described with corners splayed.
Chilled hardened cast iron pile shoe size 300mm x 300mm x 400mm overall (weighing ……kg) with cast iron point splayed on four sizes with 4 nos. 50mm x 13mm galvanised mild steel straps 450mm girth with fishtailed ends and casting onto end of piles
Supply Of Extension Piles
Supply, deliver and unload on site 300mm x 300mm extension piles exceeding 3.00m
Driven Of Piles
Drive only vertical 300mm x 300mm x 9m long precast concrete piles
Jointing Of Piles
MOHD, SAFRI OMAR JKA, POLISAS
21
KAEDAH MEMBUAT PENGUKURAN KUANTITI
C 4006/UNIT 8/ATURCARA KONTRAK DAN UKUR BINAAN 2
9/ 9
9
9
9
Item
300mm x 300mm 15mm mild steel pile extension head cap chamfered all round four times drilled four main reinforcement bar and welding ends of 4 nos. main reinforcement bars half way through thickness of cap and filled welding all round the bars at junctions with cap before casting and including forming 38mm diameter central hole.
30mm diameter mild steel centering bar 900mm long and inserting into and including boxing in concrete to form 2 nos. 38mm diameter mortices 450mm deep, 1no. in head of pile and 1no. in bottom of extension pile.
Cutt-Off
Cutt-off or b reak away and dispose off surplus length of 300mm x 300mm reinforced concrete piles from site
Preparing concrete pile head
Testing Of Piles
Provide all equipment hydraulic jack, deflection gauges , kentledges, temporary staging etc. and test on piles size 300mm x 300mm to a working load 50 tonnes including all extra cost before commencing of the main piling works
8.8 PENILAIAN KENDIRI
MOHD, SAFRI OMAR JKA, POLISAS
22
KAEDAH MEMBUAT PENGUKURAN KUANTITI
C 4006/UNIT 8/ATURCARA KONTRAK DAN UKUR BINAAN 2
ANDA TELAH MENGHAMPIRI KEJAYAAN. SILA CUBA SOALAN
PENILAIAN KENDIRI INI.
SEMOGA BERJAYA.
SOALAN
Berdasarkan pelan pada rajah 5.9 anda dikehendaki:
1. Menuliskan satu senarai butiran kerja yang lengkap untuk kerja cerucuk kayu.
2. Mengukur kuantiti kerja cerucuk kayu.
3. Menuliskan keterangan kerja cerucuk kayu.
Tugasan ini boleh disediakan secara berkumpulan tidak melebihi 3 orang pelajar bagi setiap kumpulan. Ia hendaklah dihantar dalam masa 1 minggu dari tarikh soalan diberikan.
MOHD, SAFRI OMAR JKA, POLISAS
23
SEKIAN DULU UNTUK UNIT INI
SELAMAT MENCUBA
KAEDAH MEMBUAT PENGUKURAN KUANTITI
C 4006/UNIT 8/ATURCARA KONTRAK DAN UKUR BINAAN 2
Berdasarkan pelan pada rajah 8.9, jawapan anda sepatutnya mengandungi butiran seperti berikut:
Senarai Semak Jawapan
1. Mobilisation Of Piling Plant2. Supply Of Piles3. Driven Of Piles4. Joint Of Piles5. Cutting Of Piles6. Testing Of Piles
MOHD, SAFRI OMAR JKA, POLISAS
24