CADANGAN MENGUBAHSUAI SEBUAH RUMAH BANGLO 2 TINGKAT KEPADA 3 TINGKAT DAN SEBUAH KOLAM

RENANG DI TAMAN MELAWATI, HULU KELANG, SELANGOR DARUL EHSAN UNTUKTG REMY DZULKIFLI

DISEDIAKAN OLEH :

RS ARCHITECT

KONTRAKTOR:

KHARFIDA ENGINEERING

Page 2: Cadangan Mengubahsuai Rumah Banglo 2 Tingkat Kepada 3

PELAN-PELAN AKITEK

• PELAN TINGKAT BAWAH

Page 3: Cadangan Mengubahsuai Rumah Banglo 2 Tingkat Kepada 3

PELAN-PELAN AKITEK

• PELAN TINGKAT SATU

Page 4: Cadangan Mengubahsuai Rumah Banglo 2 Tingkat Kepada 3

PELAN-PELAN AKITEK

• PELAN TINGKAT DUA

Page 5: Cadangan Mengubahsuai Rumah Banglo 2 Tingkat Kepada 3

PELAN-PELAN AKITEK

• PELAN PANDANGAN HADAPAN

Page 6: Cadangan Mengubahsuai Rumah Banglo 2 Tingkat Kepada 3

PELAN-PELAN AKITEK

• PELAN PANDANGAN SISI

Page 7: Cadangan Mengubahsuai Rumah Banglo 2 Tingkat Kepada 3

PELAN-PELAN AKITEK• PERSPEKTIF 1

Page 8: Cadangan Mengubahsuai Rumah Banglo 2 Tingkat Kepada 3

PELAN-PELAN AKITEK• PERSPEKTIF 2

Page 9: Cadangan Mengubahsuai Rumah Banglo 2 Tingkat Kepada 3

CADANGAN MENGUBAHSUAI SEBUAH RUMAH BANGLO 2 TINGKAT KEPADA 3 TINGKAT DAN SEBUAH KOLAM

RENANG DI TAMAN MELAWATI, HULU KELANG, SELANGOR

LOCATION MAP

MRR2

SEK. MENTAMAN MELAWATI

BUISNESS CENTRE TAMAN MELAWATI

Page 10: Cadangan Mengubahsuai Rumah Banglo 2 Tingkat Kepada 3

LOCATION MAP

SEK. MENTAMAN MELAWATI

SG. ULU KLANG

Page 11: Cadangan Mengubahsuai Rumah Banglo 2 Tingkat Kepada 3

DESCRIPTION UNIT QTY RATE AMOUNT

1 PRELIMINARIES    

  To provide all necessary equipment, material    

  and labour for the safety, cleanness and local    

  authority procedure to the site with temporary    

  hording, project signboard and anything that    

  involve public utility.   27,000.00

2 CONSULTANT'S    

  a. Architect   25,000.00

  b. Structure Engineer   25,000.00

  c. Electrical and Mechanical Engineer   15,000.00

3 DEMOLITION WORKS.   30,000.00

  a. Existing Main entrance / wall fencing    

  b. Existing ram and car porch    

  c. Existing mezzanine at living and staircase    

  d. Existing wall, cabinet and top at kitchen    

  e. Existing wall at bed room    

  f. Existing roof    

4 EARTHWORK.   80,000.00

  a. To excavate and chart away existing earth at    

  main entrance to the adjacent road level.    

  b. Excavation of pile cap and ground beam    

           

Page 12: Cadangan Mengubahsuai Rumah Banglo 2 Tingkat Kepada 3

  DESCRIPTION UNIT QTY RATE AMOUNT

5 PILING   50,000.00

  a. Retaining wall    

  b. New pile cap for 1st and 2nd / swimingpool    

  c. New entrance 3rd floor / connecting bridge    

6 STRUCTURE   380,000.00

  a. New slab, column, beam, stump and    

  foundation of GR, 1st, 2nd and 3rd floor.    

  b. Retaining wall    

7 SWIMMING POOL   250,000.00

  a. Structure    

  b. Tiling c/w all fin. Accessories    

  c. Piping, pump and related system    

8 GLASS WORK   80,000.00

  a. Window    

  b. Glass wall    

  c. Glass railing    

9 COLD AND HOT WATER PIPING SYSTEM   30,000.00

  a. Toilet    

  b. Kitchen    

  c. Pantry    

  d. Garden    

  e. Parking area    

Page 13: Cadangan Mengubahsuai Rumah Banglo 2 Tingkat Kepada 3

BIL DESCRIPTION UNIT QTY RATE AMOUNT

10 INTERIOR AND EXTERIOR FINISHES   300,000.00

  a. Floor - Tile, timber strip and slate    

  b. Paint - weather shield, gloss and emulsion    

  c. Toilet accessories - Jacuzzi, shower head,    

  WC, soup/tissue dispenser, mirror, tap,    

  marble top c/w sink and shower curtain.    

  d. Kitchen cabinet and all accessories.    

11 FENCING WORK   75,000.00

  a. GR beam, Bricks wall, decorative rough iron.    

  b. Decorative rough iron c/w automatic system gate    

12 ROOF    

  a.To supply and install new galvanize iron roof   50,000.00

  structure c/w insulated metal deck roofing.    

  b. Rc gutter c/w upvc down pipe system.    

13 LIFT   100,000.00

  Selected lift cabin, motor c/w tow opening    

  system and all necessary accessories    

           

Page 14: Cadangan Mengubahsuai Rumah Banglo 2 Tingkat Kepada 3

BIL DESCRIPTION UNIT QTY RATE AMOUNT

14 HARD AND SOFT LANDSCAPE   65,000.00

  a. Rock garden, pergola and tree with one year    

  maintenance    

  b. Glass Aquarium not exceed 1.8m ht c/w    

  pump, filter and all accessories    

15 ELECTRICAL   30,000.00

  a. Upgrading of incoming supply up to 3 phase    

  system and lightning arrester    

  b. New wiring to all system and DB    

  c. To supply and install lighting system.    

  d. To relocate meter and main board.    

       

16 ACCONDITION   70,000.00

  To supply and install new accond c/w all    

  necessary accessories.    

       

  TOTAL       

1,682,000.000