  • 8/19/2019 2011 Trs Sow

    1/56

     Yanbu Refinery Department

    2011 Total Refinery Shutdown

    February 2011

    Safety

    Cost

    Time

    Quality

    Scope

    TEAM

    WORK

    Cont

    Partner 

    Scope of Work

    Towers

  • 8/19/2019 2011 Trs Sow

    2/56

     Yanbu Refinery Department

    2011 Total Refinery Shutdown

    February 2011

    General Scope of Work

    1. 

    Blind Equipment

    2. 

    If applicable conduct soda ash flashing before opening drums manways and after

    cooling down.

    3. 

    Open shell man ways.

    4.  Conduct initial internal inspection.

    5.  Conduct external equipment inspection.

    6. 

    Open all tray manways.

    7. 

    Remove drum internals (distributors, demisters) as per inspection recommendations.

    8. 

    Erect internal scaffolding as recommended by inspection.

    9. 

    Conduct internal cleaning as per inspection recommendations.

    10. 

    Conduct detail internal inspection.

    11. Clean all removed internals as recommended by inspection and area engineer.

    12. 

    Based on inspection recommendations, grit blast all marked areas.

    13. 

    Conduct WFMPT, hardness test, DPT as applicable.

    14. 

    Carry on any repair recommended by inspection.

    15. 

    Install back all removed and repaired internals (distributors, demisters).

    16. 

    Replace all missing or damaged trays' valves as per Inspection recommendation

    17. 

    Conduct inspection on all internals after installing back.

    18. 

    Remove internal Scaffolding.

  • 8/19/2019 2011 Trs Sow

    3/56

     Yanbu Refinery Department

    2011 Total Refinery Shutdown

    February 2011

    19. 

    Conduct internal final cleaning.

    20. 

    Flash all nozzles and make sure there is no any dirt of plugging.

    21. 

    Conduct internal inspection.

    22. 

    Box up all tray manways.

    23. 

    Conduct final internal inspection.

    24. 

    Box up all shell manways.

    25. 

    De blind equipment

    26. 

    If applicable apply required bolts tensioning and torque.

  • 8/19/2019 2011 Trs Sow

    4/56

     Yanbu Refinery Department

    2011 Total Refinery Shutdown

    February 2011

    EIS Towers List 

    SN TAG# EQUIPTNo ofEquip.

    MO # scope of work

    Area 1 

    1 V04-V1*  Crude Column 1 30032773

    1. EIS T&I2. Revamp internals Tray# 5 to 33. Conduct P-scan on the shell external of

    the column area where internal packing islocated.4. PZV inlet lines low thicknessreplacement as per EIU (part of pipingcontract)

    2 V04-V3* KeroseneStripper

    1 300327751. EIS T&I2. Revamp internals Tray# 1 to 9

    3 V04-V4*  LDO Stripper 1 30032776

    1. EIS T&I2. Revamp internals Tray# 1 to 7

    4 V04-V5 HDO Stripper 1 30032777

    1. EIS T&I2. Operation engineer should evaluatethe cause of down comers and trayssegment bending in order to avoidreoccurrence in the future. 

    5 V04-V9 Stabilizer 1 30032779 EIS T&I

    6 V04-V11 Splitter 1 30032781 EIS T&I

    7 V13-V1Amine

    Absorber1 30032800 EIS T&I

    8 V13-V3 Extractor 1 30032802 EIS T&I

  • 8/19/2019 2011 Trs Sow

    5/56

     Yanbu Refinery Department

    2011 Total Refinery Shutdown

    February 2011

    Area 2

    1 V09-V6 Stripper 1 30032957

    1. EIS T&I2.Trays # 6 to 13 shall be replaced bynew ones.Scaffolding plan is required 

    2 V12-V1 Fuel Gas Absorber 1 30032812 EIS T&I

    3 V17-V5Amine Stripper

    OverheadReceiver

    1 30032956 EIS T&I

    4 V14-V1*  Debutanizer 1 50041615 EIS T&I & Internal Revamp

    * Columns are handled by PPEU 

    MO's Towers List

    SN TAG# EQUIPTNo ofEquip.

    MO # scope of work

    Area 2 

    1 V11-C-0101Absorber

    Column1 10627388

    EIU requirement1.Inspection of column internal surface is

    required specially bottom section. Anycolumn internals in bottom section shallbe removed and internal surface need tobe exposed for inspection2. Column tray man ways need to beopened3. Erection of internal scaffolding isrequired. 

    Area 3 

    1 V05-C-0001HP Amine

    Absorber1 10680640

    OEU requirementWater wash, open inspect for fouling asper OEU recommendation Ref. LetterOEU# 073/10

  • 8/19/2019 2011 Trs Sow

    6/56

     Yanbu Refinery Department

    2011 Total Refinery Shutdown

    February 2011

    2 V05-C-0003LP amine

    absorber1 10628237

    EIU requirement.1. Open all manways

    2. Conduct MPI test on 2” nozzle at topman way3. Carry on any cleaning might berequired.4. Open all tray man way.5. Erect internal scaffolding. Inspectionas per EIU

    3 V07-C-0002Vent gas

    absorber 1 10628018

    EIU requirement1. Indication of minor defect wasobserved.2. Open all manways.3. Open all tray manways4. Conduct MPI test.5. Cleaning as required, Inspection as perEIU

    4 V18-C-0102Net gas

    scrubber1 10618972

    EIU requirement1. Open all column manways2. Conduct visual and NDT inspection3. Replacement of 3” (Nozzle N-12) Gasinlet nozzle at column bottom.4. Open all tray manways

    5. Rotate the level sight glass to bevisible

  • 8/19/2019 2011 Trs Sow

    7/56

     

    Yanbu Refinery Department

    2011 Total Refinery Shutdown

    February 2011

    Safety

    Cost

    Time

    Quality

    Scope

    TEAM

    WORK

    Cont

    Partner 

    Scope of Work

    Stacks & Flares

  • 8/19/2019 2011 Trs Sow

    8/56

     

    Yanbu Refinery Department

    2011 Total Refinery Shutdown

    February 2011

    General Scope of Work (STACKS)

    1. 

    Blind Equipment

    2. 

    Open bottom door manways

    3.  Conduct initial inspection on bottom section.

    4. 

    Conduct external inspection

    5. 

    Conduct internal inspection using Crane & basket.

    6. 

    Repair damaged refractory as recommended by Inspection.

    7. 

    Carryout final cleaning, clean bottom floor, remove all maintenance debris, prior to

    box-up Stack door.

    8.  Repair external coating as recommended by Inspection.

    9. 

    De blind equipments

    ==========================================================================

    General Scope of Work (Flares)

    1. 

    Blind Equipment as per Operation list.

    2. 

    Open all manways on Flare Stack assembly (Molecular Seal & Water Seal Drums, etc.)

    3.  Install air-movers for purging as necessary.

    4.  Conduct Initial Inspection.

    5. 

    Clean and inspect internals of Molecular Seal & water Seal drums.

    6. 

    Dismantle, remove Flare Tip & put it on the ground for Inspection.

    7. 

    Erect scaffolding to the top of the tip

  • 8/19/2019 2011 Trs Sow

    9/56

     

    Yanbu Refinery Department

    2011 Total Refinery Shutdown

    February 2011

    8. 

    Conduct T&I, NDT inspection.

    9. 

    Carryout recommended repairs by EIU.

    10. 

    Final Inspection of Flare Stack assembly (Molecular Seal & Water Seal Drums, etc.)

    11. 

    Reinstall back Flare Tip, box-up all flanges with permanent gaskets.

    12. 

    Box-up all manways on Flare Stack assembly (Molecular Seal & Water Seal Drums,

    etc.) with permanent gaskets.

    13. 

    De-blind nozzles and box-up with permanent gaskets.

  • 8/19/2019 2011 Trs Sow

    10/56

     

    Yanbu Refinery Department

    2011 Total Refinery Shutdown

    February 2011

    EIS Stacks and Flares List

    SN TAG# EQUIPTNO OFEQUIP.

    EQUIP.TYPE

    MO # SCOPE OF WORK

    Area 1

    1 V04-STK-AStack For

    CrudeHeater

    1 Stack 30032768

    1. EIS T&I

    2. Coating external surface using APCS-11C from middle of Stack to Top byusing crane. This will be done byOtaishan contractor)

    3. Stack aircraft light system will beupgraded by PPEU.

    2 V35-ME-1Emergency

    FlareAssembly

    1 Flare 30033783

    1. EIS T&I for Flare Tip, Molecular Seal &Water Seal Drums.

    2. Replacement of 3'' dia Pipe. (pipingcontract under the metal shop)

    3. External Coating of Water Seal Drumbottom portion. Scaffolding plan isrequired.

    4. Inspection of internal BALZONAcoating at bottom of Water Seal Drum,applied during 2008 I-T&I

    3 V35-ME-2Operating

    FlareAssembly

    1 Flare 30033784

    1. EIS T&I

    2. Scaffolding is required.

  • 8/19/2019 2011 Trs Sow

    11/56

     

    Yanbu Refinery Department

    2011 Total Refinery Shutdown

    February 2011

    Area 2 

    1 V11-STK-B Stack 1 Stack 30033798

    1. EIS T&I

    2. Coating external surface using APCS-11C from middle of Stack to Top.

    UTILITY

    1 V32-STK-C Boiler Stack 1 Stack 30033967

    1. EIS T&I

    2. Coating external surface using APCS-

    11C two (2) meters at Top only. Thiswill be done by Otaishan contractor

    3. Aircraft light system will be upgradedby PPEU

    MO's Stacks and Flares List

    SN TAG# EQUIPTNO OF

    EQUIP.

    EQUIP.

    TYPELOC. RESP. MO # SCOPE OF WORK

    Area 3 

    1 V35-F-0003 Sour Flare 1 Flare PA 3 MMH 10629116

    EIU requirementRemove Flare Tip toground forInspection

    NOTE: COMMISSIONING OF NEW FLARE HEADER FLOW METER BY PPEU

  • 8/19/2019 2011 Trs Sow

    12/56

     

    Yanbu Refinery Department

    2011 Total Refinery Shutdown

    February 2011

    Safety

    Cost

    Time

    Quality

    Scope

    TEAM

    WORK

    Cont

    Partner 

    Scope of Work

    Reactors

  • 8/19/2019 2011 Trs Sow

    13/56

     

    Yanbu Refinery Department

    2011 Total Refinery Shutdown

    February 2011

    General Scope of Work

    1. 

    Blind equipment.

    2. 

    Dump all catalysts as per process engineer recommendations.

    3. 

    If applicable conduct soda ash flashing before opening reactor manways and after cooling

    down.

    4.  Open all external man ways.

    5. 

    Conduct initial internal inspection.

    6.  Conduct external equipment inspection.

    7. 

    Remove reactors internals as per inspection recommendation.8.  Erect internal scaffolding as recommended by inspection.

    9. 

    Conduct reactor internal cleaning as per inspection recommendations.

    10. 

    Conduct reactor detail internal inspection.

    11. 

    Clean all removed internals as recommended by inspection and area engineer.

    12. 

    Based on inspection recommendations, grit blast all marked areas.

    13. Conduct WFMPT, hardness test, DPT as applicable.

    14. 

    Carry on any repair recommended by inspection.

    15. 

    Install back all removed and repaired reactors internals.

    16. 

    Conduct inspection on all internals after installing back.

    17. Remove internal Scaffolding.

    18. 

    Conduct reactor final cleaning.

    19. 

    Conduct reactor final inspection.

    20. 

    Load back the catalysts.

    21. 

    Box up the reactor.

    22. Apply required bolts tensioning and torque.

    23. 

    De blind.

  • 8/19/2019 2011 Trs Sow

    14/56

     

    Yanbu Refinery Department

    2011 Total Refinery Shutdown

    February 2011

    EIS Reactors List

    SN TAG# EQUIPT No ofEquip.

    MO # scope of work

    Area 21 V17-V1 L.S.R.N Reactor 1 30033520 T&I and Catalyst skimming

    MO's Reactors List

    SN TAG# EQUIPTNo ofEquip.

    MO # scope of work

    Area 2

    1 V09-V1 NHT Reactor 1 10659299

    OEU requirement1. Catalyst Dumping and Skimming forone (1) Meter top as per OEU Letter#YR/OEU-059/0102. Replace outlet pressure gauge 3/4"globe valve

    Area 3

    1 V05-D-0001AFirst HDSreactor

    1 10619631

    OEU requirement1. DHT Reactor Top Bed CatalystDumping.2. Transportation and Regeneration ofCatalyst at Al Bilad, Jubail• Remove top 24” elbow. • Remove bottom 24”X22” spool forinspection and cleaning.• Flash outlet line starting from V05-D-0050 up to reactor bottom.• Clean out let reactor elbow byvacuum cleaner.• Erect external scaffolding on reactorshell to perform shear wave test.• Remove external insulation onreactor steam and circumferentialwelds.• Perform Shear wave inspection of theTee joints of circ to long seam weld,

    and the shell to nozzle welds at nextT&I of V05-D-0001A.• Take metallurgical replicas at theshell and the welds of V05-D-0001A forHTHA in next outage.

    2V10-D-

    1003/1004/2003/2004

    1st & 2ndConverterReactors

    41062878510628791

    OEU requirement1. Catalyst dumping & Reloading newcatalyst

  • 8/19/2019 2011 Trs Sow

    15/56

     

    Yanbu Refinery Department

    2011 Total Refinery Shutdown

    February 2011

    Safety

    Cost

    Time

    Quality

    Scope

    TEAM

    WORK

    Cont

    Partner 

    Scope of Work

    Heater

  • 8/19/2019 2011 Trs Sow

    16/56

     

    Yanbu Refinery Department

    2011 Total Refinery Shutdown

    February 2011

    General Scope of Work

    1. 

    Blind Equipment

    2. 

    Open all manways.

    3. 

    Open heater stack and duct manways.

    4. 

    Conduct initial internal inspection.

    5. 

    Conduct external inspection.

    6. 

    Remove burner assemblies and associated piping as recommended by inspection.

    7.  Cover all burners opening. (By Olayyan) 

    8. 

    Erect full internal scaffolding to reach all walls and tubes for UT, hardiness and visual

    inspection.

    9. 

    Erect scaffolding for convection section side covers opening and make it suitable for

    UT and VT tests.

    10. 

    Open all convection section side covers.

    11. 

    Open all convection section inspection windows.

    12. Brush cleans the tubes / U-bends as marked by inspection for UT survey and visual

    inspection.

    13. 

    Conduct UT tests on all tubes including convection and radiant sections.

    14. Conduct replica test if recommended by CSD.

    15. 

    Conduct RT profile shot for selected elbows.

    16. 

    Repair damaged refractory as per civil inspector recommendations.

    17. 

    Test & clean stack dampers and repair as recommended by inspection.

    18. 

    Remove all internal scaffolding.

    19. 

    Install burner assemblies and associated piping. (By Olayyan) 20. Rearrange floor bricks, clean, and replace damaged bricks.

    21. Conduct final inspection.

    22. 

    Close all Radiant & Convection section doors, duct and Stack man ways.

  • 8/19/2019 2011 Trs Sow

    17/56

     

    Yanbu Refinery Department

    2011 Total Refinery Shutdown

    February 2011

    23. 

    Close / Box-up all heater man ways.

    24. Remove scaffolding erected for convection section.

    25. 

    Perform required dry out procedure as per civil inspector recommendations.

    26. De Blind Equipment

  • 8/19/2019 2011 Trs Sow

    18/56

     

    Yanbu Refinery Department

    2011 Total Refinery Shutdown

    February 2011

    EIS Heaters List 

    SN TAG# EQUIPTNo ofEquip.

    Equip.Type

    Loc. Resp. MO # scope of work

    Area 1 

    1 V04-H1ACrude Charge

    Heater1 Heater PA1 ESP 30032505

    T&I and Replace V04-H1 B Coil Hanger andinstall gasket for 6"decoking flange leak.1- FTIS to be done by

    EIU.2- Radiant section isrequired to removehard scale.3- Scaffolding plan isrequired. 

    2 V04- H1BCrude Charge

    Heater1 Heater PA1 ESP 30032506

    Area 2

    1 V09-H1Reactor Charge

    Heater1 Heater PA 2 ESP 30033111

    T&I. Heater should beopened in 2010shutdown for re-inspection, and thefretting damageshould be reassessed.At least 30%refractory materialshould be on hand foranticipatedrepair/replacerefractory atconvection & radiantsection during thenext shut down. 

  • 8/19/2019 2011 Trs Sow

    19/56

     

    Yanbu Refinery Department

    2011 Total Refinery Shutdown

    February 2011

    2 V09-H2Stripper Reboiler

    Heater1 Heater PA 2 ESP 30033112

    T&I.1. At least 30%

    refractory materialshould be on hand foranticipatedrepair/replacerefractory atconvection & radiantsection during thenext shut down.2.Replica examinationwas done on tubesnumber 1, 2 and 3.The microstructure of

    the tubes is normalfor carbon steel asillustrated in Figures3, 4 and 5. Considerreplica testing of theheater tubes in thenext T&I. 

    3 V11-H1Platforming Charge

    Heater1 Heater PA 2 ESP 30032770

    T&I and DamperReplacement

    4 V11-H2 Platforming No. 1Inter Heater

    1 Heater PA 2 ESP 30032771

    5 V11-H3Platforming No. 2

    Inter Heater1 Heater PA 2 ESP 30032772

    6V11-H1-H2-H3

    Ducting 1 Heater PA 2 ESP 30033421 T&I Scope

    7 V14-H1Debutanizer

    Reboiler Heater1 Heater PA 2 ESP 30033113 T&I Scope

    8 V17-H1Reactor Charge

    Heater1 Heater PA 2 ESP 30032791

    T&I. Tubereplacement as

    required.

    9 V17-H2Stripper Reboiler

    Heater1 Heater PA 2 ESP 30032793 T&I Scope

    10 V12-H1 Incinerator 1 Heater PA 2 ESP 30032789 T&I Scope

    Note : Commission new flare header flow meter, PPEI were informed to commission the system

  • 8/19/2019 2011 Trs Sow

    20/56

     

    Yanbu Refinery Department

    2011 Total Refinery Shutdown

    February 2011

    MO's Heaters List

    SN TAG# EQUIPTNo ofEquip.

    Equip.Type

    Loc. Resp. MO # scope of work

    Area 2

    1V11-F101

    Platforming No.2Interheater

    1 Heaters PA 2 ESP 10628097

    INSPECTIONREQUIREMENT & RepairV11-F101 DamperPositioner.Internal scaffolding is

    required• Inspection of tubesupports and repair ofany damage support 

    Area 3

    1V05-F-0001

    Reactor feedheater

    1 Heaters PA 3 ESP 10626582

    INSPECTIONREQUIREMENT. (not T&I)• Erect internalscaffolding.• Conduct visualinspection to all tubesand supports.• Conduct UT thicknessmeasurement.

    • Open heater manwaysand inspection covers. 

    2V10-F-1003

    Reaction furnaceburner

    1 Heaters PA 3 ESP 10619295

    INSPECTIONREQUIREMENT.• Internal inspection isrequired• Replace burner nozzle/ tip assembly. Tipavailable at T&I stores• Repair of damagedrefractory• NDT (UT) test to be

    applied as required. 

  • 8/19/2019 2011 Trs Sow

    21/56

     

    Yanbu Refinery Department

    2011 Total Refinery Shutdown

    February 2011

    3V10-F-1004

    Thermal oxidizerfurnace burner

    1 Heaters PA 3 ESP 10619296

    INSPECTIONREQUIREMENT.

    • Internal inspection isrequired• Replace burner nozzle/ tip assembly. Tipavailable at T&I stores• Repair of damagedrefractory• NDT (UT) test to beapplied as required, 

    4V10-F-2002

    Thermal oxidizerfurnace

    1 Heaters PA 3 ESP 10626664

    INSPECTIONREQUIREMENT.• Internal inspection is

    required• Repair of damagedrefractory if any.• NDT (UT) test to beapplied as required. 

    5V10-F-2003

    Reaction furnaceburner

    1 Heaters PA 3 ESP 10619297

    INSPECTIONREQUIREMENT.• Internal inspection isrequired• Replace burner nozzle/ tip assembly. Tipavailable at T&I stores

    • Repair of damagedrefractory• NDT (UT) test to beapplied as required

    6V10-F-2004

    Thermal oxidizerfurnace burner

    1 Heaters PA 3 ESP 10619298

    INSPECTIONREQUIREMENT.• Internal inspection isrequired• Replace burner nozzle/ tip assembly. Tipavailable at T&I stores• Repair of damagedrefractory• NDT (UT) test to beapplied as required

  • 8/19/2019 2011 Trs Sow

    22/56

     

    Yanbu Refinery Department

    2011 Total Refinery Shutdown

    February 2011

    Safety

    Cost

    Time

    Quality

    Scope

    TEAM

    WORK

    Cont

    Partner 

    Scope of Work

    Heat Exchangers

  • 8/19/2019 2011 Trs Sow

    23/56

     

    Yanbu Refinery Department

    2011 Total Refinery Shutdown

    February 2011

    General Scope of Work

    1. 

    Blind the equipments.

    2. 

    Erect external scaffolding as required.

    3. 

    If chemical cleaning is required, install adopters for the chemical cleaning.

    (Coordinate with RISAL contractor who will perform the chemical cleaning and

    vacuum cleaning for backinox)

    4. 

    Remove channel box and shell covers.

    5.  Remove floating head cover.

    6. 

    Conduct initial inspection on assembly before tube bundle removal.

    7. 

    Remove channel box.

    8. 

    Pull out exchanger tube bundle and transport to cleaning yard at Area-25.

    9. 

    Perform visual inspection on both shell and tube bundle.

    10. 

    Hydro Jet all tubes and remove all scales’. Cleaning shall be accepted by both

    inspection and area engineer.

    11. Hydro jet shell internal surface.

    12. 

    Air blows all tubes after hydro-jetting.

    13. 

    Hydro jet bundle externally and remove any deposit in between the tubes.

    14. 

    Carry out MFL test on 10% tubes.

    15. 

    Grit blast vertical and circumferential shell weld seams (6” wide) as marked by

    Inspection for WFMPT examination

    16. 

    Clean heat exchanger components, covers, and channel box.

    17. 

    If applicable grit blast channel box and covers for re-coating as recommended by

    inspection.

    18. Apply required coating as per Saudi Aramco procedure and follow inspection

    recommendations.

    19. 

    Carry on any repair required as per inspection recommendations.

    20. 

    If applicable conduct PWHT.

  • 8/19/2019 2011 Trs Sow

    24/56

     

    Yanbu Refinery Department

    2011 Total Refinery Shutdown

    February 2011

    21. 

    Reinstall back the tube bundles.

    22. 

    Using test ring conduct hydro test for shell side as per approved procedure.23.

     

    Plug any leaking tube using in kind tube plugs.

    24. Re-install back channel box, channel box cover and floating head cover.

    25. Conduct tube side hydro test as per approved procedure.

    26. Re-install back shell cover.

    27. 

    Conduct final test as per approved procedure.

    28. 

    Carry on any repair required.

    29. 

    Remove scaffoldings

    30. 

    De blind the equipment

  • 8/19/2019 2011 Trs Sow

    25/56

     

    Yanbu Refinery Department

    2011 Total Refinery Shutdown

    February 2011

    EIS Heat Exchangers List

    SNTAG

    #EQUIPT

    No ofEquip

    EquipType

    Loc. Resp. MO # Scope Of Work

    Area 1

    1V04-E2

    ACrude

    Kerosene

    ProductExchangers

    1 H.E PA1 ESP 30032876 20% MFL shall be conducted.One bundle is re-tubed and shall beinstalled.

    The other bundle should go to Juaimafor retubing. Tubes are available inA25.

    2V04-E2

    B1 H.E PA1 ESP 30032864

    3V04-E3

    A1

    Crude LightDiesel OilProduct

    Exchangers

    1 H.E PA1 ESP 30032865To perform 20% MFL and 20% WFMPT.

    4V04-E3

    A21 H.E PA1 ESP 30032866

    5V04-E3

    B11 H.E PA1 ESP 30032867

    6V04-E3

    B21 H.E PA1 ESP 30032868

    7 V04-E4A1

    Crude No. 1CirculatingLight Diesel

    OilExchangers

    1 H.E PA1 ESP 30032884

    8V04-E4

    A21 H.E PA1 ESP 30032885

    9V04-E4

    B11 H.E PA1 ESP 30032895

    10V04-E4

    B21 H.E PA1 ESP 30032896

    11V04-E6

    A1

    DesaltedCrude Heavy

    Diesel OilProduct

    Exchanger

    1 H.E PA1 ESP 30032471Shell side blow down flange leak,

    gasket to be replaced. To perform20% MFL and 20% WFMPT.12 V04-E6A1 H.E PA1 ESP 30034145

    13V04-E6

    B11 H.E PA1 ESP 30035854 To perform 20% MFL and 20% WFMPT.

    14V04-E6

    B1 H.E PA1 ESP 30035841

    S/S blow down upstream flange leakgasket to be replaced. To perform 20%MFL and 20% WFMPT.

  • 8/19/2019 2011 Trs Sow

    26/56

     

    Yanbu Refinery Department

    2011 Total Refinery Shutdown

    February 2011

    15V04-E5A1

    Crude No. 2CirculatingLight Diesel

    OilExchangers

    1 H.E PA1 ESP 30035842

    To perform 20% MFL and 20% WFMPT.16 V04-

    E5A21 H.E PA1 ESP 30035843

    17V04-E5B1

    1 H.E PA1 ESP 30035844

    18V04-E5B2

    1 H.E PA1 ESP 30035845

    19V04-E31

    HDO trimcooler

    1 H.E PA1 ESP 30035840 To perform 100% WFMPT and 20% MFL

    20V04-E24

    LSRN trimcooler

    1 H.E PA1 ESP 30033791 To perform 40%WFMPT and 20% MFL

    21V04-E33

    LDO trimcooler

    1 H.E PA1 ESP 30035855 To perform 100% WFMPT and 20% MFL

    22 V04-E8A1

    DesaltedCrude Heavy

    Diesel OilCirculatingExchanger

    1 H.E PA1 ESP 30032850

    To perform 20% MFL and 20% WFMPT.23

    V04-E8A2

    1 H.E PA1 ESP 30032851

    24V04-E8

    B11 H.E PA1 ESP 30032852

    25V04-E8

    B21 H.E PA1 ESP 30032472

    26V04-E9

    A1

    DesaltedCrude HotReducedCrude

    Exchangers

    1 H.E PA1 ESP 30032853

    Repair copper heated Tube Side InletFlange & To perform 20% MFL and 20%WFMPT.

    27V04-E9

    A21 H.E PA1 ESP 30032854

    Repair copper heated Tube Side InletFlange & To perform 20% MFL and 20%WFMPT.

    28V04-E9

    A31 H.E PA1 ESP 30032855

    To perform 20% MFL and 20% WFMPT.29

    V04-E9A4

    1 H.E PA1 ESP 30032856

    30V04-E9

    A51 H.E PA1 ESP 30032857 To perform 30% MFL and 20% WFMPT

    31V04-E9

    B11 H.E PA1 ESP 30032858

    Repair copper heated Tube Side InletFlange & To perform 20% MFL and 20%

    WFMPT.

    32V04-E9

    B21 H.E PA1 ESP 30032859

    Repair copper heated Tube Side InletFlange & To perform 20% MFL and 20%WFMPT.

    33V04-E9

    B31 H.E PA1 ESP 30032860 To perform 20% MFL and 20% WFMPT.

  • 8/19/2019 2011 Trs Sow

    27/56

     

    Yanbu Refinery Department

    2011 Total Refinery Shutdown

    February 2011

    34V04-E9

    B4

    1 H.E PA1 ESP 30032861

    Repair copper heated Tube SideFlange & To perform 20% MFL and 20%

    WFMPT.

    35V04-E9

    B51 H.E PA1 ESP 30032862

    To perform 30% MFL and 100% WFMPT

    36V04-E17 A

    StabilizerFeed

    Exchangers

    1 H.E PA1 ESP 30032478

    To perform 20% MFL and 20% WFMPT.37

    V04-E17 B

    1 H.E PA1 ESP 30033091

    38V04-E19 A

    StabilizerReboiler

    1 H.E PA1 ESP 30032479Repair copper heated Channel Box &To perform 20% MFL and 20% WFMPT.

    39V04-E19 B 1 H.E PA1 ESP 30033092

    Repair copper heated Channel Box &To perform 20% MFL and 20% WFMPT.

    40V04-E22 A

    HeavyNaphtha

    Product TrimCoolers

    1 H.E PA1 ESP 30032481 To perform 20% MFL and 20% WFMPT.Inspect the coating at channel boxcover.41

    V04-E22 B

    1 H.E PA1 ESP 30033093

    42V04-E23 A Splitter

    Reboiler

    1 H.E PA1 ESP 30032483 One tube bundle to be sent toJuaymah for retubing as perinspection decision. Tube available atArea 25.

    43V04-E23 B

    1 H.E PA1 ESP 30033094

    44V04-E29 A

    CirculatingCoolingWater

    Coolers

    1 H.E PA1 ESP 30032838

    To perform 20% MFL and 20% WFMPT.Inspect the coating at channel boxcover. Required chemical cleaning &changing of anodes.

    45V04-E29 B

    1 H.E PA1 ESP 30032839

    46V04-E29 C

    1 H.E PA1 ESP 30032840

    47V04-E29 D

    1 H.E PA1 ESP 30032486

    48V13-E1

    A CausticHeater

    1 H.E PA1 ESP 30032498

    To perform 20%MFL and 20% WFMPT.49

    V13-E1B

    1 H.E PA1 ESP 30034143

    Area 2

    1 V09-E2 A ReactorProducts

    TrimCondenser

    1 H.E PA 2 ESP 30032581 EIU Inspection, Anode consumedUpgrade anodes to Al• Install ferrules @ inlet side.Require for soda ashneutralization.

    2 V09-E2 B 1 H.E PA 2 ESP 30032897

    3 V09-E3CStripper Feed

    BottomsExchangers

    1 H.E PA 2 ESP 30032559

    Replace tube bundle. Tube bundlereceived,

  • 8/19/2019 2011 Trs Sow

    28/56

     

    Yanbu Refinery Department

    2011 Total Refinery Shutdown

    February 2011

    4 V09-E5

    StripperOverhead

    TrimCondenser

    1 H.E PA 2 ESP 30032582 T&I Scope

    5 V12-E1Kerosene

    Unibon GasCoolers

    1 H.E PA 2 ESP 30032562 T&I Scope

    6 V12-E3Amine

    StripperReboiler

    1 H.E PA 2 ESP 30032560T&I Scope

    7 V12-E4 A

    AmineExchangers

    1 H.E PA 2 ESP 30032564 T&I Scope

    8 V12-E4 B 1 H.E PA 2 ESP 30032845 T&I Scope

    9 V12-E4 C 1 H.E PA 2 ESP 30032846

    Install V12-E4 C (new shell & U-tube bundle). Will require

    cutting/ fabrication of new pipespool for V12 E4C to match thealignment of new headattachment.

    10 V12-E6 Amine Cooler 1 H.E PA 2 ESP 30032561 T&I Scope

    11 V14-E8DE-

    ETHANIZERFEED EXCHER

    1 H.E PA 2 ESP 30037263 T&I Scope

    12 V14-E9REBOILER

    DETHANIZER1 H.E PA 2 ESP 30037264 T&I Scope

    13 V14-E10ACONDENSERDETHANIZR

    O/HEAD1 H.E PA 2 ESP 30037265 T&I Scope

    14 V14-E10BCONDENSERDETHANIZR

    O/HEAD1 H.E PA 2 ESP 30037266 T&I Scope

    15 V17-E1 A1

    CombinedFeed Effluent

    Exchanger

    1 H.E PA 2 ESP 30032586 T&I Scope

    16 V17-E1 A2 1 H.E PA 2 ESP 30032886 T&I Scope

    17 V17-E1 A3 1 H.E PA 2 ESP 30032887Also include Soda ash cleaningbefore pulling out of tube bundle.

    18 V17-E1 A4 1 H.E PA 2 ESP 30032888Also include Soda ash cleaningbefore pulling out of tube bundle.

    19 V17-E1 B1 1 H.E PA 2 ESP 30032889 T&I Scope

    20 V17-E1 B2 1 H.E PA 2 ESP 30032890 T&I Scope

    21 V17-E1 B3 1 H.E PA 2 ESP 30032891 Also includes Soda ash cleaningbefore pulling out of tube bundle.

    22 V17-E1 B4 1 H.E PA 2 ESP 30032892Also includes Soda ash cleaningbefore pulling out of tube bundle.

    23 V17-E3Make-Up Gas

    Cooler1 H.E PA 2 ESP 30032604 T&I Scope

    24 V17-E4 A Stripper FeedBottoms

    1 H.E PA 2 ESP 30032608 T&I Scope25 V17-E4 B 1 H.E PA 2 ESP 30032882 T&I Scope

  • 8/19/2019 2011 Trs Sow

    29/56

     

    Yanbu Refinery Department

    2011 Total Refinery Shutdown

    February 2011

    26 V17-E4 C Exchangers 1 H.E PA 2 ESP 30032883 T&I Scope

    27 V17-E6

    Stripper

    Bottoms TrimCooler

    1 H.E PA 2 ESP 30032568 T&I Scope

    MO's Heat Exchangers List

    SN TAG# EQUIPTNo ofEquip.

    Equip. Type Loc. Resp MO # scope of work

    Area 2

    1 V09-E4 A

    NHTstripper

    bottomcooler

    1 H.E. PA 2 ESP 10632464

    T&I and Chemicalcleaning. Chemical

    cleaning.

    2 V09-E4 B

    NHTstripperbottomcooler

    1 H.E. PA 2 ESP 10633245

    T&I and Chemicalcleaning. Chemicalcleaning.

    3 V11-E3 APlatformer

    producttrim cooler

    1 H.E. PA 2 ESP 10632662100% MFL at all tubes.

    4 V11-E3 BPlatformer

    producttrim cooler

    1 H.E. PA 2 ESP 10633231100% MFL at all tubes.

    5 V11-E3 C

    Platformer

    producttrim cooler

    1 H.E. PA 2 ESP 10633237

    100% MFL at all tubes.

    6 V11-E3 DPlatformer

    producttrim cooler

    1 H.E. PA 2 ESP 10633238100% MFL at all tubes.

    7 V11-E-106Gas

    Exchanger1 H.E. PA 2 ESP 10670173

    • 100% MFL test shall beconducted.• Sample tube shall becut.• Tube plugging mightbe done for tubes with >50 tube thinning

    8 V11-E-107Feed GasChiller

    1 H.E. PA 2 ESP 10670266

    • 100% MFL test shall beconducted.• Sample tube shall becut.• Tube plugging mightbe done for tubes with >50 tube thinning

  • 8/19/2019 2011 Trs Sow

    30/56

     

    Yanbu Refinery Department

    2011 Total Refinery Shutdown

    February 2011

    9 V11 E0108PreSatCooler

    1 H.E. PA 2 ESP 10689169 Inspection Requirement

    10V11-E109

    AAET crossexchanger

    1 H.E. PA 2 ESP 10632761

    100% MFL at all tubes.• Sample tube shall becut.• Tube plugging mightbe done for tubes with >50 tube thinning

    11V11-E109

    BAET crossexchanger

    1 H.E. PA 2 ESP 10633289

    100% MFL at all tubes.• Sample tube shall becut.• Tube plugging mightbe done for tubes with >50 tube thinning

    12V11-E109

    CAET crossexchanger

    1 H.E. PA 2 ESP 10633291

    100% MFL at all tubes.• Sample tube shall becut.• Tube plugging mightbe done for tubes with >50 tube thinning

    13V11-E109

    DAET crossexchanger

    1 H.E. PA 2 ESP 10633295

    Replace V11-E109D(Complete set, as perinspection IR)

    14

    V11-E110

    A

    AET cross

    exchanger 1 H.E. PA 2 ESP 10632914

    100% MFL at all tubes.• Sample tube shall becut.

    • Tube plugging mightbe done for tubes with >50 tube thinning

    15V11-E110

    BAET crossexchanger

    1 H.E. PA 2 ESP 10633300

    100% MFL at all tubes.• Sample tube shall becut.• Tube plugging mightbe done for tubes with >50 tube thinning

    16

    V11-E110

    C

    AET cross

    exchanger 1 H.E. PA 2 ESP 10633304

    100% MFL at all tubes.• Sample tube shall becut.• Tube plugging mightbe done for tubes with >50 tube thinning

  • 8/19/2019 2011 Trs Sow

    31/56

     

    Yanbu Refinery Department

    2011 Total Refinery Shutdown

    February 2011

    17 V11-E110D

    AET crossexchanger

    1 H.E. PA 2 ESP 10633307

    100% MFL at all tubes.• Sample tube shall be

    cut.• Tube plugging mightbe done for tubes with >50 tube thinning

    18V11-E110

    EAET crossexchanger

    1 H.E. PA 2 ESP 10633308

    100% MFL at all tubes.• Sample tube shall becut.• Tube plugging mightbe done for tubes with >50 tube thinning

    19 V11-E0111Platformate

    Chiller1 H.E. PA 2 ESP 10689171

    Inspection requirements

    20 V11-E-116Recontact

    Chiller1 H.E. PA 2 ESP 10670168

    100% MFL at all tubes.• Sample tube shall becut.• Tube plugging mightbe done for tubes with >50 tube thinning

    21 V11-E0117Propane

    Condenser1 H.E. PA 2 ESP 10630249

    100%MFL at all tubes.Repair for both shellcover due to galvaniccorrosion(CS/Monel).Preparewelding procedure fordissimilar materials.• EIU to provide WPS. • 10% to 20% tubethinning as per MFLresult of 2008 T&I• Sample tube shall becut.• Tube plugging mightbe done for tubes with >50 tube thinning

    22V11-E-0119

    Heater 1Reduction

    Gas1 H.E. PA 2 AMG 10627130

    Replace Heater element.Spare heater isavailable.

  • 8/19/2019 2011 Trs Sow

    32/56

     

    Yanbu Refinery Department

    2011 Total Refinery Shutdown

    February 2011

    23 V11-E121Regeneratio

    n GasHeater

    1 H.E. PA 2 ESP 10627968

    V11-E121 ReplaceDefective element &

    inspection of nipplewelds, repair nipple ifrequired. (New heaterelement available atArea 25 Electrical Yard).

    24 V11-E122 Air Heater 1 H.E. PA 2 ESP 10627704

    V11-E122 ReplaceDefective element.Electrical Shop toidentify the defectiveelement to be replaced.

    25 V11-E-123Reduction

    GasExchanger

    1 H.E. PA 2 ESP 10670258

    To be opened forinspection as per EIU.

    • 100% MFL test shall beconducted.• Sample tube shall becut.• Tube plugging mightbe done for tubes with >50 tube thinning

    26V11 E-0130

    Lube oilCooler

    1 H.E. PA 2 ESP 10630248

    100%MFL at all tubes.Repair for both shellcover due to galvaniccorrosion(CS/Monel).Prepare welding procedurefor dissimilar materials.• Tube bundle pull out isrequired• Internal cleaning isrequired using Hydrotest• Repair of damagedinternal cladding isrequired• 10% to 20% tube metalloss reported as per MFLresult of 2008 T&I• 100% MFL test shall beconducted.• Sample tube shall becut.• Tube plugging mightbe done for tubes with >50 tube thinning. EIU toprovide WPS

  • 8/19/2019 2011 Trs Sow

    33/56

     

    Yanbu Refinery Department

    2011 Total Refinery Shutdown

    February 2011

    27 V14-E1ADebutanizer

    Feed

    Exchanger

    1 H.E. PA 2A.

    Planner

    10585947 One sent to Juaymah for

    retubing and the otherone to be sent duringshutdown.28 V14-E1B

    DebutanizerFeed

    Exchanger1 H.E. PA 2

    A.Planner

    10585948

    29 V14-E3ADebutanizer

    BottomCooler

    1 H.E. PA 2A.

    Planner10585949

    To be sent to Juaymahfor retubing.

    30 V14-E12BDepropanizr

    BottomCooler

    1 H.E. PA 2A.

    Planner10568356

    Pull-out bundle andreplace with sparebundle.

    31V14-E

    101A/B

    DebutanizerFeed

    Exchanger2 H.E. PA 2 ESP

    1067026110670262

    To be opened forinspection as EIU. • 20%

    to 40% tube metal losswas reported as per MFLresult of 2008 T&I• 100% MFL test shall beconducted.• Sample tube shall becut.• Tube plugging mightbe done for tubes with >50 tube thinning

    32V14 E-0102 A

    DebutanizerBottom Trim

    Cooler1 H.E. PA 2 ESP 10630250

    100%MFL at all tubes.Repair for both shell

    cover due to galvaniccorrosion(CS/Monel).Preparewelding procedure fordissimilar materials.Repair for both shellcover due to galvaniccorrosion (CS/Monel)• 20% to 40% tube metalloss was reported as perMFL result of 2008 T&I• 100% MFL test shall be

    conducted.• Sample tube shall becut.• Tube plugging mightbe done for tubes with >50 tube thinning

  • 8/19/2019 2011 Trs Sow

    34/56

     

    Yanbu Refinery Department

    2011 Total Refinery Shutdown

    February 2011

    33V14 E-0102 B

    DebutanizerBottom Trim

    Cooler1 H.E. PA 2 ESP 10630251

    100%MFL at all tubes.Repair for both shell

    cover due to galvaniccorrosion(CS/Monel).Preparewelding procedure fordissimilar materials.Repair for both shellcover due to galvaniccorrosion (CS/Monel)• 20% to 40% tube metalloss was reported as perMFL result of 2008 T&I• 100% MFL test shall be

    conducted.• Sample tube shall becut.• Tube plugging mightbe done for tubes with >50 tube thinning 

    34V14 E0103

    ADebutanizer

    overheadtrim cooler

    1 H.E. PA 2 ESP1063257810630238

    Repair channel box &100% MFL + ChemicalCleaning. • Tube bundleremoval• Tube cleaning hydro test

    • Repair of damageinternal claddingReplace all damagedferrules. Repair channelbox• 30% to 40% tube metalloss was reported as perMFL result of 2008 T&I• Sample tube shall becut.• Tube plugging mightbe done for tubes with >

    50 tube thinning 

  • 8/19/2019 2011 Trs Sow

    35/56

     

    Yanbu Refinery Department

    2011 Total Refinery Shutdown

    February 2011

    35V14 E0103

    BDebutanizer

    overheadtrim cooler

    1 H.E. PA 2 ESP1063328310630241

    Repair channel box &100% MFL + Chemical

    Cleaning. • Tube bundleremoval• Tube cleaning hydro test• Repair of damageinternal claddingReplace all damagedferrules 

    36V14 E0103

    CDebutanizer

    overheadtrim cooler

    1 H.E. PA 2 ESP1063328410630242

    Repair channel box &100% MFL + ChemicalCleaning. • 30% to 40%tube metal loss was

    reported as per MFLresult of 2008 T&I• Sample tube shall becut.• Tube plugging mightbe done for tubes with >50 tube thinning

    37V14 E0103

    DDebutanizer

    overheadtrim cooler

    1 H.E. PA 2 ESP1063328710630244

    Repair channel box &100% MFL + ChemicalCleaning. • 30% to 40%tube metal loss wasreported as per MFL

    result of 2008 T&I• Sample tube shall becut.• Tube plugging mightbe done for tubes with >50 tube thinning

    38V14-E-0105A

    DepropanizrNet

    OverheadCooler

    1 H.E. PA 2 ESP 10628187

    To repair at channelbox.• Tube bundle to bebulled out and internal.Hydro test will berequired.• Repair of damageinternal cladding isrequired

  • 8/19/2019 2011 Trs Sow

    36/56

     

    Yanbu Refinery Department

    2011 Total Refinery Shutdown

    February 2011

    39V14-

    E0105B

    DepropanizrNet

    OverheadCooler

    1 H.E. PA 2 ESP 10630237

    To repair at channelbox.

    • Tube bundle to bebulled out and internal.Hydro test will berequired.• Repair of damageinternal cladding isrequired

    40 V17-E-101Stripperoverhead

    Trim Cooler1 H.E. PA 2 ESP 10670163

    To be opened forinspection as EIU. • 10%to 30% tube metal losswas reported as per MFLresult of 2008 T&I

    • 100% MFL test shall beconducted.• Sample tube shall becut.• Tube plugging mightbe done for tubes with >50 tube thinning.• Repair of exchangermonel cladding andoverlay by welding buildup and cladding. 

    41

    V11- C1A-

    E1A/B

    Standby Oil

    Cooler 2 H.E. PA 2 ESP 10713805

    T&I Scope

    42V11- C1B-

    E1A/BStandby Oil

    Cooler2 H.E. PA 2 ESP 10713813

    T&I Scope

    43 V14- E11Depropanizr

    Reboiler1 H.E. PA 2 ESP 10713801

    T&I Scope

    Area 3

    1 V05-E-0001

    Reactor

    feed/effluent

    exchanger

    1 H.E. PA 3 JAZ 10626803

    Soda ash Cleaning. Performneutralization and vacuumcleaning a per OEU• Perform Shear waveinspection of the Tee jointsof circ to long seam weld,

    and the shell to nozzlewelds at next T&I of V05-E-0001.• Take metallurgicalreplicas at the shell and thewelds of V05-E-0001 forHTHA in next outage.Vacuum cleaning (OEU) 

  • 8/19/2019 2011 Trs Sow

    37/56

     

    Yanbu Refinery Department

    2011 Total Refinery Shutdown

    February 2011

    2 V05-E-0009Feed/striper bottom

    exchanger

    1 H.E. PA 3 JAZ 10626804 Vacuum Cleaning.

    3V05 E-0011A

    Producttrim cooler

    1 H.E. PA 3 ESP 10629300100%MFL at all tubes.• 30% to 40% tube metal losswas reported as per MFLresult of 2008 T&I• 100% MFL test shall beconducted.• Sample tube shall be cut. • Tube plugging might bedone for tubes with > 50tube thinning

    4V05 E-0011B

    Producttrim cooler

    1 H.E. PA 3 ESP 10629304

    5 V05-E-0015Stabilizednaphtha

    trim cooler1 H.E. PA 3 ESP 10629296

    Inspection Requirements.The channel side of V05-E-0015 should be opened inNext T&I to monitor thecondition of the repair.

    6 V05-E-0030

    Cooling

    water HeatExchanger

    1 H.E. PA 3 ESP 10629574

    Inspection Requirements. •Perform UT readings forshell part of V05-E-0030/V05-E-0031 on aregular basis as per OSIrequirements for pressurevessels to monitor thecorrosion rate.• The baffle thickness andbaffles’ tubes holes shouldbe measured when it ispossible during S/D.

    7 V05-E-0031

    Cooling

    water HeatExchanger

    1 H.E. PA 3 ESP 10629572

    Inspection Requirements. •Perform UT readings forshell part of V05-E-0030/V05-E-0031 on aregular basis as per OSI

    requirements for pressurevessels to monitor thecorrosion rate.• The baffle thickness andbaffles’ tubes holes shouldbe measured when it ispossible during S/D.

  • 8/19/2019 2011 Trs Sow

    38/56

     

    Yanbu Refinery Department

    2011 Total Refinery Shutdown

    February 2011

    8V06-E-0003C

    Amineregenerator reboilers

    1 H.E. PA 3 ESP 10630043

    Inspection Requirements. •20% to 30% tube metal loss

    was reported as per MFLresult of 2008 T&I• 100% MFL test shall beconducted.• Sample tube shall be cut. • Tube plugging might bedone for tubes with > 50tube thinning,

    9 V10-E-10021st sulfurcondenser

    1 H.E. PA 3 ESP 10635942

    Open the channel head tocheck mesh blanketcondition, TRS Scopeinclude replacement ofdemister pad as per OEU,plus inspection activities asEIU recommendation.

    10 V10-E-1003

    2nd Sulphur

    Condenser 1 H.E. PA 3 ESP 10635945

    11 V10-E-10043rd SulphurCondenser

    1 H.E. PA 3 ESP 10635946

    12 V10-E-20021st SulphurCondenser

    1 H.E. PA 3 ESP 10635943

    13 V10-E-20032nd SulphurCondenser

    1 H.E. PA 3 ESP 10635947

    14 V10-E-20043rd SulphurCondenser

    1 H.E. PA 3 ESP 10635949

    15 V10-E-2007Air

    Preheated1 H.E. PA 3 ESP 10629186

    Inspection Requirements. •20% to 40% tube metal losswas reported as per MFLresult of 2008 T&I• 100% MFL test shall beconducted.• Sample tube shall be cut.• Tube plugging might bedone for tubes with > 50tube thinning,

    16 V10-E-1007Air

    Preheated1 H.E. PA 3 ESP 10629188

    17 V18-E-103Chargeheater

    1 H.E. PA 3 ESP 10629182

    Inspection Requirements. •20% to 40% tube metal losswas reported as per MFL

    result of 2008 T&I• 100% MFL test shall beconducted.• Sample tube shall be cut. • Tube plugging might bedone for tubes with > 50tube thinning,

  • 8/19/2019 2011 Trs Sow

    39/56

     

    Yanbu Refinery Department

    2011 Total Refinery Shutdown

    February 2011

    Safety

    Cost

    Time

    Quality

    Scope

    TEAM

    WORK

    Cont

    Partner 

    Scope of Work

    Air Cooled Exchangers (Fin Fan Coolers)

  • 8/19/2019 2011 Trs Sow

    40/56

     

    Yanbu Refinery Department

    2011 Total Refinery Shutdown

    February 2011

    General Scope of Work

    1.  Blind Equipment

    2.  Remove all header plugs.

    3.  Carry on initial inspection.

    4.  Carry on external inspection.

    5.  Hydro jet all tubes internally.

    6.  Air blows all tubes after hydro-jetting.

    7.  Air blow on tubes externally and remove all dust on the bundle.

    8.  Carry out MFL test on 10% tubes.

    9.  Reinstall all header plugs.

    10. Hydro test tubes as per OEU hydro-test procedure.

    11. Carry on any repair required as per inspection recommendations.

    12. Blind Equipment

  • 8/19/2019 2011 Trs Sow

    41/56

     

    Yanbu Refinery Department

    2011 Total Refinery Shutdown

    February 2011

    2011 TRS

    EIS Fin Fans List

    SN TAG# EQUIPTNo ofEquip.

    Equip.Type

    Loc Resp MO # scope of work

    Area 11 V04-E12 A1

    Kerosene ProductCooler

    1 Fin Fan PA1 ESP 30032748

    To perform 10%

    MFL and 100%remove headerplugs

    2 V04-E12 A2 1Fin Fan 

    PA1 ESP 30034157

    3 V04-E14 A1

    Light Diesel OilProduct Cooler

    1Fin Fan 

    PA1 ESP 30032878

    4 V04-E14 A2 1 Fin Fan  PA1 ESP 30032877

    5 V04-E14 B1 1Fin Fan 

    PA1 ESP 30032879

    6 V04-E14 B2 1Fin Fan 

    PA1 ESP 30032880

    7 V04-E15 A1Heavy Diesel OilProduct Cooler

    1Fin Fan 

    PA1 ESP 30032841

    8 V04-E15 A2 1Fin Fan 

    PA1 ESP 30032842

    9 V04-E18 A1

    StabilizerCondensers

    1Fin Fan 

    PA1 ESP 30032847

    10 V04-E18 A2 1Fin Fan 

    PA1 ESP 30033095

    11 V04-E18 B1 1Fin Fan 

    PA1 ESP 30032848

    12 V04-E18 B2 1Fin Fan 

    PA1 ESP 30033096

    13 V04-E18 C1 1Fin Fan 

    PA1 ESP 30033097

    14 V04-E18 C2 1Fin Fan 

    PA1 ESP 30032849

    15 V04-E20 A1

    Splitter Condenser

    1Fin Fan 

    PA1 ESP 30033098

    16 V04-E20 A2 1 Fin Fan  PA1 ESP 30033099

    17 V04-E20 B1 1Fin Fan 

    PA1 ESP 30032824

    18 V04-E20 B2 1Fin Fan 

    PA1 ESP 30032825

    19 V04-E20 C1 1Fin Fan 

    PA1 ESP 30032827

  • 8/19/2019 2011 Trs Sow

    42/56

     

    Yanbu Refinery Department

    2011 Total Refinery Shutdown

    February 2011

    20 V04-E20 C2 1Fin Fan 

    PA1 ESP 30032869

    21 V04-E20 D1 1 Fin Fan  PA1 ESP 30032829

    22 V04-E20 D2 1Fin Fan 

    PA1 ESP 30032830

    23 V04-E20 E1 1Fin Fan 

    PA1 ESP 30032824

    24 V04-E20 E2 1Fin Fan 

    PA1 ESP 30032832

    25 V04-E20 F1 1Fin Fan 

    PA1 ESP 30032835

    26 V04-E20 F2 1Fin Fan 

    PA1 ESP 30032836

    27 V04-E21 A1Heavy NaphthaProduct Coolers

    1 Fin Fan  PA1 ESP 30032843

    28 V04-E21 A2 1Fin Fan 

    PA1 ESP 30032844

    29 V04-E25 A1

    Tempered WaterCoolers

    1Fin Fan 

    PA1 ESP 30032912

    30 V04-E25 A2 1Fin Fan 

    PA1 ESP 30032913

    31 V04-E25 B1 1Fin Fan 

    PA1 ESP 30032914

    32 V04-E25 B2 1Fin Fan 

    PA1 ESP 30032915

    33 V04-E25 C1 1 Fin Fan  PA1 ESP 30032916

    34 V04-E25 C2 1Fin Fan 

    PA1 ESP 30032917

    35 V04-E25 D1 1Fin Fan 

    PA1 ESP 30032919

    36 V04-E25 D2 1Fin Fan 

    PA1 ESP 30032920

    37 V04-E25 E1 1Fin Fan 

    PA1 ESP 30032921

    38 V04-E25 E2 1Fin Fan 

    PA1 ESP 30032922

    39 V04-E26 B 1Fin Fan 

    PA1 ESP 30034144

    To be sent to

    Juaymah MSSDShop forretubing. Tubesare at Area 25.

  • 8/19/2019 2011 Trs Sow

    43/56

     

    Yanbu Refinery Department

    2011 Total Refinery Shutdown

    February 2011

    Area 2

    1 V11-E2 A1

    Plat formingProducts

    Condenser

    1 Fin Fan  PA 2 ESP 30032899

    To perform 10%MFL and 100%remove headerplugs

    2 V11-E2 A2 1Fin Fan 

    PA 2 ESP 30032900

    3 V11-E2 B1 1Fin Fan 

    PA 2 ESP 30032901

    4 V11-E2 B2 1Fin Fan 

    PA 2 ESP 30032902

    5 V11-E2 C1 1Fin Fan 

    PA 2 ESP 30032903

    6 V11-E2 C2 1Fin Fan 

    PA 2 ESP 30032904

    7 V11-E2 D1 1Fin Fan 

    PA 2 ESP 30032905

    8 V11-E2 D2 1Fin Fan 

    PA 2 ESP 30032906

    9 V11-E2 E1 1Fin Fan 

    PA 2 ESP 30032907

    10 V11-E2 E2 1Fin Fan 

    PA 2 ESP 30032908

    11 V11-E2 F1 1Fin Fan 

    PA 2 ESP 30032909

    12 V11-E2 F2 1Fin Fan 

    PA 2 ESP 30032910

    13 V12-E2Amine Stripper

    Overhead

    Condenser

    1Fin Fan 

    PA 2 ESP 30032870

    14 V17-E2 A1Reactor Products

    Condenser

    1Fin Fan 

    PA 2 ESP 30032893

    15 V17-E2 A2 1Fin Fan 

    PA 2 ESP 30032894

    16 V17-E5Stripper Bottoms

    Cooler1

    Fin Fan PA 2 ESP 30032871

    17 V17-E7Stripper Overhead

    Condenser1

    Fin Fan PA 2 ESP 30032875

    UTILITY

    1 V32-E2Condensate

    Cooler1

    Fin Fan UTL ESP 30033478

    MO's Fin Fans List 

    SN TAG# EQUIPTNo ofEquip.

    Equip.Type

    Loc. Resp. MO #scope of

    work

    Area 21 V11-E-0114 Lube oil Cooler 1 Fin Fan PA 2 ESP 10628850 T&I Scope

  • 8/19/2019 2011 Trs Sow

    44/56

     

    Yanbu Refinery Department

    2011 Total Refinery Shutdown

    February 2011

    Safety

    Cost

    Time

    Quality

    Scope

    TEAM

    WORK

    Cont

    Partner 

    Scope of Work

    Drums & Miscellaneous

  • 8/19/2019 2011 Trs Sow

    45/56

     

    Yanbu Refinery Department

    2011 Total Refinery Shutdown

    February 2011

    General Scope of Work for (Drums)

    1. 

    Blind equipment.

    2. 

    If applicable conduct soda ash flashing before opening drums manways and after cooling down.

    3. 

    Open shell man ways.

    4. 

    Conduct initial internal inspection.

    5.  Conduct external equipment inspection.

    6. 

    Remove drums internals (distributors, demisters) as per inspection recommendations.

    7.  Erect internal scaffolding as recommended by inspection.

    8. 

    Conduct internal cleaning as per inspection recommendations.9.  Conduct detail internal inspection.

    10. 

    Clean all removed internals as recommended by inspection and area engineer.

    11. 

    Based on inspection recommendations, grit blast all marked areas.

    12. Conduct WFMPT, hardness test, DPT as applicable.

    13. 

    Carry on any repair recommended by inspection.

    14. Install back all removed and repaired internals (distributors, demisters).

    15. 

    Conduct inspection on all internals after installing back.

    16. 

    Remove internal Scaffolding.

    17. 

    Conduct internal final cleaning.

    18. Flush all nozzles and make sure there is no any dirt of plugging.

    19. Conduct final internal inspection.

    20. 

    Box up all drums manways.

    21. If applicable apply required bolts tensioning and torque.

    22. 

    De blind.

  • 8/19/2019 2011 Trs Sow

    46/56

     

    Yanbu Refinery Department

    2011 Total Refinery Shutdown

    February 2011

    EIS Drums List

    SN TAG# EQUIPTNo ofEquip.

    Equip.Type

    Loc. Resp. MO #Scope of

    work

    Area 11 V04-V2 Flash Drum 1 Drum PA1 MMH 30032774 EIS T&I

    2 V04-V7Desalting Water Surge

    Drum1 Drum PA1 MMH 30032786

    EIS T&I

    3 V04-V8 Crude Column Receiver 1 Drum PA1 MMH 30032778 EIS T&I

    4 V04-V10 Stabilizer Receiver 1 Drum PA1 MMH 30032780 EIS T&I

    5 V04-V12 Splitter Receiver 1 Drum PA1 MMH 30032782EIS T&I

    6 V04-V13Unicor Drum ( Inj. Dosing

    chemical)1 Drum PA1 MMH 30032807

    EIS T&I

    7 V04-V14Unicor Drum ( Inj. Dosing

    chemical)1 Drum PA1 MMH 30032808

    EIS T&I

    8 V04-V15 5 Be' Caustic Storage 1 Drum PA1 MMH 30032809 EIS T&I

    9 V04-V16 Fuel Gas Knockout Pot 1 Drum PA1 MMH 30032788 EIS T&I

    10 V04-V17Tempered Water Surge

    Drum1 Drum PA1 MMH 30032805

    EIS T&I

    11 V04-V18Receiver Gas Knockout

    Pot1 Drum PA1 MMH 30032783

    EIS T&I

    12 V04-V19 Blow Case 1 Drum PA1 MMH 30032784 EIS T&I

    13 V04-V24 2 Be' Caustic Storage 1 Drum PA1 MMH 30032810 EIS T&I14 V04-V27 NALCO Injection Tank 1 Drum PA1 MMH 30033796 EIS T&I

    15 V25-V69 Crude Surge Drum 1 Drum PA1 MMH 30032787

    1. EIS T&I2. Scaffoldingplan isrequired

    16 V13-V2 Caustic Prewash 1 Drum PA1 MMH 30032801 EIS T&I

    17 V13-V4 Caustic Settler 1 Drum PA1 MMH 30032803 EIS T&I

    18 V13-V5 Sand Filter 1 Drum PA1 MMH 30032804 EIS T&I

    19 V13-V6 Oxidizer 1 Drum PA1 MMH 30032794 EIS T&I

    20 V13-V7 Di-sulfide Separator 1 Drum PA1 MMH 30032795 EIS T&I

    21 V13-V8 Vent Tank 1 Drum PA1 MMH 30032796 EIS T&I

    22 V13-V9 Catalyst Addition Pot 1 Drum PA1 MMH 30032797 EIS T&I

    23 V13-V10Spent Caustic Degasing

    Drum1 Drum PA1 MMH 30032798

    EIS T&I

    24 V35-V1 Flare Knockout Drum 1 Drum PA1 MMH 30032799EIS T&I

  • 8/19/2019 2011 Trs Sow

    47/56

     

    Yanbu Refinery Department

    2011 Total Refinery Shutdown

    February 2011

    Area 2

    1 V11-V4Platforming Product

    Separator1 Drum PA 2 MMH 30033519

    1. EIS T&I2. Demisterremoval andscaffoldingerection3. Gritblasting isrequired forinternalcleaning

    2 V12-V2Fuel Gas Absorber

    Knockout Drum1 Drum PA 2 MMH 30032813

    EIS T&I

    3 V12-V3Fuel Gas Absorber

    Interface Pot

    1 Drum PA 2 MMH 30032814EIS T&I

    4 V12-V5Amine Stripper Overhead

    Receiver1 Drum PA 2 MMH 30032815

    EIS T&I

    5 V12-V9 Fuel Gas Knockout Drum 1 Drum PA 2 MMH 30032818 EIS T&I

    6 V12-V10 Amine Knockout Drum 1 Drum PA 2 MMH 30032816 EIS T&I

    7 V12-V11 Amine Gas Scubber 1 Drum PA 2 MMH 30032817 EIS T&I

    8 V14-V4Deethanizer Feed Surge

    Drum1 Drum PA 2 MMH 30033131

    EIS T&I

    9 V14-V6Deethanizer Receiver

    Drum1 Drum PA 2 MMH 30037253

    EIS T&I

    10 V17-V2 Charge Surge Drum 1 Drum PA 2 MMH 30033103

    1. EIS T&I2. Scaffolding

    plan isrequired

    11 V17-V3 High Pressure Separator 1 Drum PA 2 MMH 300331041. EIS T&I2. Replacedemister pad

    12 V17-V4 Low Pressure Flash Drum 1 Drum PA 2 MMH 30033105 EIS T&I

    13 V17-V7Recycle Compressor

    Suction Drum1 Drum PA 2 MMH 30033106

    1. EIS T&I2. Replacedemister pad

    14 V17-V8Make up Compressor

    Suction Drum1 Drum PA 2 MMH 30033107

    1. EIS T&I2. Replacedemister pad

    15 V17-V9 Fuel Gas Knockout Drum 1 Drum PA 2 MMH 30033108 EIS T&I

    16 V30-V1 Fuel Gas Drum 1 Drum PA 2 MMH 30032819 EIS T&I

    UTLITY1 V32-V1 Condensate Flash Drum 1 Drum UTL MMH 30033364 EIS T&I

    2 V32-V2Continous Blowdown

    Drum1 Drum UTL MMH 30033365

    EIS T&I

    3 V32-V3Intermittent Blowdown

    Drum1 Drum UTL MMH 30033366

    EIS T&I

  • 8/19/2019 2011 Trs Sow

    48/56

     

    Yanbu Refinery Department

    2011 Total Refinery Shutdown

    February 2011

    4 V32-V4 Condensate Surge Drum 1 Drum UTL MMH 30033367 EIS T&I

    5 V32-V5 Fuel Gas Knockoout Drum 1 Drum UTL MMH 30033368 EIS T&I

    6 V32-ME-1 Feedwater Deaerator 1 Drum UTL MMH 30032014 EIS T&I

    MO's Drums List

    SN TAG# EQUIPTNo ofEquip.

    Equip.Type

    Loc. Resp. MO # Scope of work

    Area 2

    1 V11-D-0110 Presat Separator 1 Drum PA 2 ESP 10689167

    OPEN / CLEAN /INSPECT as PEROME, Cleaningrequired

    2 V11-D-147 CCR Coalecer 1 Drum PA 2 JAZ 10644524CCR Coalecer filterelementreplacement

    3 V11-D-0148 A/BDessicant Dust Filter

    Drum2 Drum PA 2 MMH 10655504

    Open, dump,replace Dessicants

    4 V11-D156 Dust Collector 1 Drum PA 2 JAZ 10671936Dust Collector filterelementreplacement

    Area 3

    1 V05-D-0016 Coalescer Drum 1 Drum PA 3 ESP 10672124EIU requirementOpen / inspect

    2 V05-D-0022Cold feed coalescer

    drum1 Drum PA 3 MMH 10643758

    CSD Healthrequirement •Inspect V05-D-0022

    during Next T&I.• Perform magneticparticle inspectionon all of the nozzleto shell welds andat least 12” on eachside of the Teeintersections of theshell to nozzlewelds.

  • 8/19/2019 2011 Trs Sow

    49/56

     

    Yanbu Refinery Department

    2011 Total Refinery Shutdown

    February 2011

    3 V06-D-0001Rich amine flash

    drum1 Drum PA 3 MMH 10627428

    Inspection as PerEIU. • 2” Nozzle

    was repaired due tocrack found.• Shall be opened. • MPI to beconducted.

    4 V06-D-0003Amine regenerator

    reflux drum1 Drum PA 3 MMH 10625651

    EIU requirementOpen, checkBELZONA coatingcondition applied in2008 I-T&I.

    5 V07-D-0001Sour water degassing

    drum1 Drum PA 3 MMH 10644109

    EIU requirementOpen, check coatingcondition applied in

    2008 I-T&I.

    6 V07-D-0005SWS overhead

    receiver1 Drum PA 3 MMH 10618933

    EIU requirement1. Repair,replacement of 4"OD nozzle (N1).

    7 V18-D-0102 Stabilizer receiver 1 Drum PA 3 MMH 10627970

    EIU requirementOpen, check BELZONAcoating conditionapplied in 2008 I-T&I.

    8V18-D-0106

    A/BMakeup gas dryers 2 Drum PA 3 MMH

    1062887210628876

    OEU requirementUnload and RefillISOM DryersAbsorbent as per

    OEUrecommendation

    9 V18-D-0108 Caustic drain tank 1 Drum PA 3 MMH 10627992

    EIU requirementOpen, checkBELZONA coatingcondition applied in2008 I-T&I.

    10V18-D-0110

    A/BFeed dryers 2 Drum PA 3 MMH

    1062895910628960

    OEU requirementUnload and RefillISOM DryersAbsorbent as perOEUrecommendation

    11V41-D-0006

    A/BSulfur silos 2 Drum PA 3 MMH

    1063126410631266

    EIU requirement1.Conveyor BucketWheel Base Upperside to be replaced(Cutting & welding)2. Open side covers,for BELZONA, visualinspection IR # A3-2008-014

  • 8/19/2019 2011 Trs Sow

    50/56

     

    Yanbu Refinery Department

    2011 Total Refinery Shutdown

    February 2011

    General Scope of Work for (Miscellaneous)

    1. 

    Blind equipment.

    2. 

    Open manways.

    3.  Conduct initial inspection.

    4. 

    Repair as per inspection recommendation.

    5. 

    Hydro jet internal surface as per inspection recommendation.

    6. 

    Remove internal scaffolding if applicable.

    7. 

    Perform final inspection.

    8. 

    Close all manways.

    9.  Remove external scaffoldings.

    10. 

    De blind.

  • 8/19/2019 2011 Trs Sow

    51/56

     

    Yanbu Refinery Department

    2011 Total Refinery Shutdown

    February 2011

    EIS Misc List

    SN TAG# EQUIPTNo ofEquip.

    Equip.Type

    Loc. Resp. MO # scope of work

    Area 1

    1 V04-M1

    Steam Separator

    1 Misc PA1 MMH 30033795 EIS T&I

    2 V04-M2 1 Misc PA1 MMH 30034125 EIS T&I

    3 V04-M3 1 Misc PA1 MMH 30034126 EIS T&I

    4 V04-M4 1 Misc PA1 MMH 30034127 EIS T&I

    5 V04-Y450 psig SteamDesuperheater 1 Misc PA1 MMH 30033797

    EIS T&I

    MO's Misc List

    SN TAG# EQUIPTNo ofEquip.

    Equip.Type

    Loc. Resp. MO # scope of work

    Area 3

    1 V05-D-0009 Feed filter 1 Filter PA 3 ESP 10641322OEU requirementHydrojetting andcleaning

    2 V05-D-0011Sour water

    mechanical filter1 Filter PA 3 ESP 10646363

    EIU requirement1. Open, Inspection andreplace filter elements.2. Inspection for HICresistant, the inspectionfor the hydrogen inducescracking or blisters.

    3 V05-D-0047 V05-E-0009 Coldside Inlet Filter

    1 Filter PA 3 ESP 10641323 EIU requirement1. Open, Inspection andclean filter basket.

    4 V05-D-0048Hot side Inlet

    Filter1 Filter PA 3 ESP 10641324

    EIU requirement1. Open, Inspection andclean, repair filterbasket.

  • 8/19/2019 2011 Trs Sow

    52/56

     

    Yanbu Refinery Department

    2011 Total Refinery Shutdown

    February 2011

    5V05-D-

    0049A

    Feed / EffluentExchanger-Feed

    Filter1 Filter PA 3 ESP 10641325

    EIU requirement1. Open, Inspection and

    clean, repair filterbasket.

    6V05-D-0049B

    Feed / EffluentExchanger-Feed

    Filter1 Filter PA 3 ESP 10641326

    EIU requirement1. Open, Inspection andclean, repair filterbasket.

    7 V05-D-0050

    Feed / Effluent

    Exchanger-FeedFilter

    1 Filter PA 3 MMH 10630789

    OEU Requirement1. Replace Filter Elementwith new one.EUI requirement• Upstream anddownstream line shall beflashed and cleaned.• Perform Shear waveinspection of the Teejoints of circ to longseam weld, and the shellto nozzle welds

    8V41-D-1008

    / 2008Sulfur Pits 2 Pit PA 3 JAZ

    1067319310673204

    Open, clean, unplugsolidified sulfur. (Al-dossary contractor)

  • 8/19/2019 2011 Trs Sow

    53/56

     

    Yanbu Refinery Department

    2011 Total Refinery Shutdown

    February 2011

    Safety

    Cost

    Time

    Quality

    Scope

    TEAM

    WORK

    Cont

    Partner 

    Scope of Work

    Basin

  • 8/19/2019 2011 Trs Sow

    54/56

     

    Yanbu Refinery Department

    2011 Total Refinery Shutdown

    February 2011

    EIS Basin List

    SN TAG# EQUIPTNo ofEquip.

    Equip.Type

    Loc. Resp. MO #scope of

    work

    TANK FARM

    1 CWRBCooling Water

    Retension Basin @Tankfarm

    2 Basin TF ESP 10710716 T&I Scope

    Scope of Work for (V25 CWRB– Tankfarm Cooling Retension Bond

    Basin) 

    1. 

    Lock-out and isolate power.

    2. 

    Drain out water from the basin (activities by Ops).

    3.  Pumping out of remaining water (pump supplied by Aramco).

    4.  Initial inspection.

    5. 

    Internal cleaning of basin – (remove sludge debris)

    6. 

    Inspection activities – Civil and mechanical.

    7. 

    Repair work as per EIU recommendations

    8. 

    Final inspection

    9. 

    Clean clear site.

  • 8/19/2019 2011 Trs Sow

    55/56

     

    Yanbu Refinery Department

    2011 Total Refinery Shutdown

    February 2011

    EIS Basin List

    SN TAG# EQUIPTNo ofEquip.

    Equip.Type

    Loc. Resp. MO # scope of work

    MARINE

    1 CWIBCooling WaterIntake Basin @

    Marine1 Basin MTF ESP 10619959 T&I Scope

    Scope of Work for (V29 CWIB – Marine Intake Basin)

    1. 

    Diver - to remove marine growth on stop gate guide to free-up stop gate into closed

    position.

    2. 

    Saudi Aramco crane to assist in installing & lowering the stop gate.

    3. 

    Diver to put and arrange sand bags at bottom of intake stop gate. (to minimize seepage

    of seawater into the basin)

    4.  Pumping out of seawater from the basin by Ops.

    5.  Lock-out and isolate power after pumping out intake basin.

    6. 

    Pumping out of remaining water (Aramco Water Pump).

    7. 

    Confine entry permit - Initial inspection – use monkey ladder.

    8. 

    Erect tower scaffolding inside the basin.

    9. 

    Internal cleaning - Remove sludge debris, marine growth from intake basin.

    10. 

    Inspection activities – Civil and mechanical:

    a) 

    MECHANICAL INSPECTION:

      Check cooling water pump suction strainers

      Inspect metal underwater structures

      Check drum screen rack assembly.

      Check under water anodes.

  • 8/19/2019 2011 Trs Sow

    56/56

     

    Yanbu Refinery Department

    2011 Total Refinery Shutdown

    February 2011

    b) 

    CIVIL CONCRETE INSPECTION

      Check concrete structure. 

      Check coating on intake basin internal surface.

    11. 

    Conduct repair as require per EIU inspector recommendations.

    12. 

    Final inspection.

    13. 

    Remove internal scaffolding.

    14. 

    Diver to remove temporary sand bags.

    15. 

    S. Aramco crane to assist diver to lift remove stop gate.

    16. 

    Clean and clear site.