LAPORAN PROJEK SIAP FASA 1
(3 JANUARI 2013)
PROJEK KERJA-KERJA MENAIKTARAF
SURAU AL-IZZAH FASA 1 TAMAN SAMUDERA A FASA 1, BATU CAVES
SELANGOR
2
1. MAKLUMAT PROJEK
BIL PERKARA
1. NAMA PROJEK KERJA-KERJA MENAIKTARAF SURAU AL-IZZAH FASA 1 ,TAMAN SAMUDERA A FASA 1, BATU CAVES , SELANGOR
2. NAMA KONTRAKTOR
1. HIJRAH ENTERPRISE (000825356-P) NO.80-2B , JALAN 3, BATU CAVES CENTRE POINT, 68100 BATU CAVES, SELANGOR DARUL EHSAN
2. KONTRAKTOR ELEKTRIKAL - MASRI
3. NO KONTRAK 1/SH/SA-FASA 1/2012
4. HARGA KONTRAK (BANGUNAN)
HARGA KONTRAK (KERJA ELKTRIKAL)
KOS KONTRAK KESELURUHAN
RM 99,429.00
RM 2,338.00
RM 101,767.00
5. TEMPOH KONTRAK 15 MAC 2012 HINGGA 31 MEI 2012 LANJUTAN MASA NO.1- 18 JUN 2012
6. TARIKH SIAP ASAL
TARIKH SIAP SEBENAR
31 MEI 2012
6 JULAI 2012
7. TEMPOH MEMBAIKI KECACATAN 7 JULAI 2012 – 7 JANUARI 2013 (6 BULAN )
8. PENGARAH PROJEK / WAKIL PENGARAH PROJEK
HJ.SUHAIRY BIN HJ.SAYUTI / MOHD RAHIM BIN HJ.KAWANGIT
3
2. LAPORAN KEMAJUAN BERGAMBAR
GAMBAR SEBELUM KERJA-KERJA PEMBINAAN
TARIKH GAMBAR KEMAJUAN AKTIVITI
15.3.2012
PERBINCANGAN ANTARA KONTRAKTOR DENGAN SUB KONTRAKTOR
15.3.2012
PERBINCANGAN ANTARA KONTRAKTOR DENGAN SUB KONTRAKTOR
18.3.2012
KERJA UKUR ARAS SEDANG DIJALANKAN
4
18.3.2012
KERJA UKUR ARAS SEDANG DIJALANKAN
GAMBAR SEMASA KERJA-KERJA PEMBINAAN
TARIKH GAMBAR KEMAJUAN AKTIVITI
22.3.2012
KERJA-KERJA PEMBERSIHAN TAPAK DI BAHAGIAN SURAU
22.3.2012
KERJA-KERJA PEMBERSIHAN TAPAK DI TEMPAT LETAK KERETA
5
25.3.2012
KERJA-KERJA PENYEDIAAN FOOTING
27.3.2012
KERJA-KERJA KONKRIT UNTUK FOOTING
30.3.2012
KERJA-KERJA MEMBINA RASUK TANAH
3.4.2012
KERJA-KERJA KONKRIT RASUK TANAH
6
10.4.2012
KERJA-KERJA KONKRIT LANTAI & STRUKTUR TIANG
20.4.2012
KERJA-KERJA PEMASANGAN DINDING BATA , KEKISI KONKRIT DAN BUMBUNG
20.4.2012- 30.4.2012
KERJA-KERJA PLASTERING
20.4.2012 -30.4.2012
KERJA-KERJA PEMASANGAN BUMBUNG DAN PLASTERING
7
2.5.201
KERJA-KERJA PEMBERSIHAN TAPAK LETAK KERETA KALI KE 2
2.5.2012
KERJA-KERJA PEMASANGAN TANGKI NAJIS
5.5.2012
KERJA-KERJA PEMASANGAN PAIP AIR DALAMAN
15.5.2012
KERJA-KERJA MEMBINA STRUKTUR MENARA TANGKI AIR
8
GAMBAR KEMAJUAN KERJA SIAP
TARIKH GAMBAR KEMAJUAN AKTIVITI
8.7.2012
PANDANGAN SISI BANGUNAN
8.7.2012
PANDANGAN SISI BANGUNAN
8.7.2012
PANDANGAN BELAKANG BANGUNAN
9
8.7.2012
TEMPAT WUDHU’ LUAR
8.7.2012
PANDANGAN TIPIKAL TEMPAT WUDHU
8.7.2012
BASIN BASUH TANGAN TIPIKAL
8.7.2012
TANDAS JENIS DUDUK TIPIKAL
10
8.7.2012
BESIN BASUH DAN ‘TABLE TOP’ DI RUANG DAPUR
8.7.2012
PEMASANGAN ‘SWITCH BOX’ BARU
8.7.2012
PEMASANGAN POINT LAMPU DAN POINT KUASA