gambar utk report harian

18
HV DEAD END CLAMP LV DEAD END CLAMP

Upload: sakinah-najjah

Post on 15-Oct-2014

241 views

Category:

Documents


7 download

TRANSCRIPT

Page 1: Gambar Utk Report Harian

HV DEAD END CLAMP LV DEAD END CLAMP

HV SUSPENSION CLAMP LV SUSPENSION CLAMP

J HOOK UNIVERSAL BAND

Page 2: Gambar Utk Report Harian

TRINGULAR BRACKET

CABLE SLAB CONCRETE(33KV) TIANG SPUN 10-5KN

KABEL ABC 33KV(3x150mmp+70mmp- 500m/drum)

Page 3: Gambar Utk Report Harian

LUBANG TIANG DIKOREK MENGGUNAKAN KREN AUGER SEDALAM 1.7m

TIANG DIANGKUT DAN DITANAM ATAU DITEGAKKAN MENGGUNAKAN KREN AUGER.

TIANG TELAH SELESAI DITANAM KAN.

Page 4: Gambar Utk Report Harian

PERATURAN KESELAMATAN LALU-LINTAS HENDAKLAH DIPATUHI APABILA KERJA-KERJA DILAKUKAN DI TEPI JALAN MENGIKUT PERATURAN KESELAMATAN LALU-LINTASOLEH SPESIFIKASI JKR.

TIANG SPUN.

Page 5: Gambar Utk Report Harian

MENAMPUNG PEPASANGAN MAKSIMUM (2LITAR HV ABC,2LITAR LV ABC)

Page 6: Gambar Utk Report Harian

-EARTHWIRE DI DALAM TIANG DISEDIAKAN UNTUKMEMBUMIKAN DAWAI NEUTRAL DANAKSESORI SISTEM

LV ABC SAHAJA

-TAMBAHAN EARTHWIRE YANG BERASINGANDIGUNAKAN UNTUK MEMBUMIKANSAMBUNGAN

(EARTH BONDING JOINT)SAHAJA.

- PEMASANGAN EARTH WIRE INI KEPADA HV ABCMESSENGER WIRE ATAU AKSESORI HV ABC ADALAH TIDAK DIBENARKAN.

TIANG SUDUT 90 ⁰ TIANG TAMATAN

TIANG SAMBUNGAN PANDANGAN ATAS TIANG SAMBUNGAN

PANDANGAN SISI TIANG SAMBUNGAN TIANG SESALUR TERUS

Page 7: Gambar Utk Report Harian

TIANG SUDUT KURANG 90⁰ PEMASANGAN TRIANGULAR BRACKET

HV CABLE TRAY PANDANGAN BAWAH HV CABLE TRAY PANDANGAN ATAS

CABLE TRAY MEMPUNYAI LUBANG DI BAHAGIAN BAWAH UNTUK MENGELAKKAN AIR BERTAKUNG

PEMASANGAN HV CABLE TRAY HV CABLE TRAY YNG TELAH SIAP DIPASANG

Page 8: Gambar Utk Report Harian

PEMASANGAN CABLE TRAY UTK SAMBUNGAN KABEL JARAK SPAN ANTARA TIANG ADALAH 30-35m

KELEGAAN DARI PARAS TANAH MELINTASI JALANRAYA. 1 METER DARI KIRI,KANAN DAN BAWAH SISTEM HV ABC

SEMUA DAHAN YANG DIATAS SISTEM MELINTASI TALIAN ATAS VOLTAN TINGGI TIDAK BETEBAT

HV ABC MESTI DICANTAS.

Page 9: Gambar Utk Report Harian

BAHAN-BAHAN PEMBINAAN UMBANG.

TIANG SUDUT-BIL UMBANG=2 TIANG SAMBUNGAN-BIL UMBANG=2

Page 10: Gambar Utk Report Harian

TIANG TAMATAN-BIL UMBANG=2 TIANG PEMBAHAGIAN-BIL UMBANG=2KIRI,2KANAN

HV ABC ROLLER ROLLER DIPASANG PADA TIANG SEMASA MERENTANG KABEL

SINGLE CIRCUIT END BRACKET