PA 6.1. 1 m' Pagar Sementara dari kayu tinggi 2 meter
6.1.1. Bahan- Kayu Laut/Dolken 1.250 Btg x Rp 19,250 = Rp 24,062.50
- Semen Portland 2.500 Kg x Rp 1,270 = Rp 3,175.00
- Pasir Beton 0.005 M3 x Rp 87,800 = Rp 439.00
- Koral Beton 0.009 M3 x Rp 170,900 = Rp 1,538.10
- Kayu 5/7 0.038 M3 x Rp 3,107,500 = Rp 118,085.00
- Paku Biasa 2" - 5" 0.060 Kg x Rp 14,520 = Rp 871.20
- Residu/colter 0.400 Lt x Rp 6,530 = Rp 2,612.00
Jumlah (1) = Rp 150,782.80
6.1.2. Tenaga
- Tukang kayu 0.200 Oh x Rp 78,800 = Rp 15,760.00
- Pekerja 0.400 Oh x Rp 52,500 = Rp 21,000.00
- Kepala tukang 0.020 Oh x Rp 91,900 = Rp 1,838.00
- Mandor 0.020 Oh x Rp 65,600 = Rp 1,312.00 Jumlah (2) = Rp 39,910.00
Jumlah (1) + (2) = Rp 190,692.80
PA 6.2. 1 m' Pagar sementara dari seng gelombang tinggi 2 meter
6.2.1. Bahan
- Kayu Laut/Dolken 1.250 Btg x Rp 19,250 = Rp 24,062.50
- Semen Portland 2.500 Kg x Rp 1,270 = Rp 3,175.00
- Seng Gelombang 1.200 Lbr x Rp 59,640 = Rp 71,568.00
- Pasir beton 0.005 M3 x Rp 87,800 = Rp 439.00
- Koral beton 0.009 M3 x Rp 170,900 = Rp 1,538.10
- Kayu 5/7 0.012 M3 x Rp 3,107,500 = Rp 37,290.00- Paku biasa 2" - 5" 0.060 Kg x Rp 14,520 = Rp 871.20
- Meni besi 0.450 Kg x Rp 25,410 = Rp 11,434.50
Jumlah (1) = Rp 150,378.30
6.2.2. Tenaga
- Tukang kayu 0.200 Oh x Rp 78,800 = Rp 15,760.00
- Pekerja 0.400 Oh x Rp 52,500 = Rp 21,000.00
- Kepala tukang 0.020 Oh x Rp 91,900 = Rp 1,838.00
- Mandor 0.020 Oh x Rp 65,600 = Rp 1,312.00
Jumlah (2) = Rp 39,910.00
Jumlah (1) + (2) = Rp 190,288.30
ANALISA BIAYA KONSTRUKSI
PEKERJAAN PERSIAPAN
-
5/21/2018 Daftar Analisa Sni 2010 (1)
2/143
PA 6.3 1 M' Pagar sementara dari kawat duri tinggi 1,8 meter
6.3.1. Bahan
- Kayu Laut/Dolken 1.000 Btg x Rp 19,250 = Rp 19,250.00
- Semen Portland 2.000 Kg x Rp 1,270 = Rp 2,540.00
- Kawat duri 1.625 Kg x Rp 4,030 = Rp 6,548.75
- Pasir beton 0.005 M3 x Rp 87,800 = Rp 439.00
- Koral beton 0.009 M3 x Rp 170,900 = Rp 1,538.10- Paku biasa 2" - 5" 0.060 Kg x Rp 14,520 = Rp 871.20
Jumlah (1) = Rp 31,187.05
6.3.2. Tenaga
- Tukang kayu 0.200 Oh x Rp 78,800 = Rp 15,760.00
- Pekerja 0.400 Oh x Rp 52,500 = Rp 21,000.00
- Kepala tukang 0.020 Oh x Rp 91,900 = Rp 1,838.00
- Mandor 0.020 Oh x Rp 65,600 = Rp 1,312.00
Jumlah (2) = Rp 39,910.00
Jumlah (1) + (2) = Rp 71,097.05
PA 6.4 Pengukuran dan Pemasangan bouplank
6.4.1. Bahan- Kayu 5/7 0.012 M3 x Rp 3,107,500 = Rp 37,290.00
- Paku biasa 2" - 5" 0.020 Kg x Rp 14,520 = Rp 290.40
- Kayu papan 3/20 0.007 M3 x Rp 3,107,500 = Rp 21,752.50
Jumlah (1) = Rp 59,332.90
6.4.2. Tenaga
- Tukang kayu 0.100 Oh x Rp 78,800 = Rp 7,880.00
- Pekerja 0.100 Oh x Rp 52,500 = Rp 5,250.00
- Kepala tukang 0.010 Oh x Rp 91,900 = Rp 919.00
- Mandor 0.005 Oh x Rp 65,600 = Rp 328.00
Jumlah (2) = Rp 14,377.00
Jumlah (1) + (2) = Rp 73,709.90
PA 6.5 1 m2 Pembuatan Kantor Sementara dengan Lantai Plesteran
6.5.1. Bahan
- Kayu Laut/Dolken 1.250 Btg x Rp 19,250 = Rp 24,062.50
- Kayu 0.180 M3 x Rp 37,400 = Rp 6,732.00
- Batu Belah/Kali 15 - 20 cm 0.850 Kg x Rp 125,900 = Rp 138,490.00
- Besi Strip 1.100 Kg x Rp 87,800 = Rp 3,073,000.00
- Semen Portland 35.000 Kg x Rp 1,270 = Rp 190.50
- Pasir pasang 0.150 M3 x Rp 150,200 = Rp 15,020.00
- Pasir beton 0.100 M3 x Rp 165,200 = Rp 24,780.00
- Koral beton 0.150 M3 x Rp 185,900 = Rp 5,577,000.00
- Bata merah 30.000 Bh x Rp 64,400 = Rp 16,100.00
- Seng plat 0.250 Lbr x Rp 4,180 = Rp 8,360.00
- Jendela nako 2.000 Bh x Rp 13,590 = Rp 1,087.20
- Kaca polos 0.080 M2 x Rp 145,200 = Rp 21,780.00
- Kunci tanam 0.150 Bh x Rp 170,900 = Rp 10,254.00
- Plywood 4 mm 0.060 Lbr x Rp 202,700 = Rp 0.00
Jumlah (1) = Rp 8,916,856.20
6.5.2. Tenaga
- Tukang kayu 2.000 Oh x Rp 78,800 = Rp 157,600.00
- Tukang batu 1.000 Oh x Rp 78,800 = Rp 78,800.00
- Pekerja 2.000 Oh x Rp 52,500 = Rp 105,000.00
-
5/21/2018 Daftar Analisa Sni 2010 (1)
3/143
- Kepala tukang 0.300 Oh x Rp 91,900 = Rp 27,570.00
- Mandor 0.050 Oh x Rp 65,600 = Rp 3,280.00
Jumlah (2) = Rp 372,250.00
Jumlah (1) + (2) = Rp 9,289,106.20
PA 6.6. 1 M Pembuatan gudang semen dan alat - alat
6.6.1. Bahan
- Kayu Laut/Dolken 1.700 Btg x Rp 19,250 = Rp 32,725.00
- Kayu 0.210 M3 x Rp 37,400 = Rp 7,854.00
- Paku biasa 0.300 Kg x Rp 125,900 = Rp 37,770.00
- Semen Portland 10.500 Kg x Rp 1,270 = Rp 13,335.00
- Pasir beton 0.030 M3 x Rp 165,200 = Rp 4,956.00
- Koral beton 0.050 M3 x Rp 185,900 = Rp 9,295.00
- Seng gelombang bjls 20 - 7" 1.500 Lbr x Rp 59,640 = Rp 89,460.00
Jumlah (1) = Rp 195,395.00
6.2.2. Tenaga
- Tukang kayu 0.200 Oh x Rp 78,800 = Rp 15,760.00
- Pekerja 0.400 Oh x Rp 52,500 = Rp 21,000.00
- Kepala tukang 0.020 Oh x Rp 91,900 = Rp 1,838.00- Mandor 0.020 Oh x Rp 65,600 = Rp 1,312.00
Jumlah (2) = Rp 39,910.00
Jumlah (1) + (2) = Rp 235,305.00
PA 6.7 1m Pembuatan rumah jaga / kontruksi kayu
6.7.1 Bahan
- Kayu Laut/Dolken 3.000 Btg x Rp 19,250 = Rp 57,750.00
- Kayu 0.276 M x Rp 37,400 = Rp 10,322.40
- Paku biasa 0.700 Kg x Rp 125,900 = Rp 88,130.00
- Seng gelombang bjls 20 - 7" 1.500 Lbr x Rp 59,640 = Rp 89,460.00
Jumlah (1) = Rp 245,662.40
6.7.2 Tenaga
- Tukang kayu 1.500 Oh x Rp 78,800 = Rp 118,200.00
- Pekerja 1.000 Oh x Rp 52,500 = Rp 52,500.00
- Kepala Tukang 0.150 Oh x Rp 91,900 = Rp 13,785.00
- Mandor 0.050 Oh x Rp 65,600 = Rp 3,280.00
Jumlah (2) = Rp 187,765.00
Jumlah (1) + (2) = Rp 433,427.40
PA 6.8 1 m Membersihkan lapangan dan perataan
6.8.1 Tenaga
- Pekerja 0.100 Oh x Rp 52,500 = Rp 5,250.00
- Mandor 0.050 Oh x Rp 65,600 = Rp 3,280.00
Jumlah = Rp 8,530.00
PA 6.9 1 m Pembuatan bedeng buruh
6.9.1 Bahan
- Kayu Laut/Dolken 1.250 Btg x Rp 19,250 = Rp 24,062.50
- Kayu 0.186 M x Rp 37,400 = Rp 6,956.40
- Paku biasa 0.300 Kg x Rp 125,900 = Rp 37,770.00
- Semen portland 18.000 Kg x Rp 1,270 = Rp 22,860.00
- Pasir beton 0.030 M x Rp 165,200 = Rp 4,956.00
-
5/21/2018 Daftar Analisa Sni 2010 (1)
4/143
- Koral beton 0.050 M x Rp 185,900 = Rp 9,295.00
- Seng gelombang bjls 20 - 7" 1.500 Lbr x Rp 59,640 = Rp 89,460.00
- Plywood 4mm 1.350 Lbr x Rp 202,700 = Rp 273,645.00
Jumlah (1) = Rp 469,004.90
6.9.2 Tenaga
- Tukang kayu 2.000 Oh x Rp 78,800 = Rp 157,600.00
- Pekerja 1.000 Oh x Rp 52,500 = Rp 52,500.00- Kepala tukang 0.200 Oh x Rp 91,900 = Rp 18,380.00
- Mandor 0.050 Oh x Rp 65,600 = Rp 3,280.00
Jumlah (2) = Rp 231,760.00
Jumlah (1) + (2) = Rp 700,764.90
PA 6.10. 1 m Pembuatan bak adukan ukuran ( 40 x 50 x 20 ) cm
6.10.1. Bahan
- Waterfroof 0.036 M3 x Rp 52,300 = Rp 1,882.80
- Paku biasa 0.080 Kg x Rp 125,900 = Rp 10,072.00
- Kaso 5/7 1.000 Btg x Rp 1,270 = Rp 1,270.00
Jumlah (1) = Rp 13,224.80
6.10.2 Tenaga
- Tukang kayu 0.300 Oh x Rp 78,800 = Rp 23,640.00
- Mandor 0.002 Oh x Rp 65,600 = Rp 98.40
Jumlah (2) = Rp 23,738.40
Jumlah (1) + (2) = Rp 36,963.20
PA 6.11. 1 m Pembuatan Stegger dari bambu, ukuran ( 40 x 50 x 20 ) cm
6.11.1 Bahan
- Bambu 6 - 8 / 600 cm 1.000 Btg x Rp 62,900 = Rp 62,900.00
- Tali ijuk 0.250 Kg x Rp #REF! = Rp #REF!
Jumlah (1) = Rp #REF!
6.11.2 Tenaga
- Tukang kayu 0.017 Oh x Rp 78,800 = Rp 1,339.60
- Kepala tukang 0.002 Oh x Rp 91,900 = Rp 183.80
- Pekerja 0.250 Oh x Rp 52,500 = Rp 13,125.00
- Mandor 0.013 Oh x Rp 65,600 = Rp 852.80
Jumlah (2) = Rp 15,501.20
Jumlah (1) + (2) = Rp #REF!
PA 6.12 1 m Pembuatan jalan sementara
6. 12.1 Bahan
- Batu belah 15/20 0.150 M x Rp 125,900 = Rp 18,885.00
- Batu pecah 5/7 0.090 M x Rp 150,200 = Rp 13,518.00
- Pasir pasang 0.010 M x Rp 76,500 = Rp 765.00
Jumlah (1) = Rp 33,168.00
6.12.2 Tenaga
- Pekerja 1.000 Oh x Rp 52,500 = Rp 52,500.00
- Mandor 0.050 Oh x Rp 65,600 = Rp 3,280.00
Jumlah (2) = Rp 55,780.00
-
5/21/2018 Daftar Analisa Sni 2010 (1)
5/143
Jumlah (1) + (2) = Rp 88,948.00
PA 6.13 1 m Bongkaran beton betulang
6.13.1 Tenaga
- Pekerja 6.667 Oh x Rp 52,500 = Rp 350,017.50
- Mandor 0.333 Oh x Rp 65,600 = Rp 21,844.80
Jumlah = Rp 371,862.30
PA 6.14 1m Bongkaran dinding tembok bata merah
6.14.1 Tenaga
- Pekerja 5.000 Oh x Rp 52,500 = Rp 262,500.00
- Mandor 0.250 Oh x Rp 65,600 = Rp 16,400.00
Jumlah = Rp 278,900.00
PA 6.15 1m Pasangan pagar kawat jaring galvanis, tinggi 1.00 m
6.15.1 Bahan
- Kawat jaring galvanis/BRC 0.434 Lbr x Rp 235,950 = Rp 102,402.30
Jumlah (1) = Rp 102,402.30
6.15.2. Tenaga
- Pekerja 0.042 Oh x Rp 52,500 = Rp 2,205.00
- Kepala tukang 0.004 Oh x Rp 91,900 = Rp 367.60
- Tukang 0.042 Oh x Rp 78,800 = Rp 3,309.60
- Mandor 0.002 Oh x Rp 65,600 = Rp 131.20
Jumlah (2) = Rp 6,013.40
Jumlah (1) + (2) = Rp 108,415.70
PA 6.16 1 m' Pasang pagar beton pracetak (5 x 50 x 213) cm
6.16.1. Bahan
- Panel beton pracetak 0.986 Lbr x Rp 177,700 = Rp 175,212.20
- Kolom beton pracetak 0.525 Btg x Rp 0 = Rp 0.00
- Pasir beton 0.074 M x Rp 165,200 = Rp 12,224.80
- Koral 2/3 0.146 M x Rp 0 = Rp 0.00
- Batu Bata biasa 5x10x20 cm 45.000 Kg x Rp 1,270 = Rp 57,150.00
Jumlah (1) = Rp 244,587.00
6.16.2. Tenaga
- Pekerja 0.042 Oh x Rp 52,500 = Rp 2,205.00
- Kepala tukang 0.004 Oh x Rp 91,900 = Rp 367.60
- Tukang 0.042 Oh x Rp 78,800 = Rp 3,309.60
- Mandor 0.002 Oh x Rp 65,600 = Rp 131.20
Jumlah (2) = Rp 6,013.40
Jumlah (1) + (2) = Rp 250,600.40
-
5/21/2018 Daftar Analisa Sni 2010 (1)
6/143
PT 6.1. 1 m Galian tanah biasa sedalam 1 meter
6.1.1. Tenaga
- Pekerja 0.400 Oh x Rp. 52,500 = Rp. 21,000.00
- Mandor 0.040 Oh x Rp. 65,600 = Rp. 2,624.00
Jumlah (1) = Rp. 23,624.00
PT 6.2. 1 m Galian tanah biasa sedalam 2 meter
6.2.1. Tenaga
- Pekerja 0.526 Oh x Rp. 52,500 = Rp. 27,615.00
- Mandor 0.0526 Oh x Rp. 65,600 = Rp. 3,450.56
Jumlah (1) = Rp. 31,065.56
PT 6.3. 1 m Galian tanah biasa sedalam 3 meter
6.3.1. Tenaga
- Pekerja 0.735 Oh x Rp. 52,500 = Rp. 38,587.50
- Mandor 0.0735 Oh x Rp. 65,600 = Rp. 4,821.60
Jumlah (1) = Rp. 43,409.10
PT 6.4. 1 m Galian tanah keras sedalam 1 meter
6.4. Tenaga
- Pekerja 0.625 Oh x Rp. 52,500 = Rp. 32,812.50
- Mandor 0.062 Oh x Rp. 65,600 = Rp. 4,067.20
Jumlah = Rp. 36,879.70
PT 6.5. 1 m Galian tanah cadas sedalam 1 meter
6.5.1. Tenaga
- Pekerja 1.250 Oh x Rp. 52,500 = Rp. 65,625.00
- Mandor 0.125 Oh x Rp. 65,600 = Rp. 8,200.00
Jumlah = Rp. 73,825.00
PT 6.6.. 1 m Galian tanah lumpur sedalam 1 meter
6.6.1. Tenaga
- Pekerja 0.823 Oh x Rp. 52,500 = Rp. 43,207.50
- Mandor 0.083 Oh x Rp. 65,600 = Rp. 5,444.80
Jumlah = Rp. 48,652.30
PT 6.7. 1 m Pekerjaan stripping setinggi 1 meter
6.7.1. Tenaga
- Pekerja 0.050 Oh x Rp. 52,500 = Rp. 2,625.00
- Mandor 0.005 Oh x Rp. 65,600 = Rp. 328.00
Jumlah (1) = Rp. 2,953.00
PT 6.8. 1 m Pembuangan tanah sejauh 150 meter
6.8.1. Tenaga
- Pekerja 0.515 Oh x Rp. 52,500 = Rp. 27,037.50
- Mandor 0.0515 Oh x Rp. 65,600 Rp. 3,378.40
Jumlah = Rp. 30,415.90
ANALISA BIAYA KONSTRUKSI
PEKERJAAN TANAH
-
5/21/2018 Daftar Analisa Sni 2010 (1)
7/143
PT 6.9. 1 m Urugan kembali
6.9.1. Tenaga
- Pekerja 0.192 Oh x Rp. 52,500 = Rp. 10,080.00
- Mandor 0.019 Oh x Rp. 65,600 = Rp. 1,246.40
Jumlah = Rp. 11,326.40
PT 6.10. 1 m Pemadatan tanah
6.10.1. Tenaga
- Pekerja 0.500 Oh x Rp. 52,500 = Rp. 26,250.00
- Mandor 0.050 Oh x Rp. 65,600 = Rp. 3,280.00
Jumlah = Rp. 29,530.00
PT 6.11. 1 m Urugan pasir
6.11.1. Bahan
- Pasir urug 1.200 M x Rp. 64,400 = Rp. 77,280.00
Jumlah (1) = Rp. 77,280.00
6.11.2. Tenaga
- Pekerja 0.300 Oh x Rp. 52,500 = Rp. 15,750.00
- Mandor 0.015 Oh x Rp. 65,600 = Rp. 984.00
Jumlah (2) = Rp. 16,734.00
Jumlah (1) + (2) = Rp. 94,014.00
-
5/21/2018 Daftar Analisa Sni 2010 (1)
8/143
PT 6.12. 1 m Lapisan pudel campuran 1 Kp : 3 Ps : 7 TL
6.12.1. Bahan
- Pasir urug 0.330 M x Rp. 64,400 = Rp. 21,252.00
- Kapur padam 0.109 M x Rp. 1,840 = Rp. 200.56
- Tanah liat 0.763 M x Rp. 62,900 = Rp. 47,992.70
Jumlah (1) = Rp. 69,445.26
6.12.2. Tenaga
- Pekerja 0.500 Oh x Rp. 52,500 = Rp. 26,250.00
- Mandor 0.050 Oh x Rp. 65,600 = Rp. 3,280.00
Jumlah (2) = Rp. 29,530.00
Jumlah (1) + (2) = Rp. 98,975.26
PT 6.13. 1 m Lapisan pudel campuran 1 Kp : 5 TL
6.13.1. Bahan
- Kapur padam 0.200 M x Rp. 1,840 = Rp. 368.00
- Tanah liat 1.000 M x Rp. 62,900 = Rp. 62,900.00
Jumlah (1) = Rp. 63,268.00
6.13.2. Tenaga
- Pekerja 0.500 Oh x Rp. 52,500 = Rp. 26,250.00
- Mandor 0.050 Oh x Rp. 65,600 = Rp. 3,280.00
Jumlah (2) = Rp. 29,530.00
Jumlah (1) + (2) = Rp. 92,798.00
PT 6.16. 1 m Pembuatan jalan sementara, tebal 25 cm
6.16.1. Bahan
- Batu belah 10/15 0.275 M x Rp. 140,900 = Rp. 38,747.50
- Batu koral 5/7 0.030 M x Rp. 170,900 = Rp. 5,127.00
- Pasir pasang 0.050 M x Rp. 76,500 = Rp. 3,825.00
Jumlah (1) = Rp. 47,699.50
6.16.2. Tenaga
- Pekerja 0.500 Oh x Rp. 52,500 = Rp. 26,250.00
- Mandor 0.050 Oh x Rp. 65,600 = Rp. 3,280.00
Jumlah (2) = Rp. 29,530.00
Jumlah (1) + (2) = Rp. 77,229.50
-
5/21/2018 Daftar Analisa Sni 2010 (1)
9/143
PP 6.1. 1 M Pasangan pondasi batu kali, 1 Pc : 1 Ps
6.1.1. Bahan :
- Batu belah 15/20 1.100 M x Rp. 125,900.00 = Rp. 138,490.00
- Semen porland 392.000 Kg x Rp. 1,270.00 = Rp. 497,840.00
- Pasir pasang 0.314 M x Rp. 76,500.00 = Rp. 24,021.00
Jumlah (1) = Rp. 660,351.00
6.1.2. Tenaga
- Pekerja 1.500 Oh x Rp. 52,500.00 = Rp. 78,750.00
- Tukang batu 0.600 Oh x Rp. 78,800.00 = Rp. 47,280.00
- Kepala tukang 0.060 Oh x Rp. 91,900.00 = Rp. 5,514.00
- Mandor 0.075 Oh x Rp. 65,600.00 = Rp. 4,920.00
Jumlah (2) = Rp. 136,464.00
Jumlah (1) + (2) = Rp. 796,815.00
PP 6.2. 1 M Pasang pondasi batu kali 1 Pc : 2 Ps
6.2.1. Bahan
- Batu belah 15/20 cm 1.100 M x Rp. 125,900.00 = Rp. 138,490.00
- Semen porland 267.000 Kg x Rp. 1,270.00 = Rp. 339,090.00
- Pasir Pasang 0.427 M x Rp. 76,500.00 = Rp. 32,665.50
Jumlah (1) = Rp. 510,245.50
6.2.2. Tenaga
- Pekerja 1.500 Oh x Rp. 52,500.00 = Rp. 78,750.00
- Tukang batu 0.600 Oh x Rp. 78,800.00 = Rp. 47,280.00
- Kepala tukang 0.060 Oh x Rp. 91,900.00 = Rp. 5,514.00
- Mandor 0.075 Oh x Rp. 65,600.00 = Rp. 4,920.00
Jumlah (2) = Rp. 136,464.00
Jumlah (1) +(2) = Rp. 646,709.50
PP 6.3. 1 M Pasang pondasi batu kali, 1 Pc : 2,5 Ps
6.3.1. Bahan
- Batu belah 15/20 cm 1.100 M x Rp. 125,900.00 = Rp. 138,490.00
- Semen porland 392.000 Kg x Rp. 1,270.00 = Rp. 497,840.00
- Pasir Pasang 0.314 M x Rp. 76,500.00 = Rp. 24,021.00
Jumlah (1) = Rp. 660,351.00
6.3.2. Tenaga
- Pekerja 1.500 Oh x Rp. 52,500.00 = Rp. 78,750.00
- Tukang batu 0.600 Oh x Rp. 78,800.00 = Rp. 47,280.00
- Kepala tukang 0.060 Oh x Rp. 91,900.00 = Rp. 5,514.00
- Mandor 0.075 Oh x Rp. 65,600.00 = Rp. 4,920.00
Jumlah (2) = Rp. 136,464.00
Jumlah (1) +(2) = Rp. 796,815.00
ANALISA BIAYA KONSTRUKSI
PEKERJAAN PONDASI
-
5/21/2018 Daftar Analisa Sni 2010 (1)
10/143
PP 6.4. 1 M Pasang pondasi batu kali, 1 Pc : 3 Ps
6.4.1. Bahan
- Batu belah 15/20 cm 1.100 M x Rp. 125,900.00 = Rp. 138,490.00
- Semen porland 202.000 Kg x Rp. 1,270.00 = Rp. 256,540.00
- Pasir Pasang 0.485 M x Rp. 76,500.00 = Rp. 37,102.50
Jumlah (1) = Rp. 432,132.50
6.4.2. Tenaga
- Pekerja 1.500 Oh x Rp. 52,500.00 = Rp. 78,750.00
- Tukang batu 0.600 Oh x Rp. 78,800.00 = Rp. 47,280.00
- Kepala tukang 0.060 Oh x Rp. 91,900.00 = Rp. 5,514.00
- Mandor 0.075 Oh x Rp. 65,600.00 = Rp. 4,920.00
Jumlah (2) = Rp. 136,464.00
Jumlah (1) +(2) = Rp. 568,596.50
PP 6.5. 1 M Pasang pondasi batu kali, 1 Pc : 4 Ps.
6.5.1. Bahan
- Batu belah 15/20 cm 1.100 M x Rp. 125,900.00 = Rp. 138,490.00
- Semen porland 163.000 Kg x Rp. 1,270.00 = Rp. 207,010.00
- Pasir Pasang 0.520 M x Rp. 76,500.00 = Rp. 39,780.00
Jumlah (1) = Rp. 385,280.00
6.5.2. Tenaga
- Pekerja 1.500 Oh x Rp. 52,500.00 = Rp. 78,750.00
- Tukang batu 0.600 Oh x Rp. 78,800.00 = Rp. 47,280.00
- Kepala tukang 0.060 Oh x Rp. 91,900.00 = Rp. 5,514.00
- Mandor 0.075 Oh x Rp. 65,600.00 = Rp. 4,920.00
Jumlah (2) = Rp. 136,464.00
Jumlah (1) +(2) = Rp. 521,744.00
PP 6.6. 1 M Pasang pondasi batu kali, 1 Pc : 5 Ps
6.6.1. Bahan
- Batu belah 15/20 cm 1.100 M x Rp. 125,900.00 = Rp. 138,490.00- Semen porland 136.000 Kg x Rp. 1,270.00 = Rp. 172,720.00
- Pasir Pasang 0.544 M x Rp. 76,500.00 = Rp. 41,616.00
Jumlah (1) = Rp. 352,826.00
6.6.2. Tenaga
- Pekerja 1.500 Oh x Rp. 52,500.00 = Rp. 78,750.00
- Tukang batu 0.600 Oh x Rp. 78,800.00 = Rp. 47,280.00
- Kepala tukang 0.060 Oh x Rp. 91,900.00 = Rp. 5,514.00
- Mandor 0.075 Oh x Rp. 65,600.00 = Rp. 4,920.00
Jumlah (2) 136,464.00
Jumlah (1) +(2) 489,290.00
PP 6.7. 1 M Pasang pondasi batu kali, 1 Pc : 6 Ps
6.7.1. Bahan
- Batu belah 15/20 cm 1.100 M x Rp. 125,900.00 = Rp. 138,490.00
- Semen porland 117.000 Kg x Rp. 1,270.00 = Rp. 148,590.00
- Pasir Pasang 0.561 M x Rp. 76,500.00 = Rp. 42,916.50
Jumlah (1) = Rp. 329,996.50
6.7.2. Tenaga
- Pekerja 1.500 Oh x Rp. 52,500.00 = Rp. 78,750.00
- Tukang batu 0.600 Oh x Rp. 78,800.00 = Rp. 47,280.00
-
5/21/2018 Daftar Analisa Sni 2010 (1)
11/143
- Kepala tukang 0.060 Oh x Rp. 91,900.00 = Rp. 5,514.00
- Mandor 0.075 Oh x Rp. 65,600.00 = Rp. 4,920.00
Jumlah (2) = Rp. 136,464.00
Jumlah (1) +(2) = Rp. 466,460.50
PP 6.8. 1 M Pasang pondasi batu kali, Pc : 8 Ps
6.8.1. Bahan- Batu belah 15/20 cm 1.100 M x Rp. 125,900.00 = Rp. 138,490.00
- Semen porland 91.000 Kg x Rp. 1,270.00 = Rp. 115,570.00
- Pasir Pasang 0.561 M x Rp. 76,500.00 = Rp. 42,916.50
Jumlah (1) = Rp. 296,976.50
6.8.2. Tenaga
- Pekerja 1.500 Oh x Rp. 52,500.00 = Rp. 78,750.00
- Tukang batu 0.600 Oh x Rp. 78,800.00 = Rp. 47,280.00
- Kepala tukang 0.060 Oh x Rp. 91,900.00 = Rp. 5,514.00
- Mandor 0.075 Oh x Rp. 65,600.00 = Rp. 4,920.00
Jumlah (2) = Rp. 136,464.00
Jumlah (1) +(2) = Rp. 433,440.50
PP 6.9. 1 M Pasang pondasi batu kali, 1 Kp : 1 Sm : 1 Ps
6.9.1. Bahan- Batu belah 15/20 cm 1.100 M x Rp. 125,900.00 = Rp. 138,490.00
- Kapur pasang 0.229 Kg x Rp. 187,000.00 = Rp. 42,823.00
- Batu Bata biasa 5x10x20 cm 0.229 M x Rp. 25,080.00 = Rp. 5,743.32
- Pasir Pasang 0.544 M x Rp. 6,270.00 = Rp. 3,410.88
Jumlah (1) = Rp. 190,467.20
6.9.2. Tenaga
- Pekerja 1.500 Oh x Rp. 52,500.00 = Rp. 78,750.00
- Tukang batu 0.600 Oh x Rp. 78,800.00 = Rp. 47,280.00
- Kepala tukang 0.060 Oh x Rp. 91,900.00 = Rp. 5,514.00
- Mandor 0.075 Oh x Rp. 65,600.00 = Rp. 4,920.00
Jumlah (2) = Rp. 136,464.00
Jumlah (1) +(2) = Rp. 326,931.20
PP 6.10. 1 M Pasang pondasi batu kali, 1 Kp : 1 SM : 2 Ps
6.10.1.Bahan
- Batu belah 15/20 cm 1.100 M x Rp. 125,900.00 = Rp. 138,490.00
- Kapur pasang 0.170 Kg x Rp. 187,000.00 = Rp. 31,790.00
- Batu Bata biasa 5x10x20 cm 0.170 M x Rp. 25,080.00 = Rp. 4,263.60
- Pasir Pasang 0.340 M x Rp. 6,270.00 = Rp. 2,131.80
Jumlah (1) = Rp. 176,675.40
6.10.2.Tenaga
- Pekerja 1.500 Oh x Rp. 52,500.00 = Rp. 78,750.00
- Tukang batu 0.600 Oh x Rp. 78,800.00 = Rp. 47,280.00
- Kepala tukang 0.060 Oh x Rp. 91,900.00 = Rp. 5,514.00
- Mandor 0.075 Oh x Rp. 65,600.00 = Rp. 4,920.00
Jumlah (2) = Rp. 136,464.00Jumlah (1) +(2) = Rp. 313,139.40
PP 6.11. 1 M Pasangan pondasi batu kali, 1 Pc : 1/4 Kp : 4 Ps
6.11.1.Bahan
- Batu belah 15/20 cm 1.100 M x Rp. 125,900.00 = Rp. 138,490.00
- Kayu Profil 4" 156.000 Kg x Rp. 25,080.00 = Rp. 3,912,480.00
- Kapur pasang 0.032 M x Rp. 187,000.00 = Rp. 5,984.00
- Pasir Pasang 0.584 M x Rp. 6,270.00 = Rp. 3,661.68
-
5/21/2018 Daftar Analisa Sni 2010 (1)
12/143
Jumlah (1) = Rp. 4,060,615.68
6.11.2.Tenaga
- Pekerja 1.500 Oh x Rp. 52,500.00 = Rp. 78,750.00
- Tukang batu 0.600 Oh x Rp. 78,800.00 = Rp. 47,280.00
- Kepala tukang 0.060 Oh x Rp. 91,900.00 = Rp. 5,514.00
- Mandor 0.075 Oh x Rp. 65,600.00 = Rp. 4,920.00
Jumlah (2) = Rp. 136,464.00Jumlah (1) +(2) = Rp. 4,197,079.68
PP 6.12. 1 M Pasang pondasi batu kali, 1 Pc : 3 Kp : 10 Ps
6.12.1.Bahan
- Batu belah 15/20 cm 1.100 M x Rp. 125,900.00 = Rp. 138,490.00
- Kayu Profil 4" 61.000 Kg x Rp. 25,080.00 = Rp. 1,529,880.00
- Kapur pasang 0.147 M x Rp. 187,000.00 = Rp. 27,489.00
- Pasir Pasang 0.492 M x Rp. 6,270.00 = Rp. 3,084.84
Jumlah (1) = Rp. 1,698,943.84
6.12.2.Tenaga
- Pekerja 1.500 Oh x Rp. 52,500.00 = Rp. 78,750.00
- Tukang batu 0.600 Oh x Rp. 78,800.00 = Rp. 47,280.00
- Kepala tukang 0.060 Oh x Rp. 91,900.00 = Rp. 5,514.00- Mandor 0.075 Oh x Rp. 65,600.00 = Rp. 4,920.00
Jumlah (2) = Rp. 136,464.00
Jumlah (1) +(2) = Rp. 1,835,407.84
PP 6.13. 1 M Pasang pondasi batu kali, 1/4 Pc : 1 Kp : 4 Ps
6.13.1.Bahan
- Batu belah 15/20 cm 1.100 M x Rp. 125,900.00 = Rp. 138,490.00
- Kayu Profil 4" 41.000 Kg x Rp. 25,080.00 = Rp. 1,028,280.00
- Kapur pasang 0.131 M x Rp. 187,000.00 = Rp. 24,497.00
- Pasir Pasang 0.523 M x Rp. 6,270.00 = Rp. 3,279.21
Jumlah (1) = Rp. 1,194,546.21
6.13.2.Tenaga- Pekerja 1.500 Oh x Rp. 52,500.00 = Rp. 78,750.00
- Tukang batu 0.600 Oh x Rp. 78,800.00 = Rp. 47,280.00
- Kepala tukang 0.060 Oh x Rp. 91,900.00 = Rp. 5,514.00
- Mandor 0.075 Oh x Rp. 65,600.00 = Rp. 4,920.00
Jumlah (2) = Rp. 136,464.00
Jumlah (1) +(2) = Rp. 1,331,010.21
PP 6.14. 1 M Pasang pondasi batu kosong
6.14.1.Bahan
- Batu belah 10/15 cm 1.200 M x Rp. 140,900.00 = Rp. 169,080.00
- Pasir pasang 0.300 M x Rp. 76,500.00 = Rp. 22,950.00
Jumlah (1) = Rp. 192,030.00
6.14.2.Tenaga
- Pekerja 0.780 Oh x Rp. 52,500.00 = Rp. 40,950.00- Tukang batu 0.390 Oh x Rp. 78,800.00 = Rp. 30,732.00
- Kepala tukang 0.039 Oh x Rp. 91,900.00 = Rp. 3,584.10
- Mandor 0.039 Oh x Rp. 65,600.00 = Rp. 2,558.40
Jumlah (2) = Rp. 77,824.50
Jumlah (1) +(2) = Rp. 269,854.50
-
5/21/2018 Daftar Analisa Sni 2010 (1)
13/143
PP 6.15. 1 M Pasang pondasi siklop 40 % batu kali
6.15.1.Bahan
- Besi beton 75.000 Kg x Rp. 14,410.00 = Rp. 1,080,750.00
- Semen portland 202.000 Kg x Rp. 1,270.00 = Rp. 256,540.00
- Pasir beton 0.320 Kg x Rp. 87,800.00 = Rp. 28,096.00
- Koral beton 0.490 M x Rp. 185,900.00 = Rp. 91,091.00
- Kawat beton 0.800 Kg x Rp. 16,830.00 = Rp. 13,464.00Jumlah (1) = Rp. 1,469,941.00
6.15.2.Tenaga
- Pekerja 3.000 Oh x Rp. 52,500.00 = Rp. 157,500.00
- Tukang batu 0.850 Oh x Rp. 78,800.00 = Rp. 66,980.00
- Kepala tukang 0.085 Oh x Rp. 91,900.00 = Rp. 7,811.50
- Mandor 0.150 Oh x Rp. 65,600.00 = Rp. 9,840.00
Jumlah (2) = Rp. 242,131.50
Jumlah (1) +(2) = Rp. 1,712,072.50
PP 6.16. 1 M Pasang pondasi sumuran diameter 100 Cm
6.16.1.Bahan
- Batu belah 15/20 cm 0.450 M x Rp. 125,900.00 = Rp. 56,655.00
- Semen portland 280.000 Kg x Rp. 1,270.00 = Rp. 355,600.00- Pasir Pasang 0.670 M x Rp. 76,500.00 = Rp. 51,255.00
Jumlah (1) = Rp. 463,510.00
6.16.2.Tenaga
- Pekerja 2.380 Oh x Rp. 52,500.00 = Rp. 124,950.00
- Tukang batu 0.300 Oh x Rp. 78,800.00 = Rp. 23,640.00
- Kepala tukang 0.030 Oh x Rp. 91,900.00 = Rp. 2,757.00
- Mandor 0.080 Oh x Rp. 65,600.00 = Rp. 5,248.00
Jumlah (2) = Rp. 156,595.00
Jumlah (1) +(2) = Rp. 620,105.00
PP 6.17. 1 M Pembuatan tiang pancang (40 x 40) Cm, beton bertulang
6.17.1.Bahan- Pasir urug darat 0.019 M x Rp. 64,400.00 = Rp. 1,223.60
- Pasir beton 0.094 M x Rp. 87,800.00 = Rp. 8,253.20
- Koral beton 0.150 M x Rp. 185,900.00 = Rp. 27,885.00
- Semen porland 60.500 Kg x Rp. 1,270.00 = Rp. 76,835.00
- Besi beton 45.000 Kg x Rp. 14,410.00 = Rp. 648,450.00
- Kawat beton 0.900 Kg x Rp. 16,830.00 = Rp. 15,147.00
- Kayu kaso 5/7 0.032 M x Rp. 3,107,500.00 = Rp. 99,440.00
- Paku 0.120 Kg x Rp. 14,520.00 = Rp. 1,742.40
- Minyak bekisting 0.090 Lt x Rp. 6,290.00 = Rp. 566.10
- Plamur tembok 0.240 Kg x Rp. 15,730.00 = Rp. 3,775.20
Jumlah (1) = Rp. 883,317.50
6.17.2.Tenaga
- Pekerja 1.000 Oh x Rp. 52,500.00 = Rp. 52,500.00
- Tukang batu 0.670 Oh x Rp. 78,800.00 = Rp. 52,796.00
- Kepala tukang 0.067 Oh x Rp. 91,900.00 = Rp. 6,157.30- Mandor 0.050 Oh x Rp. 65,600.00 = Rp. 3,280.00
Jumlah (2) = Rp. 114,733.30
Jumlah (1) +(2) = Rp. 998,050.80
-
5/21/2018 Daftar Analisa Sni 2010 (1)
14/143
PP 6.18. 1 M Pembuatan tiang pancang (35 x 35) Cm, beton bertulang
6.18.1.Bahan
- Pasir urug darat 0.016 M x Rp. 64,400.00 = Rp. 1,030.40
- Pasir beton 0.080 M x Rp. 87,800.00 = Rp. 7,024.00
- Koral beton 0.125 M x Rp. 185,900.00 = Rp. 23,237.50
- Semen porland 49.000 Kg x Rp. 1,270.00 = Rp. 62,230.00
- Besi beton 34.500 Kg x Rp. 14,410.00 = Rp. 497,145.00- Kawat beton 0.700 Kg x Rp. 16,830.00 = Rp. 11,781.00
- Kayu kaso 5/7 0.027 M x Rp. 3,107,500.00 = Rp. 83,902.50
- Paku 0.120 Kg x Rp. 14,520.00 = Rp. 1,742.40
- Minyak bekisting 0.090 Lt x Rp. 6,290.00 = Rp. 566.10
- Plamur tembok 0.200 Kg x Rp. 15,730.00 = Rp. 3,146.00
Jumlah (1) = Rp. 691,804.90
6.18.2.Tenaga
- Pekerja 0.800 Oh x Rp. 52,500.00 = Rp. 42,000.00
- Tukang batu 0.500 Oh x Rp. 78,800.00 = Rp. 39,400.00
- Kepala tukang 0.050 Oh x Rp. 91,900.00 = Rp. 4,595.00
- Mandor 0.040 Oh x Rp. 65,600.00 = Rp. 2,624.00
Jumlah (2) = Rp. 88,619.00
Jumlah (1) +(2) = Rp. 780,423.90
-
5/21/2018 Daftar Analisa Sni 2010 (1)
15/143
PD 6.1. 1 M Pasangan bata merah tebal 1 bata, 1 Pc : 1 Ps
6.1.1. Bahan
- Bata merah 5 x 10 x 20 cm 140.000 Bh x Rp. 720 = Rp 100,800.00- Semen portland 64.030 Kg x Rp. 1,270 = Rp 81,318.10
- Pasir pasang 0.059 M x Rp. 76,500 = Rp 4,513.50
Jumlah (1) = Rp 186,631.60
6.1.2 Tenaga
- Pekerja 0.650 Oh x Rp. 52,500 = Rp 34,125.00
- Tukang batu 0.200 Oh x Rp. 78,800 = Rp 15,760.00
- Kepala tukang 0.020 Oh x Rp. 91,900 = Rp 1,838.00
- Mandor 0.030 Oh x Rp. 65,600 = Rp 1,968.00
Jumlah (2) = Rp 53,691.00
Jumlah (1) + (2) = Rp 240,322.60
PD 6.2 1m Pasangan bata merah tebal 1 bata, 1Pc : 2 Ps
6.2.1 Bahan
- Bata merah 5 x 10 x 20 cm 140.000 Bh x Rp. 720 = Rp 100,800.00
- Semen portland 43.500 Kg x Rp. 1,270 = Rp 55,245.00
- Pasir pasang 0.080 M x Rp. 76,500 = Rp 6,120.00
Jumlah (1) = Rp 162,165.00
6.2.2 Tenaga
- Pekerja 0.650 Oh x Rp. 52,500 = Rp 34,125.00
- Tukang batu 0.200 Oh x Rp. 78,800 = Rp 15,760.00
- Kepala tukang 0.020 Oh x Rp. 91,900 = Rp 1,838.00
- Mandor 0.030 Oh x Rp. 65,600 = Rp 1,968.00
Jumlah (2) = Rp 53,691.00
Jumlah (1) + (2) = Rp 215,856.00
PD 6.3 1 m Pasangan bata merah tebal 1 bata, 1Pc : 3 Ps
6.3.1 Bahan
- Bata merah 5 x 10 x 20 cm 140.000 Bh x Rp. 720 = Rp 100,800.00
- Semen portland 32.950 Kg x Rp. 1,270 = Rp 41,846.50
- Pasir pasang 0.091 M x Rp. 76,500 = Rp 6,961.50
Jumlah (1) = Rp 149,608.00
6.3.2 Tenaga
- Pekerja 0.650 Oh x Rp. 52,500 = Rp 34,125.00
- Tukang batu 0.200 Oh x Rp. 78,800 = Rp 15,760.00
- Kepala tukang 0.020 Oh x Rp. 91,900 = Rp 1,838.00
- Mandor 0.030 Oh x Rp. 65,600 = Rp 1,968.00
Jumlah (2) = Rp 53,691.00
Jumlah (1) + (2) = Rp 203,299.00
PD 6.4 1 m Pasangan bata merah tebal 1 bata, 1Pc : 4 Ps
6.4.1 Bahan
- Bata merah 5 x 10 x 20 cm 140.000 Bh x Rp. 720 = Rp 100,800.00
ANALISA BIAYA KONSTRUKSI
PEKERJAAN DINDING
-
5/21/2018 Daftar Analisa Sni 2010 (1)
16/143
- Semen portland 26.550 Kg x Rp. 1,270 = Rp 33,718.50
- Pasir pasang 0.093 M x Rp. 76,500 = Rp 7,114.50
Jumlah (1) = Rp 141,633.00
6.4.2 Tenaga
- Pekerja 0.650 Oh x Rp. 52,500 = Rp 34,125.00
- Tukang batu 0.200 Oh x Rp. 78,800 = Rp 15,760.00
- Kepala tukang 0.020 Oh x Rp. 91,900 = Rp 1,838.00- Mandor 0.030 Oh x Rp. 65,600 = Rp 34,125.00
Jumlah (2) = Rp 51,723.00
Jumlah (1) + (2) = Rp 193,356.00
PD 6.5 1 m Pasangan bata merah tebal 1 bata, 1Pc : 5 Ps
6.5.1 Bahan
- Bata merah 5 x 10 x 20 cm 140.000 Bh x Rp. 720 = Rp 100,800.00
- Semen portland 22.200 Kg x Rp. 1,270 = Rp 28,194.00
- Pasir pasang 0.102 M x Rp. 76,500 = Rp 7,803.00
Jumlah (1) = Rp 136,797.00
6.5.2 Tenaga
- Pekerja 0.650 Oh x Rp. 52,500 = Rp 34,125.00- Tukang batu 0.200 Oh x Rp. 78,800 = Rp 0.00
- Kepala tukang 0.020 Oh x Rp. 91,900 = Rp 0.00
- Mandor 0.030 Oh x Rp. 65,600 = Rp 1,968.00
Jumlah (2) = Rp 36,093.00
Jumlah (1) + (2) = Rp 172,890.00
PD 6.6 1 m Pasangan bata merah tebal 1 bata, 1Pc : 6 Ps
6.6.1 Bahan
- Bata merah 5 x 10 x 20 cm 140.000 Bh x Rp. 720 = Rp 100,800.00
- Semen portland 22.200 Kg x Rp. 1,270 = Rp 28,194.00
- Pasir pasang 0.102 M x Rp. 76,500 = Rp 7,803.00
Jumlah (1) = Rp 136,797.00
6.6.2 Tenaga
- Pekerja 0.650 Oh x Rp. 52,500 = Rp 34,125.00
- Tukang batu 0.200 Oh x Rp. 78,800 = Rp 15,760.00
- Kepala tukang 0.020 Oh x Rp. 91,900 = Rp 1,838.00
- Mandor 0.030 Oh x Rp. 65,600 = Rp 1,968.00
Jumlah (2) = Rp 53,691.00
Jumlah (1) + (2) = Rp 190,488.00
-
5/21/2018 Daftar Analisa Sni 2010 (1)
17/143
PD 6.7 1 m Pasangan bata merah tebal 1 bata, 1Pc : 3 Kp : 10 Ps
6.7.1 Bahan
- Bata merah 5 x 10 x 20 cm 140.000 Bh x Rp. 720 = Rp 100,800.00
- Semen portland 10.080 Kg x Rp. 1,270 = Rp 12,801.60
- Pasir pasang 0.0925 M x Rp. 76,500 = Rp 7,076.25
Jumlah (1) = Rp 19,877.85
6.7.2 Tenaga
- Pekerja 0.650 Oh x Rp. 52,500 = Rp 34,125.00
- Tukang batu 0.200 Oh x Rp. 78,800 = Rp 15,760.00
- Kepala tukang 0.020 Oh x Rp. 91,900 = Rp 1,838.00
- Mandor 0.030 Oh x Rp. 65,600 = Rp 1,968.00
Jumlah (2) = Rp 53,691.00
Jumlah (1) + (2) = Rp 73,568.85
PD 6.8 1 m Pasangan bata merah tebal 1/2 bata, 1Pc : 1 Ps
6.8.1 Bahan
- Bata merah 5 x 10 x 20 cm 70.000 Bh x Rp. 720 = Rp 50,400.00
- Semen portland 27.800 Kg x Rp. 1,270 = Rp 35,306.00
- Pasir pasang 0.028 M x Rp. 76,500 = Rp 2,142.00Jumlah (1) = Rp 87,848.00
6.8.2 Tenaga
- Pekerja 0.320 Oh x Rp. 52,500 = Rp 16,800.00
- Tukang batu 0.100 Oh x Rp. 78,800 = Rp 7,880.00
- Kepala tukang 0.010 Oh x Rp. 91,900 = Rp 919.00
- Mandor 0.015 Oh x Rp. 65,600 = Rp 984.00
Jumlah (2) = Rp 26,583.00
Jumlah (1) + (2) = Rp 114,431.00
PD 6.9 1 m Pasangan bata merah tebal 1/2 bata, 1Pc : 2 Ps
6.9.1 Bahan
- Bata merah 5 x 10 x 20 cm 70.000 Bh x Rp. 720 = Rp 50,400.00- Semen portland 18.950 Kg x Rp. 1,270 = Rp 24,066.50
- Pasir pasang 0.038 M x Rp. 76,500 = Rp 2,907.00
Jumlah (1) = Rp 77,373.50
6.9.2 Tenaga
- Pekerja 0.320 Oh x Rp. 52,500 = Rp 16,800.00
- Tukang batu 0.100 Oh x Rp. 78,800 = Rp 7,880.00
- Kepala tukang 0.010 Oh x Rp. 91,900 = Rp 919.00
- Mandor 0.015 Oh x Rp. 65,600 = Rp 984.00
Jumlah (2) = Rp 26,583.00
Jumlah (1) + (2) = Rp 103,956.50
-
5/21/2018 Daftar Analisa Sni 2010 (1)
18/143
PD 6.10 1 m Pasangan bata merah tebal 1/2 bata, 1Pc : 3 Ps
6.10.1 Bahan
- Bata merah 5 x 10 x 20 cm 70.000 Bh x Rp. 720 = Rp 50,400.00
- Semen portland 14.370 Kg x Rp. 1,270 = Rp 18,249.90
- Pasir pasang 0.040 M x Rp. 76,500 = Rp 3,060.00
Jumlah (1) = Rp 71,709.90
6.10.2 Tenaga
- Pekerja 0.320 Oh x Rp. 52,500 = Rp 16,800.00
- Tukang batu 0.100 Oh x Rp. 78,800 = Rp 7,880.00
- Kepala tukang 0.010 Oh x Rp. 91,900 = Rp 919.00
- Mandor 0.015 Oh x Rp. 65,600 = Rp 984.00
Jumlah (2) = Rp 26,583.00
Jumlah (1) + (2) = Rp 98,292.90
PD 6.11 1 m Pasangan bata merah tebal 1/2 bata, 1Pc : 4 Ps
6.11.1 Bahan
- Bata merah 5 x 10 x 20 cm 70.000 Bh x Rp. 720 = Rp 50,400.00
- Semen portland 11.500 Kg x Rp. 1,270 = Rp 14,605.00
- Pasir pasang 0.043 M x Rp. 76,500 = Rp 3,289.50Jumlah (1) = Rp 68,294.50
6.11.2 Tenaga
- Pekerja 0.320 Oh x Rp. 52,500 = Rp 16,800.00
- Tukang batu 0.100 Oh x Rp. 78,800 = Rp 7,880.00
- Kepala tukang 0.010 Oh x Rp. 91,900 = Rp 919.00
- Mandor 0.015 Oh x Rp. 65,600 = Rp 984.00
Jumlah (2) = Rp 26,583.00
Jumlah (1) + (2) = Rp 94,877.50
PD 6.12 1 m Pasangan bata merah tebal 1/2 bata, 1Pc : 5 Ps
6.12.1 Bahan
- Bata merah 5 x 11 x 22 cm 70.000 Bh x Rp. 720 = Rp 50,400.00- Semen portland 9.680 Kg x Rp. 1,270 = Rp 12,293.60
- Pasir pasang 0.045 M x Rp. 76,500 = Rp 3,442.50
Jumlah (1) = Rp 66,136.10
6.12.2 Tenaga
- Pekerja 0.320 Oh x Rp. 52,500 = Rp 16,800.00
- Tukang batu 0.100 Oh x Rp. 78,800 = Rp 7,880.00
- Kepala tukang 0.010 Oh x Rp. 91,900 = Rp 919.00
- Mandor 0.015 Oh x Rp. 65,600 = Rp 984.00
Jumlah (2) = Rp 26,583.00
Jumlah (1) + (2) = Rp 92,719.10
-
5/21/2018 Daftar Analisa Sni 2010 (1)
19/143
PD 6.13 1 m Pasangan bata merah tebal 1/2 bata, 1Pc : 6 Ps
6.13.1 Bahan
- Bata merah 5 x 11 x 22 cm 70.000 Bh x Rp. 720 = Rp 50,400.00
- Semen portland 8.320 Kg x Rp. 1,270 = Rp 10,566.40
- Pasir pasang 0.049 M x Rp. 76,500 = Rp 3,748.50
Jumlah (1) = Rp 64,714.90
6.13.2 Tenaga
- Pekerja 0.320 Oh x Rp. 52,500 = Rp 16,800.00
- Tukang batu 0.100 Oh x Rp. 78,800 = Rp 7,880.00
- Kepala tukang 0.010 Oh x Rp. 91,900 = Rp 919.00
- Mandor 0.015 Oh x Rp. 65,600 = Rp 984.00
Jumlah (2) = Rp 26,583.00
Jumlah (1) + (2) = Rp 91,297.90
PD 6.14 1 m Pasangan bata merah tebal 1/2 bata, 1Pc : 8 Ps
6.14.1 Bahan
- Bata merah 5 x 11 x 22 cm 70.000 Bh x Rp. 720 = Rp 50,400.00
- Semen portland 6.500 Kg x Rp. 1,270 = Rp 8,255.00
- Pasir pasang 0.050 M x Rp. 76,500 = Rp 3,825.00Jumlah (1) = Rp 62,480.00
6.14.2 Tenaga
- Pekerja 0.320 Oh x Rp. 52,500 = Rp 16,800.00
- Tukang batu 0.100 Oh x Rp. 78,800 = Rp 7,880.00
- Kepala tukang 0.010 Oh x Rp. 91,900 = Rp 919.00
- Mandor 0.015 Oh x Rp. 65,600 = Rp 984.00
Jumlah (2) = Rp 26,583.00
Jumlah (1) + (2) = Rp 89,063.00
PD 6.15 1 m Pasangan bata merah tebal 1/2 bata, 1Pc : 3 Kp : 10 Ps
6.15.1 Bahan
- Bata merah 5 x 11 x 22 cm 70.000 Bh x Rp. 720 = Rp 50,400.00- Semen portland 4.500 Kg x Rp. 1,270 = Rp 5,715.00
- Pasir pasang 0.050 M x Rp. 76,500 = Rp 3,825.00
- Kapur pasang 0.015 M x Rp. 0 = Rp 0.00
Jumlah (1) = Rp 59,940.00
6.15.2 Tenaga
- Pekerja 0.320 Oh x Rp. 52,500 = Rp 16,800.00
- Tukang batu 0.100 Oh x Rp. 78,800 = Rp 7,880.00
- Kepala tukang 0.010 Oh x Rp. 91,900 = Rp 919.00
- Mandor 0.015 Oh x Rp. 65,600 = Rp 984.00
Jumlah (2) = Rp 26,583.00
Jumlah (1) + (2) = Rp 86,523.00
-
5/21/2018 Daftar Analisa Sni 2010 (1)
20/143
PD 6.16 1 m Pasangan bata merah tebal 1/2 bata, 1Kp : 1 Sm : 1 Ps
6.16.1 Bahan
- Bata merah 5 x 11 x 22 cm 70.000 Bh x Rp. 720 = Rp 50,400.00
- Kawat Duri 0.018 M x Rp. 4,030 = Rp 72.54
- Pasir pasang 0.018 M x Rp. 76,500 = Rp 1,377.00
- Kapur padam 0.018 M x Rp. 68,290 = Rp 1,229.22
Jumlah (1) = Rp 53,078.76
6.16.2 Tenaga
- Pekerja 0.320 Oh x Rp. 52,500 = Rp 16,800.00
- Tukang batu 0.100 Oh x Rp. 78,800 = Rp 7,880.00
- Kepala tukang 0.010 Oh x Rp. 91,900 = Rp 919.00
- Mandor 0.015 Oh x Rp. 65,600 = Rp 984.00
Jumlah (2) = Rp 26,583.00
Jumlah (1) + (2) = Rp 79,661.76
PD 6.17 1 m Pasangan bata merah tebal 1/2 bata, 1Kp : 1 Sm : 2 Ps
6.17.1 Bahan
- Bata merah 5 x 11 x 22 cm 70.000 Bh x Rp. 720 = Rp 50,400.00- Kawat Duri 0.014 Kg x Rp. 1,270 = Rp 17.78
- Pasir pasang 0.028 M x Rp. 76,500 = Rp 2,142.00
- Kapur padam 0.014 M x Rp. 68,290 = Rp 956.06
Jumlah (1) = Rp 53,515.84
6.17.2 Tenaga
- Pekerja 0.320 Oh x Rp. 52,500 = Rp 16,800.00
- Tukang batu 0.100 Oh x Rp. 78,800 = Rp 7,880.00
- Kepala tukang 0.010 Oh x Rp. 91,900 = Rp 919.00
- Mandor 0.015 Oh x Rp. 65,600 = Rp 984.00
Jumlah (2) = Rp 26,583.00
Jumlah (1) + (2) = Rp 80,098.84
PD 6.18 1 m Pasangan dinding holowblock (HB.20)
6.18.1 Bahan
- Hollow block (HB.20) 12.500 Bh x Rp. 17,070 = Rp 213,375.00
- Semen portland 13.500 Kg x Rp. 1,270 = Rp 17,145.00
- Pasir pasang 0.048 M x Rp. 76,500 = Rp 3,672.00
- Besi beton polos 1.950 M x Rp. 168,250 = Rp 328,087.50
Jumlah (1) = Rp 562,279.50
6.18.2 Tenaga
- Pekerja 0.320 Oh x Rp. 52,500 = Rp 16,800.00
- Tukang batu 0.150 Oh x Rp. 78,800 = Rp 11,820.00
- Kepala tukang 0.015 Oh x Rp. 91,900 = Rp 1,378.50
- Mandor 0.017 Oh x Rp. 65,600 = Rp 1,115.20
Jumlah (2) = Rp 31,113.70Jumlah (1) + (2) = Rp 593,393.20
-
5/21/2018 Daftar Analisa Sni 2010 (1)
21/143
PD 6.19 1 m Pasangan dinding holowblock (HB.15)
6.19.1 Bahan
- Hollow block (HB.15) 12.500 Bh x Rp. 8,540 = Rp 106,750.00
- Semen portland 10.450 Kg x Rp. 1,270 = Rp 13,271.50
- Pasir pasang 0.038 M x Rp. 76,500 = Rp 2,907.00
- Besi beton polos 1.950 M x Rp. 168,250 = Rp 328,087.50
Jumlah (1) = Rp 451,016.00
6.19.2 Tenaga
- Pekerja 0.320 Oh x Rp. 52,500 = Rp 16,800.00
- Tukang batu 0.120 Oh x Rp. 78,800 = Rp 9,456.00
- Kepala tukang 0.012 Oh x Rp. 91,900 = Rp 1,102.80
- Mandor 0.015 Oh x Rp. 65,600 = Rp 984.00
Jumlah (2) = Rp 28,342.80
Jumlah (1) + (2) = Rp 479,358.80
PD 6.20 1 m Pasangan dinding holowblock (HB.10)
6.20.1 Bahan
- Hollow block (HB.10) 12.500 Bh x Rp. 17,330 = Rp 216,625.00
- Semen portland 7.500 Kg x Rp. 1,270 = Rp 9,525.00- Pasir pasang 0.027 M x Rp. 76,500 = Rp 2,065.50
- Besi beton polos 1.950 M x Rp. 168,250 = Rp 328,087.50
Jumlah (1) = Rp 556,303.00
6.20.2 Tenaga
- Pekerja 0.320 Oh x Rp. 52,500 = Rp 16,800.00
- Tukang batu 0.100 Oh x Rp. 78,800 = Rp 7,880.00
- Kepala tukang 0.010 Oh x Rp. 91,900 = Rp 919.00
- Mandor 0.015 Oh x Rp. 65,600 = Rp 984.00
Jumlah (2) = Rp 26,583.00
Jumlah (1) + (2) = Rp 582,886.00
PD 6.21 1 m Pasangan dinding conblock (CB.20)
6.21.1 Bahan
- Concrete block (CB 20) 12.500 Bh x Rp. 2,920 = Rp 36,500.00
- Semen portland 14.050 Kg x Rp. 1,270 = Rp 17,843.50
- Pasir beton 0.004 M x Rp. 87,800 = Rp 351.20
- Pasir pasang 0.042 M x Rp. 76,500 = Rp 3,213.00
- Besi beton polos 3.870 Bh x Rp. 14,410 = Rp 55,766.70
- Paku biasa 2" - 5" 0.006 Kg x Rp. 14,520 = Rp 87.12
- Kayu sembarang 0.001 M x Rp. 3,107,500 = Rp 3,107.50
- Kawat beton 0.030 M x Rp. 16,830 = Rp 504.90
- Koral beton 0.005 M x Rp. 185,900 = Rp 929.50
Jumlah (1) = Rp 118,303.42
-
5/21/2018 Daftar Analisa Sni 2010 (1)
22/143
6.21.2 Tenaga
- Pekerja 0.370 Oh x Rp. 52,500 = Rp 19,425.00
- Tukang batu 0.157 Oh x Rp. 78,800 = Rp 12,371.60
- Tukang besi 0.007 Oh x Rp. 78,800 = Rp 551.60
- Kepala tukang 0.0164 Oh x Rp. 91,900 = Rp 1,507.16
- Mandor 0.0185 Oh x Rp. 65,600 = Rp 1,213.60
Jumlah (2) = Rp 35,068.96
Jumlah (1) + (2) = Rp 153,372.38
PD 6.22 1 m Pasangan dinding Conblock (CB.15)
6.22.1 Bahan
- Concrete block (CB 15) 12.500 Bh x Rp. 1,600 = Rp 20,000.00
- Semen portland 10.460 Kg x Rp. 1,270 = Rp 13,284.20
- Pasir beton 0.003 M x Rp. 87,800 = Rp 263.40
- Pasir pasang 0.032 M x Rp. 76,500 = Rp 2,448.00
- Besi beton polos 8 mm 2.870 Bh x Rp. 14,410 = Rp 41,356.70
- Paku biasa 2" - 5" 0.004 Kg x Rp. 14,520 = Rp 58.08
- Kayu sembarang 0.001 M x Rp. 3,107,500 = Rp 3,107.50
- Kawat beton 0.020 M x Rp. 16,830 = Rp 336.60
- Koral beton 0.004 M x Rp. 185,900 = Rp 743.60
Jumlah (1) = Rp 81,598.08
6.22.2 Tenaga
- Pekerja 0.340 Oh x Rp. 52,500 = Rp 17,850.00
- Tukang batu 0.130 Oh x Rp. 78,800 = Rp 10,244.00
- Tukang besi 0.007 Oh x Rp. 78,800 = Rp 551.60
- Kepala tukang 0.0137 Oh x Rp. 91,900 = Rp 1,259.03
- Mandor 0.017 Oh x Rp. 65,600 = Rp 1,115.20
Jumlah (2) = Rp 31,019.83
Jumlah (1) + (2) = Rp 112,617.91
PD 6.23 1 m Pasangan dinding Conblock (CB.10)
6.23.1 Bahan
- Concrete block (CB 10) 12.500 Bh x Rp. 740 = Rp 9,250.00- Semen portland 7.200 Kg x Rp. 1,270 = Rp 9,144.00
- Pasir beton 0.002 M x Rp. 87,800 = Rp 175.60
- Pasir pasang 0.021 M x Rp. 76,500 = Rp 1,606.50
- Besi beton polos 2.540 Bh x Rp. 14,410 = Rp 36,601.40
- Paku biasa 2" - 5" 0.003 Kg x Rp. 14,520 = Rp 43.56
- Kayu sembarang 0.001 M x Rp. 3,107,500 = Rp 3,107.50
- Kawat beton 0.015 M x Rp. 16,830 = Rp 252.45
- Koral beton 0.003 M x Rp. 185,900 = Rp 557.70
Jumlah (1) = Rp 60,738.71
6.23.2 Tenaga
- Pekerja 0.340 Oh x Rp. 52,500 = Rp 17,850.00
- Tukang batu 0.107 Oh x Rp. 78,800 = Rp 8,431.60
- Tukang besi 0.007 Oh x Rp. 78,800 = Rp 551.60
- Kepala tukang 0.0114 Oh x Rp. 91,900 = Rp 1,047.66- Mandor 0.017 Oh x Rp. 65,600 = Rp 1,115.20
Jumlah (2) = Rp 28,996.06
Jumlah (1) + (2) = Rp 89,734.77
-
5/21/2018 Daftar Analisa Sni 2010 (1)
23/143
PD 6.24 1 m Pasang dinding lantai
6.24.1 Bahan
- Bondbeam 40 x 20 x 20 cm 2.500 Bh x Rp. 30,250 = Rp 75,625.00
- Semen portland 5.100 Kg x Rp. 1,270 = Rp 6,477.00
- Pasir beton 0.080 M x Rp. 87,800 = Rp 7,024.00
- Besi beton polos 1.500 Kg x Rp. 14,410 = Rp 21,615.00
- Koral beton 0.150 M x Rp. 185,900 = Rp 27,885.00Jumlah (1) = Rp 138,626.00
6.24.2 Tenaga
- Pekerja 0.100 Oh x Rp. 52,500 = Rp 5,250.00
- Tukang batu 0.030 Oh x Rp. 78,800 = Rp 2,364.00
- Tukang besi 0.030 Oh x Rp. 78,800 = Rp 2,364.00
- Kepala tukang 0.006 Oh x Rp. 91,900 = Rp 551.40
- Mandor 0.005 Oh x Rp. 65,600 = Rp 328.00
Jumlah (2) = Rp 10,857.40
Jumlah (1) + (2) = Rp 149,483.40
PD 6.25 1 m Pasang dinding roster / terawang
6.25.1 Bahan
- Roster/terawang 36.000 Bh x Rp. 3,030 = Rp 109,080.00
- Semen portland 12.800 Kg x Rp. 1,270 = Rp 16,256.00- Pasir pasang 0.035 M x Rp. 76,500 = Rp 2,677.50
Jumlah (1) = Rp 128,013.50
6.25.2 Tenaga
- Pekerja 0.300 Oh x Rp. 52,500 = Rp 15,750.00
- Tukang batu 0.100 Oh x Rp. 78,800 = Rp 7,880.00
- Kepala tukang 0.010 Oh x Rp. 91,900 = Rp 919.00
- Mandor 0.015 Oh x Rp. 65,600 = Rp 984.00
Jumlah (2) = Rp 25,533.00
Jumlah (1) + (2) = Rp 153,546.50
PD 6.26 1 m Pasang bata berongga ukuran ( 5 x 10 x 20 ) cm
6.26.1 Bahan
- Batu berongga 80.000 Bh x Rp. 610 = Rp 48,800.00
- Semen portland 23.650 Kg x Rp. 1,270 = Rp 30,035.50
- Pasir pasang 0.570 M x Rp. 76,500 = Rp 43,605.00
Jumlah (1) = Rp 122,440.50
6.26.2 Tenaga
- Pekerja 0.320 Oh x Rp. 52,500 = Rp 16,800.00
- Tukang batu 0.150 Oh x Rp. 78,800 = Rp 11,820.00
- Kepala tukang 0.015 Oh x Rp. 91,900 = Rp 1,378.50
- Mandor 0.015 Oh x Rp. 65,600 = Rp 984.00
Jumlah (2) = Rp 30,982.50
Jumlah (1) + (2) = Rp 153,423.00
-
5/21/2018 Daftar Analisa Sni 2010 (1)
24/143
PD 6.27 1 m Pasang dinding anyaman bambu, rangka kayu
6.27.1 Bahan
- Bilik bambu 1.500 M x Rp. 16,340 = Rp 24,510.00
- Kayu 5/7 0.014 M x Rp. 5,225,000 = Rp 73,150.00
- Paku 0.012 Kg x Rp. 14,520 = Rp 174.24
- List kayu 2/4 0.003 M x Rp. 5,225,000 = Rp 15,675.00
Jumlah (1) = Rp 113,509.24
6.27.2 Tenaga
- Pekerja 0.100 Oh x Rp. 52,500 = Rp 5,250.00
- Tukang batu 0.050 Oh x Rp. 78,800 = Rp 3,940.00
- Kepala tukang 0.005 Oh x Rp. 91,900 = Rp 459.50
- Mandor 0.002 Oh x Rp. 65,600 = Rp 131.20
Jumlah (2) = Rp 9,780.70
Jumlah (1) + (2) = Rp 123,289.94
-
5/21/2018 Daftar Analisa Sni 2010 (1)
25/143
PPL 6.1. 1 M Plesteran 1 Pc : 1 Ps, tebal 15 mm
6.1.1. Bahan
- Semen portland 12.920 Kg x Rp. 1,270 = Rp. 16,408.40- Pasir pasang 0.013 M x Rp. 76,500 = Rp. 994.50
Jumlah (1) = Rp. 17,402.90
6.1.2. Tenaga
- Pekerja 0.200 Oh x Rp. 52,500 = Rp. 10,500.00
- Tukang batu 0.150 Oh x Rp. 78,800 = Rp. 11,820.00
- Kepala tukang 0.015 Oh x Rp. 91,900 = Rp. 1,378.50
- Mandor 0.010 Oh x Rp. 65,600 = Rp. 656.00
Jumlah (2) = Rp. 24,354.50
Jumlah (1) + (2) = Rp. 41,757.40
PPL 6.2. 1 M Plesteran 1 Pc : 2 Ps, tebal 15 mm
6.2.1. Bahan
- Semen portland 8.520 Kg x Rp. 1,270 = Rp. 10,820.40
- Pasir pasang 0.017 M x Rp. 76,500 = Rp. 1,300.50
Jumlah (1) = Rp. 12,120.90
6.2.2. Tenaga
- Pekerja 0.200 Oh x Rp. 52,500 = Rp. 10,500.00
- Tukang batu 0.150 Oh x Rp. 78,800 = Rp. 11,820.00
- Kepala tukang 0.015 Oh x Rp. 91,900 = Rp. 1,378.50
- Mandor 0.010 Oh x Rp. 65,600 = Rp. 656.00
Jumlah (2) = Rp. 24,354.50
Jumlah (1) + (2) = Rp. 36,475.40
PPL 6.3. 1 M Plesteran 1 Pc : 3 Ps, tebal 15 mm
6.3.1. Bahan
- Semen portland 6.480 Kg x Rp. 1,270 = Rp. 8,229.60
- Pasir pasang 0.019 M x Rp. 76,500 = Rp. 1,453.50
Jumlah (1) = Rp. 9,683.10
6.3.2. Tenaga
- Pekerja 0.200 Oh x Rp. 52,500 = Rp. 10,500.00
- Tukang batu 0.150 Oh x Rp. 78,800 = Rp. 11,820.00
- Kepala tukang 0.015 Oh x Rp. 91,900 = Rp. 1,378.50
- Mandor 0.010 Oh x Rp. 65,600 = Rp. 656.00
Jumlah (2) = Rp. 24,354.50
Jumlah (1) + (2) = Rp. 34,037.60
PPL 6.4. 1 M Plesteran 1 Pc : 4 Ps, tebal 15 mm
6.4.1. Bahan
- Semen portland 5.200 Kg x Rp. 1,270 = Rp. 6,604.00
- Pasir pasang 0.020 M x Rp. 76,500 = Rp. 1,530.00
Jumlah (1) = Rp. 8,134.00
ANALISA BIAYA KONSTRUKSI
PEKERJAAN PLESTERAN
-
5/21/2018 Daftar Analisa Sni 2010 (1)
26/143
6.4.2. Tenaga
- Pekerja 0.200 Oh x Rp. 52,500 = Rp. 10,500.00
- Tukang batu 0.150 Oh x Rp. 78,800 = Rp. 11,820.00
- Kepala tukang 0.015 Oh x Rp. 91,900 = Rp. 1,378.50
- Mandor 0.010 Oh x Rp. 65,600 = Rp. 656.00
Jumlah (2) = Rp. 24,354.50
Jumlah (1) + (2) = Rp. 32,488.50
PPL 6.5. 1 M Plesteran 1 Pc : 5 Ps, tebal 15 mm
6.5.1. Bahan
- Semen portland 4.320 Kg x Rp. 1,270 = Rp. 5,486.40
- Pasir pasang 0.022 M x Rp. 76,500 = Rp. 1,683.00
Jumlah (1) = Rp. 7,169.40
6.5.2. Tenaga
- Pekerja 0.200 Oh x Rp. 52,500 = Rp. 10,500.00
- Tukang batu 0.150 Oh x Rp. 78,800 = Rp. 11,820.00
- Kepala tukang 0.015 Oh x Rp. 91,900 = Rp. 1,378.50
- Mandor 0.010 Oh x Rp. 65,600 = Rp. 656.00
Jumlah (2) = Rp. 24,354.50
Jumlah (1) + (2) = Rp. 31,523.90
PPL 6.6. 1 M Plesteran 1 Pc : 6 Ps, tebal 15 mm
6.6.1. Bahan
- Semen portland 3.680 Kg x Rp. 1,270 = Rp. 4,673.60
- Pasir pasang 0.023 M x Rp. 76,500 = Rp. 1,759.50
Jumlah (1) = Rp. 6,433.10
6.6.2. Tenaga
- Pekerja 0.200 Oh x Rp. 52,500 = Rp. 10,500.00
- Tukang batu 0.150 Oh x Rp. 78,800 = Rp. 11,820.00
- Kepala tukang 0.015 Oh x Rp. 91,900 = Rp. 1,378.50
- Mandor 0.010 Oh x Rp. 65,600 = Rp. 656.00
Jumlah (2) = Rp. 24,354.50
Jumlah (1) + (2) = Rp. 30,787.60
PPL 6.7. 1 M Plesteran 1 Pc : 8 Ps, tebal 15 mm
6.7.1. Bahan
- Semen portland 2.880 Kg x Rp. 1,270 = Rp. 3,657.60
- Pasir pasang 0.024 M x Rp. 76,500 = Rp. 1,836.00
Jumlah (1) = Rp. 5,493.60
6.7.2. Tenaga
- Pekerja 0.200 Oh x Rp. 52,500 = Rp. 10,500.00
- Tukang batu 0.150 Oh x Rp. 78,800 = Rp. 11,820.00
- Kepala tukang 0.015 Oh x Rp. 91,900 = Rp. 1,378.50
- Mandor 0.010 Oh x Rp. 65,600 = Rp. 656.00
Jumlah (2) = Rp. 24,354.50Jumlah (1) + (2) = Rp. 29,848.10
-
5/21/2018 Daftar Analisa Sni 2010 (1)
27/143
PPL 6.8. 1 M Plesteran 1 Pc : 0,5 Kp : 3 Ps, tebal 15 mm
6.8.1. Bahan
- Semen portland 5.760 Kg x Rp. 1,270 = Rp. 7,315.20
- Kapur padam 0.003 M x Rp. 8,470 = Rp. 25.41
- Pasir pasang 0.013 M x Rp. 76,500 = Rp. 994.50
Jumlah (1) = Rp. 8,335.11
6.8.2. Tenaga
- Pekerja 0.200 Oh x Rp. 52,500 = Rp. 10,500.00- Tukang batu 0.150 Oh x Rp. 78,800 = Rp. 11,820.00
- Kepala tukang 0.015 Oh x Rp. 91,900 = Rp. 1,378.50
- Mandor 0.010 Oh x Rp. 65,600 = Rp. 656.00
Jumlah (2) = Rp. 24,354.50
Jumlah (1) + (2) = Rp. 32,689.61
PPL 6.9. 1 M Plesteran 1 Pc : 3 Kp : 10 Ps, tebal 15 mm
6.9.1. Bahan
- Semen portland 1.840 Kg x Rp. 1,270 = Rp. 2,336.80
- Kapur padam 0.006 M x Rp. 8,470 = Rp. 50.82
- Pasir pasang 0.014 M x Rp. 76,500 = Rp. 1,071.00
Jumlah (1) = Rp. 3,458.626.9.2. Tenaga
- Pekerja 0.200 Oh x Rp. 52,500 = Rp. 10,500.00
- Tukang batu 0.150 Oh x Rp. 78,800 = Rp. 11,820.00
- Kepala tukang 0.015 Oh x Rp. 91,900 = Rp. 1,378.50
- Mandor 0.010 Oh x Rp. 65,600 = Rp. 656.00
Jumlah (2) = Rp. 24,354.50
Jumlah (1) + (2) = Rp. 27,813.12
PPL 6.12. 1 M Plesteran 1 Kp : 1 Sm : 2 Ps, tebal 15 mm
6.12.1. Bahan
- Bingkai Naco Niki Hita 0.007 Kg x Rp. 1,270 = Rp. 8.89
- Kapur padam 0.007 M x Rp. 8,470 = Rp. 59.29- Pasir pasang 0.015 M x Rp. 76,500 = Rp. 1,147.50
Jumlah (1) = Rp. 1,215.68
6.12.2. Tenaga
- Pekerja 0.200 Oh x Rp. 52,500 = Rp. 10,500.00
- Tukang batu 0.150 Oh x Rp. 78,800 = Rp. 11,820.00
- Kepala tukang 0.015 Oh x Rp. 91,900 = Rp. 1,378.50
- Mandor 0.010 Oh x Rp. 65,600 = Rp. 656.00
Jumlah (2) = Rp. 24,354.50
Jumlah (1) + (2) = Rp. 25,570.18
PPL 6.13. 1 M Plesteran 1 Pc : 2 Ps, tebal 20 mm
6.13.1. Bahan- Semen Portland 14.280 Kg x Rp. 1,270 = Rp. 18,135.60
- Pasir pasang 0.023 M x Rp. 76,500 = Rp. 1,759.50
Jumlah (1) = Rp. 19,895.10
-
5/21/2018 Daftar Analisa Sni 2010 (1)
28/143
6.13.2. Tenaga
- Pekerja 0.250 Oh x Rp. 52,500 = Rp. 13,125.00
- Tukang batu 0.200 Oh x Rp. 78,800 = Rp. 15,760.00
- Kepala tukang 0.020 Oh x Rp. 91,900 = Rp. 1,838.00
- Mandor 0.0125 Oh x Rp. 65,600 = Rp. 820.00
Jumlah (2) = Rp. 31,543.00
Jumlah (1) + (2) = Rp. 51,438.10
PPL 6.14. 1 M Plesteran 1 Pc : 3 Ps, tebal 20 mm
6.14.1. Bahan
- Semen Portland 10.800 Kg x Rp. 1,270 = Rp. 13,716.00
- Pasir pasang 0.026 M x Rp. 76,500 = Rp. 1,989.00
Jumlah (1) = Rp. 15,705.00
6.14.2. Tenaga
- Pekerja 0.250 Oh x Rp. 52,500 = Rp. 13,125.00
- Tukang batu 0.200 Oh x Rp. 78,800 = Rp. 15,760.00
- Kepala tukang 0.020 Oh x Rp. 91,900 = Rp. 1,838.00
- Mandor 0.0125 Oh x Rp. 65,600 = Rp. 820.00
Jumlah (2) = Rp. 31,543.00
Jumlah (1) + (2) = Rp. 47,248.00
PPL 6.15. 1 M Plesteran 1 Pc : 4 Ps, tebal 20 mm
6.15.1. Bahan
- Semen Portland 8.680 Kg x Rp. 1,270 = Rp. 11,023.60
- Pasir pasang 0.028 M x Rp. 76,500 = Rp. 2,142.00
Jumlah (1) = Rp. 13,165.60
6.15.2. Tenaga
- Pekerja 0.250 Oh x Rp. 52,500 = Rp. 13,125.00
- Tukang batu 0.200 Oh x Rp. 78,800 = Rp. 15,760.00
- Kepala tukang 0.020 Oh x Rp. 91,900 = Rp. 1,838.00
- Mandor 0.0125 Oh x Rp. 65,600 = Rp. 820.00
Jumlah (2) = Rp. 31,543.00
Jumlah (1) + (2) = Rp. 44,708.60
PPL 6.16. 1 M Plesteran 1 Pc : 5 Ps, tebal 20 mm
6.16.1. Bahan
- Semen Portland 7.290 Kg x Rp. 1,270 = Rp. 9,258.30
- Pasir pasang 0.028 M x Rp. 76,500 = Rp. 2,142.00
Jumlah (1) = Rp. 11,400.30
6.16.2. Tenaga
- Pekerja 0.250 Oh x Rp. 52,500 = Rp. 13,125.00
- Tukang batu 0.200 Oh x Rp. 78,800 = Rp. 15,760.00
- Kepala tukang 0.020 Oh x Rp. 91,900 = Rp. 1,838.00
- Mandor 0.0125 Oh x Rp. 65,600 = Rp. 820.00
Jumlah (2) = Rp. 31,543.00
Jumlah (1) + (2) = Rp. 42,943.30
PPL 6.17. 1 M Plesteran 1 Pc : 6 Ps, tebal 20 mm
6.17.1. Bahan
- Semen Portland 6.240 Kg x Rp. 1,270 = Rp. 7,924.80
- Pasir pasang 0.030 M x Rp. 76,500 = Rp. 2,295.00
Jumlah (1) = Rp. 10,219.80
6.17.2. Tenaga
- Pekerja 0.250 Oh x Rp. 52,500 = Rp. 13,125.00
- Tukang batu 0.200 Oh x Rp. 78,800 = Rp. 15,760.00
-
5/21/2018 Daftar Analisa Sni 2010 (1)
29/143
- Kepala tukang 0.020 Oh x Rp. 91,900 = Rp. 1,838.00
- Mandor 0.0125 Oh x Rp. 65,600 = Rp. 820.00
Jumlah (2) = Rp. 31,543.00
Jumlah (1) + (2) = Rp. 41,762.80
PPL 6.18. 1 M Plesteran 1 Kp : 1 Sm : 2 Ps, tebal 20 mm
6.18.1. Bahan- Bingkai Naco Niki Hita 0.009 M x Rp. 1,270 = Rp. 11.43
- Kapur padam 0.009 M x Rp. 8,470 = Rp. 76.23
- Pasir pasang 0.018 M x Rp. 76,500 = Rp. 1,377.00
Jumlah (1) = Rp. 1,464.66
6.18.2. Tenaga
- Pekerja 0.250 Oh x Rp. 52,500 = Rp. 13,125.00
- Tukang batu 0.200 Oh x Rp. 78,800 = Rp. 15,760.00
- Kepala tukang 0.020 Oh x Rp. 91,900 = Rp. 1,838.00
- Mandor 0.0125 Oh x Rp. 65,600 = Rp. 820.00
Jumlah (2) = Rp. 31,543.00
Jumlah (1) + (2) = Rp. 33,007.66
PPL 6.19. 1 M Plesteran 1 Pc : 2 Ps, tebal 25 mm
6.19.1. Bahan
- Semen Portland 15.500 Kg x Rp. 1,270 = Rp. 19,685.00
- Pasir pasang 0.013 M x Rp. 76,500 = Rp. 994.50
Jumlah (1) = Rp. 20,679.50
6.19.2. Tenaga
- Pekerja 0.300 Oh x Rp. 52,500 = Rp. 15,750.00
- Tukang batu 0.200 Oh x Rp. 78,800 = Rp. 15,760.00
- Kepala tukang 0.020 Oh x Rp. 91,900 = Rp. 1,838.00
- Mandor 0.013 Oh x Rp. 65,600 = Rp. 820.00
Jumlah (2) = Rp. 34,168.00
Jumlah (1) + (2) = Rp. 54,847.50
PPL 6.20. 1 M Plesteran 1 Pc : 3 Ps, tebal 25 mm
6.20.1. Bahan
- Semen Portland 11.750 Kg x Rp. 1,270 = Rp. 14,922.50
- Pasir pasang 0.035 M x Rp. 76,500 = Rp. 2,677.50
Jumlah (1) = Rp. 17,600.00
6.20.2. Tenaga
- Pekerja 0.300 Oh x Rp. 52,500 = Rp. 15,750.00
- Tukang batu 0.200 Oh x Rp. 78,800 = Rp. 15,760.00
- Kepala tukang 0.020 Oh x Rp. 91,900 = Rp. 1,838.00
- Mandor 0.013 Oh x Rp. 65,600 = Rp. 852.80
Jumlah (2) = Rp. 34,200.80
Jumlah (1) + (2) = Rp. 51,800.80
PPL 6.21. 1 M Plesteran 1 Pc : 4 Ps, tebal 25 mm
6.21.1. Bahan
- Semen Portland 9.480 Kg x Rp. 1,270 = Rp. 12,039.60
- Pasir pasang 0.038 M x Rp. 76,500 = Rp. 2,907.00
Jumlah (1) = Rp. 14,946.60
-
5/21/2018 Daftar Analisa Sni 2010 (1)
30/143
6.21.2. Tenaga
- Pekerja 0.300 Oh x Rp. 52,500 = Rp. 15,750.00
- Tukang batu 0.200 Oh x Rp. 78,800 = Rp. 15,760.00
- Kepala tukang 0.020 Oh x Rp. 91,900 = Rp. 1,838.00
- Mandor 0.013 Oh x Rp. 65,600 = Rp. 852.80
Jumlah (2) = Rp. 34,200.80
Jumlah (1) + (2) = Rp. 49,147.40
PPL 6.22. 1 M Plesteran 1 Pc : 5 Ps, tebal 25 mm
6.22.1. Bahan
- Semen Portland 7.940 Kg x Rp. 1,270 = Rp. 10,083.80
- Pasir pasang 0.039 M x Rp. 76,500 = Rp. 2,983.50
Jumlah (1) = Rp. 13,067.30
6.22.2. Tenaga
- Pekerja 0.300 Oh x Rp. 52,500 = Rp. 15,750.00
- Tukang batu 0.200 Oh x Rp. 78,800 = Rp. 15,760.00
- Kepala tukang 0.020 Oh x Rp. 91,900 = Rp. 1,838.00
- Mandor 0.013 Oh x Rp. 65,600 = Rp. 852.80
Jumlah (2) = Rp. 34,200.80
Jumlah (1) + (2) = Rp. 47,268.10
PPL 6.23. 1 M Plesteran 1 Pc : 2 Ps, tebal 30 mm
6.23.1. Bahan
- Semen Portland 18.650 Kg x Rp. 1,270 = Rp. 23,685.50
- Pasir pasang 0.035 M x Rp. 76,500 = Rp. 2,677.50
Jumlah (1) = Rp. 26,363.00
6.23.2. Tenaga
- Pekerja 0.320 Oh x Rp. 52,500 = Rp. 16,800.00
- Tukang batu 0.250 Oh x Rp. 78,800 = Rp. 19,700.00
- Kepala tukang 0.025 Oh x Rp. 91,900 = Rp. 2,297.50
- Mandor 0.015 Oh x Rp. 65,600 = Rp. 984.00
Jumlah (2) = Rp. 39,781.50
Jumlah (1) + (2) = Rp. 66,144.50
PPL 6.24. 1 M Plesteran 1 Pc : 3 Ps, tebal 30 mm
6.24.1. Bahan
- Semen Portland 14.150 Kg x Rp. 1,270 = Rp. 17,970.50
- Pasir pasang 0.039 M x Rp. 76,500 = Rp. 2,983.50
Jumlah (1) = Rp. 20,954.00
6.24.2. Tenaga
- Pekerja 0.320 Oh x Rp. 52,500 = Rp. 16,800.00
- Tukang batu 0.250 Oh x Rp. 78,800 = Rp. 19,700.00
- Kepala tukang 0.025 Oh x Rp. 91,900 = Rp. 2,297.50
- Mandor 0.015 Oh x Rp. 65,600 = Rp. 984.00
Jumlah (2) = Rp. 39,781.50
Jumlah (1) + (2) = Rp. 60,735.50
PPL 6.25. 1 M Plesteran 1 Pc : 4 Ps, tebal 30 mm
6.25.1. Bahan
- Semen Portland 11.380 Kg x Rp. 1,270 = Rp. 14,452.60
- Pasir pasang 0.042 M x Rp. 76,500 = Rp. 3,213.00
Jumlah (1) = Rp. 17,665.60
6.25.2. Tenaga
- Pekerja 0.320 Oh x Rp. 52,500 = Rp. 16,800.00
- Tukang batu 0.250 Oh x Rp. 78,800 = Rp. 19,700.00
-
5/21/2018 Daftar Analisa Sni 2010 (1)
31/143
- Kepala tukang 0.025 Oh x Rp. 91,900 = Rp. 2,297.50
- Mandor 0.015 Oh x Rp. 65,600 = Rp. 984.00
Jumlah (2) = Rp. 39,781.50
Jumlah (1) + (2) = Rp. 57,447.10
PPL 6.26. 1 M Plesteran 1 Pc : 4 Ps, tebal 30 mm
6.26.1. Bahan
- Semen Portland 8.190 Kg x Rp. 1,270 = Rp. 10,401.30- Pasir pasang 0.045 M x Rp. 76,500 = Rp. 3,442.50
Jumlah (1) = Rp. 13,843.80
6.26.2. Tenaga
- Pekerja 0.320 Oh x Rp. 52,500 = Rp. 16,800.00
- Tukang batu 0.250 Oh x Rp. 78,800 = Rp. 19,700.00
- Kepala tukang 0.025 Oh x Rp. 91,900 = Rp. 2,297.50
- Mandor 0.015 Oh x Rp. 65,600 = Rp. 984.00
Jumlah (2) = Rp. 39,781.50
Jumlah (1) + (2) = Rp. 53,625.30
PPL 6.27. 1 M Berapen 1 Pc : 3 Ps, tebal 30 mm
6.27.1. Bahan
- Semen Portland 7.070 Kg x Rp. 1,270 = Rp. 8,978.90- Pasir pasang 0.021 M x Rp. 76,500 = Rp. 1,606.50
Jumlah (1) = Rp. 10,585.40
6.27.2. Tenaga
- Pekerja 0.150 Oh x Rp. 52,500 = Rp. 7,875.00
- Tukang batu 0.070 Oh x Rp. 78,800 = Rp. 5,516.00
- Kepala tukang 0.007 Oh x Rp. 91,900 = Rp. 643.30
- Mandor 0.008 Oh x Rp. 65,600 = Rp. 524.80
Jumlah (2) = Rp. 14,559.10
Jumlah (1) + (2) = Rp. 25,144.50
PPL 6.28. 1 M Berapen 1 Pc : 5 Ps, tebal 30 mm
6.28.1. Bahan- Semen Portland 5.670 Kg x Rp. 1,270 = Rp. 7,200.90
- Pasir pasang 0.023 M x Rp. 76,500 = Rp. 1,759.50
Jumlah (1) = Rp. 8,960.40
6.28.2. Tenaga
- Pekerja 0.150 Oh x Rp. 52,500 = Rp. 7,875.00
- Tukang batu 0.070 Oh x Rp. 78,800 = Rp. 5,516.00
- Kepala tukang 0.007 Oh x Rp. 91,900 = Rp. 643.30
- Mandor 0.008 Oh x Rp. 65,600 = Rp. 524.80
Jumlah (2) = Rp. 14,559.10
Jumlah (1) + (2) = Rp. 23,519.50
-
5/21/2018 Daftar Analisa Sni 2010 (1)
32/143
PPL 6.29. 1 M Plesteran Beton 1 Pc : 2 Ps, tebal 15 mm
6.29.1. Bahan
- Semen Portland 9.300 Kg x Rp. 1,270 = Rp. 11,811.00
- Pasir pasang 0.018 M x Rp. 76,500 = Rp. 1,377.00
Jumlah (1) = Rp. 13,188.00
6.29.2. Tenaga
- Pekerja 0.260 Oh x Rp. 52,500 = Rp. 13,650.00
- Tukang batu 0.200 Oh x Rp. 78,800 = Rp. 15,760.00- Kepala tukang 0.020 Oh x Rp. 91,900 = Rp. 1,838.00
- Mandor 0.013 Oh x Rp. 65,600 = Rp. 852.80
Jumlah (2) = Rp. 32,100.80
Jumlah (1) + (2) = Rp. 45,288.80
PPL 6.30. 1 M Plesteran Beton 1 Pc : 3 Ps, tebal 15 mm
6.30.1. Bahan
- Semen Portland 7.070 Kg x Rp. 1,270 = Rp. 8,978.90
- Pasir pasang 0.021 M x Rp. 76,500 = Rp. 1,606.50
Jumlah (1) = Rp. 10,585.40
6.30.2. Tenaga
- Pekerja 0.260 Oh x Rp. 52,500 = Rp. 13,650.00
- Tukang batu 0.200 Oh x Rp. 78,800 = Rp. 15,760.00- Kepala tukang 0.020 Oh x Rp. 91,900 = Rp. 1,838.00
- Mandor 0.013 Oh x Rp. 65,600 = Rp. 852.80
Jumlah (2) = Rp. 32,100.80
Jumlah (1) + (2) = Rp. 42,686.20
PPL 6.31. 1 M Plesteran Skoning 1 Pc : 2 Ps
6.31.1. Bahan
- Semen Portland 0.500 Kg x Rp. 1,270 = Rp. 635.00
- Pasir pasang 0.002 M x Rp. 76,500 = Rp. 153.00
Jumlah (1) = Rp. 788.00
6.31.2. Tenaga
- Pekerja 0.057 Oh x Rp. 52,500 = Rp. 2,992.50
- Tukang batu 0.038 Oh x Rp. 78,800 = Rp. 2,994.40- Kepala tukang 0.038 Oh x Rp. 91,900 = Rp. 3,492.20
- Mandor 0.002 Oh x Rp. 65,600 = Rp. 131.20
Jumlah (2) = Rp. 9,610.30
Jumlah (1) + (2) = Rp. 10,398.30
PPL 6.32. 1 M Plesteran Granito, 1 Pc warna : 2 Granito, tebal 10 mm
6.32.1. Bahan
- PC warna 0.144 Kg x Rp. = Rp. 0.00
- Batu granito 15.000 Kg x Rp. = Rp. 0.00
Jumlah (1) = Rp. 0.00
6.32.2. Tenaga
- Pekerja 0.050 Oh x Rp. 52,500 = Rp. 2,625.00- Tukang batu 0.020 Oh x Rp. 78,800 = Rp. 1,576.00
- Kepala tukang 0.002 Oh x Rp. 91,900 = Rp. 183.80
- Mandor 0.005 Oh x Rp. 65,600 = Rp. 328.00
Jumlah (2) = Rp. 4,712.80
Jumlah (1) + (2) = Rp. 4,712.80
-
5/21/2018 Daftar Analisa Sni 2010 (1)
33/143
PPL 6.33. 1 M Plesteran Teraso, 1 Pc warna : 2 Batu Teraso, tebal 10 mm
6.33.1. Bahan
- PC warna 0.440 Kg x Rp. = Rp. 0.00
- Batu teraso 11.500 Kg x Rp. = Rp. 0.00
Jumlah (1) = Rp. 0.00
6.33.2. Tenaga
- Pekerja 0.450 Oh x Rp. 52,500 = Rp. 23,625.00
- Tukang batu 0.200 Oh x Rp. 78,800 = Rp. 15,760.00- Kepala tukang 0.020 Oh x Rp. 91,900 = Rp. 1,838.00
- Mandor 0.025 Oh x Rp. 65,600 = Rp. 1,640.00
Jumlah (2) = Rp. 42,863.00
Jumlah (1) + (2) = Rp. 42,863.00
PPL 6.34. 1 M Plesteran Ciprat, 1 Pc : 2 Ps, tebal 10 mm
6.34.1. Bahan
- Semen portland 4.320 Kg x Rp. 1,270 = Rp. 5,486.40
- Pasir pasang 0.016 M x Rp. 76,500 = Rp. 1,224.00
Jumlah (1) = Rp. 6,710.40
6.34.2. Tenaga
- Pekerja 0.250 Oh x Rp. 52,500 = Rp. 13,125.00- Tukang batu 0.100 Oh x Rp. 78,800 = Rp. 7,880.00
- Kepala tukang 0.010 Oh x Rp. 91,900 = Rp. 919.00
- Mandor 0.015 Oh x Rp. 65,600 = Rp. 984.00
Jumlah (2) = Rp. 22,908.00
Jumlah (1) + (2) = Rp. 29,618.40
PPL 6.35. 1 M Plesteran Siar adukan, 1 Pc : 2 Ps
6.35.1. Bahan
- Semen portland 4.320 Kg x Rp. 1,270 = Rp. 5,486.40
- Pasir pasang 0.016 M x Rp. 76,500 = Rp. 1,224.00
Jumlah (1) = Rp. 6,710.40
6.35.2. Tenaga- Pekerja 0.150 Oh x Rp. 52,500 = Rp. 7,875.00
- Tukang batu 0.070 Oh x Rp. 78,800 = Rp. 5,516.00
- Kepala tukang 0.007 Oh x Rp. 91,900 = Rp. 643.30
- Mandor 0.008 Oh x Rp. 65,600 = Rp. 524.80
Jumlah (2) = Rp. 14,559.10
Jumlah (1) + (2) = Rp. 21,269.50
PPL 6.36. 1 M Plesteran waterfroof bata cote 3 lapis
6.36.1. Bahan
- Semen portland 0.500 Kg x Rp. 1,270 = Rp. 635.00
- Kosen Pintu / Jendela 2.900 Kg x Rp. 66,550 = Rp. 192,995.00
- Pasir pasang 0.006 M x Rp. 76,500 = Rp. 459.00
Jumlah (1) = Rp. 194,089.006.36.2. Tenaga
- Pekerja 0.300 Oh x Rp. 52,500 = Rp. 15,750.00
- Tukang batu 0.200 Oh x Rp. 78,800 = Rp. 15,760.00
- Kepala tukang 0.020 Oh x Rp. 91,900 = Rp. 1,838.00
- Mandor 0.015 Oh x Rp. 65,600 = Rp. 984.00
Jumlah (2) = Rp. 34,332.00
Jumlah (1) + (2) = Rp. 228,421.00
-
5/21/2018 Daftar Analisa Sni 2010 (1)
34/143
-
5/21/2018 Daftar Analisa Sni 2010 (1)
35/143
PK 6.1. 1 M Pasang kusen pintu dan jendela kayu jati :
6.1.1. Bahan- Kayu jati, balok 1.100 M x Rp. 23,925,000.00 = Rp. 26,317,500.00
Jumlah (1) = Rp. 26,317,500.00
6.1.2. Tenaga
- Pekerja 6.000 Oh x Rp. 52,500.00 = Rp. 315,000.00
- Tukang kayu 20.000 Oh x Rp. 78,800.00 = Rp. 1,576,000.00
- Kepala tukang 2.000 Oh x Rp. 91,900.00 = Rp. 183,800.00
- Mandor 0.300 Oh x Rp. 65,600.00 = Rp. 19,680.00
Jumlah (2) = Rp. 2,094,480.00
Jumlah (1) +(2) = Rp. 28,411,980.00
PK 6.2. 1 M Pasang kusen pintu dan jendela kayu damar laut :
6.2.1. Bahan
- Kayu meranti , balok 1.200 M x Rp. 9,075,000.00 = Rp. 10,890,000.00
Jumlah (1) = Rp. 10,890,000.00
6.2.2. Tenaga
- Pekerja 6.000 Oh x Rp. 52,500.00 = Rp. 315,000.00
- Tukang kayu 18.000 Oh x Rp. 78,800.00 = Rp. 1,418,400.00
- Kepala tukang 2.000 Oh x Rp. 91,900.00 = Rp. 183,800.00
- Mandor 0.300 Oh x Rp. 65,600.00 = Rp. 19,680.00
Jumlah (2) = Rp. 1,936,880.00
Jumlah (1) +(2) = Rp. 12,826,880.00
PK 6.3. 1 M Pasang kusen pintu dan jendela kayu meranti :
6.3.1. Bahan- Kayu kapur, balok 1.200 M x Rp. 6,490,000.00 = Rp. 7,788,000.00
Jumlah (1) = Rp. 7,788,000.00
6.3.2. Tenaga
- Pekerja 6.000 Oh x Rp. 52,500.00 = Rp. 315,000.00
- Tukang kayu 18.000 Oh x Rp. 78,800.00 = Rp. 1,418,400.00
- Kepala tukang 2.000 Oh x Rp. 91,900.00 = Rp. 183,800.00
- Mandor 0.300 Oh x Rp. 65,600.00 = Rp. 19,680.00
Jumlah (2) = Rp. 1,936,880.00
Jumlah (1) +(2) = Rp. 9,724,880.00
PK 6.4. 1 M Pasang kusen pintu dan jendela kayu damar laut :
6.4.1. Bahan- Kayu damar laut, balok 1.200 M x Rp. 9,350,000.00 = Rp. 11,220,000.00
Jumlah (1) = Rp. 11,220,000.00
6.4.2. Tenaga
- Pekerja 6.000 Oh x Rp. 52,500.00 = Rp. 315,000.00
ANALISA BIAYA KONSTRUKSI
PEKERJAAN KAYU
-
5/21/2018 Daftar Analisa Sni 2010 (1)
36/143
- Tukang kayu 18.000 Oh x Rp. 78,800.00 = Rp. 1,418,400.00
- Kepala tukang 2.000 Oh x Rp. 91,900.00 = Rp. 183,800.00
- Mandor 0.300 Oh x Rp. 65,600.00 = Rp. 19,680.00
Jumlah (2) = Rp. 1,936,880.00
Jumlah (1) +(2) = Rp. 13,156,880.00
PK 6.5. 1 M Pasang pintu klamp kayu meranti batu
6.5.1. Bahan
- Kayu meranti batu, papan 0.036 M x Rp. 9,375,000.00 = Rp. 337,500.00
- Paku biasa 2" - 5" 0.050 Kg x Rp. 14,520.00 = Rp. 726.00
Jumlah (1) = Rp. 338,226.00
6.5.2. Tenaga
- Pekerja 0.350 Oh x Rp. 52,500.00 = Rp. 18,375.00
- Tukang kayu 1.050 Oh x Rp. 78,800.00 = Rp. 82,740.00
- Kepala tukang 0.105 Oh x Rp. 91,900.00 = Rp. 9,649.50
- Mandor 0.018 Oh x Rp. 65,600.00 = Rp. 1,180.80
Jumlah (2) = Rp. 111,945.30
Jumlah (1) +(2) = Rp. 450,171.30
PK 6.6. 1 M Pasang pintu klamp kayu jati
6.6.1. Bahan
- Kayu jati, papan 0.036 M x Rp. 24,104,440.00 = Rp. 867,759.84
- Paku biasa 2" - 5" 0.050 Kg x Rp. 14,520.00 = Rp. 726.00
Jumlah (1) = Rp. 868,485.84
6.6.2. Tenaga
- Pekerja 0.350 Oh x Rp. 52,500.00 = Rp. 18,375.00
- Tukang kayu 1.050 Oh x Rp. 78,800.00 = Rp. 82,740.00
- Kepala tukang 0.105 Oh x Rp. 91,900.00 = Rp. 9,649.50
- Mandor 0.018 Oh x Rp. 65,600.00 = Rp. 1,180.80
Jumlah (2) = Rp. 111,945.30
Jumlah (1) +(2) = Rp. 980,431.14
PK 6.7. 1 M Pasang pintu panel kayu jati :
6.7.1. Bahan
- Kayu jati, papan 0.036 M x Rp. 24,104,440.00 = Rp. 867,759.84
Jumlah (1) 867,759.84
6.7.2. Tenaga
- Pekerja 1.000 Oh x Rp. 52,500.00 = Rp. 52,500.00
- Tukang kayu 2.500 Oh x Rp. 78,800.00 = Rp. 197,000.00
- Kepala tukang 0.250 Oh x Rp. 91,900.00 = Rp. 22,975.00
- Mandor 0.050 Oh x Rp. 65,600.00 = Rp. 3,280.00
Jumlah (2) = Rp. 275,755.00
Jumlah (1) +(2) = Rp. 1,143,514.84
-
5/21/2018 Daftar Analisa Sni 2010 (1)
37/143
PK 6.8. 1 M Pasang pintu panel kayu meranti batu
6.8.1. Bahan
- Kayu meranti batu, papan 0.040 M x Rp. 9,375,000.00 = Rp. 375,000.00
Jumlah (1) = Rp. 375,000.00
6.8.2. Tenaga
- Pekerja 1.000 Oh x Rp. 52,500.00 = Rp. 52,500.00
- Tukang kayu 2.500 Oh x Rp. 78,800.00 = Rp. 197,000.00- Kepala tukang 0.250 Oh x Rp. 91,900.00 = Rp. 22,975.00
- Mandor 0.050 Oh x Rp. 65,600.00 = Rp. 3,280.00
Jumlah (2) = Rp. 275,755.00
Jumlah (1) +(2) = Rp. 650,755.00
PK 6.9. 1 M Pasang pintu dan jendela kaca panel kayu jati :
6.9.1. Bahan
- Kayu jati, papan 0.035 M x Rp. 24,104,440.00 = Rp. 843,655.40
- Kaca polos 5 mm 0.800 M x Rp. 145,200.00 = Rp. 116,160.00
Jumlah (1) = Rp. 959,815.40
6.9.2. Tenaga
- Pekerja 0.800 Oh x Rp. 52,500.00 = Rp. 42,000.00- Tukang kayu 2.000 Oh x Rp. 78,800.00 = Rp. 157,600.00
- Kepala tukang 0.200 Oh x Rp. 91,900.00 = Rp. 18,380.00
- Mandor 0.040 Oh x Rp. 65,600.00 = Rp. 2,624.00
Jumlah (2) = Rp. 220,604.00
Jumlah (1) +(2) = Rp. 1,180,419.40
PK 6.10. 1 M Pasang pintu dan jendela kaca panel kayu meranti batu :
6.10.1. Bahan
- Kayu meranti batu, papan 0.035 M x Rp. 9,375,000.00 = Rp. 328,125.00
- Kaca polos 5 mm 0.800 M x Rp. 145,200.00 = Rp. 116,160.00
Jumlah (1) = Rp. 444,285.00
6.10.2. Tenaga
- Pekerja 0.800 Oh x Rp. 52,500.00 = Rp. 42,000.00
- Tukang kayu 2.000 Oh x Rp. 78,800.00 = Rp. 157,600.00
- Kepala tukang 0.200 Oh x Rp. 91,900.00 = Rp. 18,380.00
- Mandor 0.040 Oh x Rp. 65,600.00 = Rp. 2,624.00
Jumlah (2) = Rp. 220,604.00
Jumlah (1) +(2) = Rp. 664,889.00
-
5/21/2018 Daftar Analisa Sni 2010 (1)
38/143
PK 6.11. 1 M Pasang pintu dan jendela kaca panel kayu meranti :
6.11.1. Bahan
- Kayu meranti, papan 0.035 M x Rp. 5,475,000.00 = Rp. 191,625.00
- Kaca polos 5 mm 0.800 M x Rp. 145,200.00 = Rp. 116,160.00
Jumlah (1) = Rp. 307,785.00
6.11.2. Tenaga
- Pekerja 0.800 Oh x Rp. 52,500.00 = Rp. 42,000.00- Tukang kayu 2.000 Oh x Rp. 78,800.00 = Rp. 157,600.00
- Kepala tukang 0.200 Oh x Rp. 91,900.00 = Rp. 18,380.00
- Mandor 0.040 Oh x Rp. 65,600.00 = Rp. 2,624.00
Jumlah (2) = Rp. 220,604.00
Jumlah (1) +(2) = Rp. 528,389.00
PK 6.12. 1 M Pasang pintu dan jendela jalusi kayu jati :
6.12.1. Bahan
- Kayu jati, papan 0.064 M x Rp. 24,104,440.00 = Rp. 1,542,684.16
Jumlah (1) = Rp. 1,542,684.16
6.12.2. Tenaga- Pekerja 1.000 Oh x Rp. 52,500.00 = Rp. 52,500.00
- Tukang kayu 3.000 Oh x Rp. 78,800.00 = Rp. 236,400.00
- Kepala tukang 0.300 Oh x Rp. 91,900.00 = Rp. 27,570.00
- Mandor 0.300 Oh x Rp. 65,600.00 = Rp. 19,680.00
Jumlah (2) = Rp. 336,150.00
Jumlah (1) +(2) = Rp. 1,878,834.16
PK 6.13. 1 M Pasang pintu dan jendela jalusi kayu meranti batu :
6.13.1. Bahan
- Kayu meranti batu, papan 0.064 M x Rp. 9,375,000.00 = Rp. 600,000.00
Jumlah (1) = Rp. 600,000.00
6.13.2. Tenaga
- Pekerja 1.000 Oh x Rp. 52,500.00 = Rp. 52,500.00
- Tukang kayu 3.000 Oh x Rp. 78,800.00 = Rp. 236,400.00
- Kepala tukang 0.300 Oh x Rp. 91,900.00 = Rp. 27,570.00
- Mandor 0.500 Oh x Rp. 65,600.00 = Rp. 32,800.00
Jumlah (2) = Rp. 349,270.00
Jumlah (1) +(2) = Rp. 949,270.00
PK 6.14. 1 M Pasang pintu plywood rangka, rangka kayu jati :
6.14.1. Bahan
- Kayu jati, papan 0.0196 M x Rp. 24,104,440.00 = Rp. 472,447.02
- Paku biasa " - 1" 0.030 Kg x Rp. 16,940.00 = Rp. 508.20- Lem kayu 0.300 Lt x Rp. 37,400.00 = Rp. 11,220.00
- Playwood 4' x 3' x 4 mm 1.000 Lbr x Rp. 51,920.00 = Rp. 51,920.00
Jumlah (1) = Rp. 536,095.22
-
5/21/2018 Daftar Analisa Sni 2010 (1)
39/143
6.14.2. Tenaga
- Pekerja 0.600 Oh x Rp. 52,500.00 = Rp. 31,500.00
- Tukang kayu 2.000 Oh x Rp. 78,800.00 = Rp. 157,600.00
- Kepala tukang 0.200 Oh x Rp. 91,900.00 = Rp. 18,380.00
- Mandor 0.030 Oh x Rp. 65,600.00 = Rp. 1,968.00
Jumlah (2) = Rp. 209,448.00
Jumlah (1) +(2) = Rp. 745,543.22
PK 6.15. 1 M Pasang pintu plywood rangka, rangka kayu meranti batu :
6.15.1. Bahan
- Kayu meranti batu, papan 0.0196 M x Rp. 9,375,000.00 = Rp. 183,750.00
- Paku biasa " - 1" 0.030 Kg x Rp. 16,940.00 = Rp. 508.20
- Lem kayu 0.300 Lt x Rp. 37,400.00 = Rp. 11,220.00
- Playwood 4' x 3' x 4 mm 1.000 Lbr x Rp. 51,920.00 = Rp. 51,920.00
Jumlah (1) = Rp. 247,398.20
6.15.2. Tenaga
- Pekerja 0.600 Oh x Rp. 52,500.00 = Rp. 31,500.00
- Tukang kayu 2.000 Oh x Rp. 78,800.00 = Rp. 157,600.00
- Kepala tukang 0.200 Oh x Rp. 91,900.00 = Rp. 18,380.00
- Mandor 0.030 Oh x Rp. 65,600.00 = Rp. 1,968.00Jumlah (2) = Rp. 209,448.00
Jumlah (1) +(2) = Rp. 456,846.20
PK 6.16. 1 M Pasang jalusi mati kusen kayu jati :
6.16.1. Bahan
- Kayu jati, papan 0.060 M x Rp. 24,104,440.00 = Rp. 1,446,266.40
- Paku biasa " - 1" 0.150 Kg x Rp. 16,940.00 = Rp. 2,541.00
Jumlah (1) = Rp. 1,448,807.40
6.16.2. Tenaga
- Pekerja 0.500 Oh x Rp. 52,500.00 = Rp. 26,250.00
- Tukang kayu 2.000 Oh x Rp. 78,800.00 = Rp. 157,600.00
- Kepala tukang 0.200 Oh x Rp. 91,900.00 = Rp. 18,380.00
- Mandor 0.025 Oh x Rp. 65,600.00 = Rp. 1,640.00
Jumlah (2) = Rp. 203,870.00
Jumlah (1) +(2) = Rp. 1,652,677.40
PK 6.17. 1 M Pasang jalusi mati kusen kayu damar laut :
6.17.1. Bahan
- Kayu damar laut, papan 0.060 M x Rp. 9,650,000.00 = Rp. 579,000.00
- Paku biasa " - 1" 0.150 Kg x Rp. 16,940.00 = Rp. 2,541.00
Jumlah (1) = Rp. 581,541.00
6.17.2. Tenaga
- Pekerja 0.500 Oh x Rp. 52,500.00 = Rp. 26,250.00
- Tukang kayu 2.000 Oh x Rp. 78,800.00 = Rp. 157,600.00
- Kepala tukang 0.200 Oh x Rp. 91,900.00 = Rp. 18,380.00- Mandor 0.025 Oh x Rp. 65,600.00 = Rp. 1,640.00
Jumlah (2) = Rp. 203,870.00
Jumlah (1) +(2) = Rp. 785,411.00
-
5/21/2018 Daftar Analisa Sni 2010 (1)
40/143
PK 6.18. 1 M Pasang pintu plywood rangka, rangka kayu meranti :
6.18.1. Bahan
- Kayu meranti, papan 0.0196 M x Rp. 5,475,000.00 = Rp. 107,310.00
- Paku biasa " - 1" 0.030 Kg x Rp. 16,940.00 = Rp. 508.20
- Lem kayu 0.300 Lt x Rp. 37,400.00 = Rp. 11,220.00
- Playwood 4' x 3' x 4 mm 1.000 Lbr x Rp. 51,920.00 = Rp. 51,920.00
Jumlah (1) = Rp. 63,140.006.18.2. Tenaga
- Pekerja 0.600 Oh x Rp. 52,500.00 = Rp. 31,500.00
- Tukang kayu 2.000 Oh x Rp. 78,800.00 = Rp. 157,600.00
- Kepala tukang 0.200 Oh x Rp. 91,900.00 = Rp. 18,380.00
- Mandor 0.030 Oh x Rp. 65,600.00 = Rp. 1,968.00
Jumlah (2) = Rp. 209,448.00
Jumlah (1) +(2) = Rp. 272,588.00
PK 6.19. 1 M Pasang pintu teakwood rangka, rangka kayu jati :
6.19.1. Bahan
- Kayu jati, papan 0.0196 M x Rp. 24,104,440.00 = Rp. 472,447.02
- Paku biasa " - 1" 0.300 Kg x Rp. 16,940.00 = Rp. 5,082.00- Lem kayu 0.300 Lt x Rp. 37,400.00 = Rp. 11,220.00
- Teakwood 4' x 8' x 4 mm 1.000 Lbr x Rp. 54,450.00 = Rp. 54,450.00
Jumlah (1) = Rp. 543,199.02
6.19.2. Tenaga
- Pekerja 0.600 Oh x Rp. 52,500.00 = Rp. 31,500.00
- Tukang kayu 2.000 Oh x Rp. 78,800.00 = Rp. 157,600.00
- Kepala tukang 0.200 Oh x Rp. 91,900.00 = Rp. 18,380.00
- Mandor 0.030 Oh x Rp. 65,600.00 = Rp. 1,968.00
Jumlah (2) = Rp. 209,448.00
Jumlah (1) +(2) = Rp. 752,647.02
PK 6.20. 1 M Pasang pintu teakwood rangka, rangka kayu meranti batu :
6.20.1. Bahan
- Kayu meranti batu, papan 0.0196 M x Rp. 9,375,000.00 = Rp. 183,750.00
- Paku biasa " - 1" 0.300 Kg x Rp. 16,940.00 = Rp. 5,082.00
- Lem kayu 0.300 Lt x Rp. 37,400.00 = Rp. 11,220.00
- Teakwood 4' x 8' x 4 mm 1.000 Lbr x Rp. 54,450.00 = Rp. 54,450.00
Jumlah (1) = Rp. 254,502.00
6.20.2. Tenaga
- Pekerja 0.600 Oh x Rp. 52,500.00 = Rp. 31,500.00
- Tukang kayu 2.000 Oh x Rp. 78,800.00 = Rp. 157,600.00
- Kepala tukang 0.200 Oh x Rp. 91,900.00 = Rp. 18,380.00
- Mandor 0.030 Oh x Rp. 65,600.00 = Rp. 1,968.00
Jumlah (2) = Rp. 209,448.00
Jumlah (1) +(2) = Rp. 463,950.00
-
5/21/2018 Daftar Analisa Sni 2010 (1)
41/143
PK 6.21. 1 M Pasang pintu plywood & formika, rangka kayu jati :
6.21.1. Bahan
- Kayu jati, papan 0.0196 M x Rp. 24,104,440.00 = Rp. 472,447.02
- Paku biasa " - 1" 0.300 Kg x Rp. 16,940.00 = Rp. 5,082.00
- Lem kayu 0.800 Lt x Rp. 37,400.00 = Rp. 29,920.00
- Plywood 4' x 8' x 4 mm 1.000 Lbr x Rp. 51,920.00 = Rp. 51,920.00
- Formica 4' x 8' 1.000 Lbr x Rp. 74,250.00 = Rp. 74,250.00 Jumlah (1) = Rp. 633,619.02
6.21.2. Tenaga
- Pekerja 0.800 Oh x Rp. 52,500.00 = Rp. 42,000.00
- Tukang kayu 2.500 Oh x Rp. 78,800.00 = Rp. 197,000.00
- Kepala tukang 0.250 Oh x Rp. 91,900.00 = Rp. 22,975.00
- Mandor 0.040 Oh x Rp. 65,600.00 = Rp. 2,624.00
Jumlah (2) = Rp. 264,599.00
Jumlah (1) +(2) = Rp. 898,218.02
PK 6.22. 1 M Pasang pintu plywood & formika, rangka kayu meranti batu :
6.22.1. Bahan
- Kayu meranti batu, papan 0.0196 M x Rp. 9,375,000.00 = Rp. 183,750.00- Paku biasa " - 1" 0.300 Kg x Rp. 16,940.00 = Rp. 5,082.00
- Lem kayu 0.800 Lt x Rp. 37,400.00 = Rp. 29,920.00
- Plywood 4' x 8' x 4 mm 1.000 Lbr x Rp. 51,920.00 = Rp. 51,920.00
- Formica 4' x 8' 1.000 Lbr x Rp. 74,250.00 = Rp. 74,250.00
Jumlah (1) = Rp. 344,922.00
6.22.2. Tenaga
- Pekerja 0.800 Oh x Rp. 52,500.00 = Rp. 42,000.00
- Tukang kayu 2.500 Oh x Rp. 78,800.00 = Rp. 197,000.00
- Kepala tukang 0.250 Oh x Rp. 91,900.00 = Rp. 22,975.00
- Mandor 0.040 Oh x Rp. 65,600.00 = Rp. 2,624.00
Jumlah (2) = Rp. 264,599.00
Jumlah (1) +(2) = Rp. 609,521.00
PK 6.23. 1 M Pasang pintu plywood & formika, rangka kayu jati :
6.23.1. Bahan
- Kayu jati, papan 0.0196 M x Rp. 24,104,440.00 = Rp. 472,447.02
- Paku biasa " - 1" 0.300 Kg x Rp. 16,940.00 = Rp. 5,082.00
- Lem kayu 0.800 Lt x Rp. 37,400.00 = Rp. 29,920.00
- Teakwood 4' x 8' x 4 mm 1.000 Lbr x Rp. 54,450.00 = Rp. 54,450.00
- Formica 4' x 8' 1.000 Lbr x Rp. 74,250.00 = Rp. 74,250.00
Jumlah (1) = Rp. 636,149.02
6.23.2. Tenaga
- Pekerja 0.800 Oh x Rp. 52,500.00 = Rp. 42,000.00
- Tukang kayu 2.500 Oh x Rp. 78,800.00 = Rp. 197,000.00
- Kepala tukang 0.250 Oh x Rp. 91,900.00 = Rp. 22,975.00- Mandor 0.040 Oh x Rp. 65,600.00 = Rp. 2,624.00
Jumlah (2) = Rp. 264,599.00
Jumlah (1) +(2) = Rp. 900,748.02
-
5/21/2018 Daftar Analisa Sni 2010 (1)
42/143
PK 6.24. 1 M Pasang pintu plywood & formika, rangka kayu damar laut (divermis) :
6.24.1. Bahan
- Kayu meranti batu, papan 0.0196 M x Rp. 9,375,000.00 = Rp. 183,750.00
- Paku biasa " - 1" 0.300 Kg x Rp. 16,940.00 = Rp. 5,082.00
- Lem kayu 0.800 Lt x Rp. 37,400.00 = Rp. 29,920.00
- Teakwood 4' x 8' x 4 mm 0.500 Lbr x Rp. 54,450.00 = Rp. 27,225.00
- Vernis 0.500