effect of progressive payment on lad, interim payment certificates

50
[2012] 1 LNS 720 Legal Network Series DALAM MAHKAMAH TINGGI MALAYA DI MUAR DALAM NEGERI JOHOR DARUL TAKZIM [GUAMAN SIVIL NO: 23-47-2008] BETWEEN CAMELLIA VIEW SDN BHD ... PLAINTIF AND ENVIPRO SDN BHD ... DEFENDEN [GUAMAN SIVIL NO: 22-98-2008] ANTARA ENVIPRO SDN BHD ... PLAINTIF DAN CAMELLIA VIEW SDN BHD ... DEFENDAN (dipindahkan dari Mahkamah Sesyen Batu Pahat dan digabungkan melalui Perintah bertarikh 31 haribulan Mac 2009) 1

Upload: cassandragan

Post on 16-Sep-2015

266 views

Category:

Documents


1 download

DESCRIPTION

ghhgfhfhf

TRANSCRIPT

  • [2012] 1 LNS 720 Legal Network Series

    DALAM MAHKAMAH TINGGI MALAYA DI MUARDALAM NEGERI JOHOR DARUL TAKZIM

    [GUAMAN SIVIL NO: 23-47-2008]

    BETWEEN

    CAMELLIA VIEW SDN BHD ... PLAINTIF

    AND

    ENVIPRO SDN BHD ... DEFENDEN

    [GUAMAN SIVIL NO: 22-98-2008]

    ANTARA

    ENVIPRO SDN BHD ... PLAINTIF

    DAN

    CAMELLIA VIEW SDN BHD ... DEFENDAN

    (dipindahkan dari Mahkamah Sesyen Batu Pahat dan digabungkanmelalui Perintah bertarikh 31 haribulan Mac 2009)

    1

  • [2012] 1 LNS 720 Legal Network Series

    CONTRACT: Breach - Contract for work done and material supplied- Whether defendant breached its obligation by changing pilingmaterial without consent of plaintiff - Whether plaintiff entitled todifference in costs for unilateral change of piling material - Whetherit was defendant's fault in building the sewage treatment plant (STP)out of position - Whether defendant depended on the accuracy ofplaintiff's demarcation of the site of the STP - Whether plaintiffestopped from denying that it had knowledge of the error and signedthe Amended Plan in order to have it submitted to relevant authorityfor approval

    CONTRACT: Breach - Delay - Damages - Whether defendantdelayed in completing and handing over the STP on or before31.12.2005 - Whether plaintiff entitled to liquidated ascertaineddamages (LAD) - Whether fact that plaintiff made progress paymentsto defendant meant that plaintiff waived its rights to claim LADagainst defendant

    CONTRACT: Building contract - Progress payments - Pegasusinformally engaged by plaintiff as superintending engineer - WhetherPegasus's role purely that of an employee of plaintiff or its"agent" for purposes of Contract - Whether basic principlespertaining to role of a superintending engineer or architectapplicable to Pegasus - Whether role included issuance ofCertificate of Practical Completion (CPC) - Whether it waspremature of Pegasus to have issued CPC - Whether progresspayments made by plaintiff to defendant vis Progress PaymentCertificates Nos. 5 to 7 prevented plaintiff from challenging decisionof Pegasus - Whether plaintiff was estopped from disputing CPC -Whether CPC should have been issued much later - Whether CPCwas wrongly issued by Pegasus and therefore invalid

    2

  • [2012] 1 LNS 720 Legal Network Series

    [For the 2008 case, special damages comprising of deductions in costof piling material at RM4,952.00 and LAD of RM240,000.00 allowed;general damages as a result of the encroachment into the buffer zonedisallowed; a declaration that the CPC issued by Pegasus on 2.1.2006was null and void allowed with interest and costs; For the 2009 case,RM129,998.00 is payable by Plaintiff to Defendant which shall beset-off from sums due from Defendant to Plaintiff in the 2008 Casewith interest and costs.]

    Case(s) referred to:Hiap Hong & Co Pte Ltd v. Ong Huat Development Co (Pte) Ltd[2001] 2 SLR 458 (refd)Ooi Yoke In (F) and Anor v. Public Finance Bhd [1993] 2 CLJ 464 (refd)Sakinas Sdn Bhd v. Slew Yik Hau & Anor [2002] 5 MLJ 497 (refd)Serangoon Garden Estate Ltd v. Marian Chye [1959] 25 MLJ 113 (refd)Syarikat Ong Yoke Lin Sdn. Bhd. v. Giant Cash and Carry Sdn Bhd &Ors [2000] 4 CLJ 733 (HC) @ 759 (refd)

    Legislation referred to:

    Contracts Act 1950, s. 75

    Evidence Act 1950, s. 114(g)

    Other source(s) referred to:

    Hudson's Building And Engineering Contract , 12 th Edition, Sweet andMaxwell, 2010, under the sub-heading of Design and BuildContracts, at pages 522, 523, 524 paragraph 3-130

    Nigel M Robinson , et al, Construction Law in Singapore andMalaysia, Second Edition, Butterworths Asia, 1996, pg. 301-302, 344-346

    3

  • [2012] 1 LNS 720 Legal Network Series

    GROUNDS OF JUDGMENT

    A. PRELIMINARIES:

    [1] For the purposes of these actions, the Court will refer the parties

    as in Civil Suit No. 23-47-2008 (the 2008 Case) as the Plaintiff and the

    Defendant respectively.

    [2] The Defendant had commenced an action against the Plaintiff at

    the Batu Pahat Sessions Court for the sum of RM129,998.00 being the

    balance of payment due under several Progress Payment Certificates;

    whilst the Plaintiff had commenced an action (being the 2008 Case)

    against the Defendant at the Muar High Court as remedies sought by

    the Plaintiff involved higher amounts than being within the jurisdiction of

    the Sessions Court. The Sessions Court case was then transferred to

    the Muar High Court and re-registered as Civil Suit No. 22-98-2009 (the

    2009 Case). Both the 2008 Case and the 2009 Case were

    consolidated on 6.3.2012.

    4

  • [2012] 1 LNS 720 Legal Network Series

    B. THE 2008 CASE:

    [3] In the 2008 Case, the Plaintiff claimed against the Defendant for:-

    3.1. special damages comprising of:-

    3.1.1. deductions in cost of piling material for the sum of

    RM12,963.20;

    3.1.2. liquidated and ascertained damages (LAD) of RM289,500.00;

    3.2. general damages, including loss and damage suffered as a result

    of the encroachment by the Defendant into the buffer zone;

    3.3. a declaration that the Certificate of Practical Completion (CPC)

    issued by Pegasus Engineers Sdn. Bhd. (Pegasus) on 2.1.2006

    is null and void;

    3.4. interest and costs.

    C. THE 2009 CASE:

    [4] In the 2009 Case, the Defendant claimed against the Plaintiff for

    the sum of RM129,998.00 together with interest and costs in respect of

    7 Progress Payment Certificates issued by Pegasus.

    D. THE FACTS:

    [5] The Plaintiff is a company carrying on the business as a housing

    5

  • [2012] 1 LNS 720 Legal Network Series

    developer. The Defendant is an environmental engineering company

    which specialises in the building of sewage treatment plants.

    [6] By letters dated 7.4.2005 and 28.6.2005 between the Plaintiff and

    the Defendant forming the contract between them (the said Contract),

    the Plaintiff had engaged the Defendant to execute and complete a

    sewage treatment plant (the STP) on Lot 9254 situated within the

    Plaintiff's housing development area called Taman Flora Utama in

    Mukim Simpang Kanan, Batu Pahat Johor in accordance with the Site

    Plan for an Extended Aeration Process System for 6500 PE dated July

    2005 (page 37, B), (the Site Plan).

    [7] The essential terms of the said Contract were:-

    7.1. the contract sum was RM1,350,000.00;

    7.2. the said Contract was a design and build contract where the

    Defendant was responsible for, amongst other things, all

    authorities submissions, approval, inspection and handing over to

    the authorities upon completion;

    7.3. the date of site possession was 1.7.2005;

    7.4. the date of completion of the whole works was 31.12.2005; and

    7.5. the LAD was fixed at RM1,500.00 per day.

    6

  • [2012] 1 LNS 720 Legal Network Series

    The Plaintiff's Case

    [8] The Plaintiff alleged that in breach of the said Contract, the

    Defendant had used bakau piles instead of reinforced concrete piles for

    the piling works of the main tank. Hence it was the contention of the

    Plaintiff that it was entitled to retain the actual savings that had resulted

    from the change in the piling material amounting to RM12,963.20 .

    [9] The Plaintiff alleged that in breach of the said Contract, the

    Defendant had constructed the STP in such a manner that its outer

    boundary wall had encroached into the buffer zone of the STP of

    approximately 7.8 metres between the outer boundary wall of the STP

    and the row of shop houses (namely Lot PTD 39455), and

    approximately 8.8 metres between the outer boundary wall of the STP

    and the row of double-storey terrace houses (namely Lots PTD 39412,

    PTD 39413, PTD 39414 and PTD 39415) wherein the buffer zone must

    at least be 12 metres wide. As a result of the said encroachment the

    Plaintiff was initially unable to sell Lot PTD 39455 and had only

    succeeded in selling the said Lot for a lower sum of RM390,000.00.

    Similarly, the Plaintiff only succeeded in selling the double-storey terrace

    houses at a lower price of RM266,800.00. The Plaintiff had therefore

    suffered losses and damages as a result of the Defendant 's breach.

    7

  • [2012] 1 LNS 720 Legal Network Series

    [10] The Plaintiff alleged that the Defendant had only completed and

    handed over the STP to the Sewerage Service Department on

    13.7.2006, thus incurring a delay of 193 days. The Plaintiff therefore

    claimed LAD of RM289,500.00 against the Defendant.

    [11] As the Plaintiff alleged that the Defendant had only completed the

    whole works on 13.7.2006, the Plaintiff's superintending engineer,

    Pegasus, had erroneously issued the CPC certifying that the Defendant

    had practically completed the works on 31.12.2005. The Plaintiff

    therefore sought for a declaration that the CPC was null and void.

    The Defendant's Case.

    [12] The Defendant in essence denied the Plaintiff's claim against it.

    With regard to the Plaintiff's claim to the savings in respect of the use of

    bakau piles, it was the Defendant's contention that the bakau piles were

    used at the Plaintiff's request resulting in the said Contract price was

    reduced from RM1,350,000.00 to RM1,345,048.00.

    [13] As for the Plaintiff's allegation that the Defendant had constructed

    the STP in a manner where the boundary wall of the STP had

    encroached into the buffer zone, the Defendant denied the allegation

    8

  • [2012] 1 LNS 720 Legal Network Series

    and instead alleged that even if there had been encroachment, it was

    due to the Plaintiff's submission of the Amended Plan to the authorities

    in December 2005 by Pegasus and which was approved on 23.1.2006.

    That the construction of the STP was in accordance with the Amended

    Plan. Further, the Plaintiff had sold the double-storey houses Lot PTD

    39412 and Lot PTD 39413 without incurring any loses whilst the buffer

    zone vis Lot 39415 had not changed from 12 metres wide,

    [14] The Defendant alleged that there was no delay in completing the

    works since it was by the Plaintiff's own action vis its superintending

    engineer Pegasus which had caused the Plan to be amended and

    consent to the amendment of the Plan was only obtained on 23.1.2006 .

    The Defendant alleged that the Plaintiff had waived the date of

    completion since the Plaintiff had made payments to the Defendant to

    the sum of RM1,215,050.00 under the said Contract.

    [15] It was the Defendant's contention that the CPC was issued by the

    Plaintiff itself vis Pegasus and therefore the Plaintiff was estopped from

    disputing the CPC.

    9

  • [2012] 1 LNS 720 Legal Network Series

    [16] Instead the Defendant claimed that the Plaintiff owed it the sum of

    RM129,998.00 as per the Defendant's claim in the 2009 Case.

    E. THE ISSUES:

    [17] The parties had agreed to 11 issues to be tried. However I have

    adopted the 4 main issues as proposed by the Plaintiff's counsel, with

    some modifications, in his submission as well as 1 issue in respect of

    the Defendant's claim against the Plaintiff. They are:-

    17.1. whether the Defendant had breached its obligation by changing

    the piling material without the consent of the Plaintiff;

    17.2. whether the Defendant was at fault in the STP being built not in

    accordance with the Site Plan;

    17.3. whether the Defendant had delayed in completing and handing

    over the STP on or before 31.12.2005;

    17.4. whether the superintending engineer Pegasus had erroneously

    issued the CPC dated 2.1.2006; and

    17.5. whether the Plaintiff owed the Defendant the sum of

    RM129,998.00, being the balance of the said Contract sum

    remaining unpaid.

    10

  • [2012] 1 LNS 720 Legal Network Series

    F. Whether the Defendant had breached its obligation by

    changing the piling material without the consent of the

    Plaintiff.

    [18] It was submitted for the Plaintiff that the Defendant had without its

    knowledge and consent unilaterally changed the piling materials of the

    main tank from reinforced concrete piling to bakau piling which was a

    cheaper alternative in contravention of Clause 6.7.1 of the Defendant's

    Quotations (page 3, B). The Plaintiff had never at any material time

    consented to such changes.

    [19] That the Defendant's second witness, SD2, had stated in his

    Witness Statement D2, Q & A 25, 26, 27, 28 that the Plaintiff had agreed

    to the quotation stated in the Projected Cost of Piling Work at pge 3, C,

    (Projected Cost) which was RM95,048.00. It thus reduced the contract

    sum from RM1,350,000.00 to RM1,345,048.00. When SD2 was cross-

    examined that the Plaintiff could not have agreed for the use of the

    bakau piles at the cost of RM95,048.00 in June or July as the quotation

    was dated 17.9.2005, SD2 had denied the matter (page 47, Notes of

    Evidence). SD2 had admitted that the quotation in the Projected Cost

    was for the actual costs of bakau piling after completion of piling works

    11

  • [2012] 1 LNS 720 Legal Network Series

    (page 47, Notes of Evidence). Therefore, it was submitted that SD2's

    testimony that the quotation was agreed to in June 2005 cannot be

    accepted as in June he would not have actual costs of construction

    using bakau piles to obtain the Plaintiff's agreement. There was

    therefore no such estimation being presented to the Plaintiff for the

    Plaintiff's approval. Moreover, SD2 had also admitted under cross-

    examination that, with reference to page 58, B, the Defendant had as at

    15.8.2005 already gone ahead to order bakau piles without obtaining the

    Plaintiff's consent and that there was no written letter from the Plaintiff to

    agree to the use of bakau piles (pages 46-48, Notes of Evidence).

    [20] In view of these facts, it was submitted by the Plaintiff that it should

    be compensated with a minimum sum of RM12,963.20 being the

    difference in costs for the unilateral change of the piling material.

    [21] It was submitted by the Defendant that the Plaintiff had raised this

    issue as an after thought seeing that vide Envipro's letter to Pegasus

    dated 12.1.2006, carbon copied to the Plaintiff, on pages 56-57, B,

    clearly showed the Plaintiff's knowledge and consent to the use of the

    bakau piles for all piling works after a discussion and soil test was done.

    Moreover, the Plaintiff had not at any time disputed nor objected to the

    12

  • [2012] 1 LNS 720 Legal Network Series

    use of the bakau piles for all piling works especially in respect of all

    payments made after 12.1 200& It was the Defendant's contention that

    the document on page 3, C, proved that the Plaintiff had agreed and

    consented to the Defendant using the bakau piles.

    [22] After a close perusal of SD2's testimony, I find that the learned

    counsel for the Plaintiff had been mistaken in stating that SD2 had

    testified that the Plaintiff had agreed to the quotation stated in the

    Projected Cost in June 2005 when the Projected Cost was dated

    17.9.2005. What SD2 stated in his Answers 25, 26 and 27, D2, was that

    in the month of June, July 2005 after soil tests were carried out, there

    was a discussion held in early August 2005 wherein the Plaintiff had

    directed the Defendant to use bakau wood for all piling in the

    construction of the STP and whereby the new contract price for the STP

    was RM1,345,048.00 with the cost of the bakau wood being agreed at

    RM95,048.00 as per the Projected Cost on page 3, C. I quote at length

    below the Q & A 25 - 27 of SD2 for a better understanding:-

    S25: Minta jelaskan samada harga kontrak RM1,350,000.00 itu dikekalkan

    atau terdapat perubahan kepada harga kontrak itu.

    J25: Pada bulan Jun, Julai 2005 selepas menjalankan ujian tanah (soil test)

    satu perbincangan telah diadakan pada awal bulan Ogos 2005 di

    13

  • [2012] 1 LNS 720 Legal Network Series

    mana Camellia mengarahkan Envipro menggunakan kayu bakau untuk

    semua piling untuk pembinaan loji tersebut di mana jumlah harga

    kontrak pembinaan loji baru adalah RM1,345,048.00.

    S26: Adakah Envipro mengeluarkan sebut harga untuk bakau piling yang

    diarahkan oleh Camellia?

    J26: Ada, kos untuk bakau piling adalah sebanyak berjumlah RM95,048.00.

    Minta lihat muka surat 3 Ikatan Dokumen Tambahan Defendan.

    S27: Minta jelaskan pembezaan di antara harga asal RM1,350,000,00

    dengan harga baru RM1,345,048.00 yang berjumlah RM4,952.00.

    J27: Pada awalnya Camellia bersetuju RC Piling dengan harga

    RM70,000.00 dan bakau piling dengan harga RM30,000.00 berjumlah

    RM100,000.00 seperti di revised quotation Envipro di muka surat 3

    Ikatan Dokumen Bersama. Selepas kajian tanah pada Jun, Julai 2005

    Camellia mengarahkan Envipro menggunakan kayu bakau untuk

    semua piling dengan harga yang dipersetujui RM95,048.00. Ini

    terdapat perbezaan RM4,952.00 apabila ditolak daripada harga

    asal RM100,000.00. Justeru, harga baru kontrak menjadi

    RM1,345,048.00,

    [23] Even though I find learned counsel for the Plaintiff was mistaken, I,

    however, find that he was correct in saying that SD2 had stated the

    agreed price for the bakau piles was RM95,048.00 as quoted by the

    Defendant in the Pro jec ted Cos t on page 3 , C , which was da ted

    14

  • [2012] 1 LNS 720 Legal Network Series

    17.9.2005, which could not be the case seeing that the purported

    agreement by Mr Wong / SP1 of the Plaintiff of the new price had

    purportedly taken place some time in early August 2005.

    [24] This issue was further complicated when SD2 attempted to explain

    during cross-examination the discrepancy between the date of the

    quotation in the Projected Cost on page 3, C, that is, 17.9.2005 and the

    ability of the Plaintiff agreeing with that quotation in Jun, July 2009. In

    giving his explanation, SD2 had contradicted his earlier testimony during

    examination-in-chief by referring to a letter written by him for the

    Defendant dated 5.8.2005 on pages 39-42, B, to the Plaintiff purportedly

    giving the Plaintiff / SP1 the estimated cost of bakau piles for all

    estimated to be at RM109,898.00 including the cost of the soil

    investigation. SD2 then stated that once SP1 had agreed with

    Appendix E (on page 42, B), the Defendant had proceeded with the

    bakau piling (page 47 Notes of Evidence). In so stating, I find once

    again SD2 had contradicted himself when he later admitted during

    cross-exmination that, with reference to page 58, B, the Defendant had

    as at 15.8.2005 already gone ahead to order bakau piles without

    obtaining the Plaintiff's consent (page 48, Notes of Evidence) and that

    15

  • [2012] 1 LNS 720 Legal Network Series

    there was no written letter from the Plaintiff to agree to the use of bakau

    piles

    [25] As for the Defendant's letter dated 12.1.2006, purportedly carbon

    copied to the Plaintiff, I am at a loss to understand how this letter could

    be said to clearly show the Plaintiff's knowledge and consent to the use

    of bakau piles for all piling works. In the first place, this letter was dated

    12.1.2006 when the bakau piling works had already been completed. In

    the second place, the intent of this letter was to ask Pegasus's consent

    for the extension of time to complete the STP works; failure on the

    Defendant's part to obtain Pegasus's consent would mean that the

    Defendant had delayed completing the works on time as per the

    contracted date of 31.12.2005. In the third place, the contract between

    the parties was a design and build contract which meant that once the

    Plaintiff had agreed to the terms of the said Contract the Defendant was

    left to ensure the performance of the said Contract to this completion.

    [26] In view of these material contradictions in SD2's evidence and no

    documentary evidence to prove that the Plaintiff / SP1 did agree to the

    use of bakau piles for all the construction of the STP, I find that the

    Defendant had breached its contractual obligations by changing the

    16

  • [2012] 1 LNS 720 Legal Network Series

    piling material, namely the R.C. piles for the main tank to bakau piles,

    without the consent of the Plaintiff. A perusal of the Defendant's letter

    dated 5.8.2005 (page 39, B,) to the Plaintiff showed very clearly there

    was no attempt made by the Defendant to obtain the consent of the

    Plaintiff on the use of the bakau pile in spite knowing that the said

    Contract was a design and build one. Instead, the said letter was written

    to the Plaintiff by stating as a fact that:-

    With reference to the above-mentioned matter, please be informed that

    the projected cost of bakau piling work as per latest consultant design is

    RM109,898.00. Kindly refer to Appendix E and drawing No.

    ESB1152/2005/RC-005 for details .

    [27] The Plaintiff had proposed to the Court to grant it the sum of

    RM12,963.00, being the difference in costs for unilateral change of piling

    material. I find the said amount as not justifiable because the original

    Contract sum was RM1,350,000.00 whereas the revised quotation

    taking into account the use of bakau piles wholly was RM1,345,048.00.

    This meant that the difference in price, or cost savings was RM4,952.00.

    In the circumstances I do so grant the said sum of RM4,952.00 to the

    Plaintiff as being appropriate damages suffered by the Plaintiff.

    17

  • [2012] 1 LNS 720 Legal Network Series

    G. Whether the Defendant was at fault in the STP being built not

    in accordance with the Site Plan.

    [28] It was not in dispute that the Site Plan was designed by the

    Defendant and accepted by the Plaintiff and approved by the relevant

    authorities. It was also not in dispute that the STP was built out of

    position from that found in the Site Plan. The questions therefore arose

    whether it was the Defendant's fault in building the STP out of position

    and whether the defence of estoppel applied against the Plaintiff.

    [29] The Defendant chose to deal with this issue, as well as other

    issues raised by the Plaintiff, by taking the position that the Plaintiff was

    estopped from raising it. According to the Defendant, the Plaintiff itself

    had prepared the Amended Plan as contained in page 53, B, and which

    was approved on 23.1.2006 by the relevant authorities. That the Plaintiff

    had never raised any objection to the change in the position of the STP

    until the Defendant filed the 2009 Case in the Sessions Court. Neither

    did the Plaintiff raise any objection when it made progress payments to

    the Defendant. Learned counsel for the Defendant urged the Court to

    invoke the adverse inference against the Plaintiff under section 114(g)

    Evidence Act 1950 (Evidence Act) for the Plaintiff's failure to call as its

    18

  • [2012] 1 LNS 720 Legal Network Series

    witness the expert surveyor who had surveyed the Site. Further,

    pursuant to Clauses 9.6 and 9.7 of the said Contract (pages 1-7, B) it

    was submitted that the burden of proof was on the Plaintiff to prove the

    terms and conditions stipulated therein and that it was not the

    responsibility of the Defendant to survery the site of the STP.

    [30] The Defendant submitted that it was mere speculation on the part

    of the Plaintiff when the Plaintif submitted that even if the Plaintiff was

    told about the shift of the STP the Plaintiff had no choice but to accept

    the construction as it was and to sign the Amended Plan and submit to

    the authorities for approval. Otherwise it would mean that the Defendant

    would have to re-construct the STP according to the Plan, which in turn

    would not be viable for the Plaintiff as the Plaintiff needed to handover

    32 units of double storey shop houses to the purchasers by early March

    2006.

    [31] As for the losses suffered by the Plaintiff under this issue, the

    Defendant submitted that the burden of proof was on the Plaintiff to

    prove specifically its claims for losses and compensation and the

    Plaintiff was precluded from submitting that the Defendant's counsel had

    19

  • [2012] 1 LNS 720 Legal Network Series

    not specifically cross-examined the Plaintiff's sole witness on this

    aspect.

    [32] It was the submission of the Plaintiff that the Defendant's position

    that the demarcation of the STP site was to be provided by boundary

    stones and that the Defendant's reliance on Clause 9.6 of the so-called

    Revised Quotation (pages 1-9, B) was wrong, as according to SD1

    Clause 9.6 implied that the demarcation was provided by boundary

    stones. Whereas, and as submitted by the Plaintiff, this Clause had no

    relation to the boundary stones on the Site but relate to the demarcation

    of the STP reserve on the layout plan for the entire housing project. The

    Plaintiff's contention was supported by the testimony of SD1, who had

    designed the original plan of the STP. SD1 had testified that Clause 9.6

    meant that the specific place where the STP would be built would have

    been disclosed to the Defendant in the layout plan itself and that the

    demarcation on the layout plan had allowed SD1 of the Defendant to

    design the STP (page 22, Notes of Evidence).

    [33] It was further submitted that the Defendant knew from day one the

    requirement for a buffer zone and had prepared the Site Plan. The

    Defendant therefore should have done a survey according to the Plan

    20

  • [2012] 1 LNS 720 Legal Network Series

    prepared by it to ascertain the proper boundary for the STP and cannot

    now blame the Plaintiff by saying that the Plaintiff had provided a wrong

    demarcation of the STP reserve to it when no such demarcation by way

    of boundary stones was ever given.

    [34] It was the Plaintiff's position that the wrong positioning of the STP

    was done by the Defendant from day one. SD2 had admitted that he did

    not discover the error until December 2005, which was toward the end of

    the contract term. The Defendant did not inform the Plaintiff specifically

    about the mistake; neither was there a letter indicating to the Plaintiff

    that the STP had been built out of its original location.

    [35] As for the signing of the Amended Plan by SP1, being the

    Defendant's strong point in invoking the principle of estoppel against the

    Plaintiff, it was submitted by the Plaintiff that SD2 had on or about

    15.12.2005 come to see the Plaintiff's Managing Director / SP1 and

    represented to him that there were documents which needed to be

    signed in order to facilitate submissions and approval from the relevant

    authorities. SD2 then left with the signed Amended Plan. However,

    SD2 denied he had anything to do with the signing of the Amended Plan

    and taking it back. But as SD1 had testified that the Amended Plan was

    21

  • [2012] 1 LNS 720 Legal Network Series

    received by her directly from SD2, and as SD2 had admitted that there

    was no covering letter from the Plaintiff enclosing the Amended Plan

    back to the Defendant, it was submitted by the Plaintiff that this went to

    support and corroborate the Plaintiff's contention that the Defendant did

    misrepresent to the Plaintiff's Managing Director / SP1 in getting the

    latter to sign the Amended Plan.

    [36] As SP1 testified that the Plaintiff had never received a copy of the

    letter at page 45, B, (which explained about the reduction of buffer

    zones of the STP) and as SD1 had testified that she had prepared the

    same by using the letter head of Pegasus, it was submitted by the

    Plaintiff that this showed the Plaintiff had no knowledge of the changes

    to the buffer zone at this point in time and had never agreed to the

    changes. Therefore, the Plaintiff argued that the principle of estoppel

    was not applicable to the Plaintiff.

    [37] Under Clauses 9.6 and 9.7 (page 4, B) of the Revised Quotation,

    which fall under the heading in Clause 9.0 General Assumptions, the

    parties had agreed to these two assumptions as follows:-

    9.6. Demarcation of Sewage Treatment Plant reserve will be available.

    22

  • [2012] 1 LNS 720 Legal Network Series

    9.7. STP reserve, setback and buffer zone comply with requirement by

    authorities.

    As there are no other provisions in the said Contract which could throw

    any light on the responsibilities of both parties in respect of the Site

    issue, I will have to decide the issue based on these 2 Clauses. I rule

    that based on these 2 Clauses, it was the responsibility of the Plaintiff to

    demarcate the site of the STP on the ground taking into account the

    measurement of the STP reserve, set back and buffer zone as approved

    by the authorities. It was not good enough for the Plaintiff to merely

    provide the Defendant with the demarcation for the Site Plan purposes;

    the Plaintiff was also required to provide the boundary stone on the

    ground for the STP reserve and the buffer zone. My finding of fact is

    corroborated by the testimony of SP1 himself when he stated as follows

    (page 10, Notes of Evidence):-

    Pages 1-7, B referred.

    Q: Refer page 4, B, item 9.0 especially 9.6 explain what is this Clause

    9.6 is about? Is it the duty of the Plaintiff under this clause to provide the

    demarcation of the STP to be made available?

    A: By 9.6, it means for the Plaintiff to see what is the shape of the land where

    the STP is supposed to be built upon because if don't show him where the

    STP is, they would not know where the STP is to be.

    23

  • [2012] 1 LNS 720 Legal Network Series

    Surely, SP1 could not have meant literally just to see the site and the

    Defendant would know what to do. I had scrutinised the Revised

    Quotation agreed to by the Plaintiff and I do not find any item of work

    and costs pertaining to the need of the Defendant to cause the survey of

    the Site for the location of the STP and its buffer zone before starting

    construction works. Such an absence, and in view of Clauses 9.6 and

    9.7, can only mean that it was the responsibility of the Plaintiff to

    demarcate the site for the STP and its buffer zone, it being the

    assumption of both parties that this was the case. Further, during cross-

    examination, and with reference to page 45, B, SD1 had agreed to the

    Plaintiff's counsel's suggestion that penandaan batu sempadan rezab

    meant it was the stone marker setting out the corner of the land on

    which the STP plant was to be built (page 43, Notes of Evidence). On

    further questioning, SD2 had this to say about the demarcation stones

    (page 44, Notes of Evidence):-

    Q: When before you start the piling would you not engage a surveyor to

    peg the location of the buildings?

    A: Normally we'll not hire a surveyor because the Plaintiff had already

    given us the boundary stone or rather Plaintiff has already done the

    demarcation of the STP reserve. We only do the necessary internal set

    back.

    24

  • [2012] 1 LNS 720 Legal Network Series

    . . .

    Q: Where boundary stones are concerned you stated they are at the

    corner of the property?

    A: Yes.

    Q: If boundary stones are placed at the corners of the property one would

    have to engage a surveyor to ensure the line are straight?

    A: I disagree. It is unnecessary because the Plaintiff already hired

    surveyor to mark out the STP area.

    [38] I'm fortified in my finding by referring to the authoritative textbook

    on building contracts entitled Hudson's Building And Engineering

    Contract, 12 th Edition, Sweet and Maxwell, 2010, under the sub-

    heading of Design and Build Contracts, at pages 522, 523, 524

    paragraph 3-130, entitled (iv) Responsibility for accuracy of information

    as to the site and its effect on design where it is stated as follows:-

    One of the key sources of Employer - supplied information affecting the

    efficacy of the design and build Contractor's design is the accuracy and

    completeness of information as to the site. Unforeseen site conditions are

    a fertile source of dispute in all building and engineering contracts. If price

    certainty and single point responsibility are the prime factors in a design

    and build project, the scope for additional cost, delay and ultimately failure

    of the project arising from conditions encountered at site which adversely

    25

  • [2012] 1 LNS 720 Legal Network Series

    affect construction because they fail to comply with the parameters or

    bases of the design cannot be underestimated.

    .. .

    The provision of information about the site and underground

    conditions is generally the responsibility of the Employer.

    Nonetheless, the importance of site conditions to the success of a design

    gives rise to particular issues in the context of design and build contracts.

    Particular issues that arise with respect to design and build contracts are:

    (a) the extent to which the Contractor is required to obtain or verify site

    information for itself or may rely only on that provided by the

    Employer, (b) the responsibility of the Contractor for inaccuracies or

    incompletness of site information, and (c) the placing of the risk of

    unforeseen conditions.

    . . .

    Most standard form contracts do not place the burden of site conditions

    quite so clearly upon the Contractor. Generally the Employer remains

    responsible for the accuracy of the information i t provides and

    the Contractor is responsible for the appropriate interpretation of that

    information.

    [Tekanan ditambahkan.]

    [39] In this regard, the Plaintiff's reference to SD1's testimony that

    Clause 9.6 referred to the demarcation in the layout plan of the Plaintiff

    26

  • [2012] 1 LNS 720 Legal Network Series

    the specific place where the STP would be built would contradict what

    SP1 himself had said, that is, if the Plaintiff did not show the Defendant

    where the STP was on the ground, the Defendant would not know where

    the STP was to be. In any case, that was the view expressed by SDI. I

    agree with SD1's testimony in the sense of the Plaintiff was responsible

    for the demarcation in the layout plan of the Plaintiff the specific place

    where the STP would be built, but disagree with her testimony that that

    was all that was provided for under Clause 9.6.

    [40] In view of my finding that it was the responsibility of the Plaintiff to

    demarcate the STP and its buffer zone, and since the Defendant had

    depended on the boundary stones of the STP as demarcated by the

    Plaintiff's surveyor before the Defendant started work on the STP, I

    therefore find that it was the Plaintiff's fault that the STP was built out of

    position. This was because the Defendant had depended on the

    accuracy of the Plaintiff's demarcation of the site of the STP, which, as it

    turned out, was not the case.

    [41] As for the Plaintiff's/SP1's allegation that SD2 had misrepresented

    to him with regard to the signing of the Amended Plan, I find that the

    Plaintiff had fai led to prove on a balance of probabil i t ies that the

    27

  • [2012] 1 LNS 720 Legal Network Series

    Defendant / SD2 had misrepresented to SP1. It is trite law that a person

    is bound by any document he has signed knowingly or unknowingly of

    its contents unless he can prove that he had signed it due to fraud or

    misrepresentation (see Serangoon Garden Estate Ltd v. Marian Chye

    [1959] 25 MLJ 113; Ooi Yoke In (F) and Anor v. Public Finance Bhd

    [1993] 2 CLJ 464). SP1 was the managing director of the Plaintiff, which

    is a housing developer. It is hard for me to accept the testimony of SP1

    that he did not know / understand the contents of the Amended Plan

    when he signed it. As the managing director of the Plaintiff, he would be

    used to reading Site Plans and signing such Plans should there be a

    need to amend it. It is not plausible to me to accept the Plaintiff's

    contention that when SP1 signed the Amended Plan for the alleged

    purpose of obtaining the approval of the relevant authority that he did

    not closely scrutinize the Amended Plan to see what was needed to be

    amended and why it needed to be amended. It is my finding that SP1

    knew what he was signing and therefore had known about the shift in

    the positioning of the STP and had agreed to the amendment. It must

    be remembered that Pegasus had all these time approved the interim

    certificates for progress payments to the Defendant and Pegasus would

    have also known about this error when it signed the relevant stage

    28

  • [2012] 1 LNS 720 Legal Network Series

    payment. Since Pegasus was in the employ of the Plaintiff, at the very

    least Pegasus', knowledge of this fact must be imputed to the Plaintiff. If

    Pegasus saw it fit not to inform the Plaintiff about the error it was not for

    the Plaintiff to lay the burden wholly on the Defendant to inform it of the

    error, seeing especially that the Plaintiff was under the duty to provide

    the site information / demarcation in the first place.

    [42] In this context I am disturbed by the fact that the Plaintiff did not

    see it fit to call Pegasus or its representative as the Plaintiff's witness

    seeing that Pegasus was the Plaintiff's consulting engineer for the STP

    project. Likewise, the Plaintiff had failed to call its surveyor who had

    surveyed the Site. I therefore invoke the provisions of section 114(g) of

    the Evidence Act against the Plaintiff for failing to call these persons as

    its witnesses.

    [43] In the circumstances, I agree with the learned counsel for the

    Defendant's submission that the Plaintiff is now estopped from denying

    that it had knowledge of the error and had signed the Amended Plan in

    order to have it submitted to the relevant authority for that authority's

    approva l . The Amended P lan moreover was sen t to the re levan t

    29

  • [2012] 1 LNS 720 Legal Network Series

    authority for its approval via Pegasus's letter dated 20.12.2005 at page

    45, B and was carbon copied to the Plaintiff.

    [44] Since I have found that the Defendant was not at fault in building

    the STP out of position and that the defence of estoppel applied against

    the Plaintiff, I therefore dismiss the Plaintiff's claim for general damages

    in respect of the so-called encroachment by the Defendant into the

    buffer zone.

    H. Whether the Defendant had delayed in completing and

    handing over the STP on or before 31.12.2005.

    [45] The Contract completion date was agreed to be on 31.12.2005.

    But the STP was only completed and handed over to the Sewerage

    Service Department on 13.7.2006 (page 32, B; page 48 Notes of

    Evidence), after a delay of 193 days

    [46] The Defendant's defence was that:-

    46.1. there was no delay;

    46.2. the Plaintiff, vide Pegasus, had on 21.12.2005 forwarded the

    Amended Plan signed by the Plaintiff and which was approved

    on 23.1.2006;

    30

  • [2012] 1 LNS 720 Legal Network Series

    46.3. even if there was any delay the parties had waived the time limit

    as evidenced by the fact that the Plaintiff had made payments for

    the sum of RM1,215,050.00 or 90% of the said Contract sum

    without any objection nor dispute, between the period 2005 until

    2007 and had not set off its alleged claim for LAD;

    46.4. the Plaintiff had failed to obtain the electricity supply as was

    required under Appendix A, page 3, B, Clause 8.1 of the said

    Contract, seeing that Tenaga Nasional would install the electricity

    meter only on 26.5.2006 (page 129, B);

    46.5. the Plaintiff had made all the payments under the said Contract

    from 2005 to 2007 without raising any objection nor dispute on the

    delay in completion and handover of the STP;

    46.6. in view of the above, the Plaintiff was estopped from raising this

    issue.

    [47] The Plaintiff submitted that:-

    47.1. the Defendant's witness, SD2 had admitted that as at 15.1.2006,

    the works were not completed yet as no testing and

    commissioning had been done (page 48, Notes of Evidence);

    47.2. with reference to the Defendant's letter to Pegasus on page 56, B,

    31

  • [2012] 1 LNS 720 Legal Network Series

    dated 12.1.2006, requesting for extension of time, SD2 had

    confirmed that the Defendant did not receive any response from

    Pegasus. Neither did the Defendant adduce any evidence to

    show that the Plaintiff had specifically waived the time limit (page

    49, Notes of Evidence);

    47.3. as for the Plaintiffs failure to obtain the electricity supply, SD2 had

    admitted that the Defendant did have temporary electricity supply

    and had given unsatisfactory explanation as to why the Defendant

    could not do the testing and commissioning by saying that the

    electricity was for light usage only (page 48, Notes of Evidence).

    SD2 had also failed to explain why the Defendant did not apply for

    an extension of time by reason of there was no supply of electricity

    other than to state that supply of electricity was not within the

    scope of the Defendant's work (page 49, Notes of Evidence);

    47.4. if the non-supply of electricity was the main reason for the delay,

    the least the Defendant should have done was to put it on record

    to the Plaintiff and to Pegasus, which would shield the Defendant

    from any claim of LAD. As the Defendant failed to do so, it

    showed that the delay was never caused by the Plaintiff's failure to

    obtain electricity supply.

    32

  • [2012] 1 LNS 720 Legal Network Series

    [48] The Plaintiff therefore submitted based on section 75 of the

    Contracts Act 1950 and Sakinas Sdn. Bhd v. Slew Yik Hau & Anor

    [2002] 5 MLJ 497 it was entitled to recover LAD at the rate of

    RM1,500.00 per day x 193 days = RM289,500.00

    [49] Once again I wish to reiterate that the said Contract was a design

    and build contract whereby upon the Defendant presenting its bills for

    payments, the Plaintiff, through Pegasus issuing the Progress Payment

    Certificates, would have to honour the said payments. The fact that the

    Plaintiff had made the progress payments to the Defendant did not

    mean that the Plaintiff had waived its rights to claim LAD against the

    Defendant. After all, it was very important for the Plaintiff that the

    Defendant completed the construction of the STP so as not to cause the

    Plaintiff itself in delaying the completion of its housing and commercial

    shop lots project. Whatever dispute it may have with the Defendant

    could be taken up at a later time, and which the Plaintiff did in this

    action. As for the setting - off issue, that was exactly what the Plaintiff

    did by refusing to pay the balance of the said Contract price of

    RM129,998.00 to the Defendant.

    33

  • [2012] 1 LNS 720 Legal Network Series

    [50] As for the non-supply of electricity, I agree with the submission of

    learned counsel for the Plaintiff that it was not the cause of the

    Defendant's delay in completing the STP. In the first place, and as

    admitted by SD2, there was a temporary supply of electricity to the Site

    which could easily be used for the purposes of testing and

    commissioning the STP. Secondly, if it was true that a proper supply

    of electricity was required by the Defendant for the express purpose of

    testing and commissioning the STP, it is hard to understand why the

    Defendant failed to apply for an extension of time seeing that the

    electricity supply was required for the testing and commissioning of the

    STP, being within the scope of works of the Defendant. The Defendant

    saw it fit to apply for an extension of time for soil testing and piling

    design, shortage of bakau piles and rain factor in its letter dated

    12.1.2006 to Pegasus (pages 56-61, B), and yet did not see it fit to apply

    for an extension of time in regard to the electricity supply essential to its

    completion of the STP works. This served to show to me that the non-

    supply of the electricity to the Site by the Plaintiff was not essential as

    there was a temporary supply of electricity and it did not cause the delay

    in the completion of the STP. Further, as Pegasus failed to respond to

    the Defendant's request for an extension of time and nothing was done

    34

  • [2012] 1 LNS 720 Legal Network Series

    by the Defendant to pursue the matter, there was no extension of time

    granted to the Defendant by the Plaintiff.

    [51] Be that as it may, since the Plaintiff, vide Pegasus, had forwarded

    the Amended Plan to the relevant authority on 21.12,2005, which was

    approved on 23.1.2006, it is only fair to me to allow the Defendant an

    extension of time of 33 days (from 21.12.2005 to 23.1.2006) to enable

    the Defendant to accommodate the time required to wait for the outcome

    of the relevant authority's approval. This would mean the Defendant is

    to be faulted for 160 days delay in completing the STP, which in turn

    means the Plaintiff is entitled to a LAD of 160 days x RM1,500.00 =

    RM240,000.00. I do so hold as the parties had not disputed on the rate

    of the LAD and I regard the rate as being reasonable in the

    circumstances.

    I. Whether the Superintending Engineer/ Pegasus had

    erroneously issued the Certificate of Practical Completion

    dated 2.1.2006.

    [52] The CPC dated 2.1.2006 (CPC) was issued by Pegasus (pages

    5455, B).

    35

  • [2012] 1 LNS 720 Legal Network Series

    [53] It was the Plaintiff's submission that:-

    53.1. the CPC was invalid as it had been issued by mistake or without

    legal basis;

    53.2. the Plaintiff's contention was supported by the fact that the

    Defendant had on or about 12.1.2006, about 12 days after the

    purported issuance of the CPC, requested for an extension of time

    to complete the works and to extend the physical completion to

    15.1.2006 (pages 56-61, B);

    53.3. SD2 had admitted that as at 15.1.2006 the works were not yet

    completed as no testing nor commissioning had been done (page

    48, Notes of Evidence);

    53.4. and yet Pegasus continued to issue 3 Progress Payment

    Certificates No. 5 dated 24.1.2006 (pages 26-27, B), No. 6 dated

    24.8.2006 (pages 67-68, B) and No. 7 dated 24.9.2007 (pages 75-

    76, B) after the issuance of the CPC. It was absurd of Pegasus to

    have issued the CPC when substantial works were still in

    progress;

    53.5. it is well established principle of law that the date of Practical

    Completion usually indicates the end of the construction period

    and the commencement of the period of making good defects and

    36

  • [2012] 1 LNS 720 Legal Network Series

    the defect liability period; end of the period of the contractor's

    general possession of the site, site responsibility and full control

    reverts to the employer / owner; end of certification of regular

    interim payments etc. (see pages 301 - 302, Nigel M. Robinson,

    et al, Construction Law in Singapore and Malaysia , Second

    Edition, Butterworths Asis, 1996). However, the factual matrix of

    this case showed the opposite state of affairs after the issuance of

    the CPC. The physical possession of the STP was given to the

    Sewerage Service Department on 13.7.2006 (page 32, B) and 3

    Progress Payment Certificates amounting to RM529,998.00 were

    issued after the date of Practical Completion.

    [54] It was submitted by the Defendant that:-

    54.1. this issue raised by the Plaintiff was a non-issue;

    54.2. the Plaintiff had never disputed nor questioned the actions taken

    by Pegasus in particular Pegasus's action in issuing all the

    Progrerss Payment Certificates and the CPC before the filing of

    this action;

    54.3. the Plaintiff had made payments to the Defendant from 2005 to

    2007 based on the Progress Payment Certificates issued by

    Pegasus without registering any protest or dispute;

    37

  • [2012] 1 LNS 720 Legal Network Series

    54.4. the Plaintiff did not raise any objection nor dispute against the

    issuance of the CPC dated 2.1,2006 until the Defendant filed the

    2009 Case in the Sessions Court on 4.8.2008;

    54.5. the Plaintiff did not institute any action against Pegasus in respect

    of the CPC nor added Pegasus as a party in this suit;

    54.6. the Plaintiff had admitted to receiving the STP in 2006 without

    raising any objection, dispute against the Defendant nor with

    Pegasus;

    54.7. moreover, Pegasus was the Plaintiff's representative and or agent

    in respect of the STP project.

    [55] Even though Pegasus was engaged by the Plaintiff as the

    superintending engineer, Pegasus's role cannot be purely said to be that

    of an employee of the Plaintiff nor its agent for the purposes of the

    said Contract. Even though the said Contract between the Plaintiff and

    Defendant was an informal one (there was no form of contract executed

    between them) I am of the view that the basic principles pertaining to the

    role of a superintending engineer or architect, as the case may be, are

    applicable to Pegasus. This role of Pegasus can be understood by my

    quoting extracts from case law as follows:-

    38

  • [2012] 1 LNS 720 Legal Network Series

    Syar i ka t Ong Yoke L in Sdn . Bhd . v. Gian t Cash and Carry Sdn .

    Bhd & Ors [2000] 4 CLJ 733 (H.C. ) @ 759: -

    As alluded to earlier, the third defendant was a mere architect of the

    Giant hypermarket. The third defendant was employed by the first

    defendant. The duties of the third defendant as an architect and the

    obligat ions that f lowed under i t can readi ly be seen in exhibi t TUH

    1 of encl. 11. According to the case of Sutcliffe v. Thackrah And

    Others [1974] 2 WLR 295, the architect has got certain roles to play

    Lord Reid described the posit ion of the architect in that case in these

    fine words (see page 299 of the report):-

    Now I can come to the pos i t ion o f an a rch i t ec t . He i s emplo yed

    by the bui lding owner but has no contract with the contractor. We

    d o n o t i n t h i s c a s e h a v e o c c a s i o n t o c o n s i d e r w h e t h e r

    never theless he may have some duty to the contractor : I do not

    think that a considera t ion of that matter would help in the present

    case. The R.I .B.A. form of contract sets out the archi tect ' s

    functions in great detail. It has often been said, I think rightly, that

    the archi tect has two different types of funct ion to perform. In

    many matters he is bound to act on his c l ient ' s ins truct ions ,

    whether he agrees with them or not ; but in many other mat ters

    requir ing profess ional ski l l he must form and act on his own

    opinion.

    39

  • [2012] 1 LNS 720 Legal Network Series

    Man y ma t t e r s ma y a r i se in the course o f the execu t ion o f a

    bu i ld ing con t rac t where a dec i s ion has to be made which wi l l

    a ffec t the amount o f money which the con t rac to r ge t s . Under

    R. I .B .A. con t rac t man y such dec i s ions have to be made b y the

    arch i tec t and the par t i es ag ree to accep t h i s dec i s ions . For

    example , he dec ides whe ther the con t rac to r shou ld be

    re imbursed fo r los s under c lause 11 (var i a t ion) , c lause 24

    (d i s tu rbance) o r c l ause 34 (an t iqu i t i es ) ; whe ther he shou ld be

    a l lowed ex t ra t ime (c lause 23) ; o r where work ough t r easonab l y

    have been comple t ed (c lause 22) . And , pe rhaps mos t impor tan t ,

    he has to dec ide whe ther work i s de fec t ive . These dec i s ions wi l l

    be reflected in the amounts contained in certificates issued by the

    arch i tec t .

    The building owner and the contrac tor make their contrac t on the

    understanding that in all such matters the architect will act in a fair

    and unbiased manner and i t mus t therefore be implici t in the

    owner 's contract with the archi tect that he shal l not only exerc ise

    due care and ski l l but a lso reach such decis ions fa ir ly, holding the

    balance between his cl ient and the contrac tor.

    I t would be cor rec t to say tha t the du ty o f the a rch i tec t i s to i s sue

    certificate and certify whether the contractor has met its contractual

    obligation so as to entitle the contractor to receive interim payments

    during the progress of the works. In discharging i ts duty, the architect

    40

  • [2012] 1 LNS 720 Legal Network Series

    must be seen to be impar t i a l and mus t ac t f a i l y and p rofess iona l l y

    when exerc i s ing i t s independen t j udgmen t . I f the a rch i tec t f a i l s to

    fu l f i l these requ i rements , the aggr ieved par ty ma y cha l lenge the

    dec i s ion o f the a rch i t ec t .

    Hiap Hong & Co. Pte L td v. Ong Huat Deve lopment Co (P te )L td [2001] 2 SLR 458 (C.A. S ingapore) a t pages 464 , 465 : -

    15. It is settled law that an architect under a building contract is not

    an arbi trator. But he has a dual funct ion. In the words of Lord Reid

    in Sutc l i f f e v. Thackrah [1974] AC 727 a t 737 ; [1974] 1 Al l ER 859

    at 863: ' In many mat ters he is bound to act on his cl ient ' s

    ins truct ions , whether he agrees with them or not ; but in many other

    mat ters requir ing profess ional ski l l , he must form and act on his own

    opinion ' .

    16. I t is equal ly set t led law that an owner and a contrac tor would

    have made their contract on the unders tanding tha t in al l matters

    where the archi tec t has to apply his profess ional ski l l and judgment,

    the archi tect wil l act in a fair and unbiased manner in applying the

    terms of the contract . Such mat ters wil l inc lude the issue of

    certificates for payments and the grant of extension of time. While an

    archi tec t under such a contrac t is the employer ' s agent , in the

    exercise of his funct ions requir ing ski l l and judgment, he must act

    fai ly and profess ional ly and nei ther par ty should seek to unfair ly or

    unduly inf luence him in the discharge of those funct ions .

    41

  • [2012] 1 LNS 720 Legal Network Series

    At page 470:-

    35. It is vitally important to bear in mind the nature of the duties of the

    architect when he I exercising the function of a certifier, As stated

    before, it is settled law that he is to act faily and independently. He is not

    subject to the directions or instructions of either party although he must

    listen to both parties before he arrives at his own decision. Thus, in

    exercising the function of certification the architect cannot be the agent

    of the owners. The nature of that function is wholly inconsistent with the

    architect being an agent of the owner. In Emden's Construction Law

    Issue 56/Jun 1999 at p. II 275 the authors stated 'When issuing

    certificates the architect or other certifier is not acting as the employer's

    agent but must form and act on his own opinion.' In 4(2) Halsbury's

    Laws of England (4th Ed Reissue) the learned authors stated that the

    architect's duties as certifier are different from his duties as agent or

    arbitrator although sometimes it is not easy to distinguish them.'

    36. It is true that the architect is employed by the owner and to that extent

    the latter has control over him. But such control must necessarily be

    confined to matters in which the architect acts as the owner's agent and

    not in relation to matters where the architect is accorded a special role

    under the contract and where he is expected to exercise independent

    judgment. In para 6.228 of Hudson's the authors, after referring to

    matters on which the owner exercises control over the architect, go on to

    state that 'the owner of necessity ceases to be entitled to control (the

    42

  • [2012] 1 LNS 720 Legal Network Series

    architect's) activities in relation to the matter he is called upon to decide,

    whether as certifier or arbitrator.

    The role of the superintending engineer as elucidated above must

    necessarily include his role as the issuer of the Certificate of Practical

    Completion, not only for the purpose of issuing Progress Payment

    Certificate. Based on the said role played by Pegasus vis the Plaintiff

    and the Defendant, the CPC issued by Pegasus can be challenged by

    the Plaintiff for illegality.

    [56] Even though it was most regrettable that the Plaintiff did not see it

    fit to sue Pegasus in this action nor call the representative of Pegasus

    as its witness, but based on the factual matrix of this case and in respect

    of this issue on the legality of the CPC, I hold that the CPC was wrongly

    issued by Pegasus and therefore was invalid.

    [57] I agree with the submissions of learned counsel for the Plaintiff on

    this issue. I hold that Pegasus in issuing the 3 Progress Payment

    Certificates Nos. 5 to 7 amounting to RM529,998.00 or 39% of the

    Contract Sum after the CPC was issued showed very clearly that a

    substantial portion of the works in completing the STP had yet to be

    43

  • [2012] 1 LNS 720 Legal Network Series

    done by the Defendant. That being the case, it was premature of

    Pegasus to have issued the CPC. On top of that, the testing,

    commissioning and handing over of the STP was only completed on

    13.7.2006, that is, over 6 months after the CPC was issued.

    [58] The progress payments made by the Plaintiff to the Defendant vis

    Progress Payment Certificates Nos. 5 to 7 cannot prevent the Plaintiff

    from challenging the decision of Pegasus since the Plaintiff was only

    doing that which it was obliged to do by virtue of the said Progress

    Payment Certificates being issued by Pegasus. It is an established

    principle that an interim certificate is a condition precedent to payment.

    any party aggrieved by the amount stated as due in a certificate can only

    challenge it at arbitration or to commence an action for damages for

    breach after issuance of the Certificate of Practical Completion. [See

    Nigel M. Robinson, Construction Law in Singapore and Malaysia

    (supra) at pages 344-346].

    [59] As for the Defendant's contention that the Plaintiff had filed this

    action only after the Defendant had filed the 2009 Case on 4.8.2008 at

    Batu Pahat Sessions Court, I note the Plaintiff's submission that the

    44

  • [2012] 1 LNS 720 Legal Network Series

    Plaintiff, through its previous solicitors, did send a Letter of Demand

    dated 3.7.2007 on pages 69 - 70, B, to the Defendant demanding

    damages and compensation in respect of the breaches of contract

    pertaining to the construction of the STP, that is, before the date the

    Defendant filed the 2009 Case in the Batu Pahat Sessions Court. The

    Defendant's contention therefore had no merits.

    [60] I consequently hold that the CPC should have been issued much

    later on and certainly not on 2.1.2006.

    J. Whether the Plaintiff owed the Defendant the sum of

    RM129,998.00, being the balance of the contract sum

    remaining unpaid.

    [61] According to the Defendant's pleadings, and which was not

    disputed by the Plaintiff in so far as the Progress Payment Certificates

    and payments had been made to the Defendant vis the said Certificates,

    Pegasus had issued 7 Progress Payment Certificates as follows:-

    Certificate No. Date of Certificate Amount (RM)

    1 6.9.2005 36,450.00

    2 3.10.2005 182,880.00

    45

  • [2012] 1 LNS 720 Legal Network Series

    3 7.11.2005 141,885.00

    4 19.12.2005 453,835.00

    5 24.1.2006 414,950.00

    7 24.9.2007 80,702.88To t a l p a y m e n t t o

    b e m a d e1,345,048.00

    [62] The Plaintiff had made 7 progress payments as follows:-

    Date Amount (RM)

    29.9.2005 36,450.00

    17.10.2005 182,880.00

    24.1.2006 522,113.50

    4.5.2006 73,606.50

    30.8.2006 150,000.00

    3.11.2006 150,000.00

    7.2.2007 100,000.00

    Total Payment made 1,215,050.00

    46

  • [2012] 1 LNS 720 Legal Network Series

    This meant that there was a balance of RM129,998.00 due from and

    owing by the Plaintiff to the Defendant. The Defendant now claims from

    the Plaintiff the said amount seeing that the Defects Liability Period had

    ended in 2007.

    [63] The Plaintif on the other hand alleged that it had never agreed to

    the reduction in the Contract Sum by the use of cheaper bakau piles by

    the Defendant, that the said sum was not owed by the Plaintiff to the

    Defendant or alternatively was set-off with the amount accrued and

    owed by the Defendant to the Plaintiff in the 2008 Case.

    [64] In view of the fact that the Plaintiff did not see it fit to bring

    Pegasus as a party to the 2008 Case, nor call a representative of

    Pegasus as a witness, I take the view that the Plaintiff did not wish to

    dispute the said Progress Payment Certificates issued by Pegasus. It

    would also appear to me that the Plaintiff was contented to accept the

    Defendant's Projected Cost of RM95,048.00 as a result of the use of

    bakau pile wholly on the Site which then reduced the Contract Sum from

    RM1,350,000/- to RM1,345,048. That being the case, I find that as the

    Plaintiff had only paid the Defendant the total sum of RM1,215,050.00,

    the sum of RM129,998.00 is still due and payable from the Plaintiff to

    47

  • [2012] 1 LNS 720 Legal Network Series

    the Defendant. However, this sum is ordered to be set - off against the

    sums I have ruled to be payable by the Defendant to the Plaintiff as

    damages in the 2008 Case.

    K. CONCLUSION:

    [65] For the reasons stated above I make the following orders:-

    The 2008 Case.

    65.1. special damages comprising of:-

    (i) deductions in cost of piling material at RM4,952.00 -

    allowed;

    (ii) LAD of RM240,000.00 - allowed;

    65.2. general damages as a result of the encroachment into the buffer

    zone - disallowed;

    65.3. a declaration that the CPC issued by Pegasus on 2.1.2006 is null

    and void - allowed;

    65.4. costs at RM15,000.00 - allowed;

    65.5. interest at 5% per annum from the date of judgment until judgment

    is satisfied - allowed;

    The 2009 Case.

    65.6. the sum of RM129,998.00 shall be payable by the Plaintiff to

    48

  • [2012] 1 LNS 720 Legal Network Series

    the Defendant and which shall be set-off from the sums due

    from the Defendant to the Plaintiff in the 2008 Case;

    65.7. costs at RM15,000.00 - allowed;

    65.8. interest on the sum of RM129,998.00 at 4% per annum from the

    date of filing of the Summons (4.8.2008) to the date of judgment

    and at 5% per annum from the date of judgment until judgment is

    satisfied - allowed.

    (UMI KALTHUM ABDUL MAJID)Judge

    High Court Muar

    Dated: 14 DECEMBER 2012

    49

  • [2012] 1 LNS 720 Legal Network Series

    Counsels:

    For the plaintiff - Gideon Tan; M/s Gideon Tan Razali Zaini

    Peguambela & Peguamcara812, 8th Floor, Block A, Kelana Square17, Jalan SS 7/2647301 Petaling Jaya, Selangor Darul Ehsan

    For the defendant - M/s Mogan Karupiah

    Peguambela & Peguamcara380-C, Sin Hoe GardenBukit Baru75150 Melaka.

    50