D. PENGURUSAN PROJEK HOSPITAL INFORMATION SYSTEM (HIS) 1. LATAR BELAKANG KKM telah membangunkan Hospital Information System (HIS) pada tahun 2009 di hospital Kerajaan di bawah Pakej 1 melibatkan kos sebanyak RM104,717,205. Projek ini merangkumi 3 Hospital di iaitu Hospital Bintulu (HBTU), Sarawak, Hospital Sultanah Nur Zahirah (HSNZ), Terengganu dan Hospital Sultan Haji Ahmad Shah (HoSHAS), Pahang. Modul HIS di HBTU dan HSNZ seperti berikut: HBTU:12 Modul HSNZ:17 Modul 1. Patient Management System 1. Patient Management System 2. Patient Billing and Account Receivable System 2. Mortuary Management 3. Medical Record System 3. Electronic Medical Record (Clinical Documentation) 4. Order and Report Management 4. Medical Report 5. Radiology Information System and Picture Archiving Communication System 5. Pharmacy Information System 6. Laboratory Information System 6. Inventory 7. Pharmacy Information System 7. Orders 8. Executive Information System 8. Laboratory Information System 9. Forensic Information and Mortuary Management System 9. Operation Theatre Management System 10. Clinical Documentation 10. Centralize Sterile Tracking System 11. Discharge Summary 11. Dietary 12. Blood Bank Information System 12. Labour and Delivery 13. Hemodialysis System 14. Critical Care Information System 15. Radiology Information System 16. Blood Bank Information System 17. Executive Information System Objektif pembangunan HIS bertujuan membantu prosedur kerja supaya lebih efektif dan efisien, data dan maklumat mengenai pesakit mudah dan senang dicari dengan lebih cepat, keselamatan pesakit (patient safety), mengurangkan kesilapan data (errors), serta membantu pentadbiran hospital membuat keputusan dan pelan/perancangan yang lebih teratur.

Upload: prs75

Post on 08-Nov-2015

63 views

Category:

Documents


5 download

DESCRIPTION

Laporan Tahunan Audi Dalam KKM 2013_Bhg_VI_-D-Pengurusan HIS

TRANSCRIPT

  • D. PENGURUSAN PROJEK HOSPITAL INFORMATION SYSTEM (HIS)

    1. LATAR BELAKANG

    KKM telah membangunkan Hospital Information System (HIS) pada tahun 2009 di hospital

    Kerajaan di bawah Pakej 1 melibatkan kos sebanyak RM104,717,205. Projek ini

    merangkumi 3 Hospital di iaitu Hospital Bintulu (HBTU), Sarawak, Hospital Sultanah Nur

    Zahirah (HSNZ), Terengganu dan Hospital Sultan Haji Ahmad Shah (HoSHAS), Pahang.

    Modul HIS di HBTU dan HSNZ seperti berikut:

    HBTU:12 Modul HSNZ:17 Modul

    1. Patient Management System 1. Patient Management System

    2. Patient Billing and Account Receivable

    System 2. Mortuary Management

    3. Medical Record System 3. Electronic Medical Record (Clinical

    Documentation)

    4. Order and Report Management 4. Medical Report

    5. Radiology Information System and Picture

    Archiving Communication System 5. Pharmacy Information System

    6. Laboratory Information System 6. Inventory

    7. Pharmacy Information System 7. Orders

    8. Executive Information System 8. Laboratory Information System

    9. Forensic Information and Mortuary

    Management System 9. Operation Theatre Management System

    10. Clinical Documentation 10. Centralize Sterile Tracking System

    11. Discharge Summary 11. Dietary

    12. Blood Bank Information System 12. Labour and Delivery

    13. Hemodialysis System

    14. Critical Care Information System

    15. Radiology Information System

    16. Blood Bank Information System

    17. Executive Information System

    Objektif pembangunan HIS bertujuan membantu prosedur kerja supaya lebih efektif dan

    efisien, data dan maklumat mengenai pesakit mudah dan senang dicari dengan lebih cepat,

    keselamatan pesakit (patient safety), mengurangkan kesilapan data (errors), serta

    membantu pentadbiran hospital membuat keputusan dan pelan/perancangan yang lebih

    teratur.

  • 2 VI-PENGAUDITAN PRESTASI | 2013

    2. OBJEKTIF PENGAUDITAN

    Pengauditan dijalankan untuk menilai sama ada pengurusan HIS telah dirancang dan

    dilaksanakan dengan cekap dan berkesan serta selaras dengan objektif yang ditetapkan.

    3. SKOP DAN METODOLOGI PENGAUDITAN

    Pengauditan ini merangkumi aspek perancangan, pelaksanaan dan pemantauan yang

    dilakukan terhadap sistem ini bagi tempoh tahun 2012 dan 2013 di di HBTU dan HSNZ.

    Pengauditan telah dijalankan dengan menyemak fail, rekod dan dokumen yang berkaitan.

    Pemeriksaan ke atas HIS juga dijalankan serta membuat analisis dan mengkaji laporan-

    laporan yang dikeluarkan oleh HIS. Lawatan, pemeriksaan dan temu bual dengan pegawai

    berkaitan juga telah dibuat di hospital berkenaan.

    4. PENEMUAN AUDIT DALAM

    4.1 Perolehan Kenderaan dan Kemudahan Peralatan Di Bawah Peruntukan

    Kerja Awalan (Preliminaries)

    Surat Pekeliling Perbendaharaan Bil.13 Tahun 1999 hanya membenarkan agensi Kerajaan

    memperolehi kenderaan dan kemudahan peralatan berkaitan melalui Peruntukan Kerja

    Awalan bagi sesuatu kontrak kerja yang memudahkan pengurusan projek. SPP ini tidak

    memberi kemudahan peruntukan kerja awalan kepada kontrak bekalan dan perkhidmatan.

    Perolehan kenderaan dan kemudahan peralatan untuk projek HIS di HBTU dan HSNZ telah

    dibuat tanpa kelayakan yang dibenarkan melalui SPP Bil. 13/1999. Perolehan tersebut

    melibatkan 1 kenderaan dan 16 unit peralatan bernilai RM283,813.50 di HBTU, Sarawak

    seperti di Jadual D-1, dan 1 kenderaan dan 15 unit kemudahan peralatan bernilai

    RM113,884 di HSNZ, Terengganu seperti di Jadual D-2.

    Jadual D-1

    Senarai Kenderaan Dan Kemudahan Peralatan

    Bil. Butiran Model, Specs, Part No Kuantiti

    (Unit)

    Kos Seunit

    (RM)

    Jumlah

    (RM)

    1. Project Director

    Transport Nissan XTrail 2.0 1 182,455.08 182,455.08

    2. Sub Notebook

    Computer Fujitsu LifeBook P1610 2 7,038.00 14,076.00

    3. Notebook Computer Fujitsu LifeBook P1010 2 4,590.00 9,180.00

    4. Antivirus Software Symantec Enterprise

    Edition 10.2 4 100.98 403.92

    5. Operating System Windows Vista Business 4 527.34 2,109.36

  • 2013 | LAPORAN TAHUNAN 3

    Bil. Butiran Model, Specs, Part No Kuantiti

    (Unit)

    Kos Seunit

    (RM)

    Jumlah

    (RM)

    6. Document Editing

    Software

    Microsoft Office

    Professional 2007 4 1,133.22 4,532.88

    7. Project Scheduling

    Software Microsoft Project 2007 4 1,308.66 5,234.64

    8. 3G Data Card &

    Telephone Line Celcom 3G Card 3 3,963.00 11,889.00

    9. Printer 1 HP Printer CU5550DN 1 12,451.36 12,451.36

    10. Printer 2 HP Printer CP2025DN 1 1,723.80 1,723.80

    11. LCD Projector Geha Compact 332 1 7,705.08 7,705.08

    12. Digital Camera Sony DSC-5980 1 5,764.02 5,764.02

    13. Camcoder Sony DCR-SR47E 1 2,300.00 2,300.00

    14. Handphone 1 &

    Telepohone Line HTC Diamond 1 4,731.52 4,731.52

    15. Handphone 2 &

    Telephone Line Nokia 5800 Xpress Music 1 3,889.52 3,889.52

    16. Photocopy Machine Konica Minolta New

    Bizhub C253 1 14,551.32 14,551.32

    17. Blank CD-RW Imation Blank CD-RW 200 4.08 816.00

    JUMLAH 283,813.50

    Jadual D-2

    Senarai Kenderaan Dan Kemudahan Peralatan

    Bil. Butiran Model, Specs, Part No Kuantiti

    (Unit)

    Jumlah

    (RM)

    1. Sub Notebook Computer Fujitsu LifeBook P1610 2

    113,884

    2. Notebook Computer Fujitsu LifeBook L1010 2

    3. Printer HP Color Laserjet 4700N 1

    4. Printer HP Laserjet 4700N 1

    5. Handphone Nokia Express Music 5800 1

    6. Handphone HTC Diamond 1

    7. Digital Camera Sony Digital Cybershot Model

    DSC-S980 1

    8. Handycam Sony Digital Handycam Model

    DCR-SR47E 1

    9. LCD Projector Sony LCD Projector VPL-DX11 1

    10. Celcom Broadband 3G USB Broadband Celcom 3

    11. Photocopy Machine Color Photocopier 1

    12. Project Vehicle KIA Rondo 1

    JUMLAH 16 113,884

  • 4 VI-PENGAUDITAN PRESTASI | 2013

    4.2 Pengurusan Perkakasan dan Perisian

    Pekeliling Perbendaharaan Bil. 5 Tahun 2007 menetapkan Aset Kerajaan hendaklah

    disimpan di tempat yang selamat dan sentiasa di bawah kawalan pegawai yang

    bertanggungjawab. Aset yang dibawa keluar dari pejabat hendaklah mendapat kebenaran

    bertulis daripada Ketua Jabatan. Setiap pegawai adalah bertanggungjawab terhadap apa-

    apa kekurangan, kerosakan atau kehilangan aset di bawah tanggungjawabnya. Pegawai

    yang gagal mematuhi peraturan berkenaan boleh dikenakan tindakan termasuk surcaj di

    bawah Seksyen 18(c) Akta Prosedur Kewangan 1957. Ketua Jabatan hendaklah

    memastikan setiap peralatan yang diterima hendaklah digunakan mengikut fungsi dan

    tujuan sebenar peralatan tersebut dibeli.

    Semakan Audit Dalam mendapati perkakasan dan perisian tidak digunakan seperti berikut :

    4.2.1 Perkakasan dan Perisian Tidak Digunakan

    a) 7 unit peralatan Dot Matrix printer model Lexmark 4227 di HBTU, Sarawak

    bernilai RM24,358.32 yang telah diterima dalam bulan Oktober 2010 tidak

    digunakan seperti di Gambar D-1 hingga Gambar D-7.

    Gambar D-1 Gambar D-2

    Maklum Balas BPM:

    Pihak BPM mengambil maklum mengenai kemudahan pengangkutan dan

    peralatan tertentu yang diperolehi tidak memenuhi syarat kriteria yang ditetapkan

    dalam pekeliling tersebut dan akan memastikan ianya tidak berulang dalam projek-

    projek ICT akan datang.

  • 2013 | LAPORAN TAHUNAN 5

    Gambar D-3

    Gambar D-4

    Gambar D-5

    Gambar D-6

    Gambar D-7

    Maklum Balas HBTU:

    Peralatan telah dibekal

    mengikut kontrak berdasarkan kajian

    keperluan pengguna pada tahun

    2007. Kebanyakan hospital-hospital

    IT yang lain telah menggunakan Dot

    Matrix Printer untuk tujuan penjanaan

    resit dan bil pesakit.

    Penggunaan Dot Matrix Printer

    di HBTU akan dikaji semula dan akan

    diagihkan di lokasi lain yang lebih

    memerlukan. Perolehan bagi kertas

    jenis printer tersebut akan dibuat oleh

    pihak HBTU.

  • 6 VI-PENGAUDITAN PRESTASI | 2013

    Maklum Balas HBTU:

    Terdapat perubahan fungsi

    terhadap bilik Prosedur Klinik Pakar

    Gynea menyebabkan workstation

    RIS/PACS tersebut tidak digunakan

    dan jarang digunakan yang mana

    telah dikhususkan untuk kegunaan

    visiting specialist sahaja dan akan

    diagihkan ke lokasi lain yang lebih

    memerlukan.

    b) 1 unit RIS/PACS hardware DICOM Conversion Station model DBOX6000 3MP

    DICOM Workstation di HBTU, Sarawak bernilai RM50,321.05 di bilik Prosedur Klinik

    Pakar Gynea tidak digunakan seperti di Gambar D-8.

    c) Therapy Data Management System (TDMS) dan aksesori bernilai RM875,220 di

    HSNZ yang telah diterima pada bulan Oktober dan November 2010 tidak

    digunakan semenjak 30 September 2013 seperti di Jadual D-3 dan Gambar

    D-9 hingga D-12.

    Jadual D-3

    Senarai TDMS Dan Aksesorinya

    Bil. Butiran Item Serial No. Kuantiti

    (Unit)

    1. Therapy Monitor Server + 10 clients TDMS F988471 1

    2. Update Therapy Monitor Unlimited Client TDMS F988481 1

    3. Therapy Manager Standard 5 User TDMS F981761 1

    4. Therapy Manager Professional 5 User F981771 1

    5. Therapy Manager Upgrade Unlimited User TDI F981781 1

    6. Seca 460 RS232 Adapter F938551 1

    7. CD 1syXchange F938551 1

    8. HL7 Interface Server F988351 1

    9. Smart reader usb finess/TDMS F915481 3

    10. Patient card 5W8S M357651 160

    11. Smartcard reader F4008 decices finess F920501 31

    12. Cable 4008 BSL/isylink 2.5m finess / TDMS F914361 31

    13. Bed side link BSL 2001EC F915511 3

    14. Tape measure for wall mounting 0 200 cm - 1

    Gambar D-8

  • 2013 | LAPORAN TAHUNAN 7

    Gambar D-9 Gambar D-10

    Smart Reader Usb Finess/TDMS,

    Smartcard Reader F4008 Decices Finess,

    Cable 4008 BSL/Isylink 2.5m Finess /

    TDMS

    Patient Card 5W8S

    Gambar D-11 Gambar D-12

    Smartcard reader F4008 decices finess Tape measure for wall mounting 0 200

    cm

    Maklumbalas BPM dan HSNZ:

    Penggunaan TDMS akan dikaji semula sekiranya semua mesin hemodialisis

    dapat diintegrasi dengan TDMS, dan TDMS dengan HIS. Bagi tujuan ini,

    peruntukan yang mencukupi perlu disediakan terlebih dahulu. Change Request

    telah dibuat pada 7 Januari 2014 untuk memohon supaya integrasi di antara

    sistem HIS dan TDMS dilakukan. Anggaran kos pemasangan sistem TDMS bernilai

    RM11,000 seunit.

  • 8 VI-PENGAUDITAN PRESTASI | 2013

    d) Perisian SAS ver 9.2 di HSNZ yang digunakan untuk mereka bentuk modul

    EIS bernilai RM221,950 telah diinstall dan digunakan pada peringkat awal.

    BPM telah membuat bayaran berjumlah RM155,365 (70%), walau

    bagaimanapun perisian ini tidak digunakan semenjak November 2012 kerana

    laporan yang dijana tidak memenuhi kehendak pengguna seperti di Gambar

    D-13.

    e) 20 daripada 80 unit Bamboo Pen & Touch di HSNZ bernilai RM38,400 yang

    diterima pada 10 Januari dan 17 Januari 2011 masih belum diagihkan seperti

    di Gambar D-14 dan D-15.

    Gambar D-14 Gambar D-15

    20 unit Bamboo Pen & Touch masih belum diagihkan dan disimpan di bilik Pegawai Unit Pengurusan

    Maklumat, HSNZ

    Gambar D-13

    Perisian SAS ver 9.2 yang tidak

    digunakan

    Maklumbalas BPM dan HSNZ:

    Pembangunan modul EIS di

    dalam Oracle masih berjalan

    sehingga sekarang manakala

    modul pembangunan EIS di dalam

    SAS telah tergendala semenjak 21

    November 2012 kerana lesen

    penggunaan SAS telah tamat.

    Pihak HSNZ dan KKM bersetuju

    pembangunan modul EIS di dalam

    SAS diganti dengan menggunakan

    perisian Speed Miner. Sehingga ke

    hari ini modul EIS belum siap dan

    masih lagi di peringkat

    pembangunan.

  • 2013 | LAPORAN TAHUNAN 9

    f) 4 daripada 18 unit bamboo pen di HSNZ yang diagihkan ke Klinik Ortopedik

    tidak digunakan (Gambar D-16 dan D-17) dan baki 14 unit tidak dapat

    dikesan.

    Gambar D-16 Gambar D-17

    4 unit Bamboo Pen & Touch di Klinik Ortopedik tidak digunakan

    g) 1 unit toughbook di HSNZ bernilai RM12,000 di Bilik Pakar Perunding

    Ortopedik tidak digunakan seperti di Gambar D-18.

    Maklum Balas HNSZ:

    Pihak Jabatan Ortopedik telah menjumpai kesemua 18 unit Bamboo Pen

    yang telah diberi kepada mereka sebelum ini.

    Maklum Balas BPM:

    Bamboo Pen tidak digunakan kerana kurang user friendly dan pihak hospital

    tidak dapat mengambil tindakan kerana Bamboo Pen tidak termasuk di dalam

    kontrak asal. Bagi mengatasi masalah ini, latihan penggunaan Bamboo Pen akan

    diadakan oleh pihak kontraktor pada 6 Mac 2014.

    Baki 20 unit Bamboo Pen telah diagihkan ke Jabatan Perubatan (10);

    Anestesiologi (3); Dermatologi (2); dan Oftalmologi (5) pada 12-16 Februari 2014.

  • 10 VI-PENGAUDITAN PRESTASI | 2013

    h) Lapan (8) set peralatan Frame Grabber Workstation di HSNZ, Terengganu

    yang diterima pada 24 September 2010 tidak digunakan dengan alasan tidak

    sesuai digunakan dengan modality sedia ada. Didapati, 3 set Frame Grabber

    tersebut telah dipasang di Bilik Endoscopy Ultrasound, Endoscopy Laser dan

    Ujian Pendengaran Otorinalaringology tetapi masih tidak digunakan seperti di

    Gambar D-19 hingga D-21. Manakala 5 set peralatan berkenaan masih

    belum direkodkan.

    Gambar D-19 Gambar D-20

    Bilik Endoscopy Ultrasound Bilik Endoscopy Laser

    Gambar D-18

    Maklum Balas BPM:

    Satu kajian telah dilakukan pada 9

    Februari 2014 bagi menentukan sama ada

    Jabatan yang telah diberi toughbook

    menggunakan peralatan tersebut atau

    tidak. Satu surat arahan telah dikeluarkan

    kepada jabatan-jabatan tersebut supaya

    menggunakan toughbook tersebut.

    Sekiranya tiada keperluan untuk

    menggunakannya, jabatan diminta untuk

    memulangkan peralatan tersebut kepada IT

    HSNZ untuk diagihkan kepada pihak yang

    lebih memerlukan.

  • 2013 | LAPORAN TAHUNAN 11

    4.2.2 Peralatan Tidak Dapat Dikesan Dan Disimpan Di Luar Premis

    Kerajaan

    Daripada 5 set Frame Grabber yang belum direkod seperti perenggan di atas, 4 unit

    CPU, 2 unit monitor, 5 unit UPS dan 1 unit pedal infinitt tidak dapat dikesan.

    Manakala 1 unit CPU, 3 unit monitor, 4 unit pedal infinitt dan 1 unit Barco 2MP

    colour monitor telah disimpan di luar premis Kerajaan tanpa dokumen kebenaran

    dari Ketua Jabatan seperti di Gambar D-22 hingga D-32.

    Perkakasan 5 set Frame Grabber di Luar Premis Kerajaan

    Gambar D-22 Gambar D-23

    Gambar D-21

    Bilik Ujian Pendengaran

    Otorinalaringology

    Maklumbalas HSNZ:

    Peralatan 8 set Frame Grabber

    tersebut telah diagihkan ke Jabatan lain

    iaitu Klinik Oftalmologi, Klinik ORL, Unit

    Endoskopi dan Dewan Bedah tetapi

    masih tidak digunakan kerana imej yang

    dihasilkan adalah hitam putih. Ke

    semua peralatan RIS/PACS tidak

    didaftarkan secara rasmi dengan

    Bahagian Aset dan Perolehan kerana

    tiada dokumen lengkap diberikan

    oleh kontraktor third-party.

    Pihak HSNZ menaiktaraf Frame

    Graber daripada hitam putih kepada

    berwarna menggunakan peruntukan

    HSNZ secara berperingkat.

  • 12 VI-PENGAUDITAN PRESTASI | 2013

    3 unit Monitor Frame Grabber

    Gambar D-24

    Gambar D-25

    Gambar D-26

    4 unit Pedal Infinitt

    Gambar D-27 Gambar D-28

    1 unit CPU Frame Grabber

    Gambar D-29 Gambar D-30

  • 2013 | LAPORAN TAHUNAN 13

    1 unit Barco 2MP Colour Monitor yang dianggarkan

    bernilai melebihi RM70,000

    Gambar D-31 Gambar D-32

    4.3 Peralatan Rosak Tidak Diganti

    Merujuk kepada kontrak perjanjian HIS Para

    14.3 Appendix 2 Technical Requirements If

    a critical equipment has to be removed for

    repair or service or be made inoperable in

    excess of two (2) hours, the Contractor shall

    provide and install a temporary replacement

    unit with an equivalent configuration

    immediately for the whole duration of repair.

    Gambar D-33

    Maklum Balas HSNZ:

    Pemindahan peralatan ini adalah atas arahan pihak pengurusan hospital untuk

    memindahkan segera akibat ancaman bencana alam (ribut Sonamu) yang dijangka

    berlaku pada 7 Januari 2013.

    Pihak HSNZ telah menghantar surat rasmi kepada kontraktor bagi meminta

    penjelasan mengenai kehilangan Frame Grabber. Pihak Strateq Sdn. Bhd telah

    mengemukakan satu surat rasmi berkenaan kronologi kehilangan Frame Graber.

    Susulan daripada penemuan audit, tindakan telah diambil dengan mengarahkan pihak

    kontraktor membawa baki peralatan Frame Grabber ke HSNZ dengan segera. Pihak

    kontraktor juga telah membuat laporan polis berkenaan premis mereka diceroboh

    sehingga menyebabkan kehilangan perkakasan Frame Grabber.

  • 14 VI-PENGAUDITAN PRESTASI | 2013

    Semakan Audit Dalam mendapati seunit Firewall - Fortinate Fortigate FG-500A-BDL di HBTU

    bernilai RM108,259.20 (Gambar D-33) yang rosak dan dihantar untuk pembaikan pada 10

    Julai 2012 masih belum diterima semula daripada kontraktor sehingga tarikh pengauditan.

    Peralatan tersebut adalah bertujuan untuk mencegah daripada pencerobohan ke atas

    sistem. Sekiranya primary firewall tidak berfungsi, risiko pencerobohan ke atas sistem

    adalah tinggi kerana secondary firewall tidak ada.

    4.4 FM-200 Gas Fire Suppression System tidak disokong dengan Sijil Bomba

    Semakan Audit Dalam mendapati 1 unit FM-200 Gas

    Fire Suppression System di HSNZ bernilai RM57,574

    yang dibekal dan dipasang di bilik Data Centre tidak

    disokong dengan Sijil Bomba seperti di Gambar D-

    34.

    4.5 Pelan Kesinambungan Perkhidmatan Tidak Lengkap

    Pelan Kesinambungan Perkhidmatan perlu disediakan bagi memastikan kesinambungan

    sistem yang dibangunkan termasuklah mewujudkan off site back up data dan perisian

    komputer serta prosedur pemulihan bencana. Dasar Keselamatan ICT, KKM (DKICT KKM)

    yang dikeluarkan pada 2010 dan yang terkini semakan no. 4 tahun 2013 menyatakan

    Salinan Penduaan (Backup) perlu disediakan bagi memastikan sistem dapat dibangunkan

    semula setelah berlakunya bencana dan salinan penduaan juga hendaklah dilakukan setiap

    kali konfigurasi berubah.

    Semakan Audit Dalam mendapati pihak hospital telah membuat salinan penduaan ke atas

    semua data dan maklumat secara harian, mingguan dan bulanan. Bagaimanapun, salinan

    penduaan tidak disimpan di lokasi yang berlainan (off site). Juga didapati, pengujian

    Gambar D-34

    Maklum Balas BPM:

    Sijil Bomba Kompleks Rawatan Harian

    telah diperolehi pada 2 Januari 2014.

    Maklum Balas BPM:

    Surat peringatan telah dihantar kepada pihak PJSB pada 22 Januari 2014.

    Maklumbalas dari pihak PJSB menyatakan peralatan tersebut tidak dapat dibaiki dan

    pengantian akan dilakukan dalam masa terdekat. BPM dan Unit ICT HBTU akan

    memastikan penggantian dibuat dengan kadar segera.

  • 2013 | LAPORAN TAHUNAN 15

    backup sedia ada tidak dilaksanakan sekurang-kurangnya sekali setahun bagi memastikan

    ianya dapat berfungsi dengan sempurna, boleh dipercayai dan berkesan apabila digunakan

    khususnya pada waktu kecemasan.

    4.6 Modul Billing & Account Receivable di HBTU Tidak Digunakan Secara

    Keseluruhan

    4.6.1 Kod Hasil Bagi Bayaran Balik Deposit Tidak Diwujudkan

    Di dalam Surat Edaran Bahagian Akaun Bil. 7 Tahun 2010 mengenai Garis Panduan

    Penggunaan Akaun Panjar Khas Pesakit Hospital, penggunaan kod untuk bayaran

    balik (refund) adalah seperti berikut:

    i. Deposit Bayaran Cagaran Hospital (Warganegara Malaysia) Kod 76302

    (eSPKB) / 876302 (GFMAS)

    ii. Deposit Bayaran Cagaran Hospital (Warganegara Asing) - Kod 76303 (eSPKB) /

    876303 (GFMAS)

    Semakan Audit Dalam mendapati bayaran balik deposit bagi Kod Perakaunan 76302

    dan 76303 tidak dilaksanakan melalui modul Account Receivable kerana kod tersebut

    tidak diwujudkan. Pelaksanaan bayaran balik deposit ini telah dibuat melalui sistem

    e-Terimaan.

    Maklum Balas BPM:

    Keperluan penambahbaikan bagi mewujudkan kod hasil baru merupakan

    keperluan baru dan diluar skop projek. Pihak Kontraktor telah bersetuju untuk

    melaksanakan penambahbaikan kod hasil baru tanpa sebarang kos.

    Penambahbaikan sistem bagi kod hasil baru telah dilaksanakan pihak Kontraktor

    namun masih gagal memenuhi keperluan pengguna sehingga kontrak telah

    tamat. Modul PBAR dalam HIS telah diintegrasi dengan Sistem eTerimaan dan

    kebanyakan fungsi-fungsi yang terdapat di PBAR telah digunakan di dalam Sistem

    eTerimaan. Sebarang penambahbaikan/enhancement yang terhadap sistem

    selepas tarikh penerimaan pengujian akhir sistem (FAT) perlu melalui proses

    Change Request yang mugkin mempunyai implikasi kos sekiranya melibatkan

    major enhancement.

    Maklum Balas BPM:

    Pihak HSNZ sedang menguruskan back up data dalam bentuk tape untuk disimpan di Unit Teknologi Maklumat, JKNT. Bagi tujuan pengujian backup (restore)

    HSNZ akan membuat pengujian pada bulan Jun 2014.

  • 16 VI-PENGAUDITAN PRESTASI | 2013

    4.6.2 Surat Peringatan Tidak Dapat Dijana

    Modul PJMedica PB&ARPatient Billing and Account Receivable Module berkebolehan

    untuk menjana surat-surat peringatan bagi bil-bil pesakit kakitangan

    Kerajaan/tanggungan dan persendirian yang masih belum dijelaskan atau

    tertunggak.

    Semakan ke atas modul PJMedica PB&AR mendapati semua surat peringatan tidak

    dapat dijana dari sistem. Surat tersebut adalah seperti berikut:

    i. Surat peringatan pertama bayaran persendirian;

    ii. Surat peringatan kedua bayaran persendirian;

    iii. Surat peringatan ketiga bayaran persendirian; dan

    iv. Surat peringatan pertama penjawat awam.

    4.6.3 Laporan Cek Tendang Tidak Tepat

    Laporan Cek Tendang bertujuan memaparkan maklumat cek yang telah

    dikembalikan oleh pihak bank. Semakan Audit Dalam mendapati Laporan Cek

    Tendang tidak menyenaraikan cek-cek yang telah dikembalikan oleh bank tetapi

    hanya menyenaraikan bayaran secara tunai dan cek yang sah dalam Laporan

    tersebut.

    Penambahbaikan yang telah dimajukan kepada pihak Kontraktor (Request

    ID 15896/24.01.14) masih di dalam tindakan pihak Kontraktor. Contoh laporan

    bayaran balik deposit yang telah dikemaskini akan dikemukakan kepada pihak

    audit selepas kerja-kerja penambahbaikan selesai.

  • 2013 | LAPORAN TAHUNAN 17

    4.7 Pengiraan Jumlah Hari Kemasukan Wad Dan Discaj Pesakit Tidak Tepat

    Kawalan pemprosesan bertujuan memastikan setiap transaksi yang dilakukan oleh sistem

    adalah sah dan diproses dengan betul. Di bawah PERINTAH FEE (PERUBATAN) 1982,

    bagi maksud pengiraan bayaran wad, jumlah hari yang dikira adalah seperti berikut:

    (a) hari kemasukan hendaklah dikira sebagai satu hari penuh;

    (b) hari discaj hendaklah dikira sebagai satu hari penuh jika ia melebihi dua belas jam.

    Semakan Audit Dalam terhadap modul revenue system yang dibangunkan di Unit Hasil

    mendapati proses pengiraan jumlah hari kemasukan dan discharge pesakit dalam sistem

    tersebut tidak tepat. Proses pengiraan tersebut adalah secara auto generate dalam sistem

    tersebut. Contoh pengiraan yang tidak tepat bagi kes 1 dan 2 seperti di Jadual D-4 dan

    D-5.

    Kes 1: Pengiraan Terkurang:

    Bilangan hari yang patut dikira di dalam bil ialah dua hari tetapi telah dikira

    sebagai satu hari.

    Maklum Balas BPM:

    HBTU telah mengkaji semula laporan-laporan yang ada di dalam sistem HIS samada laporan-laporan tersebut diperlukan atau tidak bagi mengelakkan pembaziran seterusnya dari segi wang, tenaga dan masa untuk sesuatu yang tidak diperlukan.

    Unit Hasil, HBTU memutuskan untuk dinyahaktifkan laporan/modul yang berikut:

    i) Bill Management View dishonoured cheque Government Servant Reminder (kakitangan awam diberi

    pengecualian penuh)

    Refund Acknowledgement Letter (kos percetakan yang tinggi-kertas dan ink)

    ii) Account Penyesuaian Akaun Hasil (menggunakan sistem eTerimaan) Penyesuaian Akaun Amanah(menggunakan sistem eTerimaan) Write Off

    iii) Report Laporan Cek Tak Laku (menggunakan laporan sistem eTerimaan)

    iv) Generated Bill Blood Bank External (tiada link dengan billing) Misscellaneous (tiada link dengan billing)

  • 18 VI-PENGAUDITAN PRESTASI | 2013

    Jadual D-4

    Pengiraan Jumlah Hari Yang Dikenakan Bayaran Wad

    Tarikh Perintah Fee (Perubatan)

    1982

    Bil. Hari

    Yang

    Dikira

    Kiraan Bil Yang

    Dijana Dalam

    Sistem

    Tarikh

    Masuk

    18/09/2013

    23:58

    hari kemasukan hendaklah

    dikira sebagai satu hari penuh. 1 hari Tiada

    Tarikh

    Keluar

    19/09/2013

    12:47

    hari discaj hendaklah dikira

    sebagai satu hari penuh jika ia

    melebihi dua belas jam.

    1 hari 1 hari

    Jumlah hari yang perlu dikenakan bayaran 2 hari 1 hari

    Kes 2: Pengiraan Terlebih:

    Bilangan hari yang patut dikira di dalam bil ialah satu hari tetapi telah dikira

    sebagai dua hari.

    Jadual D-5

    Pengiraan Jumlah Hari Yang Dikenakan Bayaran Wad

    Tarikh Perintah Fee (Perubatan)

    1982

    Bil. Hari

    Yang

    Dikira

    Kiraan Bil Yang

    Dijana Dalam

    Sistem

    Tarikh

    Masuk

    20/10/2013

    01:00

    hari kemasukan hendaklah

    dikira sebagai satu hari penuh. 1 hari 1 hari

    Tarikh

    Keluar

    21/09/2013

    11:36

    haridischarge hendaklah dikira

    sebagai satu hari penuh jika ia

    melebihi dua belas jam.

    Tidak

    dikira 1 hari

    Jumlah hari yang perlu dikenakan bayaran 1 hari 2 hari

    4.8 Modul Executive Information System (EIS) Di HBTU Tidak Sempurna

    EIS menyediakan maklumat pengurusan pesakit dari pelbagai sumber bagi membantu pihak

    pengurusan membuat keputusan dan perancangan. Perisian Crystal Reports digunakan

    untuk merekabentuk dan menghasilkan statistik dan laporan. Sejumlah 291 laporan telah

    disediakan dan boleh diakses oleh pegawai yang dibenarkan sahaja. Walkthrough ke atas

    sistem ini mendapati kelemahan-kelemahan berikut:

    a) Laporan Reporting Death In Paediatric tidak dapat dijana.

    b) Laporan Buku Daftar Bersalin yang dijana tidak lengkap dengan maklumat

    Kumpulan Etnik/ Bangsa, Tarikh daftar masuk wad dan tarikh kelahiran bayi.

    Maklum Balas BPM:

    Bagi tindakan pembetulan, satu Change Request telah dihantar kepada pihak

    kontraktor pada 17 Februari 2014.

  • 2013 | LAPORAN TAHUNAN 19

    4.9 Preventive Maintenance Tidak Dilaksanakan Mengikut Kontrak

    Di dalam Appendix 2 Technical Requirements, Para 14.5 the Contractor shall provide a

    Planned Preventive Maintenance (PPM) schedule at least four (4) preventive maintenance

    services annually. Maintenance services must include dusting, vacuuming and shampooing

    of all ICT equipment

    Semakan Audit Dalam mendapati preventive maintenance bagi peralatan ICT hanya

    dilaksanakan sekali setahun berbanding 4 kali seperti yang ditetapkan mengikut kontrak.

    Tarikh Preventive Maintenance Yang Dilaksanakan

    Pada Tahun 2011 dan 2012

    Tahun Nombor Rujukan Tarikh Preventive Maintenance

    2011 HBB/ICT/300/1-3(9) 5 hingga 29 Disember

    2012 HBB/ICT/300/1-1(15) 12 hingga 30 Mac

    4.10 Latihan Daripada Pihak Kontraktor Tidak Mencukupi

    Berdasarkan Schedule 9, Training And Transfer Of Technology, pihak kontraktor hendaklah

    memberikan latihan seperti yang telah dinyatakan dalam kontrak. Jadual dari Perenggan

    29.1 adalah dirujuk. Manakala Schedule 9, Paragraph 4, menyatakan bahawa sijil

    penyertaan akan diberikan kepada setiap peserta.

    a) Latihan Daripada Pihak Pembekal Tidak Mencukupi

    Semakan Audit Dalam terhadap Training Report HIS Application Phase 1 dan 2 di

    HBTU mendapati latihan yang diberikan oleh pembekal kepada pengguna adalah

    tidak mencukupi seperti yang ditetapkan dalam kontrak. Butiran lanjut seperti di

    Jadual D-6.

    Maklum Balas BPM:

    BPM mengambil maklum dan akan memastikan perkara sama tidak berulang

    dalam projek-projek ICT akan datang.

    Maklum Balas BPM:

    Laporan Reporting Death In Paediatric dan Buku Daftar Bersalin telah

    diperbetulkan.

  • 20 VI-PENGAUDITAN PRESTASI | 2013

    Jadual D-6

    Latihan Daripada Pihak Pembekal Tidak Mencukupi

    Bil Tajuk Modul Kategori

    Pengguna

    Jumlah Latihan

    Seperti Dalam

    Kontrak

    (jam)

    Jumlah

    Latihan

    Telah

    Diberikan

    (jam)

    Jumlah

    Latihan

    Kurang

    Diberikan

    (Jam)

    1. Person Management

    System (PMS)

    Doctors 16 8 8

    Registration Clerk 20 8 12

    2. Pateint Billing & AR Nurse 40 0 40

    Super User 14 8 6

    3. Manage Diseases Person

    (FIMMS)

    Medical Assistant 20 8 12

    4. Medical Record

    Management

    Medical Record

    Staff

    32 16 16

    5. Discharge Summary Doctor 28 4 24

    6. Order and Report

    Management

    Doctor 16 8 8

    Sp Clinic Nurse/MA

    and Physiotherapy

    16 12 4

    7. Clinical Documentation Doctor 36 12 24

    8. System Administration for

    Profdoc HIS

    System

    Administrator / Unit

    Administrator

    46 9 37

    9. Laboratory Information

    System

    User Training I

    Laboratory Staff

    16 8 8

    10. System Administration for

    Training Profdoc LIS

    System

    Administrator / Unit

    Administrator

    46 4 42

    11. Pharmacy Information

    System (PhIS) & MMS

    Store (MM) 16 0 16

    Super User 20 8 12

    12. RIS/PACS Doctor, MA, Nurse 20 12 8

    Radiographer 20 12 8

    IT Administrator 12 4 8

    b) Sijil Penyertaan Menghadiri Latihan Tidak Diberikan Kepada Peserta

    Semakan Audit Dalam terhadap fail latihan di HBTU mendapati sijil penyertaan setiap

    peserta tidak diberikan oleh pihak kontraktor apabila tamat sesuatu latihan.

    c) Latihan Daripada Pihak Pembekal di HSNZ Tidak Dapat Disahkan

    Semakan Audit Dalam di HSNZ mendapati dokumen sokongan iaitu training report tidak

    dikemukakan untuk mengesahkan bahawa pihak pembekal ada memberi latihan kepada

    pengguna.

  • 2013 | LAPORAN TAHUNAN 21

    5. RUMUSAN DAN SYOR AUDIT DALAM

    Bagi memastikan pengurusan dan penggunaan HIS di Hospital Bintulu dan HSNZ

    dilaksanakan dengan lebih teratur dan mendapat value for money terhadap perbelanjaan

    yang dibuat, adalah disyorkan perkara berikut:

    (a) Kemudahan kenderaan dan peralatan di bawah peruntukan kerja awalan

    tidak boleh dilaksanakan bagi perolehan bekalan dan perkhidmatan serta

    perolehan bekalan dan perkhidmatan yang tidak diurus bersama projek

    pembinaan;

    (b) Perancangan yang teliti terhadap keperluan perolehan perkakasan dan

    perisian boleh mengurangkan risiko berlakunya pembaziran akibat peralatan

    dan perisian tidak digunakan;

    (c) Meningkatkan pemantauan terhadap penyimpanan peralatan bagi

    memastikan ianya selamat di bawah tanggungjawab pegawai berkenaan;

    (d) Meningkatkan pemantauan terhadap peralatan yang rosak dan memastikan

    penggantian dibuat seperti yang dinyatakan dalam kontrak;

    (e) Tindakan pembetulan hendaklah dibuat terhadap modul berkaitan bagi

    memastikan output yang dikeluarkan adalah tepat;

    (f) Memastikan penyenggaraan dalam waranti dilakukan oleh pihak pembekal

    mengikut kekerapan yang ditetapkan dalam kontrak; dan

    (g) Semua pegawai hendaklah diberi latihan kepenggunaan secara berterusan.

    Maklum Balas BPM:

    Pihak HBTU telah mengadakan latihan HIS kepada pengguna pada setiap hari Khamis minggu ke-3 setiap bulan dan Sijil Penyertaan telah dikeluarkan kepada

    peserta kursus.

    Maklum Balas HSNZ:

    Pihak HSNZ masih belum menerima laporan baru daripada pembekal mengikut

    pengiraan jumlah latihan di dalam kontrak asal. Strateq telah merancang latihan HIS

    yang perlu diberikan kepada pengguna.