General Scope of Work
1.
Blind Equipment
2.
If applicable conduct soda ash flashing before opening drums manways and after
cooling down.
3.
Open shell man ways.
4. Conduct initial internal inspection.
5. Conduct external equipment inspection.
6.
Open all tray manways.
7.
Remove drum internals (distributors, demisters) as per inspection recommendations.
8.
Erect internal scaffolding as recommended by inspection.
9.
Conduct internal cleaning as per inspection recommendations.
10.
Conduct detail internal inspection.
11. Clean all removed internals as recommended by inspection and area engineer.
12.
Based on inspection recommendations, grit blast all marked areas.
13.
Conduct WFMPT, hardness test, DPT as applicable.
14.
Carry on any repair recommended by inspection.
15.
Install back all removed and repaired internals (distributors, demisters).
16.
Replace all missing or damaged trays' valves as per Inspection recommendation
17.
Conduct inspection on all internals after installing back.
18.
Remove internal Scaffolding.
-
8/19/2019 2011 Trs Sow
3/56
Yanbu Refinery Department
2011 Total Refinery Shutdown
February 2011
19.
Conduct internal final cleaning.
20.
Flash all nozzles and make sure there is no any dirt of plugging.
21.
Conduct internal inspection.
22.
Box up all tray manways.
23.
Conduct final internal inspection.
24.
Box up all shell manways.
25.
De blind equipment
26.
If applicable apply required bolts tensioning and torque.
-
8/19/2019 2011 Trs Sow
4/56
Yanbu Refinery Department
2011 Total Refinery Shutdown
February 2011
EIS Towers List
SN TAG# EQUIPTNo ofEquip.
MO # scope of work
Area 1
1 V04-V1* Crude Column 1 30032773
1. EIS T&I2. Revamp internals Tray# 5 to 33. Conduct P-scan on the shell external of
the column area where internal packing islocated.4. PZV inlet lines low thicknessreplacement as per EIU (part of pipingcontract)
2 V04-V3* KeroseneStripper
1 300327751. EIS T&I2. Revamp internals Tray# 1 to 9
3 V04-V4* LDO Stripper 1 30032776
1. EIS T&I2. Revamp internals Tray# 1 to 7
4 V04-V5 HDO Stripper 1 30032777
1. EIS T&I2. Operation engineer should evaluatethe cause of down comers and trayssegment bending in order to avoidreoccurrence in the future.
5 V04-V9 Stabilizer 1 30032779 EIS T&I
6 V04-V11 Splitter 1 30032781 EIS T&I
7 V13-V1Amine
Absorber1 30032800 EIS T&I
8 V13-V3 Extractor 1 30032802 EIS T&I
-
8/19/2019 2011 Trs Sow
5/56
Yanbu Refinery Department
2011 Total Refinery Shutdown
February 2011
Area 2
1 V09-V6 Stripper 1 30032957
1. EIS T&I2.Trays # 6 to 13 shall be replaced bynew ones.Scaffolding plan is required
2 V12-V1 Fuel Gas Absorber 1 30032812 EIS T&I
3 V17-V5Amine Stripper
OverheadReceiver
1 30032956 EIS T&I
4 V14-V1* Debutanizer 1 50041615 EIS T&I & Internal Revamp
* Columns are handled by PPEU
MO's Towers List
SN TAG# EQUIPTNo ofEquip.
MO # scope of work
Area 2
1 V11-C-0101Absorber
Column1 10627388
EIU requirement1.Inspection of column internal surface is
required specially bottom section. Anycolumn internals in bottom section shallbe removed and internal surface need tobe exposed for inspection2. Column tray man ways need to beopened3. Erection of internal scaffolding isrequired.
Area 3
1 V05-C-0001HP Amine
Absorber1 10680640
OEU requirementWater wash, open inspect for fouling asper OEU recommendation Ref. LetterOEU# 073/10
-
8/19/2019 2011 Trs Sow
6/56
Yanbu Refinery Department
2011 Total Refinery Shutdown
February 2011
2 V05-C-0003LP amine
absorber1 10628237
EIU requirement.1. Open all manways
2. Conduct MPI test on 2” nozzle at topman way3. Carry on any cleaning might berequired.4. Open all tray man way.5. Erect internal scaffolding. Inspectionas per EIU
3 V07-C-0002Vent gas
absorber 1 10628018
EIU requirement1. Indication of minor defect wasobserved.2. Open all manways.3. Open all tray manways4. Conduct MPI test.5. Cleaning as required, Inspection as perEIU
4 V18-C-0102Net gas
scrubber1 10618972
EIU requirement1. Open all column manways2. Conduct visual and NDT inspection3. Replacement of 3” (Nozzle N-12) Gasinlet nozzle at column bottom.4. Open all tray manways
5. Rotate the level sight glass to bevisible
-
8/19/2019 2011 Trs Sow
7/56
Yanbu Refinery Department
2011 Total Refinery Shutdown
February 2011
Safety
Cost
Time
Quality
Scope
TEAM
WORK
Cont
Partner
Scope of Work
Stacks & Flares
-
8/19/2019 2011 Trs Sow
8/56
Yanbu Refinery Department
2011 Total Refinery Shutdown
February 2011
General Scope of Work (STACKS)
1.
Blind Equipment
2.
Open bottom door manways
3. Conduct initial inspection on bottom section.
4.
Conduct external inspection
5.
Conduct internal inspection using Crane & basket.
6.
Repair damaged refractory as recommended by Inspection.
7.
Carryout final cleaning, clean bottom floor, remove all maintenance debris, prior to
box-up Stack door.
8. Repair external coating as recommended by Inspection.
9.
De blind equipments
==========================================================================
General Scope of Work (Flares)
1.
Blind Equipment as per Operation list.
2.
Open all manways on Flare Stack assembly (Molecular Seal & Water Seal Drums, etc.)
3. Install air-movers for purging as necessary.
4. Conduct Initial Inspection.
5.
Clean and inspect internals of Molecular Seal & water Seal drums.
6.
Dismantle, remove Flare Tip & put it on the ground for Inspection.
7.
Erect scaffolding to the top of the tip
-
8/19/2019 2011 Trs Sow
9/56
Yanbu Refinery Department
2011 Total Refinery Shutdown
February 2011
8.
Conduct T&I, NDT inspection.
9.
Carryout recommended repairs by EIU.
10.
Final Inspection of Flare Stack assembly (Molecular Seal & Water Seal Drums, etc.)
11.
Reinstall back Flare Tip, box-up all flanges with permanent gaskets.
12.
Box-up all manways on Flare Stack assembly (Molecular Seal & Water Seal Drums,
etc.) with permanent gaskets.
13.
De-blind nozzles and box-up with permanent gaskets.
-
8/19/2019 2011 Trs Sow
10/56
Yanbu Refinery Department
2011 Total Refinery Shutdown
February 2011
EIS Stacks and Flares List
SN TAG# EQUIPTNO OFEQUIP.
EQUIP.TYPE
MO # SCOPE OF WORK
Area 1
1 V04-STK-AStack For
CrudeHeater
1 Stack 30032768
1. EIS T&I
2. Coating external surface using APCS-11C from middle of Stack to Top byusing crane. This will be done byOtaishan contractor)
3. Stack aircraft light system will beupgraded by PPEU.
2 V35-ME-1Emergency
FlareAssembly
1 Flare 30033783
1. EIS T&I for Flare Tip, Molecular Seal &Water Seal Drums.
2. Replacement of 3'' dia Pipe. (pipingcontract under the metal shop)
3. External Coating of Water Seal Drumbottom portion. Scaffolding plan isrequired.
4. Inspection of internal BALZONAcoating at bottom of Water Seal Drum,applied during 2008 I-T&I
3 V35-ME-2Operating
FlareAssembly
1 Flare 30033784
1. EIS T&I
2. Scaffolding is required.
-
8/19/2019 2011 Trs Sow
11/56
Yanbu Refinery Department
2011 Total Refinery Shutdown
February 2011
Area 2
1 V11-STK-B Stack 1 Stack 30033798
1. EIS T&I
2. Coating external surface using APCS-11C from middle of Stack to Top.
UTILITY
1 V32-STK-C Boiler Stack 1 Stack 30033967
1. EIS T&I
2. Coating external surface using APCS-
11C two (2) meters at Top only. Thiswill be done by Otaishan contractor
3. Aircraft light system will be upgradedby PPEU
MO's Stacks and Flares List
SN TAG# EQUIPTNO OF
EQUIP.
EQUIP.
TYPELOC. RESP. MO # SCOPE OF WORK
Area 3
1 V35-F-0003 Sour Flare 1 Flare PA 3 MMH 10629116
EIU requirementRemove Flare Tip toground forInspection
NOTE: COMMISSIONING OF NEW FLARE HEADER FLOW METER BY PPEU
-
8/19/2019 2011 Trs Sow
12/56
Yanbu Refinery Department
2011 Total Refinery Shutdown
February 2011
Safety
Cost
Time
Quality
Scope
TEAM
WORK
Cont
Partner
Scope of Work
Reactors
-
8/19/2019 2011 Trs Sow
13/56
Yanbu Refinery Department
2011 Total Refinery Shutdown
February 2011
General Scope of Work
1.
Blind equipment.
2.
Dump all catalysts as per process engineer recommendations.
3.
If applicable conduct soda ash flashing before opening reactor manways and after cooling
down.
4. Open all external man ways.
5.
Conduct initial internal inspection.
6. Conduct external equipment inspection.
7.
Remove reactors internals as per inspection recommendation.8. Erect internal scaffolding as recommended by inspection.
9.
Conduct reactor internal cleaning as per inspection recommendations.
10.
Conduct reactor detail internal inspection.
11.
Clean all removed internals as recommended by inspection and area engineer.
12.
Based on inspection recommendations, grit blast all marked areas.
13. Conduct WFMPT, hardness test, DPT as applicable.
14.
Carry on any repair recommended by inspection.
15.
Install back all removed and repaired reactors internals.
16.
Conduct inspection on all internals after installing back.
17. Remove internal Scaffolding.
18.
Conduct reactor final cleaning.
19.
Conduct reactor final inspection.
20.
Load back the catalysts.
21.
Box up the reactor.
22. Apply required bolts tensioning and torque.
23.
De blind.
-
8/19/2019 2011 Trs Sow
14/56
Yanbu Refinery Department
2011 Total Refinery Shutdown
February 2011
EIS Reactors List
SN TAG# EQUIPT No ofEquip.
MO # scope of work
Area 21 V17-V1 L.S.R.N Reactor 1 30033520 T&I and Catalyst skimming
MO's Reactors List
SN TAG# EQUIPTNo ofEquip.
MO # scope of work
Area 2
1 V09-V1 NHT Reactor 1 10659299
OEU requirement1. Catalyst Dumping and Skimming forone (1) Meter top as per OEU Letter#YR/OEU-059/0102. Replace outlet pressure gauge 3/4"globe valve
Area 3
1 V05-D-0001AFirst HDSreactor
1 10619631
OEU requirement1. DHT Reactor Top Bed CatalystDumping.2. Transportation and Regeneration ofCatalyst at Al Bilad, Jubail• Remove top 24” elbow. • Remove bottom 24”X22” spool forinspection and cleaning.• Flash outlet line starting from V05-D-0050 up to reactor bottom.• Clean out let reactor elbow byvacuum cleaner.• Erect external scaffolding on reactorshell to perform shear wave test.• Remove external insulation onreactor steam and circumferentialwelds.• Perform Shear wave inspection of theTee joints of circ to long seam weld,
and the shell to nozzle welds at nextT&I of V05-D-0001A.• Take metallurgical replicas at theshell and the welds of V05-D-0001A forHTHA in next outage.
2V10-D-
1003/1004/2003/2004
1st & 2ndConverterReactors
41062878510628791
OEU requirement1. Catalyst dumping & Reloading newcatalyst
-
8/19/2019 2011 Trs Sow
15/56
Yanbu Refinery Department
2011 Total Refinery Shutdown
February 2011
Safety
Cost
Time
Quality
Scope
TEAM
WORK
Cont
Partner
Scope of Work
Heater
-
8/19/2019 2011 Trs Sow
16/56
Yanbu Refinery Department
2011 Total Refinery Shutdown
February 2011
General Scope of Work
1.
Blind Equipment
2.
Open all manways.
3.
Open heater stack and duct manways.
4.
Conduct initial internal inspection.
5.
Conduct external inspection.
6.
Remove burner assemblies and associated piping as recommended by inspection.
7. Cover all burners opening. (By Olayyan)
8.
Erect full internal scaffolding to reach all walls and tubes for UT, hardiness and visual
inspection.
9.
Erect scaffolding for convection section side covers opening and make it suitable for
UT and VT tests.
10.
Open all convection section side covers.
11.
Open all convection section inspection windows.
12. Brush cleans the tubes / U-bends as marked by inspection for UT survey and visual
inspection.
13.
Conduct UT tests on all tubes including convection and radiant sections.
14. Conduct replica test if recommended by CSD.
15.
Conduct RT profile shot for selected elbows.
16.
Repair damaged refractory as per civil inspector recommendations.
17.
Test & clean stack dampers and repair as recommended by inspection.
18.
Remove all internal scaffolding.
19.
Install burner assemblies and associated piping. (By Olayyan) 20. Rearrange floor bricks, clean, and replace damaged bricks.
21. Conduct final inspection.
22.
Close all Radiant & Convection section doors, duct and Stack man ways.
-
8/19/2019 2011 Trs Sow
17/56
Yanbu Refinery Department
2011 Total Refinery Shutdown
February 2011
23.
Close / Box-up all heater man ways.
24. Remove scaffolding erected for convection section.
25.
Perform required dry out procedure as per civil inspector recommendations.
26. De Blind Equipment
-
8/19/2019 2011 Trs Sow
18/56
Yanbu Refinery Department
2011 Total Refinery Shutdown
February 2011
EIS Heaters List
SN TAG# EQUIPTNo ofEquip.
Equip.Type
Loc. Resp. MO # scope of work
Area 1
1 V04-H1ACrude Charge
Heater1 Heater PA1 ESP 30032505
T&I and Replace V04-H1 B Coil Hanger andinstall gasket for 6"decoking flange leak.1- FTIS to be done by
EIU.2- Radiant section isrequired to removehard scale.3- Scaffolding plan isrequired.
2 V04- H1BCrude Charge
Heater1 Heater PA1 ESP 30032506
Area 2
1 V09-H1Reactor Charge
Heater1 Heater PA 2 ESP 30033111
T&I. Heater should beopened in 2010shutdown for re-inspection, and thefretting damageshould be reassessed.At least 30%refractory materialshould be on hand foranticipatedrepair/replacerefractory atconvection & radiantsection during thenext shut down.
-
8/19/2019 2011 Trs Sow
19/56
Yanbu Refinery Department
2011 Total Refinery Shutdown
February 2011
2 V09-H2Stripper Reboiler
Heater1 Heater PA 2 ESP 30033112
T&I.1. At least 30%
refractory materialshould be on hand foranticipatedrepair/replacerefractory atconvection & radiantsection during thenext shut down.2.Replica examinationwas done on tubesnumber 1, 2 and 3.The microstructure of
the tubes is normalfor carbon steel asillustrated in Figures3, 4 and 5. Considerreplica testing of theheater tubes in thenext T&I.
3 V11-H1Platforming Charge
Heater1 Heater PA 2 ESP 30032770
T&I and DamperReplacement
4 V11-H2 Platforming No. 1Inter Heater
1 Heater PA 2 ESP 30032771
5 V11-H3Platforming No. 2
Inter Heater1 Heater PA 2 ESP 30032772
6V11-H1-H2-H3
Ducting 1 Heater PA 2 ESP 30033421 T&I Scope
7 V14-H1Debutanizer
Reboiler Heater1 Heater PA 2 ESP 30033113 T&I Scope
8 V17-H1Reactor Charge
Heater1 Heater PA 2 ESP 30032791
T&I. Tubereplacement as
required.
9 V17-H2Stripper Reboiler
Heater1 Heater PA 2 ESP 30032793 T&I Scope
10 V12-H1 Incinerator 1 Heater PA 2 ESP 30032789 T&I Scope
Note : Commission new flare header flow meter, PPEI were informed to commission the system
-
8/19/2019 2011 Trs Sow
20/56
Yanbu Refinery Department
2011 Total Refinery Shutdown
February 2011
MO's Heaters List
SN TAG# EQUIPTNo ofEquip.
Equip.Type
Loc. Resp. MO # scope of work
Area 2
1V11-F101
Platforming No.2Interheater
1 Heaters PA 2 ESP 10628097
INSPECTIONREQUIREMENT & RepairV11-F101 DamperPositioner.Internal scaffolding is
required• Inspection of tubesupports and repair ofany damage support
Area 3
1V05-F-0001
Reactor feedheater
1 Heaters PA 3 ESP 10626582
INSPECTIONREQUIREMENT. (not T&I)• Erect internalscaffolding.• Conduct visualinspection to all tubesand supports.• Conduct UT thicknessmeasurement.
• Open heater manwaysand inspection covers.
2V10-F-1003
Reaction furnaceburner
1 Heaters PA 3 ESP 10619295
INSPECTIONREQUIREMENT.• Internal inspection isrequired• Replace burner nozzle/ tip assembly. Tipavailable at T&I stores• Repair of damagedrefractory• NDT (UT) test to be
applied as required.
-
8/19/2019 2011 Trs Sow
21/56
Yanbu Refinery Department
2011 Total Refinery Shutdown
February 2011
3V10-F-1004
Thermal oxidizerfurnace burner
1 Heaters PA 3 ESP 10619296
INSPECTIONREQUIREMENT.
• Internal inspection isrequired• Replace burner nozzle/ tip assembly. Tipavailable at T&I stores• Repair of damagedrefractory• NDT (UT) test to beapplied as required,
4V10-F-2002
Thermal oxidizerfurnace
1 Heaters PA 3 ESP 10626664
INSPECTIONREQUIREMENT.• Internal inspection is
required• Repair of damagedrefractory if any.• NDT (UT) test to beapplied as required.
5V10-F-2003
Reaction furnaceburner
1 Heaters PA 3 ESP 10619297
INSPECTIONREQUIREMENT.• Internal inspection isrequired• Replace burner nozzle/ tip assembly. Tipavailable at T&I stores
• Repair of damagedrefractory• NDT (UT) test to beapplied as required
6V10-F-2004
Thermal oxidizerfurnace burner
1 Heaters PA 3 ESP 10619298
INSPECTIONREQUIREMENT.• Internal inspection isrequired• Replace burner nozzle/ tip assembly. Tipavailable at T&I stores• Repair of damagedrefractory• NDT (UT) test to beapplied as required
-
8/19/2019 2011 Trs Sow
22/56
Yanbu Refinery Department
2011 Total Refinery Shutdown
February 2011
Safety
Cost
Time
Quality
Scope
TEAM
WORK
Cont
Partner
Scope of Work
Heat Exchangers
-
8/19/2019 2011 Trs Sow
23/56
Yanbu Refinery Department
2011 Total Refinery Shutdown
February 2011
General Scope of Work
1.
Blind the equipments.
2.
Erect external scaffolding as required.
3.
If chemical cleaning is required, install adopters for the chemical cleaning.
(Coordinate with RISAL contractor who will perform the chemical cleaning and
vacuum cleaning for backinox)
4.
Remove channel box and shell covers.
5. Remove floating head cover.
6.
Conduct initial inspection on assembly before tube bundle removal.
7.
Remove channel box.
8.
Pull out exchanger tube bundle and transport to cleaning yard at Area-25.
9.
Perform visual inspection on both shell and tube bundle.
10.
Hydro Jet all tubes and remove all scales’. Cleaning shall be accepted by both
inspection and area engineer.
11. Hydro jet shell internal surface.
12.
Air blows all tubes after hydro-jetting.
13.
Hydro jet bundle externally and remove any deposit in between the tubes.
14.
Carry out MFL test on 10% tubes.
15.
Grit blast vertical and circumferential shell weld seams (6” wide) as marked by
Inspection for WFMPT examination
16.
Clean heat exchanger components, covers, and channel box.
17.
If applicable grit blast channel box and covers for re-coating as recommended by
inspection.
18. Apply required coating as per Saudi Aramco procedure and follow inspection
recommendations.
19.
Carry on any repair required as per inspection recommendations.
20.
If applicable conduct PWHT.
-
8/19/2019 2011 Trs Sow
24/56
Yanbu Refinery Department
2011 Total Refinery Shutdown
February 2011
21.
Reinstall back the tube bundles.
22.
Using test ring conduct hydro test for shell side as per approved procedure.23.
Plug any leaking tube using in kind tube plugs.
24. Re-install back channel box, channel box cover and floating head cover.
25. Conduct tube side hydro test as per approved procedure.
26. Re-install back shell cover.
27.
Conduct final test as per approved procedure.
28.
Carry on any repair required.
29.
Remove scaffoldings
30.
De blind the equipment
-
8/19/2019 2011 Trs Sow
25/56
Yanbu Refinery Department
2011 Total Refinery Shutdown
February 2011
EIS Heat Exchangers List
SNTAG
#EQUIPT
No ofEquip
EquipType
Loc. Resp. MO # Scope Of Work
Area 1
1V04-E2
ACrude
Kerosene
ProductExchangers
1 H.E PA1 ESP 30032876 20% MFL shall be conducted.One bundle is re-tubed and shall beinstalled.
The other bundle should go to Juaimafor retubing. Tubes are available inA25.
2V04-E2
B1 H.E PA1 ESP 30032864
3V04-E3
A1
Crude LightDiesel OilProduct
Exchangers
1 H.E PA1 ESP 30032865To perform 20% MFL and 20% WFMPT.
4V04-E3
A21 H.E PA1 ESP 30032866
5V04-E3
B11 H.E PA1 ESP 30032867
6V04-E3
B21 H.E PA1 ESP 30032868
7 V04-E4A1
Crude No. 1CirculatingLight Diesel
OilExchangers
1 H.E PA1 ESP 30032884
8V04-E4
A21 H.E PA1 ESP 30032885
9V04-E4
B11 H.E PA1 ESP 30032895
10V04-E4
B21 H.E PA1 ESP 30032896
11V04-E6
A1
DesaltedCrude Heavy
Diesel OilProduct
Exchanger
1 H.E PA1 ESP 30032471Shell side blow down flange leak,
gasket to be replaced. To perform20% MFL and 20% WFMPT.12 V04-E6A1 H.E PA1 ESP 30034145
13V04-E6
B11 H.E PA1 ESP 30035854 To perform 20% MFL and 20% WFMPT.
14V04-E6
B1 H.E PA1 ESP 30035841
S/S blow down upstream flange leakgasket to be replaced. To perform 20%MFL and 20% WFMPT.
-
8/19/2019 2011 Trs Sow
26/56
Yanbu Refinery Department
2011 Total Refinery Shutdown
February 2011
15V04-E5A1
Crude No. 2CirculatingLight Diesel
OilExchangers
1 H.E PA1 ESP 30035842
To perform 20% MFL and 20% WFMPT.16 V04-
E5A21 H.E PA1 ESP 30035843
17V04-E5B1
1 H.E PA1 ESP 30035844
18V04-E5B2
1 H.E PA1 ESP 30035845
19V04-E31
HDO trimcooler
1 H.E PA1 ESP 30035840 To perform 100% WFMPT and 20% MFL
20V04-E24
LSRN trimcooler
1 H.E PA1 ESP 30033791 To perform 40%WFMPT and 20% MFL
21V04-E33
LDO trimcooler
1 H.E PA1 ESP 30035855 To perform 100% WFMPT and 20% MFL
22 V04-E8A1
DesaltedCrude Heavy
Diesel OilCirculatingExchanger
1 H.E PA1 ESP 30032850
To perform 20% MFL and 20% WFMPT.23
V04-E8A2
1 H.E PA1 ESP 30032851
24V04-E8
B11 H.E PA1 ESP 30032852
25V04-E8
B21 H.E PA1 ESP 30032472
26V04-E9
A1
DesaltedCrude HotReducedCrude
Exchangers
1 H.E PA1 ESP 30032853
Repair copper heated Tube Side InletFlange & To perform 20% MFL and 20%WFMPT.
27V04-E9
A21 H.E PA1 ESP 30032854
Repair copper heated Tube Side InletFlange & To perform 20% MFL and 20%WFMPT.
28V04-E9
A31 H.E PA1 ESP 30032855
To perform 20% MFL and 20% WFMPT.29
V04-E9A4
1 H.E PA1 ESP 30032856
30V04-E9
A51 H.E PA1 ESP 30032857 To perform 30% MFL and 20% WFMPT
31V04-E9
B11 H.E PA1 ESP 30032858
Repair copper heated Tube Side InletFlange & To perform 20% MFL and 20%
WFMPT.
32V04-E9
B21 H.E PA1 ESP 30032859
Repair copper heated Tube Side InletFlange & To perform 20% MFL and 20%WFMPT.
33V04-E9
B31 H.E PA1 ESP 30032860 To perform 20% MFL and 20% WFMPT.
-
8/19/2019 2011 Trs Sow
27/56
Yanbu Refinery Department
2011 Total Refinery Shutdown
February 2011
34V04-E9
B4
1 H.E PA1 ESP 30032861
Repair copper heated Tube SideFlange & To perform 20% MFL and 20%
WFMPT.
35V04-E9
B51 H.E PA1 ESP 30032862
To perform 30% MFL and 100% WFMPT
36V04-E17 A
StabilizerFeed
Exchangers
1 H.E PA1 ESP 30032478
To perform 20% MFL and 20% WFMPT.37
V04-E17 B
1 H.E PA1 ESP 30033091
38V04-E19 A
StabilizerReboiler
1 H.E PA1 ESP 30032479Repair copper heated Channel Box &To perform 20% MFL and 20% WFMPT.
39V04-E19 B 1 H.E PA1 ESP 30033092
Repair copper heated Channel Box &To perform 20% MFL and 20% WFMPT.
40V04-E22 A
HeavyNaphtha
Product TrimCoolers
1 H.E PA1 ESP 30032481 To perform 20% MFL and 20% WFMPT.Inspect the coating at channel boxcover.41
V04-E22 B
1 H.E PA1 ESP 30033093
42V04-E23 A Splitter
Reboiler
1 H.E PA1 ESP 30032483 One tube bundle to be sent toJuaymah for retubing as perinspection decision. Tube available atArea 25.
43V04-E23 B
1 H.E PA1 ESP 30033094
44V04-E29 A
CirculatingCoolingWater
Coolers
1 H.E PA1 ESP 30032838
To perform 20% MFL and 20% WFMPT.Inspect the coating at channel boxcover. Required chemical cleaning &changing of anodes.
45V04-E29 B
1 H.E PA1 ESP 30032839
46V04-E29 C
1 H.E PA1 ESP 30032840
47V04-E29 D
1 H.E PA1 ESP 30032486
48V13-E1
A CausticHeater
1 H.E PA1 ESP 30032498
To perform 20%MFL and 20% WFMPT.49
V13-E1B
1 H.E PA1 ESP 30034143
Area 2
1 V09-E2 A ReactorProducts
TrimCondenser
1 H.E PA 2 ESP 30032581 EIU Inspection, Anode consumedUpgrade anodes to Al• Install ferrules @ inlet side.Require for soda ashneutralization.
2 V09-E2 B 1 H.E PA 2 ESP 30032897
3 V09-E3CStripper Feed
BottomsExchangers
1 H.E PA 2 ESP 30032559
Replace tube bundle. Tube bundlereceived,
-
8/19/2019 2011 Trs Sow
28/56
Yanbu Refinery Department
2011 Total Refinery Shutdown
February 2011
4 V09-E5
StripperOverhead
TrimCondenser
1 H.E PA 2 ESP 30032582 T&I Scope
5 V12-E1Kerosene
Unibon GasCoolers
1 H.E PA 2 ESP 30032562 T&I Scope
6 V12-E3Amine
StripperReboiler
1 H.E PA 2 ESP 30032560T&I Scope
7 V12-E4 A
AmineExchangers
1 H.E PA 2 ESP 30032564 T&I Scope
8 V12-E4 B 1 H.E PA 2 ESP 30032845 T&I Scope
9 V12-E4 C 1 H.E PA 2 ESP 30032846
Install V12-E4 C (new shell & U-tube bundle). Will require
cutting/ fabrication of new pipespool for V12 E4C to match thealignment of new headattachment.
10 V12-E6 Amine Cooler 1 H.E PA 2 ESP 30032561 T&I Scope
11 V14-E8DE-
ETHANIZERFEED EXCHER
1 H.E PA 2 ESP 30037263 T&I Scope
12 V14-E9REBOILER
DETHANIZER1 H.E PA 2 ESP 30037264 T&I Scope
13 V14-E10ACONDENSERDETHANIZR
O/HEAD1 H.E PA 2 ESP 30037265 T&I Scope
14 V14-E10BCONDENSERDETHANIZR
O/HEAD1 H.E PA 2 ESP 30037266 T&I Scope
15 V17-E1 A1
CombinedFeed Effluent
Exchanger
1 H.E PA 2 ESP 30032586 T&I Scope
16 V17-E1 A2 1 H.E PA 2 ESP 30032886 T&I Scope
17 V17-E1 A3 1 H.E PA 2 ESP 30032887Also include Soda ash cleaningbefore pulling out of tube bundle.
18 V17-E1 A4 1 H.E PA 2 ESP 30032888Also include Soda ash cleaningbefore pulling out of tube bundle.
19 V17-E1 B1 1 H.E PA 2 ESP 30032889 T&I Scope
20 V17-E1 B2 1 H.E PA 2 ESP 30032890 T&I Scope
21 V17-E1 B3 1 H.E PA 2 ESP 30032891 Also includes Soda ash cleaningbefore pulling out of tube bundle.
22 V17-E1 B4 1 H.E PA 2 ESP 30032892Also includes Soda ash cleaningbefore pulling out of tube bundle.
23 V17-E3Make-Up Gas
Cooler1 H.E PA 2 ESP 30032604 T&I Scope
24 V17-E4 A Stripper FeedBottoms
1 H.E PA 2 ESP 30032608 T&I Scope25 V17-E4 B 1 H.E PA 2 ESP 30032882 T&I Scope
-
8/19/2019 2011 Trs Sow
29/56
Yanbu Refinery Department
2011 Total Refinery Shutdown
February 2011
26 V17-E4 C Exchangers 1 H.E PA 2 ESP 30032883 T&I Scope
27 V17-E6
Stripper
Bottoms TrimCooler
1 H.E PA 2 ESP 30032568 T&I Scope
MO's Heat Exchangers List
SN TAG# EQUIPTNo ofEquip.
Equip. Type Loc. Resp MO # scope of work
Area 2
1 V09-E4 A
NHTstripper
bottomcooler
1 H.E. PA 2 ESP 10632464
T&I and Chemicalcleaning. Chemical
cleaning.
2 V09-E4 B
NHTstripperbottomcooler
1 H.E. PA 2 ESP 10633245
T&I and Chemicalcleaning. Chemicalcleaning.
3 V11-E3 APlatformer
producttrim cooler
1 H.E. PA 2 ESP 10632662100% MFL at all tubes.
4 V11-E3 BPlatformer
producttrim cooler
1 H.E. PA 2 ESP 10633231100% MFL at all tubes.
5 V11-E3 C
Platformer
producttrim cooler
1 H.E. PA 2 ESP 10633237
100% MFL at all tubes.
6 V11-E3 DPlatformer
producttrim cooler
1 H.E. PA 2 ESP 10633238100% MFL at all tubes.
7 V11-E-106Gas
Exchanger1 H.E. PA 2 ESP 10670173
• 100% MFL test shall beconducted.• Sample tube shall becut.• Tube plugging mightbe done for tubes with >50 tube thinning
8 V11-E-107Feed GasChiller
1 H.E. PA 2 ESP 10670266
• 100% MFL test shall beconducted.• Sample tube shall becut.• Tube plugging mightbe done for tubes with >50 tube thinning
-
8/19/2019 2011 Trs Sow
30/56
Yanbu Refinery Department
2011 Total Refinery Shutdown
February 2011
9 V11 E0108PreSatCooler
1 H.E. PA 2 ESP 10689169 Inspection Requirement
10V11-E109
AAET crossexchanger
1 H.E. PA 2 ESP 10632761
100% MFL at all tubes.• Sample tube shall becut.• Tube plugging mightbe done for tubes with >50 tube thinning
11V11-E109
BAET crossexchanger
1 H.E. PA 2 ESP 10633289
100% MFL at all tubes.• Sample tube shall becut.• Tube plugging mightbe done for tubes with >50 tube thinning
12V11-E109
CAET crossexchanger
1 H.E. PA 2 ESP 10633291
100% MFL at all tubes.• Sample tube shall becut.• Tube plugging mightbe done for tubes with >50 tube thinning
13V11-E109
DAET crossexchanger
1 H.E. PA 2 ESP 10633295
Replace V11-E109D(Complete set, as perinspection IR)
14
V11-E110
A
AET cross
exchanger 1 H.E. PA 2 ESP 10632914
100% MFL at all tubes.• Sample tube shall becut.
• Tube plugging mightbe done for tubes with >50 tube thinning
15V11-E110
BAET crossexchanger
1 H.E. PA 2 ESP 10633300
100% MFL at all tubes.• Sample tube shall becut.• Tube plugging mightbe done for tubes with >50 tube thinning
16
V11-E110
C
AET cross
exchanger 1 H.E. PA 2 ESP 10633304
100% MFL at all tubes.• Sample tube shall becut.• Tube plugging mightbe done for tubes with >50 tube thinning
-
8/19/2019 2011 Trs Sow
31/56
Yanbu Refinery Department
2011 Total Refinery Shutdown
February 2011
17 V11-E110D
AET crossexchanger
1 H.E. PA 2 ESP 10633307
100% MFL at all tubes.• Sample tube shall be
cut.• Tube plugging mightbe done for tubes with >50 tube thinning
18V11-E110
EAET crossexchanger
1 H.E. PA 2 ESP 10633308
100% MFL at all tubes.• Sample tube shall becut.• Tube plugging mightbe done for tubes with >50 tube thinning
19 V11-E0111Platformate
Chiller1 H.E. PA 2 ESP 10689171
Inspection requirements
20 V11-E-116Recontact
Chiller1 H.E. PA 2 ESP 10670168
100% MFL at all tubes.• Sample tube shall becut.• Tube plugging mightbe done for tubes with >50 tube thinning
21 V11-E0117Propane
Condenser1 H.E. PA 2 ESP 10630249
100%MFL at all tubes.Repair for both shellcover due to galvaniccorrosion(CS/Monel).Preparewelding procedure fordissimilar materials.• EIU to provide WPS. • 10% to 20% tubethinning as per MFLresult of 2008 T&I• Sample tube shall becut.• Tube plugging mightbe done for tubes with >50 tube thinning
22V11-E-0119
Heater 1Reduction
Gas1 H.E. PA 2 AMG 10627130
Replace Heater element.Spare heater isavailable.
-
8/19/2019 2011 Trs Sow
32/56
Yanbu Refinery Department
2011 Total Refinery Shutdown
February 2011
23 V11-E121Regeneratio
n GasHeater
1 H.E. PA 2 ESP 10627968
V11-E121 ReplaceDefective element &
inspection of nipplewelds, repair nipple ifrequired. (New heaterelement available atArea 25 Electrical Yard).
24 V11-E122 Air Heater 1 H.E. PA 2 ESP 10627704
V11-E122 ReplaceDefective element.Electrical Shop toidentify the defectiveelement to be replaced.
25 V11-E-123Reduction
GasExchanger
1 H.E. PA 2 ESP 10670258
To be opened forinspection as per EIU.
• 100% MFL test shall beconducted.• Sample tube shall becut.• Tube plugging mightbe done for tubes with >50 tube thinning
26V11 E-0130
Lube oilCooler
1 H.E. PA 2 ESP 10630248
100%MFL at all tubes.Repair for both shellcover due to galvaniccorrosion(CS/Monel).Prepare welding procedurefor dissimilar materials.• Tube bundle pull out isrequired• Internal cleaning isrequired using Hydrotest• Repair of damagedinternal cladding isrequired• 10% to 20% tube metalloss reported as per MFLresult of 2008 T&I• 100% MFL test shall beconducted.• Sample tube shall becut.• Tube plugging mightbe done for tubes with >50 tube thinning. EIU toprovide WPS
-
8/19/2019 2011 Trs Sow
33/56
Yanbu Refinery Department
2011 Total Refinery Shutdown
February 2011
27 V14-E1ADebutanizer
Feed
Exchanger
1 H.E. PA 2A.
Planner
10585947 One sent to Juaymah for
retubing and the otherone to be sent duringshutdown.28 V14-E1B
DebutanizerFeed
Exchanger1 H.E. PA 2
A.Planner
10585948
29 V14-E3ADebutanizer
BottomCooler
1 H.E. PA 2A.
Planner10585949
To be sent to Juaymahfor retubing.
30 V14-E12BDepropanizr
BottomCooler
1 H.E. PA 2A.
Planner10568356
Pull-out bundle andreplace with sparebundle.
31V14-E
101A/B
DebutanizerFeed
Exchanger2 H.E. PA 2 ESP
1067026110670262
To be opened forinspection as EIU. • 20%
to 40% tube metal losswas reported as per MFLresult of 2008 T&I• 100% MFL test shall beconducted.• Sample tube shall becut.• Tube plugging mightbe done for tubes with >50 tube thinning
32V14 E-0102 A
DebutanizerBottom Trim
Cooler1 H.E. PA 2 ESP 10630250
100%MFL at all tubes.Repair for both shell
cover due to galvaniccorrosion(CS/Monel).Preparewelding procedure fordissimilar materials.Repair for both shellcover due to galvaniccorrosion (CS/Monel)• 20% to 40% tube metalloss was reported as perMFL result of 2008 T&I• 100% MFL test shall be
conducted.• Sample tube shall becut.• Tube plugging mightbe done for tubes with >50 tube thinning
-
8/19/2019 2011 Trs Sow
34/56
Yanbu Refinery Department
2011 Total Refinery Shutdown
February 2011
33V14 E-0102 B
DebutanizerBottom Trim
Cooler1 H.E. PA 2 ESP 10630251
100%MFL at all tubes.Repair for both shell
cover due to galvaniccorrosion(CS/Monel).Preparewelding procedure fordissimilar materials.Repair for both shellcover due to galvaniccorrosion (CS/Monel)• 20% to 40% tube metalloss was reported as perMFL result of 2008 T&I• 100% MFL test shall be
conducted.• Sample tube shall becut.• Tube plugging mightbe done for tubes with >50 tube thinning
34V14 E0103
ADebutanizer
overheadtrim cooler
1 H.E. PA 2 ESP1063257810630238
Repair channel box &100% MFL + ChemicalCleaning. • Tube bundleremoval• Tube cleaning hydro test
• Repair of damageinternal claddingReplace all damagedferrules. Repair channelbox• 30% to 40% tube metalloss was reported as perMFL result of 2008 T&I• Sample tube shall becut.• Tube plugging mightbe done for tubes with >
50 tube thinning
-
8/19/2019 2011 Trs Sow
35/56
Yanbu Refinery Department
2011 Total Refinery Shutdown
February 2011
35V14 E0103
BDebutanizer
overheadtrim cooler
1 H.E. PA 2 ESP1063328310630241
Repair channel box &100% MFL + Chemical
Cleaning. • Tube bundleremoval• Tube cleaning hydro test• Repair of damageinternal claddingReplace all damagedferrules
36V14 E0103
CDebutanizer
overheadtrim cooler
1 H.E. PA 2 ESP1063328410630242
Repair channel box &100% MFL + ChemicalCleaning. • 30% to 40%tube metal loss was
reported as per MFLresult of 2008 T&I• Sample tube shall becut.• Tube plugging mightbe done for tubes with >50 tube thinning
37V14 E0103
DDebutanizer
overheadtrim cooler
1 H.E. PA 2 ESP1063328710630244
Repair channel box &100% MFL + ChemicalCleaning. • 30% to 40%tube metal loss wasreported as per MFL
result of 2008 T&I• Sample tube shall becut.• Tube plugging mightbe done for tubes with >50 tube thinning
38V14-E-0105A
DepropanizrNet
OverheadCooler
1 H.E. PA 2 ESP 10628187
To repair at channelbox.• Tube bundle to bebulled out and internal.Hydro test will berequired.• Repair of damageinternal cladding isrequired
-
8/19/2019 2011 Trs Sow
36/56
Yanbu Refinery Department
2011 Total Refinery Shutdown
February 2011
39V14-
E0105B
DepropanizrNet
OverheadCooler
1 H.E. PA 2 ESP 10630237
To repair at channelbox.
• Tube bundle to bebulled out and internal.Hydro test will berequired.• Repair of damageinternal cladding isrequired
40 V17-E-101Stripperoverhead
Trim Cooler1 H.E. PA 2 ESP 10670163
To be opened forinspection as EIU. • 10%to 30% tube metal losswas reported as per MFLresult of 2008 T&I
• 100% MFL test shall beconducted.• Sample tube shall becut.• Tube plugging mightbe done for tubes with >50 tube thinning.• Repair of exchangermonel cladding andoverlay by welding buildup and cladding.
41
V11- C1A-
E1A/B
Standby Oil
Cooler 2 H.E. PA 2 ESP 10713805
T&I Scope
42V11- C1B-
E1A/BStandby Oil
Cooler2 H.E. PA 2 ESP 10713813
T&I Scope
43 V14- E11Depropanizr
Reboiler1 H.E. PA 2 ESP 10713801
T&I Scope
Area 3
1 V05-E-0001
Reactor
feed/effluent
exchanger
1 H.E. PA 3 JAZ 10626803
Soda ash Cleaning. Performneutralization and vacuumcleaning a per OEU• Perform Shear waveinspection of the Tee jointsof circ to long seam weld,
and the shell to nozzlewelds at next T&I of V05-E-0001.• Take metallurgicalreplicas at the shell and thewelds of V05-E-0001 forHTHA in next outage.Vacuum cleaning (OEU)
-
8/19/2019 2011 Trs Sow
37/56
Yanbu Refinery Department
2011 Total Refinery Shutdown
February 2011
2 V05-E-0009Feed/striper bottom
exchanger
1 H.E. PA 3 JAZ 10626804 Vacuum Cleaning.
3V05 E-0011A
Producttrim cooler
1 H.E. PA 3 ESP 10629300100%MFL at all tubes.• 30% to 40% tube metal losswas reported as per MFLresult of 2008 T&I• 100% MFL test shall beconducted.• Sample tube shall be cut. • Tube plugging might bedone for tubes with > 50tube thinning
4V05 E-0011B
Producttrim cooler
1 H.E. PA 3 ESP 10629304
5 V05-E-0015Stabilizednaphtha
trim cooler1 H.E. PA 3 ESP 10629296
Inspection Requirements.The channel side of V05-E-0015 should be opened inNext T&I to monitor thecondition of the repair.
6 V05-E-0030
Cooling
water HeatExchanger
1 H.E. PA 3 ESP 10629574
Inspection Requirements. •Perform UT readings forshell part of V05-E-0030/V05-E-0031 on aregular basis as per OSIrequirements for pressurevessels to monitor thecorrosion rate.• The baffle thickness andbaffles’ tubes holes shouldbe measured when it ispossible during S/D.
7 V05-E-0031
Cooling
water HeatExchanger
1 H.E. PA 3 ESP 10629572
Inspection Requirements. •Perform UT readings forshell part of V05-E-0030/V05-E-0031 on aregular basis as per OSI
requirements for pressurevessels to monitor thecorrosion rate.• The baffle thickness andbaffles’ tubes holes shouldbe measured when it ispossible during S/D.
-
8/19/2019 2011 Trs Sow
38/56
Yanbu Refinery Department
2011 Total Refinery Shutdown
February 2011
8V06-E-0003C
Amineregenerator reboilers
1 H.E. PA 3 ESP 10630043
Inspection Requirements. •20% to 30% tube metal loss
was reported as per MFLresult of 2008 T&I• 100% MFL test shall beconducted.• Sample tube shall be cut. • Tube plugging might bedone for tubes with > 50tube thinning,
9 V10-E-10021st sulfurcondenser
1 H.E. PA 3 ESP 10635942
Open the channel head tocheck mesh blanketcondition, TRS Scopeinclude replacement ofdemister pad as per OEU,plus inspection activities asEIU recommendation.
10 V10-E-1003
2nd Sulphur
Condenser 1 H.E. PA 3 ESP 10635945
11 V10-E-10043rd SulphurCondenser
1 H.E. PA 3 ESP 10635946
12 V10-E-20021st SulphurCondenser
1 H.E. PA 3 ESP 10635943
13 V10-E-20032nd SulphurCondenser
1 H.E. PA 3 ESP 10635947
14 V10-E-20043rd SulphurCondenser
1 H.E. PA 3 ESP 10635949
15 V10-E-2007Air
Preheated1 H.E. PA 3 ESP 10629186
Inspection Requirements. •20% to 40% tube metal losswas reported as per MFLresult of 2008 T&I• 100% MFL test shall beconducted.• Sample tube shall be cut.• Tube plugging might bedone for tubes with > 50tube thinning,
16 V10-E-1007Air
Preheated1 H.E. PA 3 ESP 10629188
17 V18-E-103Chargeheater
1 H.E. PA 3 ESP 10629182
Inspection Requirements. •20% to 40% tube metal losswas reported as per MFL
result of 2008 T&I• 100% MFL test shall beconducted.• Sample tube shall be cut. • Tube plugging might bedone for tubes with > 50tube thinning,
-
8/19/2019 2011 Trs Sow
39/56
Yanbu Refinery Department
2011 Total Refinery Shutdown
February 2011
Safety
Cost
Time
Quality
Scope
TEAM
WORK
Cont
Partner
Scope of Work
Air Cooled Exchangers (Fin Fan Coolers)
-
8/19/2019 2011 Trs Sow
40/56
Yanbu Refinery Department
2011 Total Refinery Shutdown
February 2011
General Scope of Work
1. Blind Equipment
2. Remove all header plugs.
3. Carry on initial inspection.
4. Carry on external inspection.
5. Hydro jet all tubes internally.
6. Air blows all tubes after hydro-jetting.
7. Air blow on tubes externally and remove all dust on the bundle.
8. Carry out MFL test on 10% tubes.
9. Reinstall all header plugs.
10. Hydro test tubes as per OEU hydro-test procedure.
11. Carry on any repair required as per inspection recommendations.
12. Blind Equipment
-
8/19/2019 2011 Trs Sow
41/56
Yanbu Refinery Department
2011 Total Refinery Shutdown
February 2011
2011 TRS
EIS Fin Fans List
SN TAG# EQUIPTNo ofEquip.
Equip.Type
Loc Resp MO # scope of work
Area 11 V04-E12 A1
Kerosene ProductCooler
1 Fin Fan PA1 ESP 30032748
To perform 10%
MFL and 100%remove headerplugs
2 V04-E12 A2 1Fin Fan
PA1 ESP 30034157
3 V04-E14 A1
Light Diesel OilProduct Cooler
1Fin Fan
PA1 ESP 30032878
4 V04-E14 A2 1 Fin Fan PA1 ESP 30032877
5 V04-E14 B1 1Fin Fan
PA1 ESP 30032879
6 V04-E14 B2 1Fin Fan
PA1 ESP 30032880
7 V04-E15 A1Heavy Diesel OilProduct Cooler
1Fin Fan
PA1 ESP 30032841
8 V04-E15 A2 1Fin Fan
PA1 ESP 30032842
9 V04-E18 A1
StabilizerCondensers
1Fin Fan
PA1 ESP 30032847
10 V04-E18 A2 1Fin Fan
PA1 ESP 30033095
11 V04-E18 B1 1Fin Fan
PA1 ESP 30032848
12 V04-E18 B2 1Fin Fan
PA1 ESP 30033096
13 V04-E18 C1 1Fin Fan
PA1 ESP 30033097
14 V04-E18 C2 1Fin Fan
PA1 ESP 30032849
15 V04-E20 A1
Splitter Condenser
1Fin Fan
PA1 ESP 30033098
16 V04-E20 A2 1 Fin Fan PA1 ESP 30033099
17 V04-E20 B1 1Fin Fan
PA1 ESP 30032824
18 V04-E20 B2 1Fin Fan
PA1 ESP 30032825
19 V04-E20 C1 1Fin Fan
PA1 ESP 30032827
-
8/19/2019 2011 Trs Sow
42/56
Yanbu Refinery Department
2011 Total Refinery Shutdown
February 2011
20 V04-E20 C2 1Fin Fan
PA1 ESP 30032869
21 V04-E20 D1 1 Fin Fan PA1 ESP 30032829
22 V04-E20 D2 1Fin Fan
PA1 ESP 30032830
23 V04-E20 E1 1Fin Fan
PA1 ESP 30032824
24 V04-E20 E2 1Fin Fan
PA1 ESP 30032832
25 V04-E20 F1 1Fin Fan
PA1 ESP 30032835
26 V04-E20 F2 1Fin Fan
PA1 ESP 30032836
27 V04-E21 A1Heavy NaphthaProduct Coolers
1 Fin Fan PA1 ESP 30032843
28 V04-E21 A2 1Fin Fan
PA1 ESP 30032844
29 V04-E25 A1
Tempered WaterCoolers
1Fin Fan
PA1 ESP 30032912
30 V04-E25 A2 1Fin Fan
PA1 ESP 30032913
31 V04-E25 B1 1Fin Fan
PA1 ESP 30032914
32 V04-E25 B2 1Fin Fan
PA1 ESP 30032915
33 V04-E25 C1 1 Fin Fan PA1 ESP 30032916
34 V04-E25 C2 1Fin Fan
PA1 ESP 30032917
35 V04-E25 D1 1Fin Fan
PA1 ESP 30032919
36 V04-E25 D2 1Fin Fan
PA1 ESP 30032920
37 V04-E25 E1 1Fin Fan
PA1 ESP 30032921
38 V04-E25 E2 1Fin Fan
PA1 ESP 30032922
39 V04-E26 B 1Fin Fan
PA1 ESP 30034144
To be sent to
Juaymah MSSDShop forretubing. Tubesare at Area 25.
-
8/19/2019 2011 Trs Sow
43/56
Yanbu Refinery Department
2011 Total Refinery Shutdown
February 2011
Area 2
1 V11-E2 A1
Plat formingProducts
Condenser
1 Fin Fan PA 2 ESP 30032899
To perform 10%MFL and 100%remove headerplugs
2 V11-E2 A2 1Fin Fan
PA 2 ESP 30032900
3 V11-E2 B1 1Fin Fan
PA 2 ESP 30032901
4 V11-E2 B2 1Fin Fan
PA 2 ESP 30032902
5 V11-E2 C1 1Fin Fan
PA 2 ESP 30032903
6 V11-E2 C2 1Fin Fan
PA 2 ESP 30032904
7 V11-E2 D1 1Fin Fan
PA 2 ESP 30032905
8 V11-E2 D2 1Fin Fan
PA 2 ESP 30032906
9 V11-E2 E1 1Fin Fan
PA 2 ESP 30032907
10 V11-E2 E2 1Fin Fan
PA 2 ESP 30032908
11 V11-E2 F1 1Fin Fan
PA 2 ESP 30032909
12 V11-E2 F2 1Fin Fan
PA 2 ESP 30032910
13 V12-E2Amine Stripper
Overhead
Condenser
1Fin Fan
PA 2 ESP 30032870
14 V17-E2 A1Reactor Products
Condenser
1Fin Fan
PA 2 ESP 30032893
15 V17-E2 A2 1Fin Fan
PA 2 ESP 30032894
16 V17-E5Stripper Bottoms
Cooler1
Fin Fan PA 2 ESP 30032871
17 V17-E7Stripper Overhead
Condenser1
Fin Fan PA 2 ESP 30032875
UTILITY
1 V32-E2Condensate
Cooler1
Fin Fan UTL ESP 30033478
MO's Fin Fans List
SN TAG# EQUIPTNo ofEquip.
Equip.Type
Loc. Resp. MO #scope of
work
Area 21 V11-E-0114 Lube oil Cooler 1 Fin Fan PA 2 ESP 10628850 T&I Scope
-
8/19/2019 2011 Trs Sow
44/56
Yanbu Refinery Department
2011 Total Refinery Shutdown
February 2011
Safety
Cost
Time
Quality
Scope
TEAM
WORK
Cont
Partner
Scope of Work
Drums & Miscellaneous
-
8/19/2019 2011 Trs Sow
45/56
Yanbu Refinery Department
2011 Total Refinery Shutdown
February 2011
General Scope of Work for (Drums)
1.
Blind equipment.
2.
If applicable conduct soda ash flashing before opening drums manways and after cooling down.
3.
Open shell man ways.
4.
Conduct initial internal inspection.
5. Conduct external equipment inspection.
6.
Remove drums internals (distributors, demisters) as per inspection recommendations.
7. Erect internal scaffolding as recommended by inspection.
8.
Conduct internal cleaning as per inspection recommendations.9. Conduct detail internal inspection.
10.
Clean all removed internals as recommended by inspection and area engineer.
11.
Based on inspection recommendations, grit blast all marked areas.
12. Conduct WFMPT, hardness test, DPT as applicable.
13.
Carry on any repair recommended by inspection.
14. Install back all removed and repaired internals (distributors, demisters).
15.
Conduct inspection on all internals after installing back.
16.
Remove internal Scaffolding.
17.
Conduct internal final cleaning.
18. Flush all nozzles and make sure there is no any dirt of plugging.
19. Conduct final internal inspection.
20.
Box up all drums manways.
21. If applicable apply required bolts tensioning and torque.
22.
De blind.
-
8/19/2019 2011 Trs Sow
46/56
Yanbu Refinery Department
2011 Total Refinery Shutdown
February 2011
EIS Drums List
SN TAG# EQUIPTNo ofEquip.
Equip.Type
Loc. Resp. MO #Scope of
work
Area 11 V04-V2 Flash Drum 1 Drum PA1 MMH 30032774 EIS T&I
2 V04-V7Desalting Water Surge
Drum1 Drum PA1 MMH 30032786
EIS T&I
3 V04-V8 Crude Column Receiver 1 Drum PA1 MMH 30032778 EIS T&I
4 V04-V10 Stabilizer Receiver 1 Drum PA1 MMH 30032780 EIS T&I
5 V04-V12 Splitter Receiver 1 Drum PA1 MMH 30032782EIS T&I
6 V04-V13Unicor Drum ( Inj. Dosing
chemical)1 Drum PA1 MMH 30032807
EIS T&I
7 V04-V14Unicor Drum ( Inj. Dosing
chemical)1 Drum PA1 MMH 30032808
EIS T&I
8 V04-V15 5 Be' Caustic Storage 1 Drum PA1 MMH 30032809 EIS T&I
9 V04-V16 Fuel Gas Knockout Pot 1 Drum PA1 MMH 30032788 EIS T&I
10 V04-V17Tempered Water Surge
Drum1 Drum PA1 MMH 30032805
EIS T&I
11 V04-V18Receiver Gas Knockout
Pot1 Drum PA1 MMH 30032783
EIS T&I
12 V04-V19 Blow Case 1 Drum PA1 MMH 30032784 EIS T&I
13 V04-V24 2 Be' Caustic Storage 1 Drum PA1 MMH 30032810 EIS T&I14 V04-V27 NALCO Injection Tank 1 Drum PA1 MMH 30033796 EIS T&I
15 V25-V69 Crude Surge Drum 1 Drum PA1 MMH 30032787
1. EIS T&I2. Scaffoldingplan isrequired
16 V13-V2 Caustic Prewash 1 Drum PA1 MMH 30032801 EIS T&I
17 V13-V4 Caustic Settler 1 Drum PA1 MMH 30032803 EIS T&I
18 V13-V5 Sand Filter 1 Drum PA1 MMH 30032804 EIS T&I
19 V13-V6 Oxidizer 1 Drum PA1 MMH 30032794 EIS T&I
20 V13-V7 Di-sulfide Separator 1 Drum PA1 MMH 30032795 EIS T&I
21 V13-V8 Vent Tank 1 Drum PA1 MMH 30032796 EIS T&I
22 V13-V9 Catalyst Addition Pot 1 Drum PA1 MMH 30032797 EIS T&I
23 V13-V10Spent Caustic Degasing
Drum1 Drum PA1 MMH 30032798
EIS T&I
24 V35-V1 Flare Knockout Drum 1 Drum PA1 MMH 30032799EIS T&I
-
8/19/2019 2011 Trs Sow
47/56
Yanbu Refinery Department
2011 Total Refinery Shutdown
February 2011
Area 2
1 V11-V4Platforming Product
Separator1 Drum PA 2 MMH 30033519
1. EIS T&I2. Demisterremoval andscaffoldingerection3. Gritblasting isrequired forinternalcleaning
2 V12-V2Fuel Gas Absorber
Knockout Drum1 Drum PA 2 MMH 30032813
EIS T&I
3 V12-V3Fuel Gas Absorber
Interface Pot
1 Drum PA 2 MMH 30032814EIS T&I
4 V12-V5Amine Stripper Overhead
Receiver1 Drum PA 2 MMH 30032815
EIS T&I
5 V12-V9 Fuel Gas Knockout Drum 1 Drum PA 2 MMH 30032818 EIS T&I
6 V12-V10 Amine Knockout Drum 1 Drum PA 2 MMH 30032816 EIS T&I
7 V12-V11 Amine Gas Scubber 1 Drum PA 2 MMH 30032817 EIS T&I
8 V14-V4Deethanizer Feed Surge
Drum1 Drum PA 2 MMH 30033131
EIS T&I
9 V14-V6Deethanizer Receiver
Drum1 Drum PA 2 MMH 30037253
EIS T&I
10 V17-V2 Charge Surge Drum 1 Drum PA 2 MMH 30033103
1. EIS T&I2. Scaffolding
plan isrequired
11 V17-V3 High Pressure Separator 1 Drum PA 2 MMH 300331041. EIS T&I2. Replacedemister pad
12 V17-V4 Low Pressure Flash Drum 1 Drum PA 2 MMH 30033105 EIS T&I
13 V17-V7Recycle Compressor
Suction Drum1 Drum PA 2 MMH 30033106
1. EIS T&I2. Replacedemister pad
14 V17-V8Make up Compressor
Suction Drum1 Drum PA 2 MMH 30033107
1. EIS T&I2. Replacedemister pad
15 V17-V9 Fuel Gas Knockout Drum 1 Drum PA 2 MMH 30033108 EIS T&I
16 V30-V1 Fuel Gas Drum 1 Drum PA 2 MMH 30032819 EIS T&I
UTLITY1 V32-V1 Condensate Flash Drum 1 Drum UTL MMH 30033364 EIS T&I
2 V32-V2Continous Blowdown
Drum1 Drum UTL MMH 30033365
EIS T&I
3 V32-V3Intermittent Blowdown
Drum1 Drum UTL MMH 30033366
EIS T&I
-
8/19/2019 2011 Trs Sow
48/56
Yanbu Refinery Department
2011 Total Refinery Shutdown
February 2011
4 V32-V4 Condensate Surge Drum 1 Drum UTL MMH 30033367 EIS T&I
5 V32-V5 Fuel Gas Knockoout Drum 1 Drum UTL MMH 30033368 EIS T&I
6 V32-ME-1 Feedwater Deaerator 1 Drum UTL MMH 30032014 EIS T&I
MO's Drums List
SN TAG# EQUIPTNo ofEquip.
Equip.Type
Loc. Resp. MO # Scope of work
Area 2
1 V11-D-0110 Presat Separator 1 Drum PA 2 ESP 10689167
OPEN / CLEAN /INSPECT as PEROME, Cleaningrequired
2 V11-D-147 CCR Coalecer 1 Drum PA 2 JAZ 10644524CCR Coalecer filterelementreplacement
3 V11-D-0148 A/BDessicant Dust Filter
Drum2 Drum PA 2 MMH 10655504
Open, dump,replace Dessicants
4 V11-D156 Dust Collector 1 Drum PA 2 JAZ 10671936Dust Collector filterelementreplacement
Area 3
1 V05-D-0016 Coalescer Drum 1 Drum PA 3 ESP 10672124EIU requirementOpen / inspect
2 V05-D-0022Cold feed coalescer
drum1 Drum PA 3 MMH 10643758
CSD Healthrequirement •Inspect V05-D-0022
during Next T&I.• Perform magneticparticle inspectionon all of the nozzleto shell welds andat least 12” on eachside of the Teeintersections of theshell to nozzlewelds.
-
8/19/2019 2011 Trs Sow
49/56
Yanbu Refinery Department
2011 Total Refinery Shutdown
February 2011
3 V06-D-0001Rich amine flash
drum1 Drum PA 3 MMH 10627428
Inspection as PerEIU. • 2” Nozzle
was repaired due tocrack found.• Shall be opened. • MPI to beconducted.
4 V06-D-0003Amine regenerator
reflux drum1 Drum PA 3 MMH 10625651
EIU requirementOpen, checkBELZONA coatingcondition applied in2008 I-T&I.
5 V07-D-0001Sour water degassing
drum1 Drum PA 3 MMH 10644109
EIU requirementOpen, check coatingcondition applied in
2008 I-T&I.
6 V07-D-0005SWS overhead
receiver1 Drum PA 3 MMH 10618933
EIU requirement1. Repair,replacement of 4"OD nozzle (N1).
7 V18-D-0102 Stabilizer receiver 1 Drum PA 3 MMH 10627970
EIU requirementOpen, check BELZONAcoating conditionapplied in 2008 I-T&I.
8V18-D-0106
A/BMakeup gas dryers 2 Drum PA 3 MMH
1062887210628876
OEU requirementUnload and RefillISOM DryersAbsorbent as per
OEUrecommendation
9 V18-D-0108 Caustic drain tank 1 Drum PA 3 MMH 10627992
EIU requirementOpen, checkBELZONA coatingcondition applied in2008 I-T&I.
10V18-D-0110
A/BFeed dryers 2 Drum PA 3 MMH
1062895910628960
OEU requirementUnload and RefillISOM DryersAbsorbent as perOEUrecommendation
11V41-D-0006
A/BSulfur silos 2 Drum PA 3 MMH
1063126410631266
EIU requirement1.Conveyor BucketWheel Base Upperside to be replaced(Cutting & welding)2. Open side covers,for BELZONA, visualinspection IR # A3-2008-014
-
8/19/2019 2011 Trs Sow
50/56
Yanbu Refinery Department
2011 Total Refinery Shutdown
February 2011
General Scope of Work for (Miscellaneous)
1.
Blind equipment.
2.
Open manways.
3. Conduct initial inspection.
4.
Repair as per inspection recommendation.
5.
Hydro jet internal surface as per inspection recommendation.
6.
Remove internal scaffolding if applicable.
7.
Perform final inspection.
8.
Close all manways.
9. Remove external scaffoldings.
10.
De blind.
-
8/19/2019 2011 Trs Sow
51/56
Yanbu Refinery Department
2011 Total Refinery Shutdown
February 2011
EIS Misc List
SN TAG# EQUIPTNo ofEquip.
Equip.Type
Loc. Resp. MO # scope of work
Area 1
1 V04-M1
Steam Separator
1 Misc PA1 MMH 30033795 EIS T&I
2 V04-M2 1 Misc PA1 MMH 30034125 EIS T&I
3 V04-M3 1 Misc PA1 MMH 30034126 EIS T&I
4 V04-M4 1 Misc PA1 MMH 30034127 EIS T&I
5 V04-Y450 psig SteamDesuperheater 1 Misc PA1 MMH 30033797
EIS T&I
MO's Misc List
SN TAG# EQUIPTNo ofEquip.
Equip.Type
Loc. Resp. MO # scope of work
Area 3
1 V05-D-0009 Feed filter 1 Filter PA 3 ESP 10641322OEU requirementHydrojetting andcleaning
2 V05-D-0011Sour water
mechanical filter1 Filter PA 3 ESP 10646363
EIU requirement1. Open, Inspection andreplace filter elements.2. Inspection for HICresistant, the inspectionfor the hydrogen inducescracking or blisters.
3 V05-D-0047 V05-E-0009 Coldside Inlet Filter
1 Filter PA 3 ESP 10641323 EIU requirement1. Open, Inspection andclean filter basket.
4 V05-D-0048Hot side Inlet
Filter1 Filter PA 3 ESP 10641324
EIU requirement1. Open, Inspection andclean, repair filterbasket.
-
8/19/2019 2011 Trs Sow
52/56
Yanbu Refinery Department
2011 Total Refinery Shutdown
February 2011
5V05-D-
0049A
Feed / EffluentExchanger-Feed
Filter1 Filter PA 3 ESP 10641325
EIU requirement1. Open, Inspection and
clean, repair filterbasket.
6V05-D-0049B
Feed / EffluentExchanger-Feed
Filter1 Filter PA 3 ESP 10641326
EIU requirement1. Open, Inspection andclean, repair filterbasket.
7 V05-D-0050
Feed / Effluent
Exchanger-FeedFilter
1 Filter PA 3 MMH 10630789
OEU Requirement1. Replace Filter Elementwith new one.EUI requirement• Upstream anddownstream line shall beflashed and cleaned.• Perform Shear waveinspection of the Teejoints of circ to longseam weld, and the shellto nozzle welds
8V41-D-1008
/ 2008Sulfur Pits 2 Pit PA 3 JAZ
1067319310673204
Open, clean, unplugsolidified sulfur. (Al-dossary contractor)
-
8/19/2019 2011 Trs Sow
53/56
Yanbu Refinery Department
2011 Total Refinery Shutdown
February 2011
Safety
Cost
Time
Quality
Scope
TEAM
WORK
Cont
Partner
Scope of Work
Basin
-
8/19/2019 2011 Trs Sow
54/56
Yanbu Refinery Department
2011 Total Refinery Shutdown
February 2011
EIS Basin List
SN TAG# EQUIPTNo ofEquip.
Equip.Type
Loc. Resp. MO #scope of
work
TANK FARM
1 CWRBCooling Water
Retension Basin @Tankfarm
2 Basin TF ESP 10710716 T&I Scope
Scope of Work for (V25 CWRB– Tankfarm Cooling Retension Bond
Basin)
1.
Lock-out and isolate power.
2.
Drain out water from the basin (activities by Ops).
3. Pumping out of remaining water (pump supplied by Aramco).
4. Initial inspection.
5.
Internal cleaning of basin – (remove sludge debris)
6.
Inspection activities – Civil and mechanical.
7.
Repair work as per EIU recommendations
8.
Final inspection
9.
Clean clear site.
-
8/19/2019 2011 Trs Sow
55/56
Yanbu Refinery Department
2011 Total Refinery Shutdown
February 2011
EIS Basin List
SN TAG# EQUIPTNo ofEquip.
Equip.Type
Loc. Resp. MO # scope of work
MARINE
1 CWIBCooling WaterIntake Basin @
Marine1 Basin MTF ESP 10619959 T&I Scope
Scope of Work for (V29 CWIB – Marine Intake Basin)
1.
Diver - to remove marine growth on stop gate guide to free-up stop gate into closed
position.
2.
Saudi Aramco crane to assist in installing & lowering the stop gate.
3.
Diver to put and arrange sand bags at bottom of intake stop gate. (to minimize seepage
of seawater into the basin)
4. Pumping out of seawater from the basin by Ops.
5. Lock-out and isolate power after pumping out intake basin.
6.
Pumping out of remaining water (Aramco Water Pump).
7.
Confine entry permit - Initial inspection – use monkey ladder.
8.
Erect tower scaffolding inside the basin.
9.
Internal cleaning - Remove sludge debris, marine growth from intake basin.
10.
Inspection activities – Civil and mechanical:
a)
MECHANICAL INSPECTION:
Check cooling water pump suction strainers
Inspect metal underwater structures
Check drum screen rack assembly.
Check under water anodes.
-
8/19/2019 2011 Trs Sow
56/56
Yanbu Refinery Department
2011 Total Refinery Shutdown
February 2011
b)
CIVIL CONCRETE INSPECTION
Check concrete structure.
Check coating on intake basin internal surface.
11.
Conduct repair as require per EIU inspector recommendations.
12.
Final inspection.
13.
Remove internal scaffolding.
14.
Diver to remove temporary sand bags.
15.
S. Aramco crane to assist diver to lift remove stop gate.
16.
Clean and clear site.